Attachment 4) Bldg 1075 Hot Water Heaters SOW.pdf

PDF 112 KB Posted

Attached to
Intellihot Water Heaters
Solicitation number
FA4626-24-Q-0017
Issued by

About this file

This document is a Statement of Work (SOW) for the initial startup of Intellihot tankless water heaters at Building 1075 on Malmstrom Air Force Base in Montana.

The SOW requires the contractor to provide all labor, equipment, tools, accessories, and materials needed to properly start up and ensure proper communication between the water heaters. The performance period is 30 calendar days after the order to proceed, with work hours from 7:00 AM to 4:30 PM, Monday through Friday. The contractor must coordinate the startup with the HVAC shop foreman or section chief, and provide 4 hours of training on the new equipment installation. The government will inspect and accept that the water heaters have been properly started and linked together.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

Initial Start up for Intellihot Tankless Water Heaters

MALMSTROM AFB, MT

1. GENERAL

1.1. Summary of work: The contractor shall provide all labor, equipment, tools, accessories, and materials needed to properly start up and ensure proper communication between water heaters at building 1075, on Malmstrom AFB, MT.

1.2 Anti-Terrorism Awareness Training: In accordance with DoDI O-2000.16v1_AFI 31- 145-O, Antiterrorism (AT) Program Implementation, ensure Level I - AT Awareness Training is completed by all contractors within 30 days of requiring access, and annually thereafter. The training will be provided by the government. The objective of the training is to provide personnel with requisite knowledge necessary to remain vigilant and enable employment of AT tactics, techniques, and procedures.

1.3 Force Protection: Contractor personnel are required to abide by all real-world Force Protection Condition (FPCON) measures, random anti-terrorism measures (RAMs), shelter-in-place orders, evacuations and lock-down notices as directed. Examples include mandatory badge or ID checks, facility single points-of-entry and searches of hand carried items.

1.4 Photography and Imagery: IAW 18 USC 795, any photograph, sketch, picture, drawing, map, or graphical representation of US Government property to include:

facilities, aircraft, components, equipment, or other resources, is prohibited without first obtaining permission from the government (e.g. Security Forces convoys, Helicopters, Entry Control Points, etc.)

2. MATERIALS

2.1. The contractor shall provide all material to complete the initial startup and communication link in accordance with standard commercial practices.

3. EXECUTION

3.1. The performance period will be 30 calendar days after order to proceed. Working hours will be from 7:00 AM to 4:30 PM, Monday through Friday.

3.2. The contractor shall coordinate initial start up with HVAC Shop Foreman Robert Pope or HVAC Section Chief TSgt Jordan Kirk @ 406-731-4933

3.3. The contractor shall use the proper computer for startup and linking the systems together. The contractor shall provide 4 hours of training on the new installation of equipment.

3.4. The government will inspect and accept that the water heaters have been properly started and linked together.