Attachment 3 -Statement of Work.pdf
PDF 239 KB Posted
- Attached to
- Moscow Research Station sewer line repair
- Solicitation number
- 1240LU26Q0072
- Issued by
-
Department of Agriculture Forest Service
About this file
This is a Statement of Work for a sewer line repair project at the USDA Moscow Forestry Sciences Laboratory located in Moscow.
The project scope requires the contractor to hydro-jet approximately 150 linear feet of affected sewer lines to remove roots and sediment, perform camera inspection to verify pipe cleanliness and locate damaged sections, excavate minimally as needed to access the pipes, and repair all damaged pipes in compliance with the most recent International Plumbing Code requirements. The sewer line issues stem from leaking pipes originating from the East Greenhouse with multiple blockages caused by debris and root intrusion. The contractor must contact local utility companies to locate and prevent damage to surrounding utilities, properly dispose of all waste materials, and restore excavated areas to their pre-excavation condition to the extent reasonable. The contractor is responsible for supplying all labor, materials, equipment, miscellaneous items, freight, delivery, and all necessary valid licenses. Key personnel requirements specify that the contractor or any subcontractor must hold a current plumber's license. The contractor must submit a proposed project plan during the bidding process that includes timeline, risks, responsibilities, and milestone objectives. Any planned power, water, or sewer outages require Contracting Officer Representative (COR) approval 48 hours in advance. The government will provide access to onsite restrooms and existing utilities. The facility is a secure government location requiring coordination with local personnel for building access.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| site plan.pdf | ||
| 1240LU26Q0072 Amendment 1.pdf | ||
| leak photo.pdf | ||
| Google photo.docx | DOCX document | |
| Attachment 2 - Schedule of Items.pdf | ||
| Attachment 5 - Experience Questionnaire.pdf | ||
| Attachment 4 -Wage Determinations id65.pdf | ||
| 1240LU26Q0072 Moscow RS sewer repair.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
US Department of Agriculture (USDA)
Statement of Work
Moscow Forestry Sciences Lab
Sewer Line Repair
Contents Project General Information
1.0 Scope of Work
2.0 Background
Contractor Requirements
3.0 Technical Requirements / Tasks
4.0 Government Furnished
5.0 Deliverables / Schedule
6.0 Contractor’s Key Personnel
7.0 Security Requirements
Project Moscow Forestry Sciences Sewer Line Repair
General Information
1.0 Scope of Work
This project includes assessing current site conditions to find the best possible solutions for the following: hydro-jet sewer lines (approx. 150 ft.), camera inspection of line, excavation to expose sewer pipes, repair broken sewer pipe or pipes.
2.0 Background
Moscow Forestry Sciences Laboratory has begun to have sewer line issues. After an initial assessment it was found that the sewer line coming from the East Greenhouse was leaking and the run-off was coming out of the retaining wall below it. An attempt was made to camera the line but was unsuccessful in providing a complete picture of the sewer pipe as the line was found to have multiple bellies and at least one section where roots had grown into the pipe. The pipe had multiple clogs and was found to be backed up with debris.
Contractor Requirements
3.0 Technical Requirements / Tasks
Work for this project requires the contractor to be responsible for supplying all labor, materials, equipment, miscellaneous items, freight and delivery and all necessary valid licenses and for the following:
• Hydro-jet affected sewer line (approx. 150 ft).
o Remove roots and sediment from the sewer line.
o Contact local utility companies to locate and prevent damage to other utilities in the surrounding area.
• Camera inspection o Use camera to inspect and verify that the pipe is clean and to locate the damaged pipe area.
• Excavate as needed to access all the pipes in question.
o Excavation should be as minimal as possible.
o Excavated areas should be returned to as like condition prior to excavation as is reasonable.
• Repair damaged pipe o Must comply with the most recent international plumbing code (IPC) requirements.
• Properly dispose of any waste materials
4.0 Government Furnished
Contractor shall have access to onsite restrooms and existing utilities.
5.0 Deliverables / Schedule
The contractor is required to submit a proposed project plan including timeline, risks, responsibilities, and milestone objectives for the entire contract during the bidding process.
• Obtain COR approval of any power, water, or sewer outages 48 hours in advance to allow for planned outage time.
6.0 Contractor’s Key Personnel
Contractor or Subcontractor must hold a current plumbers license.
7.0 Security Requirements
Moscow Forestry Sciences laboratory is a secure government facility and will require coordination with local personnel to gain access to the building.
| Project |
| General Information |
| 1.0 Scope of Work |
| 2.0 Background |
| Contractor Requirements |
| 3.0 Technical Requirements / Tasks |
| 4.0 Government Furnished |
| 5.0 Deliverables / Schedule |
| 6.0 Contractor’s Key Personnel |
| 7.0 Security Requirements |
File details come from the government source that posted it. Updated .