This document is an attachment to a federal contract opportunity outlining the Schedule of Deliverables for a Strategic Capital Investment Planning (SCIP) contract for Fiscal Year 2026-27.

The key details include:

  • The contract requires the contractor to provide a variety of program management, process management, records management, training development, decision process development, cost-effectiveness analysis, help desk support, and other services to support the SCIP process for FY2027.
  • The contract has 20 distinct tasks with over 40 deliverables, including items such as project management plans, programmatic support, SCIP automation tool deployment, business case validation, budget and reporting, and more.
  • Deliverables have defined due dates ranging from 7 to 579 calendar days after contract award.
  • The related federal contract opportunity is Solicitation Number 36C77624Q0182 for the SCIP IDIQ, with an initial task order for FY2026-27 support. The solicitation has a NAICS code of 541611 and a small business size standard of $24.5 million.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

TaskDeliver-ableSummary Item Description
(see PWS text for full description)Pertains to Fiscal YearQuantityPWS Deliverable Period - # of calendar days After Award
(approx. dates and subject to change)1-Jun-24required date
Task One:
Provide a PMP and BriefingOnePMP and Briefing2027Two: one PMP, including schedule and one Briefingwithin 7 calendar days after award7
Task Two:
Provide Program Management and Process Management Support throughout the PoPTwoProvide program management and process support throughout the PoP; including development of SCIP guidance, gap data, program definitions, and process requirements; SCIP correspondence. For the 2027 process, Contractor shall also support additional efforts necessary to revise processes, schedules, and procedures necessary to transition from SAT 1.0 to SAT 2.0.As appropriateAs needed through PoPFirst meeting: within 136 calendar days after award13610/15/24
Task Two (cont'd):

Lead programmatic process / program excecution in conjunction with VA officials throughout Period of Performance: Three Maintenance and distribution of the SCIP schedules and milestones; conduct / support bi-weekly SCIP process management (up to 24) meetings by leading status calls; conduct Ad Hoc meetings (up to 40) as needed. As appropriate Multiple, no more than regularly scheduled 24 status updates scheduled throughout the Period of Performance.

Up to 40 ad hoc meetings necessary for process support

As requested Support First meeting: within 136 calendar days after award

Regularly scheduled meetings to take place every two weeks and adjusted as needed.

Ad Hoc meetings and deliverables as requested by PMO13610/15/24
Task Two (cont’d):

Provide Program Management and Records Management Support for the SCIP Process and cycle years, which pertains to previous and future SCIP cycle years, as appropriate for the contract period. Four Save SCIP artifacts, records, and business products, from the SCIP- related activities throughout the contract period, to the SCIP databases including the SharePoint site and to the SCIP Automated Tool. As appropriate For 2027 SCIP

Per the volume described in the task for the deliverable in the main text of the PWS.Within 136 calendar days of documentation being in final form. Dates will vary throughout the contract period, depending on finalization dates.13610/15/24
Task Two (cont’d):
Maintain the SharePoint site used to facilitate the SCIP process thoroughout the period of performance.FiveManage/maintain appropriate identified user and stakeholder groups and their respective permission levels within the SCIP SharePoint; dispositon of group structures to ensure old users do not have unnecessary permissions;As appropriateFor 2027 SCIP
Per the volume described in the task for the deliverable in the main text of the PWS.Within 136 calendar days of documentation being in final form. Dates will vary throughout the contract period, depending on finalization dates.13610/15/24
Task Two (cont’d):
Calculate and or validate gap data supporting the SCIP processSixCalculate and or validate gap data and format for entry into the SCIP Tools for use in the 2027 processAs appropriateFor 2027 SCIP
Per the volume described in the task for the deliverable in the main text of the PWS.Within 167 calendar day after award16711/15/24
Task Three:

Develop new and or update up to five (5) separate field training materials packages necessary to execute the SCIP processes. Seven Develop training materials (slides and documents) necessary to support SCIP processes and on-line training sessions performed by OAEM. Materials planned for 2027 include: SCIP Overview training (AKA SCIP Basics); Combined action plan and business case development training; SAT 2.0 Training; and CEA training. 2027 2027 SCIP Deliverables (subject to change)

Two for SCIP Basics materials (one draft and one final product)

Two for SCIP / SAT 2.0 Training (one draft and one final product)

Two for combined Action Plan / Business case training materials (one draft and one final product)

Two for CEA slides (one draft and one final product) 2027 SCIP Deliverables

SCIP Basics materials: Draft: Within 160 calendar days after award; final Within 165 calendar days after award

SAT 2.0 Training Slides: Draft: Within 160 calendar days after award; final Within 165 calendar days after award

SCIP Combined Action Plan / Business case development materials: Draft within 160 calendar days after award; final within 165 days after award

CEA development training materials: Within 175 calendar days after award; Final CEA slides: Within 180 calendar days after award16711/15/24
Task four: Develop / maintain SCIP decision process
eightSupport / facilitate updates to SCIP decision criteria definitions2027 / 2028One set each of draft and final decision criteria definitionsFor FY 2027 SCIP (subject to change since this is not dependent on regular SCIP schedule
150-170 calendar days from award15311/1/24
Task four, cont'd: Develop / maintain SCIP decision process
nineUpdate, maintain, archive, and represent the draft and final decision criteria throughout PoP2027 / 2028One set each of draft and final decision criteria definitions maintained as described in the task for the deliverable in the main text of the PWS.For FY 2027 SCIP
Within 150 calendar days and Continuous throughout PoPcontinous throughout PoP
Task four, cont'd: Develop / maintain SCIP decision process
tenProvide two (2) priority weighting sessions for development of 2 decision models. Up to Eight (8) sessions total.

NOTE: Dates will change based on Board and Panel member’s availability and updates to the SCIP schedule 2027 / 2028 No more than eight For FY 2027 SCIP

240-270 calendar days from award2452/1/25
Task four, cont'd: Develop / maintain SCIP decision process
elevenUpdate, maintain, archive, and represent the draft and final decision models with weights for Capital programs throughout PoP2027 / 2028Three decision models (lease, construction, maintenance) with multiple representations (MS Word, VISIO, PDF, with and without weights) maintained as described in the task for the deliverable in the main text of the PWS.For FY 2027 SCIP
240-270 calendar days from award2452/1/25
Task four, cont'd: Develop / maintain SCIP decision process
twelveDocuments describing the decision and scoring process for each capital program by threshold, the submission requirements, business case questions/ requirements, gap data requirements, and scoring methodology for both panel and data scored criteria.2027 / 2028As described in PWS, draft and final documents describing decision process for each programFor FY2027 SCIP
Est Start to finish: 240-270 calendar days from award15311/1/24
Task five:

Provide updates of SCIP cost-effectiveness analysis (CEA) templates with included cost estimate sheet that is also formatted as a stand-alone file. Thirteen Update the prior SCIP cycle CEA template for VHA projects, as appropriate, including the stand-alone cost estimate sheet, and test the template prior to distribution of the signed SCIP Business Case Application call memorandum. 2027 Provide up to Five: Up to three iterations of draft VHA CEA templates, one final VHA CEA template, and one final separate VHA cost estimate sheet. 220 calendar days after award for draft (s)CEA template - depending on release of economic assumptions

225 calendar days after award for draft (s)CEA template2281/15/25
Task five (cont'd):

Provide updates of SCIP cost-effectiveness analysis (CEA) templates with included cost estimate sheet that is also formatted as a stand-alone file. fourteen Using the previous SCIP cycle CEA template, create separate templates for VBA, NCA, and possibly OIT projects that include specialized features unique to those office’s projects. 2027 Provide up to Five iterations of each template for VBA, NCA and possibly OIT: Up to three draft iterations of the VHA CEA templates, one final VHA CEA template, and one final separate VHA cost estimate sheet. 220 calendar days after award for draft (s)CEA template - depending on release of economic assumptions

225 calendar days after award for draft (s)CEA template2281/15/25
Task six:
Provide Large Group TrainingFifteenProvide up to 12 large group training sessions202712All Training to Support 2027 SCIP Process: 160-220 calendar days after award16711/15/24
Task Seven:

Provide “Help Desk” Support to the SCIP Users through Project development timeframe Sixteen Provide technical support (via e-mail and telephone) as the SCIP Users complete action plan projects, business case applications, cost estimate sheets, and CEA templates. See text of PWS for more details and the table in the text of the PWS for guidelines for the Help Desk representative’s expected level of help to be provided (Approach). 2027 For 2027 SCIP

One Help Desk support function staffed 8:00 am to 6:00 pm EST/EDT, Monday through Friday (except Gov’t holidays). For 2027 SCIP

Throughout project development timeframe: Estimated to be 165-365 calendar days after award16711/15/24
Task Seven, cont'd:

Provide “Help Desk” Support to the SCIP Users through Project development timeframe Seventeen Project logs of business cases requiring remediation and specific actions taken to correct projects ahead of completion of the final SCIP Business case submission milestone. 2027 For 2027 SCIP

Support to Admins and Staff Office Users As Needed. May involve 100's of projects. For 2027 SCIP

Throughout project development timeframe: Estimated to be 165-365 calendar days after award3656/1/25
Task Eight:
Provide program management support to test and deploy new programatic functionality being implemented in SCIP Automated Tool (SAT) functionality and small group training on how to enter projects in the SATEighteenSupport implementation/deployment of programmatic functionality and provide small group training on how to enter projects in the SAT 2.0.2027As needed through PoP150 calendar days and continous through PoP after award15311/1/24
Task Nine:

Provide/Faciliate/Conduct Initial Capital Plan Validation Nineteen Update checklist templates for initial project/plan reviews, including subject matter expert team (SME) review templates. 2027 For FY2027 SCIP

One draft set of review templates and one final product ready to be used for the actual AP review. For FY2027 SCIP

250 calendar days from award for first draft of checklist templates for validity review

260 calendar days from award for final checklist templates for validity review2592/15/25
Task Nine (cont'd):

Provide/Faciliate/Conduct Initial Capital Plan Validation Twenty Support project level validations efforts by reviewing up to 6000 projects.

Consolidate / distribute checklist templates into Excel and/or Word workbooks for corrections. 2027 For FY2027 SCIP

Up to 6000 completed project reviews

Two – one draft set of completed/consolidated workbooks and one final set for distribution to SCIP Users. For FY2027 SCIP

280 calendar days from award for first draft AP validity review packages for dist. to Field

320 calendar days from award for first draft AP validity review packages for dist. to Field2873/15/25
Task Nine (cont’d):

Provide/Faciliate/Conduct Initial Capital Plan Validation Twenty One Create Content and support Panel Review Process 2027 For FY2027 SCIP

As described in PWS For FY2027 SCIP

250 calendar days from award for first draft AP validity review packages for dist. to Field

290 calendar days from award for first draft AP validity review packages for dist. to Field2873/15/25
Task Ten:

Conduct bi-weekly performance reporting during project development milestones. Twenty Two Conduct bi-weekly project/plan reviews after initial capital plan submittal until final submission due date 2027 For FY2027 SCIP

As described in PWS For FY2027 SCIP

180 calendar days from award

430 calendar days from award - Final submission4268/1/25
Task Eleven:

Provide support for validation of Business Cases, to include validation checklists, training materials, selected validation review, and secondary validation review. Twenty Three Develop Business Case validation checklists BC validity training, as described in the main text of the PWS. 2027 For FY2027 SCIP

One draft and one final set of validation checklists. For FY2027 SCIP

320 calendar days from award for draft submission of validation checklists and draft BCA validation training materials

340 calendar days from award for final validation checklists and final BCA validity training materials3184/15/25
Task Eleven (cont’d):
Provide support for validation of Business Cases, to include validation checklists, training materials, selected validation review, and secondary validation review.Twenty FourComplete business case validations as described in the main text of this PWS.

This is known as Initial Validity. 2027 For FY2027 SCIP

Two (One draft and one final set of completed and compiled validation reviews) For FY2027 SCIP

350 calendar days from award for draft completion of 1st validity

370 calendar days from award for final completion of 1st validity and upload to SharePoint folders for distribution.3485/15/25
Task Eleven (cont’d):
Provide support for validation of Business Cases, to include validation checklists, training materials, selected validation review, and secondary validation review.Twenty FiveConduct secondary review and re-validation (second and final validity) of final business cases, as described in the main text of this PWS.2027For FY2027 SCIP

Two (one draft validity review workbook; one final validity review workbook) For FY2027 SCIP

370 calendar days from award for draft workbook

Final - 380 calendar days from award for final workbook3846/20/25
Task Twelve: Support processes necessary to develop budget year scored project lists.Twenty Six
Support OAEM Program management office efforts to score and develop and finalized project priority lists and materials/documents necessary to gain approvals through VA governance processes.2027For FY 2027 SCIP

Completed, compliant budget year scored project lists. Per the volume described in the task for the deliverable in the main text of the PWS. For FY2027 SCIP

Est Start to finish: 390-500 calendar days from award5791/1/26
Task Thirteen:

Provide reports of the SCIP Action Plan Submissions for both the OMB and Congressional Budget submissions. Twenty Seven Action Plan summaries, graphs and charts, and report materials.

This is known as the SCIP SAT project database file.

OMB Budget is officially titled, VA Construction Budget, Long Range Capital Plan, and Appendix. 2027 For FY 2026 and 2027 SCIP

Per volume described in the task for the deliverables in the main text of the PWS. For FY 2026 and 2027 SCIP

OMB: 80 calendar day from award (Aug 23, 2024)

Congressional:200 calendar days from award (Dec 27, 2024)19712/15/24
Task Fourteen:

Consolidate reporting using SCIP data and products where available per OMB M-20-3: Implementation of Agency-wide Real Property Capital Planning Twenty Eight Develop report based upon OMB M-20-3: Implementation of Agency-wide Real Property Capital Planning: 2027 For FY 2026 and 2027 SCIP

Per volume described in the task for the deliverables in the main text of the PWS. Draft Due Approx:80 calendar days after award (sept 2024)

Final Due after settlement: Approx 200 calendar days after award (Jan/Feb 2025)19712/15/24
Task Fifteen: Provide SCIP Program Office support for emergent tasks within 24-48 hours of requests (or as agreed) throughout period of performanceTwenty NineDraft responses for up to 30 separate inquiries by stakeholders based on OAEM directional guidance in MS Word format.2027Responses for up to 30 sets of questions from stakeholders.Throughout PoP, upon request
Task Fifteen, cont'd: Provide SCIP Program Office support for emergent tasks within 24-48 hours of requests (or as agreed) throughout period of performanceThirtyDraft analyses based on data in SCIP and related systems as requested in Excel Format for up to 40 separate analyses as requested by OAEM staff.2027Up to 40 separate analysesThroughout PoP, upon request
Task Sixteen: Provide OAEM Program Office support for program managmenent, reporting, analytics required for three (3) performance metrics used to measure performance of VA capital programs.Thirty OneProvide program management support for three (3) capital program performance metrics throughout PoP2027Per volume described in the task for the deliverables in the main text of the PWS.For FY 2027 SCIP (subject to change since this is not dependent on regular SCIP schedule

150-170 calendar days from award through PoP Task Sixteen, cont'd: Provide OAEM Program Office support for program managmenent, reporting, analytics required for three (3) performance metrics used to measure performance of VA capital programs. Thirty Two Develop reporting required for three (3) capital program performance metrics throughout PoP 2027 Per volume described in the task for the deliverables in the main text of the PWS. For FY 2027 SCIP (subject to change since this is not dependent on regular SCIP schedule

150-170 calendar days from award through PoP Task Sixteen, cont'd: Provide OAEM Program Office support for program managmenent, reporting, analytics required for three (3) performance metrics used to measure performance of VA capital programs. Thirty Three Conduct analyses and data management necessary for establishment and maintenance of the FCA reduction target performance metric throughout PoP 2027 Per volume described in the task for the deliverables in the main text of the PWS. For FY 2027 SCIP (subject to change since this is not dependent on regular SCIP schedule

150-170 calendar days from award through PoP

Task Seventeen: Development and maintanance of SCIP and capital planning-related Standard Operating Procedures (SOPs):Thirty FourDevelop three new standard operating procedures for SCIP and budget related processes.2027Three Standard Operating Procedure process documentsUpon Request and negotiated timeframe, throughout the PoP
Task Seventeen, cont'd: Development and maintanance of SCIP and capital planning-related Standard Operating Procedures (SOPs):Thirty FiveMaintain up to Six (6) Standard operating procedures or alike for SCIP and capital budget related processes.2027Six (6) updated Operating Procedure process documents or alikeUpon Request and negotiated timeframe, throughout the PoP
Task Eighteen: Provide SCIP survey support.Thirty SixConduct SCIP Training Surveys and Reporting2027For FY2027 SCIP

Development of 1 SCIP Survey

Execution of 1 SCIP survey including capture of feedback provided

1 report based on feedback from SCIP Survey For FY 2027

Develop Survey: Approx. 180 calendar days from award

Execute Survey and Collect Input: Approx. 210 calendar days from award

Develop final report: Approx. 240 calendar days from award18312/1/24
Task Eighteen, cont'd: Provide SCIP survey support.Thirty SevenQuarterly consolidated customer satisfaction survey and reporting2027For FY2027 SCIP

Execution of SCIP customer satisfaction survey throughout PoP

Quarterly reporting based on consolidation and analysis of customer service feedback For FY 2027

Continuous surveying throughout PoP for duration of FY2027 SCIP

Quarterly reporting on feedback for process Task Nineteen: Provide SCIP program health assessment development and reporting support. Thirty Eight Completed Program Health Report development process. 2027 For SCIP 2027

1 process flow for assessment of SCIP process For FY 2027

Develop Program Assessment Process Document and Template: Approx. 250 calendar days from award2462/2/25
Task Nineteen, cont'd: Provide SCIP program health assessment development and reporting support.Thirty NineCompleted Program Health Report template.2027For SCIP 2027

Completed Template For FY 2027

Completed Template: Approx. 450 calendar days from award4579/1/25
Task Nineteen, cont'd: Provide SCIP program health assessment development and reporting support.Forty2024 Program Health Report, reflecting assessments performed through September 2024.2027For SCIP 2027

1 Report For FY 2027

Report: Approx. 500 calendar days from award51811/1/25
Task Twenty: Provide support for the tracking and execution of SCIP approved construction projects from the SCIP processes.Fourty OneMaintain Tracking Database and Conduct Required ReportingAs appropriateMonthly (may be canceled) and as needed for 12 months from date of awardTwelve months from date of award06/1/24
Task Twenty, cont'd: Provide support for the tracking and execution of SCIP approved construction projects from the SCIP processes.Fourty TwoAttend and support up to 18 meetings including minutes and milestone reportsas appropriateUp to 18 instances from date of awardTwelve months from date of award
Task Twenty One: Provide support for the implementation and reporting of annual execution metrics for the Major, Minor, and Seismic programs.Fourty ThreeMaintain Tracking Database, to include Historical Data and Conduct Required Reportingas appropriateUp to 18 separate meetings and 18 separate reporting instances for 12 months from date of awardTwelve months from date of award

&"-,Bold"&14 &"-,Bold"&12SCIP IDIQ – SCIP 2025 Task order: FY 2025 Strategic Capital Investment Planning (SCIP) Process Support and Execution

ATTACHMENT A:

SCHEDULE OF DELIVERABLES AND DATES

&P of &N

File details come from the government source that posted it. Updated .