This document provides details regarding a federal contract opportunity to expand a mental health clinic building at the Southern Arizona VA Health Care System in Tucson, Arizona. The Department of Veterans Affairs seeks to award a firm-fixed-price contract through competitive sealed bidding procedures to a Service-Disabled Veteran-Owned Small Business for construction services including demolition, site work, utilities, and architectural, structural, mechanical, plumbing and electrical work. The solicitation is anticipated to be issued in late September or early October 2020, with a period of performance of approximately 600 calendar days from notice to proceed. The magnitude of construction is estimated between $2 million and $5 million. Questions must be submitted by email to the specified point of contact by the date listed in the forthcoming solicitation.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SAVAHCS VA Medical Center VA Project: #678-329 Tucson, AZ Expand Mental Health Clinic, B90
TABLE OF CONTENTS
00 01 10 - 1
DEPARTMENT OF VETERANS AFFAIRS
VHA MASTER SPECIFICATIONS
Section 00 01 10
DIVISION 00 - SPECIAL SECTIONS DATE
00 01 15 List of Drawing Sheets 07-15
DIVISION 01 - GENERAL REQUIREMENTS
01 00 00 General Requirements 12-18 01 32 16.15 Project Schedules (Small Projects – Design/Bid/Build) 04-13 01 33 23 Shop Drawings, Product Data, and Samples 05-17 01 35 26 Safety Requirements 02-17 01 42 19 Reference Standards 05-16 01 45 00 Quality Control 01-18 01 45 29 Testing Laboratory Services 11-18 01 45 35 Special Inspections 04-18 01 57 19 Temporary Environmental Controls 01-11 01 74 19 Construction Waste Management 09-13 01 80 00 Geotechnical Reports 01 91 00 General Commissioning Requirements 10-15
DIVISION 02 – EXISTING CONDITIONS
02 41 00 Demolition 08-17
DIVISION 03 – CONCRETE
03 30 53 (Short-Form) Cast-in-Place Concrete 02-16
DIVISION 04 – MASONRY (Not Used)
DIVISION 05 – METALS
05 05 23 Welding, Structural 05 12 00 Structural Steel Framing 11-18 05 21 00 Steel Joist Framing 11-18 05 31 00 Steel Decking 02-16 05 40 00 Cold-Formed Metal Framing 05-16 05 50 00 Metal Fabrications 08-18
DIVISION 06 – WOOD, PLASTICS, AND COMPOSITES
06 10 00 Rough Carpentry 10-17
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
00 01 10 - 2
07 21 13 Thermal Insulation 10-17 07 22 00 Roof and Deck Insulation 02-16 07 32 13 Concrete Roof Tiles 07 40 00 Roofing and Siding Panels 10-15 07 52 16.11 Cold Adhesive Styrene-Butadiene-Styrene Modified Bituminous
Membrane Roofing 08-16
07 60 00 Flashing and Sheet Metal 07-14 07 71 00 Roof Specialties 10-15 07 84 00 Firestopping 02-16 07 92 00 Joint Sealants 10-17 07 95 13 Expansion Joint Cover Assemblies 02-16
DIVISION 08 - OPENINGS
08 11 13 Hollow Metal Doors and Frames 08-16 08 14 00 Interior Wood Doors 02-16 08 31 13 Access Doors and Frames 02-16 08 34 74 Sound Control Wood Door Assemblies 08 41 13 Aluminum-Framed Entrances and Storefronts 08-16 08 51 13 Aluminum Windows 02-16 08 71 00 Door Hardware 01-16 08 71 13 Automatic Door Operators 02-16 08 80 00 Glazing 10-15
DIVISION 09 – FINISHES
09 05 16 Subsurface Preparation for Floor Finishes 02-15 09 06 00 Schedule for Finishes 04-15 09 22 16 Non-Structural Metal Framing 06-18 09 24 00 Portland Cement Plastering 10-15 09 29 00 Gypsum Board 06-18 09 30 13 Ceramic/Porcelain Tiling 09-15 09 51 00 Acoustical Ceilings 12-18 09 65 13 Resilient Base and Accessories 02-16 09 65 19 Resilient Tile Flooring 05-18 09 91 00 Painting 01-16
DIVISION 10 – SPECIALTIES
10 21 23 Cubicle Curtain Tracks 05-15 10 26 00 Wall and Door Protection 10-15 10 28 00 Toilet, Bath, and Laundry Accessories 02-16 10 44 13 Fire Extinguisher Cabinets 08-18 10 73 16 Canopies 10 81 13 Bird Control Devices
DIVISION 11 – EQUIPMENT
11 73 00 Ceiling Mounted Patient Lift System 01-17
DIVISION 12 – FURNISHINGS
00 01 10 - 3
12 32 00 Manufactured Wood Casework 09-15 12 36 00 Countertops 12-18 12 48 13 Entrance Floor Mats and Frames
DIVISION 13 - SPECIAL CONSTRUCTION
13 05 41 Seismic Restraint Requirements for Non-Structural Components 01-14
DIVISION 14– CONVEYING EQUIPEMENT (Not Used)
DIVISION 21- FIRE SUPPRESSION
21 13 13 Wet-Pipe Sprinkler Systems 06-15
DIVISION 22 – PLUMBING
22 05 11 Common Work Results for Plumbing 07-16 22 05 12 General Motor Requirements for Plumbing Equipment 09-15 22 05 23 General-Duty Valves for Plumbing Piping 09-15 22 07 11 Plumbing Insulation 09-15 22 08 00 Commissioning of Plumbing Systems 11-16 22 11 00 Facility Water Distribution 09-15 22 11 23 Domestic Water Pumps 09-15 22 13 00 Facility Sanitary and Vent Piping 09-15 22 14 00 Facility Storm Drainage 09-15 22 40 00 Plumbing Fixtures 09-15
DIVISION 23 – HEATING, VENTILATING, AND AIR CONDITIONING
(HVAC)
23 05 11 Common Work Results for HVAC 08-17 23 05 12 General Motor Requirements for HVAC and Steam Generation Equipment 08-17 23 05 41 Noise and Vibration Control for HVAC Piping and Equipment 02-15 23 05 93 Testing, Adjusting, and Balancing for HVAC 02-15 23 07 11 HVAC and Boiler Plant Insulation 02-15 23 08 00 Commissioning of HVAC Systems 11-16 23 09 23 Direct-Digital Control System for HVAC 09-11 23 21 13 Hydronic Piping 08-17 23 23 00 Refrigerant Piping 02-15 23 31 00 HVAC Ducts and Casings 03-13 23 34 00 HVAC Fans 02-15 23 36 00 Air Terminal Units 02-15 23 37 00 Air Outlets and Inlets 02-15 23 40 00 HVAC Air Cleaning Devices 02-12 23 74 13 Packaged, Outdoor, Central-Station Air-Handling Units 04-11 23 81 23 Computer-Room Air-Conditioners 04-11
DIVISION 25 – INTEGRATED AUTOMATION (Not Used)
DIVISION 26 – ELECTRICAL
00 01 10 - 4
26 05 11 Requirements for Electrical Installations 01-16 26 05 19 Low-Voltage Electrical Power Conductors and Cables 01-17 26 05 26 Grounding and Bonding for Electrical Systems 01-17 26 05 33 Raceway and Boxes for Electrical Systems 01-18 26 05 41 Underground Electrical Construction 01-17 26 09 23 Lighting Controls 01-18 26 24 16 Panelboards 01-18 26 27 26 Wiring Devices 01-18 26 29 21 Enclosed Switches and Circuit Breakers 01-17 26 51 00 Interior Lighting 01-18 26 56 00 Exterior Lighting 01-18
DIVISION 27 – COMMUNICATIONS
27 05 26 Grounding and Bonding for Communications Systems 06-15 27 05 33 Raceways and Boxes for Communications Systems 10-18 27 15 00 Communications Horizontal Cabling 01-16 27 51 16 Public Address and Mass Notification Systems 10-18 27 52 23 Nurse Call and Code Blue Systems
DIVISION 28 – ELECTRONIC SAFETY AND SECURITY
28 05 00 Common Work Results for Electronic Safety and Security 04-18 28 05 13 Conductors and Cables for Electronic Safety and Security 10-18 28 05 26 Grounding and Bonding for Electronic Safety and Security 09-11 28 05 28.33 Conduits and Backboxes for Electronic Safety and Security 28 13 00 Physical Access Control System 10-11 28 23 00 Video Surveillance 09-11 28 31 00 Fire Detection and Alarm 10-11
DIVISION 31 – EARTHWORK
31 20 11 Earthwork (Short Form) 10-12
DIVISION 32 – EXTERIOR IMPROVEMENTS
32 05 23 Cement and Concrete for Exterior Improvements 08-16 32 12 16 Asphalt Paving 09-15 32 17 23 Pavement Markings 08-16
DIVISION 33 – UTILITIES
33 10 00 Water Utilities 03-17 33 30 00 Sanitary Sewer Utilities 06-13
DIVISION 34 – TRANSPORTATION (Not Used)
LIST OF DRAWINGS
00 01 15 - 1
SECTION 00 01 15
The drawings listed below accompanying this specification form a part of the contract.
Drawing No. Title
GENERAL
90-GI-001 TITLE SHEET
90-GI-002 DRAWING SHEET INDEX
90-GI-003 GENERAL NOTES, ARCHITECTURAL SYMBOLS, AND
ABBREVIATIONS
90-GI-004 ACCESSIBILITY STANDARDS AND TYPICAL MOUNTING
HEIGHTS
90-GI-005 FIRE LIFE SAFETY PLAN
90-GC-100 OVERALL PHASING PLAN
90-GC-101 PHASING PLANS – PHASE 1 DEMOLITION
90-GC-102 PHASING PLANS – PHASE 1 NEW WORK
90-GC-103 PHASING PLANS – PHASE 2
CIVIL
90-C-000 NOTES, ABBREVIATIONS AND LEGEND
90-C-100 TOPOGRAPHY
90-C-200 DEMOLITION
90-C-300 GRADING
90-C-400 EROSION CONTROL PLAN
90-C-401 EROSION CONTROL DETAILS
90-C-500 UTILITIES
90-C-501 SEWER PLAN AND PROFILE
90-C-502 SEWER DETAILS
95-C-000 NOTES AND LEGEND
95-C-100 TOPOGRAPHY
95-C-200 DEMOLITION PLAN
95-C-300 SITE PLAN
95-C-400 GRADING
95-C-500 EROSION CONTROL
95-C-600 DETAILS
00 01 15 - 2
STRUCTURAL
90-S-001 GENERAL NOTES
90-S-101 TYPICAL DETAILS
90-S-102 TYPICAL DETAILS
90-S-103 TYPICAL DETAILS
90-S-201 FOUNDATION PLAN
90-S-202 ROOF FRAMING PLAN
90-S-301 SECTIONS & DETAILS
90-S-302 SECTIONS & DETAILS
90-S-303 SECTIONS & DETAILS
90-S-304 SECTIONS & DETAILS
90-S-401 MOMENT FRAME ELEVATIONS
ARCHITECTURAL
90-AD-101 DEMOLITION PLAN
90-AD-102 CEILING DEMOLITION PLAN
90-AS-100 SITE PLAN
90-AE-101 FLOOR PLAN
90-AE-102 FURNITURE AND EQUIPMENT PLAN
90-AE-103 REFLECTED CEILING PLAN
90-AE-104 ROOF PLAN
90-AE-201 EXTERIOR ELEVATIONS
90-AE-301 BUILDING SECTIONS
90-AE-302 BUILDING SECTIONS
90-AE-303 BUILDING SECTIONS
90-AE-304 WALL SECTIONS
90-AE-305 WALL SECTIONS
90-AE-401 ENLARGED FLOOR PLANS
90-AE-402 INTERIOR ELEVATIONS
90-AE-403 INTERIOR ELEVATIONS
90-AE-501 DETAILS
90-AE-502 DETAILS
90-AE-503 DETAILS
90-AE-504 DETAILS
90-AE-505 DETAILS
90-AE-601 DOOR AND WINDOW SCHEDULES
90-AE-602 FURNITURE AND EQUIPMENT SCHEDULES
00 01 15 - 3
90-AF-101 FINISH FLOOR PLAN
90-AF-601 INTERIOR FINISH LEGEND
90-AF-602 ROOM FINISH SCHEDULE
FIRE PROTECTION
90-FP-001 FIRE PROTECTION GENERAL NOTES AND DETAILS
90-FP-002 FIRE PROTECTION SITE PLAN
90-FD-101 FIRE PROTECTION PIPING DEMO PLAN
90-FP-102 FIRE PROTECTION PIPING NEW PLAN
PLUMBING
90-P-001 PLUMBING FRONT SHEET
90-P-002 PLUMBING SCHEDULES AND WATER CALCULATIONS
90-PD-100 PLUMBING DEMOLITION SITE PLAN
90-PD-101 PLUMBING DEMOLITION CW, HW, & HWR FLOOR PLAN
90-PD-102 PLUMBING DEMOLITION WASTE AND VENT FLOOR PLAN
90-PD-103 PLUMBING DEMOLITION STORM DRAIN FLOOR PLAN
90-PD-104 PLUMBING DEMOLITION ROOF PLAN
90-PP-101 PLUMBING NEW CW, HW, & HWR FLOOR PLAN
90-PP-102 PLUMBING NEW WASTE & VENT FLOOR PLAN
90-PP-103 PLUMBING NEW STORM DRAIN FLOOR PLAN
90-PP-104 PLUMBING NEW WORK ROOF PLAN
90-PP-105 PLUMBING DETAILS
90-PP-106 DEMOLITION AND NEW CW, HW, & HWR RISER DIAGRAMS
90-PP-107 DEMOLITION AND NEW WASTE & VENT RISER DIAGRAMS
90-PP-108 DEMOLITION AND NEW STORM RISER DIAGRAMS
MECHANICAL
90-M-001 MECHANICAL FRONT SHEET
90-MD-101 MECHANICAL DEMOLITION FLOOR PLAN
90-MH-102 MECHANICAL NEW WORK FLOOR PLAN
90-MH-103 MECHANICAL NEW WORK ZONING PLAN
90-MH-104 MECHANICAL NEW WORK ROOF PLAN
90-MP-105 MECHANICAL NEW PIPING FLOOR PLAN
90-MP-106 MECHANICAL HOT WATER SINGLE LINE PIPING DIAGRAM
90-MH-107 MECHANICAL PHASING PLAN PHASE 1
90-MH-108 MECHANICAL PHASING PLAN PHASE 2A
00 01 15 - 4
90-MH-109 MECHANICAL PHASING PLAN PHASE 2B
90-MI-501 MECHANICAL DETAILS
90-MI-502 MECHANICAL DETAILS
90-MI-503 MECHANICAL DETAILS
90-MI-504 MECHANICAL DETAILS
90-MI-601 MECHANICAL SCHEDULES
90-MI-602 MECHANICAL CONTROLS
90-MI-603 MECHANICAL CONTROLS
ELECTRICAL
90-E-001 ELECTRICAL FRONT SHEET
90-E-002 ELECTRICAL SYMBOLS, ABBREVIATIONS AND LEGENDS
90-ED-101 ELECTRICAL DEMO LIGHTING PLAN
90-ED-102 ELECTRICAL DEMO POWER PLAN
90-ED-105 ELECTRICAL DEMO PLAN DATA/COMM & FIRE ALARM
PLAN
90-ED-106 ELECTRICAL DEMO AUXILIARY SYSTEM PLAN
90-ED-108 LIGHTNING PROTECTION DEMO PLAN
90-ED-109 ELECTRICAL DEMO SITE PLAN
90-EL-201 ELECTRICAL NEW LIGHTING PLAN
90-EP-202 ELECTRICAL NEW POWER PLAN
90-EP-203 MECHANICAL EQUIPMENT ELECTRICAL NEW POWER
PLAN
90-EP-204 ELECTRICAL NEW HVAC TERMINAL UNITS PLAN
90-ET-205 ELECTRICAL NEW DATA/COMM PLAN
90-ET-206 ELECTRICAL NEW FIRE ALARM PLAN
90-EY-207 ELECTRICAL NEW AUXILIARY SYSTEM PLAN
90-EY-208 LIGHTNING PROTECTION NEW WORK PLAN
90-E-209 ELECTRICAL NEW SITE PLAN
90-E-501 SINGLE LINE DIAGRAM
90-E-502 PANEL SCHEDULES
90-E-503 NEW NURSE CALL SYSTEM
95-ED-101 ELECTRICAL DEMO B95 LIGHTING PLAN
95-EL-201 ELECTRICAL NEW B95 LIGHTING PLAN
- - - E N D - - -
GENERAL REQUIREMENTS
01 00 00 - 1
SECTION 01 00 00
1.1 SAFETY REQUIREMENTS
Refer to section 01 35 26, SAFETY REQUIREMENTS for safety and infection control requirements.
1.2 GENERAL INTENTION
A. Contractor shall completely prepare site for building operations, including demolition and removal of existing structures, and furnish labor and materials and perform work for Project 678-329, Expand Mental Health Clinic, B90 as required by drawings and specifications.
B. Visits to the site by Bidders may be made in accordance with what is listed in the solicitation and at the discretion of the Contracting Officer.
C. Offices of Schwab Engineering, as Architect-Engineers, will render certain technical services during construction. Such services shall be considered as advisory to the Government and shall not be construed as expressing or implying a contractual act of the Government without affirmations by Contracting Officer or his duly authorized representative.
D. Before placement and installation of work subject to tests by testing laboratory retained by the
Contractor, the Contractor shall notify the Project Engineer in sufficient time to enable testing laboratory personnel to be present at the site in time for proper taking and testing of specimens and field inspection. Such prior notice shall be not less than three work days unless otherwise designated by the Project Engineer.
E. All employees of general contractor and subcontractors shall comply with VA security management program and obtain permission of the VA police, be identified by project and employer, and restricted from unauthorized access.
F. The Key Personnel assigned by the contractor for the performance of work on this contract shall be acceptable to VA in terms of personal and professional conduct and technical knowledge.
Should the assignment to this contract of any person by the contractor be deemed to conflict with the interests of VA, or in the event performance is deemed to be unsatisfactory at any time during the life of the contract, the Contracting Officer may notify the contractor and request the person be removed from the assignment. The reason for removal will be documented and a request to receive key personnel replacement within three (3) business days of the notification will be made.
Replacement of key personnel qualifications shall be equal to or greater than those of the key personnel being replaced. Employment and staffing difficulties will not be justification for failure to meet established schedules. The contractor is required to submit a resume with qualifications for the proposed replacement which shall be approved by the COR and CO prior to the replacement starting work.
01 00 00 - 2
1.3 STATEMENT OF BID ITEM(S)
A. ITEM I, All work shown on drawings and in specifications. Work to be completed in 600 calendar days. New work shall include architectural, civil, structural, plumbing, electrical, mechanical, and fire protection.
B. ITEM II, All work in Bid Item I except delete work associated with Building 95. Work shall be completed in 600 calendar days.
C. ITEM III, All work in Bid Item II except delete the awnings over all of the windows. Work shall be completed in 600 calendar days.
1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR
A. Drawings and contract documents may be obtained from the website where the solicitation is posted. Additional copies will be at Contractor's expense.
1.5 CONSTRUCTION SECURITY REQUIREMENTS
A. Security Plan:
1. The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the project.
2. The General Contractor is responsible for assuring that all sub-contractors working on the project and their employees also comply with these regulations.
B. Security Procedures:
1. General Contractor’s employees shall not enter the project site without appropriate badge.
They may also be subject to inspection of their personal effects when entering or leaving the project site.
2. No photography of VA premises is allowed without written permission of the Contracting
Officer.
3. VA reserves the right to close down or shut down the project site and order General
Contractor’s employees off the premises in the event of a national emergency. The General
Contractor may return to the site only with the written approval of the Contracting Officer.
1.6 OPERATIONS AND STORAGE AREAS
A. The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the Contracting Officer. The Contractor shall hold and save the Government, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.
B. Temporary buildings (e.g., storage sheds, shops, offices) and utilities may be erected by the
Contractor only with the approval of the Contracting Officer and shall be built with labor and materials furnished by the Contractor without expense to the Government. The temporary buildings and utilities shall remain the property of the Contractor and shall be removed by the
01 00 00 - 3
Contractor at its expense upon completion of the work. With the written consent of the
Contracting Officer, the buildings and utilities may be abandoned and need not be removed.
C. The Contractor shall, under regulations prescribed by the Contracting Officer, use only established roadways, or use temporary roadways constructed by the Contractor when and as authorized by the Contracting Officer. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any federal, state, or local law or regulation. When it is necessary to cross curbs or sidewalks, the Contractor shall protect them from damage. The Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.
(FAR 52.236-10)
D. Working space and space available for storing materials shall be as shown on the drawings as determined by the COR.
E. Workers are subject to rules of the Medical Center applicable to their conduct.
F. Execute work so as to interfere as little as possible with normal functioning of Medical Center as a whole, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others. Use of equipment and tools that transmit vibrations and noises through the building structure, are not permitted in buildings that are occupied, during construction, jointly by patients or medical personnel, and Contractor's personnel, except as permitted by the COR where required by limited working space.
1. Do not store materials and equipment in other than assigned areas.
2. Schedule delivery of materials and equipment to immediate construction working areas within buildings in use by Department of Veterans Affairs in quantities sufficient for not more than two work days. Provide unobstructed access to Medical Center areas required to remain in operation.
3. Where access by Medical Center personnel to vacated portions of buildings is not required, storage of Contractor's materials and equipment will be permitted subject to fire and safety requirements.
G. Utilities Services: Where necessary to cut existing pipes, electrical wires, conduits, cables, etc., of utility services, or of fire protection systems or communications systems (except telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR.
H. Phasing:
The Medical Center must maintain its operation 24 hours a day 7 days a week. Therefore, any interruption in service must be scheduled and coordinated with the COR to ensure that no lapses in operation occur. It is the CONTRACTOR'S responsibility to develop a work plan and schedule detailing, at a minimum, the procedures to be employed, the equipment and materials to be used, 01 00 00 - 4 the interim life safety measure to be used during the work, and a schedule defining the duration of the work with milestone subtasks.
To ensure such executions, Contractor shall furnish the COR with a schedule of approximate phasing dates on which the Contractor intends to accomplish work in each specific area of site, building or portion thereof. In addition, Contractor shall notify the COR two weeks in advance of the proposed date of starting work in each specific area of site, building or portion thereof.
Arrange such phasing dates to ensure accomplishment of this work in successive phases mutually agreeable to the Medical Center Director, the COR, and Contractor, as follows and as identified in the drawings. The work to be outlined shall include, but not be limited to:
There will be two phases:
1. Phase 1: This phase includes the demolition of the site area, partial demolition of building exterior and demolition of room 1216 within the Phase 1 limit of work. Also, within this phase is the construction of the new addition for the administrative suite and clinic expansion including site work, interior work, ceiling, and roof within the Phase 1 limit of work. After Phase 1 and prior to starting Phase 2, a 2-week period will be provided for VA to move out/move in to the new admin suite. Clinic area will not be active until Phase 2 is complete.
2. Phase 2: This phase includes the partial demolition of the building exterior and interior, including walls, interior finishes, windows, doors, casework, plumbing fixtures, and ceiling within the Phase 2 limit of work. This phase also includes the construction of the renovated clinic expansion including interior work, ceilings, and roof within the Phase 2 limited of work as indicated on the drawings.
I. Building No. 90 will be occupied during performance of work; but immediate areas of alterations will be vacated.
1. Certain areas of Building(s) No. (s) 90 will be occupied by Medical Center personnel for various periods as listed below:
AREA PERIOD
(a) Existing building 90 (Mental Health Clinics) Continuously
Contractor shall take all measures and provide all material necessary for protecting existing equipment and property in affected areas of construction against dust and debris, so that equipment and affected areas to be used in the Medical Centers operations will not be hindered. Contractor shall permit access to Department of Veterans Affairs personnel and patients through other construction areas which serve as routes of access to such affected
01 00 00 - 5 areas and equipment. These routes whether access or egress shall be isolated from the construction area by temporary partitions and have walking surfaces, lighting, etc. to facilitate patient and staff access. Coordinate alteration work in areas occupied by Department of
Veterans Affairs so that Medical Center operations will continue during the construction period.
2. Immediate areas of alterations not mentioned in preceding Subparagraph 1 will be temporarily vacated while alterations are performed.
J. Construction Fence: Before construction operations begin, Contractor shall provide a chain link construction fence, 2.1 m (seven feet) minimum height, around the construction area indicated on the drawings. Provide gates as required for access with necessary hardware, including hasps and padlocks. Fasten fence fabric to terminal posts with tension bands and to line posts and top and bottom rails with tie wires spaced at maximum 375 mm (15 inches). Bottom of fences shall extend to 25mm (one inch) above grade. Remove the fence when directed by the COR.
K. When a building and/or construction site is turned over to the Contractor, Contractor shall accept entire responsibility including upkeep and maintenance therefore:
1. Contractor shall maintain a minimum temperature of 4 degrees C (40 degrees F) at all times, except as otherwise specified.
2. Contractor shall maintain in operating condition existing fire protection and alarm equipment.
In connection with fire alarm equipment, Contractor shall make arrangements for pre-inspection of site with Fire Department or Company (Department of Veterans Affairs or municipal) whichever will be required to respond to an alarm from Contractor's employee or watchman.
L. Utilities Services: Maintain existing utility services for Medical Center at all times. Provide temporary facilities, labor, materials, equipment, connections, and utilities to assure uninterrupted services. Where necessary to cut existing water, steam, gases, sewer or air pipes, or conduits, wires, cables, etc. of utility services or of fire protection systems and communications systems
(including telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by the COR.
1. No utility service such as water, gas, steam, sewers or electricity, or fire protection systems and communications systems may be interrupted without prior approval of the COR.
Electrical work shall be accomplished with all affected circuits or equipment de-energized.
When an electrical outage cannot be accomplished, work on any energized circuits or equipment shall not commence without a detailed work plan, the Medical Center Director’s prior knowledge and written approval. Refer to specification Sections 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS, 27 05 11 REQUIREMENTS FOR
COMMUNICATIONS INSTALLATIONS and 28 05 00, COMMON WORK RESULTS FOR
ELECTRONIC SAFETY AND SECURITY for additional requirements.
01 00 00 - 6
2. Contractor shall submit a request to interrupt any such services to the COR, in writing, 7 days in advance of proposed interruption. Request shall state reason, date, exact time of, and approximate duration of such interruption.
3. Contractor will be advised (in writing) of approval of request, or of which other date and/or time such interruption will cause least inconvenience to operations of Medical Center.
Interruption time approved by Medical Center may occur at other than Contractor's normal working hours.
4. Major interruptions of any system must be requested, in writing, at least 15 calendar days prior to the desired time and shall be performed as directed by the COR.
5. In case of a contract construction emergency, service will be interrupted on approval of the
COR. Such approval will be confirmed in writing as soon as practical.
M. Abandoned Lines: All service lines such as wires, cables, conduits, ducts, pipes and the like, and their hangers or supports, which are to be abandoned but are not required to be entirely removed, shall be sealed, capped or plugged at the main, branch or panel they originate from. The lines shall not be capped in finished areas, but shall be removed and sealed, capped or plugged in ceilings, within furred spaces, in unfinished areas, or within walls or partitions; so that they are completely behind the finished surfaces.
N. To minimize interference of construction activities with flow of Medical Center traffic, comply with the following:
1. Keep roads, walks and entrances to grounds, to parking and to occupied areas of buildings clear of construction materials, debris and standing construction equipment and vehicles.
Wherever excavation for new utility lines cross existing roads, at least one lane must be open to traffic at all times with approval.
2. Method and scheduling of required cutting, altering and removal of existing roads, walks and entrances must be approved by the COR.
O. Coordinate the work for this contract with other construction operations as directed by the COR.
This includes the scheduling of traffic and the use of roadways, as specified in Article, USE OF
ROADWAYS.
1.7 ALTERATIONS
A. Survey: Before any work is started, the Contractor shall make a thorough survey with the COR areas of buildings in which alterations occur and areas which are anticipated routes of access, and furnish a report, signed by both, to the Contracting Officer. This report shall list by rooms and spaces:
1. Existing condition and types of resilient flooring, doors, windows, walls and other surfaces not required to be altered throughout affected areas of building.
01 00 00 - 7
2. Existence and conditions of items such as plumbing fixtures and accessories, electrical fixtures, equipment, venetian blinds, shades, etc., required by drawings to be either reused or relocated, or both.
3. Shall note any discrepancies between drawings and existing conditions at site.
4. Shall designate areas for working space, materials storage and routes of access to areas within buildings where alterations occur, and which have been agreed upon by Contractor and the COR.
B. Any items required by drawings to be either reused or relocated or both, found during this survey to be nonexistent, or in opinion of COR, to be in such condition that their use is impossible or impractical, shall be furnished and/or replaced by Contractor with new items in accordance with specifications which will be furnished by Government. Provided the contract work is changed by reason of this subparagraph B, the contract will be modified accordingly, under provisions of clause entitled "DIFFERING SITE CONDITIONS" (FAR 52.236-2) and "CHANGES" (FAR 52.243-
4 and VAAR 852.236-88).
C. Re-Survey: Thirty days before expected partial or final inspection date, the Contractor and the
COR together shall make a thorough re-survey of the areas of buildings involved. They shall furnish a report on conditions then existing, of resilient flooring, doors, windows, walls and other surfaces as compared with conditions of same as noted in first condition survey report:
1. Re-survey report shall also list any damage caused by Contractor to such flooring and other surfaces, despite protection measures; and, will form basis for determining extent of repair work required of Contractor to restore damage caused by Contractor's workers in executing work of this contract.
D. Protection: Provide the following protective measures:
1. Wherever existing roof surfaces are disturbed they shall be protected against water infiltration. In case of leaks, they shall be repaired immediately upon discovery.
2. Temporary protection against damage for portions of existing structures and grounds where work is to be done, materials handled and equipment moved and/or relocated.
3. Protection of interior of existing structures at all times, from damage, dust and weather inclemency. Wherever work is performed, floor surfaces that are to remain in place shall be adequately protected prior to starting work, and this protection shall be maintained intact until all work in the area is completed.
1.8 DISPOSAL AND RETENTION
A. Materials and equipment accruing from work removed and from demolition of buildings or structures, or parts thereof, shall be disposed of as follows:
1. Reserved items which are to remain property of the Government are identified by attached tags or noted on drawings or in specifications as items to be stored. Items that remain property of the Government shall be removed or dislodged from present locations in such a
01 00 00 - 8 manner as to prevent damage which would be detrimental to re-installation and reuse. Store such items where directed by the COR.
2. Items not reserved shall become property of the Contractor and be removed by Contractor from Medical Center.
3. Items of portable equipment and furnishings located in rooms and spaces in which work is to be done under this contract shall remain the property of the Government. When rooms and spaces are vacated by the Department of Veterans Affairs during the alteration period, such items which are NOT required by drawings and specifications to be either relocated or reused will be removed by the Government in advance of work to avoid interfering with Contractor's operation.
1.9 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND
IMPROVEMENTS
A. The Contractor shall preserve and protect all structures, equipment, and vegetation (such as trees, shrubs, and grass) on or adjacent to the work site, which are not to be removed and which do not unreasonably interfere with the work required under this contract. The Contractor shall only remove trees when specifically authorized to do so, and shall avoid damaging vegetation that will remain in place. If any limbs or branches of trees are broken during contract performance, or by the careless operation of equipment, or by workers, the Contractor shall trim those limbs or branches with a clean cut and paint the cut with a tree-pruning compound as directed by the Contracting Officer.
B. The Contractor shall protect from damage all existing improvements and utilities at or near the work site and on adjacent property of a third party, the locations of which are made known to or should be known by the Contractor. The Contractor shall repair any damage to those facilities, including those that are the property of a third party, resulting from failure to comply with the requirements of this contract or failure to exercise reasonable care in performing the work. If the
Contractor fails or refuses to repair the damage promptly, the Contracting Officer may have the necessary work performed and charge the cost to the Contractor.
(FAR 52.236-9)
C. Refer to Section 01 57 19, TEMPORARY ENVIRONMENTAL CONTROLS, for additional requirements on protecting vegetation, soils and the environment. Refer to Articles, "Alterations", "Restoration", and "Operations and Storage Areas" for additional instructions concerning repair of damage to structures and site improvements.
1.10 RESTORATION
A. Remove, cut, alter, replace, patch and repair existing work as necessary to install new work.
Except as otherwise shown or specified, do not cut, alter or remove any structural work, and do not disturb any ducts, plumbing, steam, gas, or electric work without approval of the COR.
Existing work to be altered or extended and that is found to be defective in any way, shall be
01 00 00 - 9 reported to the COR before it is disturbed. Materials and workmanship used in restoring work, shall conform in type and quality to that of original existing construction, except as otherwise shown or specified.
B. Upon completion of contract, deliver work complete and undamaged. Existing work (walls, ceilings, partitions, floors, mechanical and electrical work, lawns, paving, roads, walks, etc.)
disturbed or removed as a result of performing required new work, shall be patched, repaired, reinstalled, or replaced with new work, and refinished and left in as good condition as existed before commencing work.
C. At Contractor's own expense, Contractor shall immediately restore to service and repair any damage caused by Contractor's workers to existing piping and conduits, wires, cables, etc., of utility services or of fire protection systems and communications systems (including telephone) which are not scheduled for discontinuance or abandonment.
D. Expense of repairs to such utilities and systems not shown on drawings or locations of which are unknown will be covered by adjustment to contract time and price in accordance with clause entitled "CHANGES" (FAR 52.243-4 and VAAR 852.236-88) and "DIFFERING SITE
CONDITIONS" (FAR 52.236-2).
1.11 PHYSICAL DATA
A. Data and information furnished or referred to below is for the Contractor's information. The
Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor.
1. The indications of physical conditions on the drawings and in the specifications are the result of site investigations by TERRCON CONSULTANTS, INC., PROJECT NO. 63105021, DATED APRIL 8, 2010.
(FAR 52.236-4)
B. Subsurface conditions have been developed by core borings and test pits. Logs of subsurface exploration are shown diagrammatically on drawings. Refer to soil report, specification section 01
80 00 GEOTECHNICAL REPORTS.
C. Government does not guarantee that other materials will not be encountered, nor that proportions, conditions or character of several materials will not vary from those indicated by explorations. Bidders are expected to examine site of work and logs of borings; and, after investigation, decide for themselves character of materials and make their bids accordingly. Upon proper application to Department of Veterans Affairs, bidders will be permitted to make subsurface explorations of their own at site.
1.12 PROFESSIONAL SURVEYING SERVICES
A registered professional land surveyor or registered civil engineer whose services are retained and paid for by the Contractor shall perform services specified herein and in other specification sections. The Contractor shall certify that the land surveyor or civil engineer is not one who is a
01 00 00 - 10 regular employee of the Contractor, and that the land surveyor or civil engineer has no financial interest in this contract.
1.13 LAYOUT OF WORK
A. The Contractor shall lay out the work from Government established base lines and bench marks, indicated on the drawings, and shall be responsible for all measurements in connection with the layout. The Contractor shall furnish, at Contractor's own expense, all stakes, templates, platforms, equipment, tools, materials, and labor required to lay out any part of the work. The
Contractor shall be responsible for executing the work to the lines and grades that may be established or indicated by the Contracting Officer. The Contractor shall also be responsible for maintaining and preserving all stakes and other marks established by the Contracting Officer until authorized to remove them. If such marks are destroyed by the Contractor or through
Contractor's negligence before their removal is authorized, the Contracting Officer may replace them and deduct the expense of the replacement from any amounts due or to become due to the
Contractor.
(FAR 52.236-17)
B. Establish and plainly mark center lines for each building and corner of column lines and/or addition to each existing building, and such other lines and grades that are reasonably necessary to properly assure that location, orientation, and elevations established for each such structure and/or addition are in accordance with lines and elevations shown on contract drawings.
C. Following completion of general mass excavation and before any other permanent work is performed, establish and plainly mark (through use of appropriate batter boards or other means) sufficient additional survey control points or system of points as may be necessary to assure proper alignment, orientation, and grade of all major features of work. Survey shall include, but not be limited to, location of lines and grades of footings, exterior walls, center lines of columns in both directions, major utilities and elevations of floor slabs:
1. Such additional survey control points or system of points thus established shall be checked and certified by a registered land surveyor or registered civil engineer. Furnish such certification to the COR before any work (such as footings, floor slabs, columns, walls, utilities and other major controlling features) is placed.
D. During progress of work Contractor shall have line grades and plumbness of all major form work checked and certified by a registered land surveyor or registered civil engineer as meeting requirements of contract drawings. Furnish such certification to the COR before any major items of concrete work are placed. In addition, Contractor shall also furnish to the COR certificates from a registered land surveyor or registered civil engineer that the following work is complete in every respect as required by contract drawings.
1. Lines of each building and/or addition.
2. Elevations of bottoms of footings and tops of floors of each building and/or addition.
01 00 00 - 11
3. Lines and elevations of sewers and of all outside distribution systems.
E. Whenever changes from contract drawings are made in line or grading requiring certificates, record such changes on a reproducible drawing bearing the registered land surveyor or registered civil engineer seal, and forward these drawings upon completion of work to the COR.
F. The Contractor shall perform the surveying and layout work of this and other articles and specifications in accordance with the provisions of Article "Professional Surveying Services".
1.14 AS-BUILT DRAWINGS
A. The Contractor shall maintain two full size sets of as-built drawings which will be kept current during construction of the project, to include all contract changes, modifications and clarifications.
B. All variations shall be shown in the same general detail as used in the contract drawings. To ensure compliance, as-built drawings shall be made available for the COR review, as often as requested.
C. Contractor shall deliver two approved completed sets of as-built drawings in the electronic version
(scanned PDF) to the COR within 15 calendar days after each completed phase and after the acceptance of the project by the COR.
D. Paragraphs A, B, & C shall also apply to all shop drawings.
1.15 WARRANTY MANAGEMENT
A. Warranty Management Plan: Develop a warranty management plan which contains information relevant to FAR 52.246-21 Warranty of Construction at least 30 days before the planned pre-warranty conference, submit four sets of the warranty management plan. Include within the warranty management plan all required actions and documents to assure that the Government receives all warranties to which it is entitled. The plan must be in narrative form and contain sufficient detail to render it suitable for use by future maintenance and repair personnel, whether tradesman, or of engineering background, not necessarily familiar with this contract. The term
“status” as indicated below must include due date and whether item has been submitted or was approved. Warranty information made available during the construction phase must be submitted to the Contracting Officer for approval prior to each monthly invoice for payment. Assemble approved information in a binder and turn over to the Government upon acceptance of the work.
The construction warranty period will begin on the date of the project acceptance and continue for the product warranty period. A joint 4 month and 9 month warranty inspection will be conducted, measured from time of acceptance, by the Contactor and the Contracting Officer. Include in the warranty management plan, but not limited to, the following:
1. Roles and responsibilities of all personnel associated with the warranty process, including points of contact and telephone numbers within the company of the Contractor, subcontractors, manufacturers or suppliers involved.
2. Furnish with each warranty the name, address and telephone number of each of the guarantor’s representatives nearest project location.
01 00 00 - 12
3. Listing and status of delivery of all Certificates of Warranty for extended warranty items, to include roofs, HVAC balancing, pumps, motors, transformers and for all commissioned systems such as fire protection and alarm systems, sprinkler systems and lightning protection systems, etc.
4. A list for each warranted equipment item, feature of construction or system indicating:
a. Name of item
b. Model and serial numbers
c. Location where installed
d. Name and phone numbers of manufacturers and suppliers
e. Name and phone numbers of manufacturers or suppliers
f. Names, addresses and phone numbers of sources of spare parts
g. Warranties and terms of warranty. Include one-year overall warranty of construction, including the starting date of warranty of construction. Items which have extended warranties must be indicated with separate warranty expiration dates.
h. Starting point and duration of warranty period
i. Summary of maintenance procedures required to continue the warranty in force
j. Cross-reference to specific pertinent Operation and Maintenance manuals
k. Organizations, names and phone numbers of persons to call for warranty service
l. Typical response time and repair time expected for various warranted equipment
5. The plans for attendance at the 4- and 9-month post construction warranty inspections conducted by the Government.
6. Procedure and status of tagging of all equipment covered by extended warranties.
7. Copies of instructions to be posted near selected pieces of equipment where operation is critical for warranty and/or safety reasons.
B. Performance Bond: The Performance Bond must remain effective throughout the construction period.
1. In the event the Contractor fails to commence and diligently pursue any construction warranty work required, the Contracting Officer will have the work performed by others, and after completion of the work, will charge the remaining construction warranty funds of expenses incurred by the Government while performing the work, including, but not limited to administrative expenses.
2. In the event sufficient funds are not available to cover the construction warranty work performed by the Government at the contractor’s expenses, the Contracting Officer will have the right to recoup expenses from the bonding company.
3. Following oral or written notification of required construction warranty repair work, the
Contractor shall respond in a timely manner. Written verification will follow oral instructions.
Failure to respond will be cause for the Contracting Officer to proceed against the Contractor.
01 00 00 - 13
C. Pre-Warranty Conference: Prior to contract completion, and at a time designated by the
Contracting Officer, the Contractor shall meet with the Contracting Officer to develop a mutual understanding with respect to the requirements of this section. Communication procedures for
Contractor notification of construction warranty defects, priorities with respect to the type of defect, reasonable time required for Contractor response, and other details deemed necessary by the Contracting Officer for the execution of the construction warranty will be established/ reviewed at this meeting. In connection with these requirements and at the time of the Contractor’s quality control completion inspection, furnish the name, telephone number and address of a licensed and bonded company which is authorized to initiate and pursue construction warranty work action on behalf of the Contractor. This point of contract will be located within the local service area of the warranted construction, be continuously available and be responsive to Government inquiry on warranty work action and status. This requirement does not relieve the Contractor of any of its responsibilities in conjunction with other portions of this provision.
D. Contractor’s Response to Construction Warranty Service Requirements:
Following oral or written notification by the Contracting Officer, the Contractor shall respond to construction warranty service requirements in accordance with the “Construction Warranty
Service Priority List” and the three categories of priorities listed below. Submit a report on any warranty item that has been repaired during the warranty period. Include within the report the cause of the problem, date reported, corrective action taken, and when the repair was completed.
If the Contractor does not perform the construction warranty within the timeframe specified, the
Government will perform the work and back charge the construction warranty payment item established.
1. First Priority Code 1. Perform onsite inspection to evaluate situation, and determine course of action within 4 hours, initiate work within 6 hours and work continuously to completion or relief.
2. Second Priority Code 2. Perform onsite inspection to evaluate situation, and determine course of action within 8 hours, initiate work within 24 hours and work continuously to completion or relief.
3. Third Priority Code 3. All other work to be initiated within 3 work days and work continuously to completion or relief.
4. The “Construction Warranty Service Priority List” is as follows:
Code 1-Life Safety Systems
a. Fire suppression systems
b. Fire alarm system(s)
Code 1-Air Conditioning Systems
a. Air conditioning leak in part of the building, if causing damage
b. Air conditioning system not cooling properly
01 00 00 - 14
Code 1 Doors
a. Interior, exterior personnel doors or hardware, not functioning properly, causing security, fire or safety problem
Code 3-Doors
a. Interior/exterior personnel doors or hardware not functioning properly
Code 1-Electrical
a. Power failure (entire area or any building operational after 1600 hours)
b. Security lights
c. Smoke detectors
Code 2-Electrical
a. Power failure (no power to a room or part of building)
b. Receptacles and lights not operational (in a room or part of building)
Code 3-Electrical
a. Exterior lights not operational
Code 1-Gas
a. Leaks and pipeline breaks
Code 1-Heat
a. Power failure affecting heat
Code 1-Plumbing
a. Hot water heater failure
b. Leaking water supply pipes
Code 2-Plumbing
a. Flush valves not operating properly
b. Fixture drain, supply line or any water pipe leaking
c. Toilet leaking at base
Code 3- Plumbing
a. Leaky faucets
Code 3-Interior
a. Floors damaged
b. Paint chipping or peeling
c. Casework damaged
Code 1-Roof Leaks
a. Damage to property is occurring
Code 2-Water (Exterior)
a. No water to facility
Code 2-Water (Hot)
a. No hot water in portion of building listed
01 00 00 - 15
Code 3
a. All work not listed above
E. Warranty Tags: At the time of installation, tag each warranted item with a durable, oil and water-resistant tag approved by the Contracting Officer. Attach each tag with a copper wire and spray with a silicone waterproof coating. Also submit two record copies of the warranty tags showing the layout and design. The date of acceptance and the QC signature must remain blank until the project is accepted for beneficial occupancy. Show the following information on the tag.
1.16 USE OF ROADWAYS
A. For hauling, use only established public roads and roads on Medical Center property and, when authorized by the COR, such temporary roads which are necessary in the performance of contract work. Temporary roads shall be constructed and restoration performed by the Contractor at Contractor's expense. When necessary to cross curbing, sidewalks, or similar construction, they must be protected by well-constructed bridges.
B. When new permanent roads are to be a part of this contract, Contractor may construct them immediately for use to facilitate building operations. These roads may be used by all who have business thereon within zone of building operations.
01 00 00 - 16
C. When certain buildings (or parts of certain buildings) are required to be completed in advance of general date of completion, all roads leading thereto must be completed and available for use at time set for completion of such buildings or parts thereof.
1.17 TEMPORARY USE OF MECHANICAL AND ELECTRICAL EQUIPMENT
A. Use of new installed mechanical and electrical equipment to provide heat, ventilation, plumbing, light and power will be permitted subject to written approval and compliance with the following provisions:
1. Permission to use each unit or system must be given by the COR in writing. If the equipment is not installed and maintained in accordance with the written agreement and following provisions, the COR will withdraw permission for use of the equipment.
2. Electrical installations used by the equipment shall be completed in accordance with the drawings and specifications to prevent damage to the equipment and the electrical systems, i.e.
This is the start of the file's text. The full file is on GovTribe.