This document is the administrative requirements attachment for a state contract opportunity issued by the California Department of Fish and Wildlife (CDFW) for the procurement of fish hauling tanks. The contract requires bidders to demonstrate a minimum of 60 months of continuous business experience in the sale/manufacturing of fish hauling tanks, and to submit descriptive literature, drawings, and customer references with their bid proposals. The contract includes a pre-construction meeting requirement, inspection and acceptance criteria, warranty terms, and delivery timelines with an end date of March 31, 2026. The contract also allows for partial deliveries, unanticipated tasks, and price escalation with proper documentation and approvals from CDFW.
The contract includes a 10% allowance for CDFW-required options, upgrades, and unanticipated tasks that must be authorized through a work authorization form process. Pricing for the tanks is subject to annual escalation, which must be substantiated and approved by CDFW. Bidders are required to provide details on their company's experience, customer references, and certification that they have reviewed and agreed to the contract requirements.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
BU 3600 Event ID 0000030454 Attachment 3
California Department of Fish and Wildlife
Fish Hauling Tanks Administrative Requirements
EXPERIENCE
The bidder shall be able to demonstrate a history and expertise in the sale/manufacturing of fish hauling tanks and shall have been in business continuously for a minimum of 60 consecutive months prior to this bid.
DESCRIPTIVE LITERATURE
Bidder shall submit complete descriptive literature with the bid and are to note their brand name and catalog or model number. Descriptive literature shall be annotated to specify the applicable page, brand, model and item(s).
FAILURE TO SUBMIT DESCRIPTIVE LITERATURE BY THE BIDDER, MAY BE
CONSIDERED NON-RESPONSIVE AND NOT ACCEPTED.
DRAWINGS
If applicable, the bidder shall submit one representative set of plans designed to coordinate with these specifications with the bid proposal.
WORKMANSHIP
The equipment and any accessories shall be a product of good workmanship and shall be free from any defects that will affect their appearance or serviceability. This includes but not limited to no scratches on paint, fiberglass, or aluminum, no sharp edges from machining or installation, wiring is securely fastened and free of obstructions, and all hardware is installed correctly. Sharp corners on all material shall be rounded to prevent personnel injury.
PRE-CONSTRUCTION MEETING
Within fourteen (14) days after receipt of Purchase Order, the California Department of Fish and Wildlife (CDFW) representatives shall schedule a pre-construction meeting with the Contractor’s representative(s). This meeting will be held over video chat, phone, or in person as determined by CDFW.
At least five (5) working days prior to the pre-construction meeting, Contractor shall provide legible drawings with dimensions (top view, side view. front view, and layout etc.) to CDFW.
The purpose of this pre-construction meeting is to review Tank drawings, design, etc. In addition, the Contractor shall provide a production timeline for construction.
CDFW representatives contact information:
Name Phone Email
TBD
INSPECTION AND ACCEPTANCE
Inspection will be done at the time of delivery at the final destination by State inspector(s). Completion of inspection or acceptance by the State inspector shall in no way release the Contractor from satisfying the requirements of the contract, specifications, and warranty. The Contractor shall correct deviations from the specified requirements that are detected by the owning agency in an expeditious manner at no expense to CDFW.
FAILED ACCEPTANCE
Should the fish hauling tanks or any of the equipment provided fail to meet the State's minimum conditions, requirements, or other applicable standards, specifications, or guidelines, the following resolution process will be employed.
A. CDFW will notify the Contractor in writing within five (5) business days after delivery of any acceptance problems by identifying the specific inadequacies and/or failures in the services performed and/or the products produced by Contractor. An email from the CDFW to Contractor will be allowed as the initial problem notification document.
B. Contractor will, within five (5) business days after initial problem notification, respond to CDFW by submitting a detailed explanation describing precisely how the identified services and/or products actually adhere to and satisfy all applicable requirements, and/or a proposed corrective action plan to address the specific inadequacies and/or failures in the identified services and/or products. Failure by the Contractor to respond to the CDFW initial problem notification within the required time limits may result in immediate contract termination. In the event of such termination, the Contractor will remove the trailer from the CDFW site and the order will be cancelled at no cost to the CDFW. An email from Contractor to the CDFW Representative Contact will be allowed as the response to initial problem notification document.
C. CDFW will, within five (5) business days after receipt of Contractor’s detailed explanation and/or proposed corrective action plan, notify the Contractor in writing whether it accepts or rejects the explanation and/or plan. If CDFW rejects the explanation and/or plan, the Contractor will submit a revised corrective action plan within five (5) business days of notification of rejection. Emails are allowed as the communication medium. Failure by the Contractor to respond to the State’s notification of rejection by submitting a revised corrective action plan within the required time limits may result in immediate contract termination.
D. CDFW will within five (5) business days of receipt of the revised corrective action plan, notify Contractor in writing whether it accepts or rejects the revised corrective action plan. Rejection of the revised corrective action plan will result in immediate contract termination. Emails are allowed as the communication medium.
BOOKS AND MANUALS
Contractor shall provide at the time of trailer delivery, at least one (1) hard copy of complete operator/instruction manual(s).
WARRANTY
Copies of the manufacturer's warranties (including purchased equipment) shall be provided at the time of delivery.
Equipment, electronics, and miscellaneous shall include manufacturers standard warranties. The manufacturer or their authorized dealer shall respond to warranty requests within five (5) business day of report of a failure from the California Department of Fish and Wildlife and shall dispatch a factory representative to address any workmanship-related issues.
Manufacturer must have a Warranty Service provider.
All products offered must conform to the warranty language identified in the General Provisions, 19, Warranty.
Contractor shall bear all material, labor and transportation costs for repair or defects as well as failures occurring within the warranty period.
DELIVERY
Delivery is to be completed in full by March 31, 2026. Delivery address: see Attachment 7 Delivery Distribution list.
Delivery timelines can be changed if both, the state, and the contractor agree. Approval for extensions will be done using a Work Authorization Form (Attachment 6). The Contractor will submit a Work Authorization Form to CDFW for approval and after CDFW ‘s approval, can proceed with the approved changes. The approved Work Authorization Form will thereby be incorporated to the contract. A Purchase Order Change or amendment will not be required.
PARTIAL DELIVERIES
The State will allow the for invoicing and payment of each unit after Contractor completes delivery and inspection of each unit is passed and accepted by CDFW.
UNANTICIPATED TASKS
For the purpose of this procurement, the State shall allow an amount equal to 10 percent of the total contract/purchase order (PO), to be added to the contract / purchase order to allow for State required options/upgrades (components, equipment, licenses, true up, parts, etc. that provide additional functionality to the specification or scope of work), unanticipated tasks (well documented and unanticipated price increase of goods/services, tax, freight/shipping/delivery or additional work that must be performed which was wholly unanticipated and is not specified in the specification, but which in the opinion of both parties is necessary), and unforeseen components or labor, etc.
necessary to complete the requirements as indicated within the agreement. This is the maximum amount that will be available for State required and approved options/upgrades, components, additional work, etc. after PO award.
All Unanticipated Tasks must be defined and authorized by a Work Authorization Form (Attachment 6). The Contractor will submit a Work Order Authorization Form to CDFW and after CDFW ‘s approval, can proceed with the approved changes, and will be paid from this reserved allowance.
Each Work Authorization Form shall consist of a detailed statement of the work to be performed, an estimated time schedule for the performance of the work, and the Contractor’s itemized and total one-time and on-going costs, or cost reductions, of the Work Authorization. Prior to commencing work, the Work Authorization Form must be signed by the Contractor’s designated representative and by CDFW ‘s or designated representative. The approved Work Authorization will thereby be included in the contract.
A Purchase Order Change or Amendment will not be needed unless there is a change to the PO amount.
The Contractor is not entitled to any portion of the additional 10 percent unless the extra components, labor, tasks, etc. are documented and approved by the (CDFW).
WORK AUTHORIZATION FORM
If the CDFW requires additional work, such as adding transactions or features, that is unanticipated and is not specified in the Contract but is, in the opinion of both parties, necessary to the successful accomplishment of the general scope of work outlined, the Work Authorization Form (Attachment 6), will be used to obtain the approval. The approved Work Authorization will thereby be included in the contract. A Purchase Order Change or Amendment will not be needed.
PRICE ESCALATION
The Contractor may submit proposed escalation notice, in writing using a Work Authorization Form (Attachment 6), to (CDFW) no earlier than one year from the PO date, and then every year thereafter throughout the remaining PO terms. Such notices shall include substantiated information to support the proposed escalation (e.g., manufacturer’s price list, significant changes in published market indicators for the industry, certified raw material cost date, and other substantiating information as requested by the State).
Upon receipt of such notice, the State reserves the right to either: Accept the escalation as competitive with the general market price at the time, effective 30 days after written approval from the State; negotiate proposed price escalation; or cancel any un-purchased balance of the PO without prejudice effective upon written notice by the State.
No price increase shall apply to quantities ordered from the PO prior to the effective date of the price increase. New prices shall be firm for a minimum of 12-months from the date effective date of escalation. The Delivery and Unanticipated Tasks clauses may be updated to better reflect new construction and delivery timeframes. All contract changes and price escalation information shall be detailed on a Work Authorization Form (Attachment 6) and must be signed by the Contractor’s designated representative and by the (CDFW) ‘s or designated representative. The executed Work Authorization will thereby be incorporated as a Schedule to this Agreement. A Purchase Order Change or Amendment will not be required unless there is a change to the PO amount.
ADDITIONAL INFORMATION AND DOCUMENTATION REQUIRED
The following supporting documentation shall be included with the bid submitted.
• Company Experience and Fish Hauling Tank information.
The bidder shall be able to demonstrate a history and expertise in the sale/manufacturing of Fish Hauling Tank(s) and shall have been in business continuously for a minimum of sixty (60) consecutive months prior to this bid.
# of years in business continuously: _______________
• Customer References Bidders shall provide a minimum of three (3) references that are currently operating the proposed Fish Hauling Tank including contact name and numbers with the bid. The state reserves the right to verify any and all references. If the reference cannot be contacted, your bid may be deemed non-responsive.
Reference #1 Company Name:
Contact Name: ________________________________ Phone #:
Type of Unit Sold: ___________________________ Date Delivered: ____________
Reference #2 Company Name:
Contact Name: ________________________________ Phone #:
Type of Unit Sold: ___________________________ Date Delivered: ____________
Reference #3 Company Name:
Contact Name: ________________________________ Phone #:
Type of Unit Sold: ___________________________ Date Delivered: ____________
** BIDDER CERTIFICATION:
Please clarify that you have received all seven (7) pages of this document and that you have reviewed and agree to the requirements, terms, and conditions within by signing below and returning all pages with the bid submission.
Printed Name ____________________________________
Signature ______________________________________
Date _____________________
Email _________________________________
| PRE-CONSTRUCTION MEETING |
| Within fourteen (14) days after receipt of Purchase Order, the California Department of Fish and Wildlife (CDFW) representatives shall schedule a pre-construction meeting with the Contractor’s representative(s). This meeting will be held over video ch... |
| At least five (5) working days prior to the pre-construction meeting, Contractor shall provide legible drawings with dimensions (top view, side view. front view, and layout etc.) to CDFW. |
| The purpose of this pre-construction meeting is to review Tank drawings, design, etc. In addition, the Contractor shall provide a production timeline for construction. |