BID SCHEDULE
(Pavillion) (21-061)
(Marais Des Cygnes)
(PLEASANTON, KS)
A. GENERAL CONDITIONS:
Division 1: General Requirements
Mobilization and demobilization $ Bond $
General Requirements (testing) $ General Requirements (other) $
Division 1 Total $
B. SUMMARY OF COST BREAKDOWN FOR MATERIALS, LABOR AND EQUIPMENT
Div. 2 Existing Conditions $
Div. 3 Concrete
Div. 6 Wood, Plastics, and Composites
Div. 7 Thermal & Moisture
Div. 26 Electrical
Div. 31 Earthwork
BASE TOTAL
OVERHEAD AND PROFIT (percentage) % % $
BASE TOTAL PLUS OVERHEAD AND PROFIT
PROJECT DESCRIPTION:
Build a 32’x40’ wood structure to provide protection from the elements while conducting hands-on programming. The structure will be placed over the remnants of the old HQ Building on a 38’x46’ concrete slab 4” thick (4,000 PSI) with #3 rebar 12” OC each way and saw cuts. Build an accessible concrete walkway connecting the new pad to the Pit Toilets. A 4'x 13’ stoop will be built at the entrances to the Pit Toilets. Options pending available funding include; 24" stone bases at each column, outdoor fireplace, and togue and groove ceiling planks attached to bottom chord of trusses.
BID SCHEDULE
(Pavillion) (21-061)
(Marais Des Cygnes)
(PLEASANTON, KS)
42" stone wainscot (to match stone at building) at each column
Stone outdoor fireplace with lockable storage cubbies on either side of fireplace. Chimney will need to be atleast 36" taller than peak of pavilion.
Tongue and Groove Pine Ceiling panels installed to the bottom chord of the trusses to close off the trusses to birds, insects, and rodents.
OPTIONS
Option1: (Stone wainscot at columns) $
(Base item cost $
Option 2: (Stone Fireplace) $
Option 3: (Finished Wood Ceiling) $
| A. GENERAL CONDITIONS: |
| BASE TOTAL PLUS OVERHEAD AND PROFIT |