Attachment 3 - Milestone Payment Schedule Template.xlsx
XLSX spreadsheet 21 KB Posted
- Attached to
- Intersection Safety Systems (ISS) Prototyping Federal contract opportunity
- Solicitation number
- 693JJ3-26-BAA-0004
About this file
This file is a Milestone Payment Schedule Template for the Intersection Safety Systems (ISS) Prototyping solicitation (693JJ3-26-BAA-0004) issued by the Department of Transportation Federal Highway Administration. The template outlines a two-phase, Fixed-Price (FFP) contract structure for developing and testing intersection safety systems to address pedestrian fatalities at traffic intersections.
Phase 1 encompasses concept development, approval, testing, and operational readiness activities across seven milestones (CLINs 1-1 through 1-7). Key Phase 1 deliverables requiring acceptance include final Concept of Operations documentation with comment resolution, final test plans, demonstration summaries, operational readiness summaries, and documented code/data packages aligned with DataHub/CodeHub guidelines. Phase 2 is structured as an optional phase with six milestones (CLINs 2-1 through 2-7) focused on site engagement, deployment planning, scenario testing, mitigation response validation, field deployment, and operational impact assessment. Critical Phase 2 deliverables include operational scenario portfolios, mitigation response evaluation reports, operational impact reports, and updated code/data documentation. The template includes columns for CLIN identification, task descriptions, milestone descriptions, 508 accessibility compliance requirements, quantity, unit pricing, and total pricing, with a designated grand total of $0.00 for cost breakdown assumptions. The schedule establishes biweekly checkpoint reporting and progress summaries throughout both phases to track development and deployment activities.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Complete Q A_ISS Prototyping.xlsx | XLSX spreadsheet | |
| 693JJ3-26-BAA-0004_ISS Prototyping.pdf | ||
| Attachment 1 - Draft Performance Work Statement.docx | DOCX document | |
| Attachment 2 - Small Business Subcontracting Plan Template.doc | DOC document | |
| Attachment 4 - Q A Template.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Milestone Payment Schedule
| Attachment 3 Milestone Payment Schedule Template | ||||
| Milestone Payment Schedule | ||||
| CLIN | TASK | MILESTONE DESCRIPTION | ||
| (Based on Acceptance of Final Deliverables Unless Otherwise Specified) | 508 Compliance Requirement | QUANTITY | PRICE PER UNIT | TOTAL PRICE |
| 00101 |
Phase 1 Pricing: FFP
| 1-1 | Kickoff Meeting | No | |
| Project Management Plan | No | ||
| Monthly Progress Reports | No | ||
| Bi-Weekly Agenda/Notes | No | ||
| 1-2 | Concept of Operations (ConOps) Walkthrough Workbook | No | |
| ConOps Walkthrough | No | ||
| Final ConOps* and Comment Resolution Log | Yes* | ||
| 1-3 | Human Use Approval and IRB Summary | No | |
| Final Test Plan* and Comment Resolution Log | Yes* | ||
| 1-4 | Checkpoint Summary Report with Updated Test Plan (if needed) (biweekly) | No | |
| 1-5 | Demonstration Summary* and Comment Resolution Log | Yes* | |
| 1-6 | Operational Readiness Summary | Yes | |
| 1-7 | Code/Data Plan, including Comment Resolution Log | No | |
| Documented Data and Code including supporting documents and metadata (per the C/DP) | Per the DataHub/CodeHub guidelines | ||
| PHASE 1 TOTAL: | |||
| 10101 |
Optional Phase 2
| FFP | 2-1 | Phase 2 Kickoff Meeting | No | ||
| Project Management Plan (Revised) | No | ||||
| Monthly Progress Reports | No | ||||
| Bi-Weekly Agenda/Notes | No | ||||
| 2-2 | Site Engagement and Deployment Plan* | ||||
| and Comment Resolution Log | Yes* | ||||
| Bi-weekly Site Engagement and Deployment Progress Summaries | No | ||||
| 2-3 | Operational Scenario Entry (per identified scenario) | No | |||
| Closed Testbed Scenario Approximation Report (per identified scenario) | No | ||||
| Operational Scenario Portfolio* | |||||
| and Comment Resolution Log | Yes* | ||||
| 2-4 | Mitigation Response Validation Plan | No | |||
| Prototype Refinement Results Portfolio for Each Experiment, and Comment Resolution Log | No | ||||
| Mitigation Response Evaluation Report | Yes | ||||
| 2-5 | Field Deployment and Demonstration Plan | Yes | |||
| Real-Time Mitigation Working Memorandum | No | ||||
| Operational Impacy Summary, at completion of each implementation | No | ||||
| Operational Impact Report* | |||||
| and Comment Log | Yes* | ||||
| 2-6 | Deployment Readiness Summary* | ||||
| and Comment Log | Yes* | ||||
| 2-7 | Code/Data Plan Updated and Comment Log | No | |||
| Documented Data and Code, including supporting documents and metadata (per the C/DP) | Per the DataHub/CodeHub guidelines | ||||
| PHASE 2 TOTAL: | |||||
| GRAND TOTAL | $0.00 |
Assumptions
Cost Breakdown