Attachment 3 SOW Install Copper and Fiber Cable .docx

DOCX document 38 KB Posted

Attached to
Install Copper and Fiber Optic cable at the ARMAG Building at Cheltenham, MD
Solicitation number
70LGLY23QSSB00067
Issued by

About this file

This statement of work outlines requirements for installing copper and fiber optic cabling at the Federal Law Enforcement Training Centers in Cheltenham, Maryland. The contractor shall provide all labor, equipment, materials, and supervision to engineer, furnish, install, test and document approximately 650 feet of shielded twisted pair copper cable and 350 feet of single mode fiber optic cable. Specific tasks include installing conduit and handholes; pulling cable from an existing handhole to a new handhole behind the ARMAG building; terminating cable onto lightning arrestors and fiber optic patch panels; and testing, labeling and documenting all installed cable and terminals. The period of performance is not to exceed five days from contract award. The solicitation is a firm fixed price contract issued by the Department of Homeland Security Federal Law Enforcement Training Center.

View the file

Other files

File Type Posted
Q and A.docx DOCX document
70LGLY23QSSB00067_0001.pdf PDF
Attachment 4 WD 2015-4281 Rv27.txt TXT text file
Sol_70LGLY23QSSB00067.pdf PDF
Attachedment 2 dhs_form_11000-6 non disclosure.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statement of Work For Install Copper and Fiber Optic cable at the ARMAG Building at Cheltenham, MD

1. Background This Statement of Work (SOW) establishes and defines the requirements for the engineering, furnishing, installation, testing and documentation of inside and outside plant fiber optic and copper cabling at Cheltenham, MD.

2. Scope of Work The contractor shall provide all personnel, equipment, tools, materials, supervision, and all other components necessary to install, test and document inside and outside plant fiber optic and copper cabling at Cheltenham, MD. All work performed in the design and installation shall conform to BICSI (Building Industry Consulting Services International) specifications to ensure consistency with current codes, standards, and regulations. The following BICSI publications apply. Outside Plant Design Reference Manual, 4th Edition and Telecommunications Distribution Methods Manual, 12th edition.

3. General.

3.1. Cable Testing. All copper cables will be tested in accordance with BICSI specifications to ensure no damage has occurred to the cable during installation. All copper cables shall be tested for cable faults prior to and after installation has been completed. If the cable is damaged during installation, the contractor shall replace the cable with one that is undamaged. All cable terminals and information boxes interface units shall be labeled with machine-generated labels. All cables shall be labeled at all termination points, building entrance terminals, patch panels, manholes, hand holes, and at all splice entrance/exit points.

3.2. Site Restoration. All non-paved surfaces (grass, sod, gravel, etc.) must be restored within 7 days. Trenches and splice pits must be mechanically compacted to compensate for future earth settlement. All roads, streets, sidewalks of concrete or asphalt construction must be restored or repaved within 3 days from the time of backfilling and compaction.

3.3. Grounding. Contractor shall ensure all equipment are secured and grounded to industry standards.

4. Description of Task

4.1. Task 1: Material to Install Copper and Fiber Optic cable at the ARMAG Building at Cheltenham, MD.

4.1.1. List of materials to be provided by the contractor.

4.1.2. Approximately 650’ Shielded Twisted Pair Copper Cable (STP)

4.1.3. Approximately 350’ 6 Strand Single Mode Fiber Optic Cable

4.1.4. Two (2) Wal Mount 12 Port Fiber Optic Patch Panel

4.1.5. Twelve (12) SC Type Fiber Connectors

4.1.6. Four (4) Lightning Arresters

4.1.7. One 17”x30”x18” Communications Handhole

4.1.8. Approximately 300 Ft of 2” schedule 40 PVC conduit

4.2. Task 2: Install Copper and Fiber Optic cable at the ARMAG Building at Cheltenham, MD.

4.2.1. Contractor shall provide and install a 17”x30”x18” handhole 2” schedule 40 PVC conduit from the existing handhole near bldg. 53 into the new hand hole installed behind the ARMAG bldg. (See Aerial Photo in Attachment 1 below)

4.2.2. Contractor shall provide and install a 2” schedule 40 PVC conduit from the existing handhole near bldg. 53 into the new hand hole installed behind the ARMAG bldg.

4.2.3. Contractor shall provide and install two (2) outside plant grade CAT 6 cable through the newly installed handhole and conduit into the ARMAG building.

4.2.4. Contractor shall terminate both ends of the STP cable onto a lightning arrester terminal.

4.2.5. Contractor shall provide and install a twelve (12) strand single mode fiber optic cable from bldg. 53 IT closet through the conduits and manholes into the ARMAG bldg.

4.2.6. Contractor shall terminate both ends of the 12-strand fiber cable onto fiber optic patch panel using SC fiber optic connectors.

4.2.7. Contractor shall tag and label the cable and terminal.

4.2.8. Contractor shall test label and tag the terminal, cables, and patch panels.

5. Deliverables

5.1. Equipment

5.2. All equipment identified in 4.1

6. Documents Item identified in Task 1 and 2

7. Period of Performance.

Period of performance for this contract is not to exceed 5 days from contract award date.

8. Contract Type This contract shall be a firm fixed price contract.

9. Place of Performance All Tasks work shall be performed at the Federal Law Enforcement Training Centers; US Department of Homeland Security; 9000 Commo Road Cheltenham, MD 20588-4000

10. Section 508 Requirements (include in the SOW, PWS, or SOO) Section 508 of the Rehabilitation Act (classified to 29 U.S.C. § 794d) requires that when Federal agencies develop, procure, maintain, or use information and communications technology (ICT), it shall be accessible to people with disabilities. Federal employees and members of the public with disabilities must be afforded access to and use of information and data comparable to that of Federal employees and members of the public without disabilities.

All products, platforms and services delivered as part of this work statement that, by definition, are deemed ICT shall conform to the revised regulatory implementation of Section 508 Standards, which are located at 36 C.F.R. § 1194.1 & Appendixes A, C & D, and available at https://www.ecfr.gov/cgi-bin/text-x?SID=e1c6735e25593339a9db63534259d8ec&mc=true&node=pt36.3.1194&rgn=div5. In the revised regulation, ICT replaced the term electronic and information technology (EIT) used in the original 508 standards. ICT includes IT and other equipment.

Exceptions for this work statement have been determined by DHS and only the exceptions described herein may be applied. Any request for additional exceptions shall be sent to the Contracting Officer and a determination will be made according to DHS Directive 139-05, Office of Accessible Systems and Technology, dated November 12, 2018, and DHS Instruction 139-05-001, Managing the Accessible Systems and Technology Program, dated November 20, 2018, or any successor publication.