Attachment 3 - CMMS Proposed Project Schedule Final.docx

DOCX document 2 MB Posted

Attached to
Computerized Maintenance Management System (CMMS)
Solicitation number
BPM059766
Issued by
Montgomery County, Maryland

About this file

This is a proposed project schedule attachment for Montgomery County Public Schools' (MCPS) Computerized Maintenance Management System (CMMS) procurement and implementation. The project encompasses a complete system replacement spanning from November 2026 through February 2028, with the RFP issuance targeted for late November 2026, proposal receipt in January 2027, vendor selection notification in February 2027, and official contract award in March 2027. The implementation timeline includes discovery and requirements validation in April 2027, system configuration from April through June 2027, user acceptance testing in July through August 2027, pilot deployment in August through September 2027, staff training in October through November 2027, and official go-live in December 2027. The project requires comprehensive governance structures including monthly Executive Steering Committee meetings from February 2027 through launch, bi-weekly Project Management Team meetings from February through November 2027, weekly configuration workshops from March through June 2027, and bi-weekly data migration meetings from April through September 2027.

The proposed schedule allocates approximately 10 months for implementation activities and 4 months for testing and training before full operational transition. MCPS will maintain its existing CMMS provider on a month-to-month basis through the new system's December 2027 launch to ensure operational continuity, facilitate data migration, enable comprehensive testing, and allow sufficient time for staff training. The project includes interface development and testing to integrate the new platform with MCPS financial, human resources, purchasing, and reporting systems, with post-go-live hypercare support and optimization extending through February 2028. Major milestones include configuration completion by June 2027, user acceptance testing completion by August 2027, staff training completion by October-November 2027, and final go-live readiness reviews scheduled at 30-day, 14-day, and 7-day intervals prior to December 2027 launch.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment 3 – Proposed Project Schedule – RFP 7923.2 Montgomery County Public Schools (MCPS) Computerized Maintenance Management System (CMMS) Proposed Project Schedule: November 2026 - February 2028

Phase
Key Activities
Target Dates
Project Initiation & Procurement
Finalize CMMS requirements, scope, evaluation criteria, and issue RFP
Late November 2026
Proposal Review & Selection
Receive proposals, conduct evaluations, demonstrations, reference checks, and shortlist vendors
January 2027
Security & Compliance Review
Technology, cybersecurity, legal, procurement, and data privacy review of selected solution
February 2027
Vendor Selection Notification
Notify selected vendor and begin contract negotiations
February 2027
Contract Award
Official contract execution and authorization to proceed
March 2027
Project Kickoff
Executive kickoff meeting, governance structure, communication plan, project charter approval
Late March to Early April 2027
Discovery & Requirements Validation
Business process review, workflow mapping, asset hierarchy validation, reporting requirements
April 2027
System Configuration
Configure preventive maintenance, work order workflows, asset management, inventory, labor tracking, dashboards, and mobile platform
April 2027
Data Preparation & Migration Planning
Asset inventory validation, data cleansing, migration strategy, interface requirements
April-May 2027
Implementation Workshops
Weekly configuration meetings with Facilities Maintenance, Service Centers, IT, Procurement, and vendor implementation team
March-June 2027
Interface Development & Testing
Integration with MCPS financial, HR, purchasing, and reporting systems (as applicable)
May-June 2027
System Testing
User Acceptance Testing (UAT), workflow validation, security testing, defect resolution
July-August 2027
Pilot Deployment
Pilot implementation with selected maintenance shops and regional service center users
August-September 2027
Training Development
Training materials, user guides, standard operating procedures, e-learning resources
August-September 2027
Staff Training
Train administrators, supervisors, planners, dispatchers, technicians, warehouse staff, and end users
October-November 2027
Go-Live Readiness Review
Final data migration, cutover planning, readiness assessments, executive approval
November 2027
CMMS Launch
Official deployment for all MCPS Facilities Maintenance operations
December 2027
Post-Go-Live Support
Hypercare support, issue resolution, optimization, performance monitoring
December 2027-February 2028

Major Milestones

Milestone
Date
RFP Issued
November 2026
Proposals Received
January 2027
Security Review Complete
February 2027
Vendor Notification
February 2027
Contract Award
March 2027
Project Kickoff
Late March to Early April 2027
Configuration Complete
June 2027
User Acceptance Testing Complete
August 2027
Staff Training Complete
October-November 2027
Go-Live
December 2027
Post Go-Live Support
December 2027-February 2028

Transition Strategy MCPS will maintain the existing CMMS provider on a month-to-month basis from the expiration of the current agreement through implementation and launch of the new platform. This approach minimizes operational risk, ensures continuity of maintenance operations, preserves work order functionality, and allows sufficient time for data migration, testing, and staff training before transitioning to the new system in December 2027.

Recommended Governance Meetings Executive Steering Committee

· Monthly from February 2027 through Launch

· Director of Maintenance, Procurement, IT, Finance, Vendor Executive Sponsor Project Management Team

· Bi-weekly from February through November 2027

· Review schedule, risks, decisions, and deliverables Configuration Workshops

· Weekly March through June 2027

· Asset management, preventive maintenance, inventory, reporting, mobile application, dashboards Data Migration Meetings

· Bi-weekly April through September 2027 Training & Change Management Meetings

· Bi-weekly August through November 2027 Go-Live Readiness Reviews

· October 2027

· Conducted at 30-day, 14-day, and 7-day intervals prior to launch This schedule provides approximately 10 months of implementation activities, 4 months of testing and training, and a controlled transition to full MCPS operation of the new CMMS platform by December 2027.