This is a Statement of Work (SOW) for a North Zone Stone Contract issued by the U.S. Department of Agriculture Forest Service for the Monongahela National Forest in West Virginia. The Forest Service anticipates awarding an Indefinite Delivery, Indefinite Quantity (IDIQ) type, Firm-Fixed Price contract for the supply and delivery of stone and aggregate materials. The contract covers the North Zone, which encompasses the Cheat, Greenbrier, and Potomac Ranger Districts in Barbour, Grant, Pendleton, Pocahontas, Preston, Randolph, and Tucker Counties in West Virginia. The contractor must provide all labor, materials, equipment, tools, supplies, transportation, and incidentals necessary to supply stone and aggregate to designated Forest Service locations and maintain a minimum delivery capacity of 300 tons per day to any designated site when directed by Task Order.
The contractor shall bid a price per ton for each material type and ranger district, with bid prices including both material and haul costs to any location within the designated districts. Material specifications reference West Virginia Department of Highways Standard Specifications for Stone and Crushed Aggregate (704), Coarse Aggregate (703), Riprap (704.2), and Shot Rock (704.8). The contractor bears responsibility for sampling and testing to verify gradation and quality compliance, while the Forest Service retains the right to perform acceptance testing. Materials failing to comply with quality requirements will not be accepted. Contractor invoices must be submitted with original and one copy, including all weigh ticket numbers, contract/task order number, Taxpayer Identification Number, description, quantity, unit price, and extended price. Individual task performance will be accomplished through the issuance of Task Orders competed among awarded IDIQ contractors, with selection based on price, past performance on previous orders, and other factors specified in each Task Order.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
US Department of Agriculture (USDA)
Statement of Work
Contents Project
General Information
1.0 Scope of Work
2.0 Background
Contractor Requirements
3.0 Technical Requirements / Tasks
4.0 Government Furnished
5.0 Deliverables / Schedule
Project
North Zone Stone Contract
General Information
1.0 Scope of Work
The Forest Service (FS) has a requirement for a North Zone Stone Contract for the Monongahela National Forest. The FS anticipates award of an IDIQ (Indefinite Delivery, Indefinite Quantity) type, Firm-Fixed Priced Contract for the products described in the Schedule of Items.
2.0 Background
The Monongahela National Forest has a diverse road network consisting of over 1500 miles of single- and two-lane roads with bituminous, aggregate, improved native, and native surfaces. The road network consists of multiple bridges, culverts, drainage dips, gates, and cattle guards. Typical road sections consist of a full-length ditch along one side. Most roads are in forested areas with heavy roadside and overhead vegetation. Aggregate and stone materials are required to maintain the forest road network.
The Monongahela National Forest is split into 2 zones, North and South. The North Zone consists of the Cheat, Greenbrier, and Potomac Ranger Districts. The Ranger Districts of the North Zone are in Barbour, Grant, Pendleton, Pocahontas, Preston, Randolph, and Tucker Counties in West Virginia.
Contractor Requirements
3.0 Technical Requirements / Tasks
Contractor shall provide all labor, materials, equipment, tools, supplies, transportation, and incidentals necessary to supply stone and aggregate to the FS at the locations and under the conditions specified in this contract for which the desired outcome is in strict accordance with the standards attached to each Task Order. Contractor shall have the capacity to deliver a minimum quantity of 300 tons per day to any designated site when directed by a Task Order.
Quantities
Quantities listed in the Schedule of Items are approximations only, based on estimates supplied by the FS. It is understood and agreed that the contract shall cover the quantities actually ordered for delivery during the term of the contract, whether more or less than the quantities shown.
Material Specifications
The material specifications are designated by, but not limited to the following:
Material: WVDOH Standard Spec Section :
Stone and Crushed Aggregate 704
Coarse Aggregate 703
Riprap 704.2
Shot Rock 704.8
Hauling Aggregate to FS Projects by Contractor
The Contractor shall deposit aggregates at the project site at the locations and in a manner directed by the FS. This may include tailgating the aggregate into an aggregate spreader or onto a roadway or dumping the aggregate into a stockpile.
The Contractor shall bid a price per ton for each item on the schedule. The bid price shall include material and haul costs to any location in designated districts. There will be three separate schedules, one for each of the three Ranger Districts in the North Zone of the Monongahela National Forest. See attached map for district locations. Estimated annual quantities shown on the schedule are estimates and for information only. If the Contractor does not produce an item or produces an item by special order, this may be indicated on the bid sheet.
In the event any Contractor does not wish to extend the prices, terms, and conditions of his bid to all areas of the North
Zone of the Monongahela National Forest, he must so indicate in a clear and unambiguous manner in his bid. This indication does not prejudice the award of the contract. If a Contractor does not indicate his refusal to extend the prices, terms, and conditions of his bid to areas of the North Zone of the Monongahela National Forest; he is bound to extend them upon issuance of a Task Order.
Weighing of Materials
Material delivered by truck shall be weighed in accordance with Section 307.8.2 of the West Virginia Department of
Transportation, Division of Highways Standard Specifications, Roads and Bridges, adopted 2023, as amended by
Supplemental Specifications. Moisture required for Stone and Crushed Aggregate shall be added after loaded trucks have been weighed.
Sampling and Testing
Sampling and testing for quality of all items furnished in this contract will be the responsibility of the Contractor. The FS retains the right to perform acceptance testing. The Contractor will be responsible for providing test results attesting to the gradation of materials delivered. Contractor is responsible for providing necessary sampling and testing for applicable sections shown in the West Virginia Department of Transportation, Division of Highways Standard Specifications, Roads and Bridges, adopted 2023, as amended by Supplemental Specifications.
Acceptance Plan
Material failing to comply with the quality requirements will not be accepted.
Contractor’s Invoices
Contractor’s invoices must be submitted in original with one copy and contain the following:
• All weigh ticket numbers for material delivered during the invoicing period.
• Name and address of the Contractor.
• Invoice date and invoice number.
• FS Contract/task order number.
• Taxpayer Identification Number (TIN).
• Description, quantity, unit of measure, unit price, and extended price (Total quantity invoiced shall be scale weights – supported by weigh tickets).
• Name (where practicable), title, phone number, and mailing address of person to notify in the event of a defective invoice.
Performance
The Contractor shall exercise caution and care while pursuing the work to prevent unnecessary conflict with, or potential hazards to road users. Whenever possible, the road shall remain passable to traffic while work is being performed. The
Contractor shall be held liable for any damage caused by his personnel or equipment to any existing structures such as bridges, culverts, signs, guardrails, or any other Government infrastructure or property. Repair or replacement to these structures shall be at the Contractor’s expense. The Government shall not be liable to loss, damage, or destruction of equipment furnished by the Contractor.
Performance of individual tasks will be accomplished by the issuance of Task Orders against the IDIQ contract. The
Performance Based Statement of Work shall consist of completing the ordered Tasks to the Acceptable Quality Level
(AQL) required in the Performance Work Statement / Quality Assurance Plan. The awarded contract and task orders shall constitute the entire agreement including all terms and conditions applicable to the contract.
Performance Work Statement/Quality Assurance Plan
Requirement Tasks / Critical Sub-tasks Quality Standards
1. Materials The Contractor shall deposit aggregates at the project site at the locations and in a manner directed by the FS
Gradation / quality meets
West Virginia Division of
Highways Standards for materials shown in Schedule of Items
AQL Method of Monitoring Incentive / Disincentive
In accordance with West
Virginia Division of
Highways Standards and accepted industry practice
Quality Control Plan and
Material Compliance
Certificates
Positive / Negative performance to be reported to
NIH with potential additional option years
4.0 Government Furnished
Government shall furnish access to the sites. Contractor to coordinate work schedule with site representative to ensure access is available.
5.0 Deliverables / Schedule
If necessary, Task Orders (TO) will be competed among the IDIQ contractors for aggregate placement on the North
Zone of the Monongahela National Forest. Each TO will list the tasks and the estimated quantities of those tasks that will be performed on the TO. In determining who will receive the TO, the FS will consider the price (as indicated in the schedule of items of the awarded contract), past performance (including past performance on previous orders under this contract), and any other factors indicated on the TO. Submittals for each TO will include the following if requested by
FS:
• Quality Control Plan – Demonstrate the ability to complete all tasks to the required Performance Quality
Standards and/or Acceptable Quality Levels
• Inspection Records – At a minimum, provide a copy of material compliance certificates (aggregate, stone, riprap, etc.)