Attachment 3 – Proposed Project Schedule – RFP 7923.2 Montgomery County Public Schools (MCPS) Computerized Maintenance Management System (CMMS) Proposed Project Schedule: November 2026 - February 2028
| Phase |
| Key Activities |
| Target Dates |
| Project Initiation & Procurement |
| Finalize CMMS requirements, scope, evaluation criteria, and issue RFP |
| Late November 2026 |
| Proposal Review & Selection |
| Receive proposals, conduct evaluations, demonstrations, reference checks, and shortlist vendors |
| January 2027 |
| Security & Compliance Review |
| Technology, cybersecurity, legal, procurement, and data privacy review of selected solution |
| February 2027 |
| Vendor Selection Notification |
| Notify selected vendor and begin contract negotiations |
| February 2027 |
| Contract Award |
| Official contract execution and authorization to proceed |
| March 2027 |
| Project Kickoff |
| Executive kickoff meeting, governance structure, communication plan, project charter approval |
| Late March to Early April 2027 |
| Discovery & Requirements Validation |
| Business process review, workflow mapping, asset hierarchy validation, reporting requirements |
| April 2027 |
| System Configuration |
| Configure preventive maintenance, work order workflows, asset management, inventory, labor tracking, dashboards, and mobile platform |
| April 2027 |
| Data Preparation & Migration Planning |
| Asset inventory validation, data cleansing, migration strategy, interface requirements |
| April-May 2027 |
| Implementation Workshops |
| Weekly configuration meetings with Facilities Maintenance, Service Centers, IT, Procurement, and vendor implementation team |
| March-June 2027 |
| Interface Development & Testing |
| Integration with MCPS financial, HR, purchasing, and reporting systems (as applicable) |
| May-June 2027 |
| System Testing |
| User Acceptance Testing (UAT), workflow validation, security testing, defect resolution |
| July-August 2027 |
| Pilot Deployment |
| Pilot implementation with selected maintenance shops and regional service center users |
| August-September 2027 |
| Training Development |
| Training materials, user guides, standard operating procedures, e-learning resources |
| August-September 2027 |
| Staff Training |
| Train administrators, supervisors, planners, dispatchers, technicians, warehouse staff, and end users |
| October-November 2027 |
| Go-Live Readiness Review |
| Final data migration, cutover planning, readiness assessments, executive approval |
| November 2027 |
| CMMS Launch |
| Official deployment for all MCPS Facilities Maintenance operations |
| December 2027 |
| Post-Go-Live Support |
| Hypercare support, issue resolution, optimization, performance monitoring |
| December 2027-February 2028 |
Major Milestones
| Proposals Received |
| January 2027 |
| Security Review Complete |
| February 2027 |
| Vendor Notification |
| February 2027 |
| Contract Award |
| March 2027 |
| Project Kickoff |
| Late March to Early April 2027 |
| Configuration Complete |
| June 2027 |
| User Acceptance Testing Complete |
| August 2027 |
| Staff Training Complete |
| October-November 2027 |
| Post Go-Live Support |
| December 2027-February 2028 |
Transition Strategy MCPS will maintain the existing CMMS provider on a month-to-month basis from the expiration of the current agreement through implementation and launch of the new platform. This approach minimizes operational risk, ensures continuity of maintenance operations, preserves work order functionality, and allows sufficient time for data migration, testing, and staff training before transitioning to the new system in December 2027.
Recommended Governance Meetings Executive Steering Committee
· Monthly from February 2027 through Launch
· Director of Maintenance, Procurement, IT, Finance, Vendor Executive Sponsor Project Management Team
· Bi-weekly from February through November 2027
· Review schedule, risks, decisions, and deliverables Configuration Workshops
· Weekly March through June 2027
· Asset management, preventive maintenance, inventory, reporting, mobile application, dashboards Data Migration Meetings
· Bi-weekly April through September 2027 Training & Change Management Meetings
· Bi-weekly August through November 2027 Go-Live Readiness Reviews
· October 2027
· Conducted at 30-day, 14-day, and 7-day intervals prior to launch This schedule provides approximately 10 months of implementation activities, 4 months of testing and training, and a controlled transition to full MCPS operation of the new CMMS platform by December 2027.