PROJECT NUMBER: ULDF 18-0323AE
CONSTRUCTION SCHEDULE
ID TASK NAME DURATION 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 - 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65
1 MOBILIZATION 3 WEEKS
2 SHOP DRAWINGS/SUBMITTALS 6 WEEKS
3 INITIAL MATERIAL DELIVERIES 12 WEEKS
4 CONSTRUCTION 50 WEEKS
6 PROJECT CLOSEOUT 4 WEEKS
AIR FORCE RESEARCH LABORATORY - ROME RESEARCH SITE
May 13, 2019REPAIR AHUS, B106
FA875120B0002
ATTACHMENT 3