Statement of Work (SOW) Project: Pineville Clear Span Hydraulic Press Demolition

GENERAL INFORMATION

1.0 Scope of Work: Demolish and remove two hydraulic presses, one oil heater and tank, a steel storage rack and remove an oven from the Clear Span Building at the Alexandria Forestry Center in Pineville, LA.

2.0 Background: The Alexandria Forestry Center, located at 2500 Shreveport Highway in Pineville, Louisiana, is a large facility that is home to the Kisatchie National Forest Supervisor’s Office (SO) as well as personnel from multiple research units of the Southern Research Station (SRS).

The Clear Span Building contains two built in hydraulic presses that are surplus to the Government’s needs. Press #1’s overall dimensions (including piping, valves, and tanks) are approximately 5-ft x 10-ft x 9 ft. Press #2’s overall dimensions (including piping, valves, and tanks) are approximately 5-ft x 7-ft x 9-ft. Press #2 also includes a separate tank and heater approximately 5-ft x 6-ft x 10-ft. The hydraulic tanks have been emptied of oil, but hydraulic oil remains in the cylinders, hoses, and piping. Electrical service has been disconnected from the presses. The insulation for the presses’ plumbing was found to contain Asbestos Containing Materials (ACM). The ACM has been removed and the asbestos survey and abatement reports will be provided to the contractor. The steel storage rack is approximately 5-ft x 5-ft x 12-ft in dimension and is bolted to the adjacent wall. The oven is a Blue M, Model MP-326G-HP, free standing unit that has had electrical service disconnected.

CONTRACTOR REQUIREMENTS

3.0 Technical Requirements/Tasks:

The Contractor shall provide all personnel for this project, to include labor, transportation, tools, and equipment to demolish and remove Press #1 (including piping, valves, and tanks), Press #2 (including piping, valves, and tanks), remote tank and heater, the steel storage rack, and the oven. The Contractor shall select the type of demolition, whether by hand or machinery, or a combination of both. The contractor shall be responsible for any damage to the Clear Span building itself during the demolition process.

· The contractor shall remove and dispose of all hydraulic oil in accordance with all applicable federal and state guidelines and regulations.

· Cut any anchors and piping in the concrete floor flush with floor level.

· All building materials shall become the property of the Contractor and removed from Government property. All work undertaken under this Scope of Work shall be performed in compliance with all applicable OSHA Regulations for protection of the workers and public.

· Existing waste bins/dumpsters maintained by the Forest Service shall not be used for disposal of materials generated from this work.

· Contractor waste bins shall be removed from the Government premises as soon as practicable after the work is completed.

4.0 Government Furnished: N/A 5.0 Deliverables / Schedule:

Period of Performance: The period of performance for this work shall be 30 days from date of contract award.

Site Access: Access to the work areas shall be coordinated with the Point of Contact (POC), Mark Gremillion, (318) 446-4310, mark.gremillion@usda.gov, and Adam Gatlin, 318-201-2327, adam.gatlin@usda.gov . In general, the site work areas will be available during normal business hours, 08:00 – 16:30 CDT, Mon – Fri. Arrangement for work outside of these hours shall be made with the POC.

6.0 Travel: N/A 7.0 Contractor Supervision:

The Contractor’s employees performing services as described herein shall be controlled, directed, and supervised, at all times, by the Contractor. Contractor management will ensure that the employees properly comply with the performance work standards outlined in this Statement of Work. The work set forth may not be interpreted or implemented in any manner that results in the Contractor creating or modifying Federal Policy. The Government will control access to the facilities and will perform the inspection and acceptance of the completed work. The term Contractor as applied herein includes Subcontractors and Trades People.

8.0 Security Requirements: N/A 9.0 Data Rights: N/A 10.0 Section 508 – Electronic and Information Technology Standards: N/A

11.0 Safety:

All work undertaken under this Statement of Work shall be performed in compliance with all applicable OSHA Regulations for protection of the workers and public.

12.0 Utilities:

Electric service (120 VAC) is available in the building.

13.0 Applicable Licenses, Codes, and References:

All work shall be in compliance with the following applicable codes, but not limited to:

· International Building Code

· International Existing Building Code

· International Mechanical Code

· International Plumbing Code

· International Fire Code

· National Electric Code

· Applicable Federal and State laws, standards, and codes for disposal of hazardous waste

14.0 Additional Information

The Contracting Officer’s Representative (COR) for this contract is Jason Thompson, 828-215-7974, jason.d.thompson@usda.gov.