This document outlines specifications for a federal construction contract opportunity with the Department of Agriculture Forest Service. The project involves removing pre-existing toilet structures and replacing them with prefabricated concrete vault toilets at multiple locations in the Mark Twain National Forest in Rolla, Missouri. Sites requiring work include Roby Lake Recreation Site, Loggers Lake Campground, Berryman Campground, Marble Creek Campground, McCormack Lake Recreation Area, and Caney Picnic Area as an optional bid item. Services required include demolition and removal of existing facilities, site preparation, placement and installation of new vault toilet buildings, and minor site work and landscaping. The anticipated period of performance is from August 1, 2021 to December 30, 2022. The solicitation will utilize NAICS code 236220 with a small business size standard of $39.5M.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 12445523R0004 - Pre-Solicitation Notice - Mark Twain NF Vault Toilets.pdf | ||
| Attachment 5 - Phelps County MO Wage Determination.pdf | ||
| Attachment 2 - Vault Toilet Specifications.pdf | ||
| Attachment 3 - Mark Twain Map.pdf | ||
| Attachment 1 - Mark Twain Schedule of Items.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Site Specific Specifications for Eastern Region Fiscal Year 2021 Vault Toilet Building Contracts Mark Twain National Forest Roby Lake Recreation site A. Roby Lake Recreation Site: Site contact Tray Hall. Tray.hall@usda.gov, (417)967-4194.
Amy Wilson, COR ambrosia.wilson@usda.gov, (573)341- 7464 B. New building to match the nearby make and model.
a) CXT: single Cascadian or similar.
b) Board and Batten upper with horizontal lap on the bottom. Color for walls should be brown.
c) Cedar shake for the roof texture and all color should be brown.
d) FS yale locks on the doors. Locks are government furnished property.
e) Toilet Paper Lock bars.
f) Door swing to out.
C. Roby Lake Rec Site: Houston Rolla Ranger district, MO. Lat: 37° 31' 20.4168'' N; Long: 92° 7' 29.1828'' W D. This work is to include installing of new single vault toilet. Place approximately 1 cubic yards (CY) crushed aggregate 1/2” minus (compacted in place) from the edge of parking area to the new vault toilet entrance. Path shall be 60 inches wide by approximately 3 feet long by 6”deep.
E. Work shall commence no sooner than August 1, 2021 and be completed by December 30, 2022. Work shall not take place on weekends or on any federal holidays.
F. It is likely that the building will need to be offloaded to a shorter truck with trailer to access this site. New site location staked by the COR. Request scheduling 1 month in advance of building delivery.
Loggers Lake A. Loggers Lake Campground: (Vault Toilet adjacent to the swimming area), Site Contact Christopher Woods. Christopher.woods@usda.gov, (573)438-5427.
Amy Wilson, COR ambrosia.wilson@usda.gov, (573)341- 7464 B. New Building to match nearby make and model within the same campground.
a) CXT; Tioga Double Vault Restroom or equivalent.
b) Split-faced block outer wall surface option and ribbed metal roof option (to match nearby vault toilet); colors- natural honey on walls and nuss brown roof.
c) Standard lay-out (door swing, etc.); Townsteel Privacy door latch.
d) Toilet paper Lock Bar.
e) Galvanized steel doors with heavy duty tamper resistant dead-bolt.
f) ABA/ADA compliant grab bars.
g) ABA/ADA compliant molded one-piece HDPE polyethylene risers on each side.
C. Loggers Lake Campground; Salem Ranger District, MO, Lat/Long: 37.3902x91.2601, see attached map.
D. Existing concrete block building and two vaults beneath will need to be removed and new CXT Tioga Double Vault will be placed onto existing footprint-. Excavate additional as needed to accommodate new vault.
E. Work shall commence no sooner than August 1, 2021 and be completed by December 30, 2022.
F. It is likely that the building will need to be off loaded to a shorter truck and trailer to access the site. New site location staked by the COR. Request scheduling 1 month in advance of building delivery.
Loggers Lake Campground Existing Toilet Building to be demolished.
Berryman Campground A. Berryman Campground: Site contact Christopher Woods. Contact information: Christopher.woods@usda.gov, (573)438-5427.
Amy Wilson, COR ambrosia.wilson@usda.gov, (573)341- 7464 B. New Building to match nearby make and model within the same Berryman Horse-riding Area.
a. CXT; Double Rocky Mountain or equal.
b. Horizontal lap siding w/River Rock on outer wall surface option and cedar shake roof option (to match nearby vault toilet); colors- natural honey on walls and nuss brown on roof
c. Standard lay-out (door swing, etc.); Townsteel Privacy door latch.
d. Toilet paper lock bar.
e. ABA/ADA compliant molded one-piece HDPE polyethylene risers on each side.
f. ABA/ADA compliant grab bars.
g. Galvanized steel doors with heavy duty tamper resistant dead-bolt.
C. Berryman Campground; Potosi Ranger District, MO, Lat/Long: 37.9292x91.0625, see attached map.
D. Existing concrete block building and two vaults beneath will need to be removed and new CXT Double Rocky Mountain will be placed onto existing footprint- some excavation may be needed as existing footprint may be a bit smaller than the dimensions of existing footprint.
G. Work shall commence no sooner than August 1, 2021 and be completed by December 30, 2022.
E. It is likely that the building will need to be offloaded to a shorter truck with trailer to access the site. New site location will be staked at the site by the COR. Request scheduling 1 month in advance of building delivery.
Existing Berryman Campground Toilet Building to be demolished
Marble Creek Campground A. Marble Creek Campground, Site contact Christopher Woods, christopher.woods@usda.gov, (573)438-5427. Amy Wilson, COR ambrosia.wilson@usda.gov, (573)341- 7464 B. New building to match nearby make and model within the same campground.
a) CXT; Tioga Double Vault Restroom or equal.
b) Barn Wood outer wall surface option and cedar shake roof option (to match nearby vault toilet); colors- natural honey on walls and nuss brown roof.
c) Standard lay-out (door swing, etc.); Townsteel Privacy door latch.
d) Toilet paper lock bar.
e) Galvanized steel doors with heavy duty tamper resistant dead-bolt.
f) ABA/ADA compliant grab bars.
g) ABA/ADA compliant molded one-piece HDPE polyethylene risers on each side.
C. Marble Creek Campground, Fredericktown Ranger District, MO, Lat/Long: 37.4503x90.5408, See attached map.
D. Existing wood building and two vaults beneath will need to be removed and new CXT Tioga Double will be placed onto existing footprint- some excavation is expected as existing footprint may be a bit smaller than the dimensions of the new building.
H. Work shall commence no sooner than August 1, 2021 and be completed by December 30, 2022.
I. It is likely that the building will need to be offloaded to a shorter truck with trailer to access the site. New site location will be staked at the site by the COR. Request scheduling 1 month in advance of building delivery.
Existing Marble Creek Campground to be demolished.
McCormack Lake A. McCormack Lake Recreation area. Site contact Ed Sherman. ejsherman@fs.fed.us, (573)996-2153. Amy Wilson, COR ambrosia.wilson@usda.gov, (573)341- 7464 B. Equal or equivalent to Double Cascadian double vault.
a) Java brown color to match other vault toilets in vicinity.
b) Galvanized steel doors with heavy duty tamper resistant dead-bolt.
c) ABA/ADA compliant grab bars.
d) ABA/ADA compliant molded one-piece HDPE polyethylene risers on each side.
e) Toilet paper lock bar.
C. McCormack Lake, 11 point Ranger District, Doniphan, MO. Lat. 36.82251300, Long. -91.35117500 D. Removal of existing toilet and fill hole. Dig and set hole for new unit as designated next to the Parking area.
E. Period of Performance: start date no sooner than July 4, 2021 and completed by December 30, 2022.
F. New site location will be staked at the site by the COR. Request scheduling 1 month in advance of building delivery.
Caney Picnic Area- Optional Bid Item A. Caney Picnic Area, Site contact Darla Rein or Tray Hall. Tray.hall@usda.gov, (417)967-4194.
Amy Wilson, COR ambrosia.wilson@usda.gov, (573)341- 7464 B. New building to match or the equivalent of the CXT Tioga.
a) Double Vault toilet.
b) Cedar Shake Roof in Rich Earth: Wall texture Barn Wood in Oatmeal.
c) Toilet paper lock bar.
d) ABA/ADA compliant molded one-piece HDPE polyethylene risers on each side.
e) ABA/ADA compliant grab bars.
f) Galvanized steel doors with heavy duty tamper resistant dead-bolt.
C. Caney Picnic Area; Ava/Cassville/ Willow Springs RD; Ava, MO. (Lat/long: 36.744750/-92.758993) D. The contractor is responsible for the removal of the above ground and vault portion of the existing vault toilet. If possible, leave the concrete apron in place, if apron is damaged and can not be saved, remove and fill with compactable ½” minus aggregate. The new vault will go in the same hole as the old vault. Once in place crushed aggregate will be compacted in place to fill any voids for approximately 3 feet around the edge of the toilet building and made level with the surrounding ground to the rock wall and stone treadway.
There is a rock wall behind the existing toilet that must be protected. Contractor is responsible for any damage to the wall. A stone walkway must be protected from the entrance to the site. Contractor is responsible for any damage. Forest Service will remove split rail fence to access the area and trim any trees needed for access. A minimum of one week in advanced notice is required for the necessary tree work and split rail removal. Place crushed ½” minus aggregate, compacted in place, from the edge of the stone walkway to the new vault toilet entrance if concrete apron is saved. See photo. Path shall fan out from the edge of the stone walkway and continue to toilet. All disturbed ground should be seeded using government approved seed mix. Aggregate quantity for this site is to be determined by the contractor.
E. Work Shall Commence no sooner than August 1, 2021 and be completed by December 30. 2022. Work shall not take place on weekends or on federal holidays. Request scheduling 1 month in advance of building delivery.
F. Access is a Forest Service Road. New site location staked by the COR.
Caney Picnic Area Existing Toilet Building to be Removed.
image1.jpg image2.jpeg image3.jpg image4.jpeg image5.jpeg image6.jpg image7.jpeg image8.jpeg image9.jpg image10.jpg image11.jpeg image12.jpg