This is a solicitation for drydock repairs to Coast Guard Cutter CGC SANIBEL. The solicitation seeks repair and maintenance services including mechanical shaft seal assemblies overhaul, ship service diesel generator renewal, drydocking, tank cleaning and inspection, exhaust piping inspection, heat exchanger cleaning and inspection, sewage and grey water tank cleaning, piping cleaning and flushing, underwater hull preservation, rudder and propeller removal and reinstallation, cathodic protection inspection, stuffing tube renewal, hull plating ultrasonic testing, sea valve overhaul, sea strainer overhaul, preservation of internal spaces, and other work. Responses are due by August 15, 2021 and award is expected by September 30, 2021. Pricing will be fixed price. The solicitation is unrestricted and open to small businesses. The Department of Homeland Security Coast Guard is the contracting agency.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

USCGC SANIBEL (WPB 1312)

SPECIFICATION FOR DRYDOCK REPAIRS

FY2021

Developed By: Tim O'Brien

(Rev-1, 17 March 2021)

USCGC SANIBEL (WPB-110A) DRYDOCK AVAILABILITY FY2021

ii (Rev-1)

TABLE OF CONTENTS

Revisions Record ......................................................................................................................................... iii Consolidated List of References ................................................................................................................... vi Consolidated List of Government-furnished Property ............................................................................... xii Consolidated List of Critical Inspection Items .......................................................................................... xiii Principal Characteristics ............................................................................................................................. xiv General Requirements WORK ITEM 1: Mechanical Shaft Seal Assemblies, Overhaul WORK ITEM 2: Ship Service Diesel Generator(s) (John Deere), Renew WORK ITEM 3: Drydock WORK ITEM 4: Temporary Services, Provide - Cutter WORK ITEM 5: Tanks (Mp Fuel Stowage And Overflow), Clean And Inspect WORK ITEM 6: Tanks (MP Fuel Service), Clean and Inspect WORK ITEM 7: Exhaust Piping System, Inspect WORK ITEM 8: Heat Exchangers; Clean, Inspect And Hydro WORK ITEM 9: Grey Water Holding Tank(s), Clean and Inspect WORK ITEM 10: Sewage Holding Tank(s), Clean and Inspect WORK ITEM 11: Grey Water Piping, Clean And Flush WORK ITEM 12: Sewage Piping, Clean And Flush WORK ITEM 13: U/W Body, Preserve (100%) WORK ITEM 14: Hull Plating Freeboard, Preserve “100%” WORK ITEM 15: Appendages (U/W), Leak Test WORK ITEM 16: Appendages (U/W) - Internal, Preserve WORK ITEM 17: Propellers; Remove, Inspect, and Reinstall WORK ITEM 18: Rudder Assembly, Remove, Inspect and Reinstall WORK ITEM 19: Impressed Current Cathodic Protection System, Inspect And Maintain WORK ITEM 20: Stuffing Tubes, Renew WORK ITEM 21: Hull Plating (Side Scan), Ultrasonic Testing WORK ITEM 22: Sea Valves , Overhaul Or Renew WORK ITEM 23: Sea Strainers - Duplex (All Sizes), Overhaul WORK ITEM 24: FWD Aux Machinery Space, Preserve WORK ITEM 25: FO Tank, Repair WORK ITEM 26: Sewage Access Space, Preserve iii (Rev-1)

REVISIONS RECORD

This page is used to record specification revisions, which may have occurred subsequent to a Revision 0 (Rev-0) package. Information listed is intended to provide contractors and field unit personnel a means to ensure all the current specification revision pages are present when reviewing or utilizing this specification package.

DATE REV# WORK ITEM TITLE CHANGES

MADE

3/17/21 1 1 Bilges Mach Space, Preserve Deleted

3/17/21 1 2 Forward Void, Preserve Deleted

3/17/21 1 3 Propulsion Shafting, Remove, Inspect, And Reinstall

Deleted

3/17/21 1 4 Alignment Survey, Conduct Deleted

3/17/21 1 7 Steering Gear (General), Overhaul Deleted

3/17/21 1 8 Aft Steering Bilge, Preserve Deleted

3/17/21 1 9 Joiner Bulkhead Panels, Renew Deleted

3/17/21 1 10 Forward Peak Compartment, Preserve Deleted

3/17/21 1 11 Forward Head, Preserve Deleted

3/17/21 1 12 Forward Berthing, Preserve Deleted

3/17/21 1 13 CPO Stateroom, Preserve Deleted

3/17/21 1 14 Decks - Exterior, Preserve Deleted

3/17/21 1 15 Superstructure, Preserve “100%” Deleted

3/17/21 1 16 Insulation, Bulkhead/Overhead, Renew Deleted

3/17/21 1 19 Sea Trial Performance, Support, Provide Deleted

3/17/21 1 20 Deck Covering, Carpeting, Renew Deleted

3/17/21 1 21 Watertight Enclosures, Conditions, Assess

Deleted

3/17/21 1 22 Hull and Structural Plating (Cracked Steel), Repair

Deleted iv (Rev-1)

3/17/21 1 25 Tanks (Potable Water), Clean and Inspect Deleted

3/17/21 1 32 Deck Covering, Wet/ Dry, Seal Deleted

3/17/21 1 33 Ventilation Systems, Commercial Clean Deleted

3/17/21 1 38 Tanks, Dirty Oil and Waste, Clean and Inspect

Deleted

3/17/21 1 39 Main Mast, Preserve, Partial Deleted

3/17/21 1 40 Stern Tube Interior Surfaces, Preserve Deleted

3/17/21 1 42 Speed Doppler, Remove, Inspect, and Reinstall

Deleted

3/17/21 1 44 Fin Stabilizers (General), Overhaul Deleted

3/17/21 1 45 Strut Cofferdams, Port & Starboard, Preserve

Deleted

3/17/21 1 46 Cathodic Protection System (Bilge and Sea Chest), Renew

Deleted

3/17/21 1 48 Magazine Space, Preserve Deleted

3/17/21 1 49 Insulation, HVAC Space, Renew Deleted

3/17/21 1 52 Aluminum Hull and Structural (5/16" Plate), Repair

Deleted

3/17/21 1 53 Aluminum Hull and Structural Plating (Eroded Weld), Repair

Deleted

3/17/21 1 54 Battery Space Bilge, Preserve Deleted

3/17/21 1 55 CO Shower Drain, Renew Deleted

3/17/21 1 56 Hull Plating (U/W Body), Inspect Deleted

3/17/21 1 57 Propulsion Shaft Bearings (External), Renew

Deleted

3/17/21 1 58 Propulsion Shaft, Stern Tube Forward Bearing, Renew

Deleted

3/17/21 1 59 Fathometer Transducer, Renew Deleted

3/17/21 1 63 Hull, Electrical Penetrations, Inspect Deleted v (Rev-1)

3/17/21 1 66 Windscreen, Open Bridge, Renew Deleted

3/17/21 1 67 Tank Access Void, Preserve Deleted

NOTE : All work item and paragraph numbers listed above for a given revision correspond to same numbers in the previous revision. This revised specification is self-contained with all of the above listed changes incorporated.

vi (Rev-1)

CONSOLIDATED LIST OF REFERENCES

The below-listed documents form a part of this specification to the extent specified herein. Approval/publication dates or revision dates/numbers are also identified, to ensure that same document versions are used at the time of specification writing and during contract execution.

All Coast guard drawings, technical publications, and standard specifications will be provided to contractors by the Coast Guard at an appropriate time, or upon request, free of charge. Other Government documents may be accessed – free of charge – from links located on the SFLC website. Commercial sites provide access to their respective documents.

COAST GUARD DRAWINGS

«CGDWGS»

Coast Guard Drawing 110 WPB 074-002, Rev -, Welding Details Handbook Coast Guard Drawing 110 WPB 079-001, Rev -, Damage Control Plan Coast Guard Drawing 110 WPB 085-001, Rev -, Tank Capacity Curves Coast Guard Drawing 110 WPB 085-002, Rev 2, Docking Plan Coast Guard Drawing 110 WPB 085-007, Rev D, Booklet of General Plans Coast Guard Drawing 110 WPB 085-009, Rev -, Master Material/Equipment List Coast Guard Drawing 110 WPB 085-010, Rev C, Docking Plan/Lifting Cradle(110-WPB,110B-

WPB,110C-WPB)

Coast Guard Drawing 110 WPB 111-001, Rev B, Shell Expansion Coast Guard Drawing 110 WPB 113-001, Rev D, Inner Bottom Plating Coast Guard Drawing 110 WPB 114-001, Rev B, Stern Flap Coast Guard Drawing 110 WPB 114-002, Rev A, Spray Rail Coast Guard Drawing 110 WPB 117-001, Rev A, Transverse Sections (1301-1311) Coast Guard Drawing 110 WPB 117-001, Rev A, Transverse Sections (1301-1311) Coast Guard Drawing 110 WPB 117-002, Rev -, Holes in Transverse Sections Coast Guard Drawing 110 WPB 121-001, Rev -, Longitudinal Bulkheads Coast Guard Drawing 110 WPB 131-001, Rev B, Deck Construction Plan (1301 - 1311) Coast Guard Drawing 110 WPB 151-004, Rev -, Superstructure Details (1301) Coast Guard Drawing 110 WPB 161-001, Rev A, Main Shaft Strut Details Coast Guard Drawing 110 WPB 161-002, Rev -, Main Shaft Strut Installation Coast Guard Drawing 110 WPB 161-003, Rev A, Intermediate Shaft Strut Details Coast Guard Drawing 110 WPB 161-004, Rev -, Intermediate Shaft Strut Installation Coast Guard Drawing 110 WPB 161-006, Rev A, Intermediate Shaft Strut Manufacturing Details

(Supercedes 110, 110B, 110C-WPB-161-003) Coast Guard Drawing 110 WPB 163-002, Rev-; Auxiliary Sea Chest Details Coast Guard Drawing 110 WPB 183-003, Rev B, Generator Foundations Modifications Coast Guard Drawing 110 WPB 201-002, Rev A, Propulsion Configuration Coast Guard Drawing 110 WPB 201-003, Rev -, Machinery Arrangement vii (Rev-1)

Coast Guard Drawing 110 WPB 243-002, Rev B, Propulsion Shafting Details Coast Guard Drawing 110 WPB 243-005, Rev -, Shaft Locking Device Coast Guard Drawing 110 WPB 243-006, Rev C, Propulsion Shaft Details Coast Guard Drawing 110 WPB 245-004, Rev A, Propeller Details Coast Guard Drawing 110 WPB 245-005, Rev -, Assembly of Oil Injection Equip Coast Guard Drawing 110 WPB 252-002, Rev -, Open Bridge Console Coast Guard Drawing 110 WPB 256-001, Rev A, Main Engine SW Cooling System A&D (1301) Coast Guard Drawing 110 WPB 256-002, Rev -, Aux SW Cooling System A&D (1301-1302) Coast Guard Drawing 110 WPB 256-003, Rev B, Mods to SW Cooling Incidental to Install of Charge Air

Cooler Diverter Valve Coast Guard Drawing 110 WPB 256-004, Rev C, SSDG Seawater Cooling Ripout & Instl Coast Guard Drawing 110 WPB 259-001, Rev D, Main Engine Exhaust Piping System Coast Guard Drawing 110 WPB 259-002, Rev -, Genset Exhaust Piping System Coast Guard Drawing 110 WPB 259-005, Rev C, 18” Raw Water Discharge Spray Ring Assembly w/

Companion Flanges & Gaskets Coast Guard Drawing 110 WPB 259-006, Rev D, MDE 8” Exhaust Flapper Valve Assembly

(w/Companion Flanges & Gaskets) Coast Guard Drawing 110 WPB 259-007, Rev A, SSDG Exhaust Piping Mod Ripout & Instl Coast Guard Drawing 110 WPB 320-001, Rev D, Ships Service Power 1-Line Diagram Coast Guard Drawing 110 WPB 321-002, Rev A, Main Wireways Coast Guard Drawing 110 WPB 321-003, Rev A, Main Cableways Arrangements & Details (MEP) Coast Guard Drawing 110 WPB 501-001, Rev E, Piping System Schematics Coast Guard Drawing 110 WPB 514-001, Rev A, Air Conditioning/Heating System Coast Guard Drawing 110 WPB 521-001, Rev B, Firemain Piping Arrg’t & Details Coast Guard Drawing 110 WPB 526-001, Rev D; Scuppers & Deck Drains Piping Arrangement Coast Guard Drawing 110 WPB 528-001, Rev B, Sewage Piping A&D Coast Guard Drawing 110 WPB 561-001, Rev -, Steering System Details Coast Guard Drawing 110 WPB 561-002, Rev -, Steering System Details, Piping Coast Guard Drawing 110 WPB 561-002, Rev -, Steering System Details, Piping Coast Guard Drawing 110 WPB 565-002, Rev -, Fin Stabilization - Piping Coast Guard Drawing 110 WPB 601-002, Rev D, Outboard Profile & Weather Deck Coast Guard Drawing 110 WPB 621-001, Rev -, Joiner Work Details Coast Guard Drawing 110 WPB 621-002, Rev -, Joiner Work Details Coast Guard Drawing 110 WPB 621-003, Rev -, Joiner Work Details Coast Guard Drawing 110 WPB 621-004, Rev -, Joiner Work Details Coast Guard Drawing 110 WPB 625-003, Rev A, Windscreen Details Coast Guard Drawing 110 WPB 633-001, Rev A; Cathodic Protection Plan & Detail Coast Guard Drawing 110 WPB 635-001, Rev -, Linings & Insulation Plan & Details Coast Guard Drawing 110 WPB 636-001, Rev A, Noise Damping Details Coast Guard Drawing 110 WPB 641-001, Rev -, Officer and CPO Stateroom (Furniture Details) Coast Guard Drawing 110 WPB 643-001, Rev -, Furniture Details, Enlisted Men’s Fwd Qtrs Coast Guard Drawing 110 WPB 713-001, Rev -, Magazine Details (1301-1305) viii (Rev-1)

Coast Guard Drawing 110 WPB 85-007, Rev D, Booklet of General Plans Coast Guard Drawing 110B WPB 171-002, Rev -, Mast Details Coast Guard Drawing 110B WPB 321-003, Rev -, Main Wireways Coast Guard Drawing 110B WPB 601-027, Rev F, Outboard Profile & Weather Deck Coast Guard Drawing 110B WPB 641-002, Rev C, Officer and CPO Stateroom (Furniture Details) Coast Guard Drawing 110B WPB 643-001, Rev D, Furniture Details, Enlisted Men’s Fwd Qtrs Coast Guard Drawing 110B WPB 713-001, Rev D, Magazine Details Coast Guard Drawing 110B-WPB 079 001, Rev B, Damage Control Plan (Compts & Accessess) Coast Guard Drawing 110C WPB 161-005, Rev G, Stern Tube Installation Details Coast Guard Drawing 110C WPB 243-002, Rev B, Propulsion Shafting & Details Coast Guard Drawing 110C WPB 562-001, Rev G, Rudder Details (Stock & Blade Details) Coast Guard Drawing 110C WPB 565-001, Rev D, Fin Stabilization System (Struct Locs & Dets) Coast Guard Drawing 110C WPB 621-002, Rev A, Joiner Work Details (CPO & Crew Area) Coast Guard Drawing 110C WPB 635-001, Rev D, Linings & Insulation Plan & Details Coast Guard Drawing 110C WPB 636-001, Rev-, Noise Damping Details Coast Guard Drawing 110C WPB 641-002, Rev A, Officer and CPO Stateroom (Furniture Details) Coast Guard Drawing 110C WPB 643-001, Rev -, Furniture Details, Enlisted Men’s Fwd Qtrs Coast Guard Drawing 110C WPB 713-001, Rev -, Magazine Details Coast Guard Drawing 110-WPB 079-001, Rev -, Damage Control Plan Coast Guard Drawing 110-WPB 526_001, Rev D, Scuppers and Deck Drains Piping A&D Coast Guard Drawing 110-WPB 633-1, Rev A, Cathodic Protection Plan & Detail Coast Guard Drawing 110-WPB 633-2, Rev -, Cathodic Protection Installation Schematic & Layout Coast Guard Drawing 110-WPB_079_001, Rev -, Damage Control Plan Coast Guard Drawing 110-WPB_085_001, Rev -, Tank Capacity Curves Coast Guard Drawing 110-WPB_085_006, Rev A, Miscellaneous Construction Sketches Coast Guard Drawing 110-WPB_501_001, Rev E, Piping System Schematics Coast Guard Drawing 110-WPB_529-001, Rev C, Bilge Piping A&D Coast Guard Drawing 110-WPB_562_002, Rev D, Gray Water Piping Arrg’t & Dets Coast Guard Drawing 110-WPB-602-1, Rev A, Visual Identification Plan Coast Guard Drawing FL 6713-203, Rev -, CRP-V850 Transducer (SS505) Adapter Assembly Coast Guard Fleet Drawing FL 2804-12, Rev -, U.S.C.G. Emblem Coast Guard Fleet Drawing FL 2804-22, Rev-, Consolidated Visual ID for Cutters Coast Guard Technical Publication (TP) 4927, May 2009, Air Conditioning System Coast Guard Yard Drawing 110-WPB_079_001, Rev-, Damage Control Plan

COAST GUARD PUBLICATIONS

Coast Guard Commandant Instruction (COMDTINST) M10360.3, Jun 2006, Coatings and Colors

Manual Coast Guard Technical Publication (TP) 2924, Jun 1990, General Information Book and Operating

Manual for USCG 110 Foot Patrol Boat, Annex 1B, Propeller Renewal Procedure Coast Guard Technical Publication (TP) 3495 – Shaft Seal System – Duramax Installation Manual ix (Rev-1)

Coast Guard Technical Publication (TP) 3495, May 2002, Chapter 243, Installation Duramax Shaft Seal System

Coast Guard Technical Publication (TP) 3988, Sept 2011, Manufacturer’s Instruction Book - SWBS Group 311, Ships Service Diesel Generator

Coast Guard Technical Publication (TP) 4655, Sep 2007, Cathodic Protection System Coast Guard Technical Publications (TP) 4613, Manufacturer’s Instruction Book – SWBS GROUP(S)

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2020, General

Requirements, 2020, General Requirements Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2020, Welding and

Allied Processes Surface Forces Logistics Center Standard Specification 3020 (SFLC Std Spec 3020), 2020, Overhaul AC

Electrical Motors Surface Forces Logistics Center Standard Specification 5000 (SFLC Std Spec 5000), 2020, Auxiliary

Machine Systems Surface Forces Logistics Center Standard Specification 5100 (SFLC Std Spec 5100), 2020, Clean

Shipboard Ventilation Systems Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2020, Requirements for Preservation of Ship Structures Surface Forces Logistics Center Standard Specification 6341 (SFLC Std Spec 6341), 2020, Install Interior

Deck Covering Systems Surface Forces Logistics Center Standard Specification 8634 (SFLC Std Spec 8634), 2020, Drydocking Surface Forces Logistics Center Standard Specification 8635 (SFLC Std Spec 8635), 2020, Temporary

Services Surface Forces Logistics Center Standard Specification 8636 (SFLC Std Spec 8636), 2020, Temporary

Hull Accesses

OTHER REFERENCES

American National Standards Institute/American Society of Mechanical Engineers (ANSI/ASME), B4.1-

1967, (reaffirmed 2009), Preferred Limits and Fits for Cylindrical Parts American National Standards Institute/American Water Works Association (ANSI/AWWA) C652, 2011, Disinfection of Water-Storage Facilities American National Standards Institute/NSF International (ANSI/NSF) 61, 2015, Drinking Water System

Components - Health Effects American Society for Nondestructive Testing (ASNT) SNT-TC-1A, 2006, Recommended Practice for

Nondestructive Testing Personnel Qualification and Certification American Society of Mechanical Engineers (ASME) B16.34, 2004, Valves-Flanged, Threaded, and

Welding End American Society of Mechanical Engineers (ASME) B16.34, 2017, Valves-Flanged, Threaded, and

Welding End ASTM International (ASTM) D1330, 2010, Standard Specification for Rubber Sheet Gaskets ASTM International (ASTM) D1330, 2015, Standard Specification for Rubber Sheet Gaskets ASTM International (ASTM) D4138, 2013, Standard Practices for Measurement of Dry Film Thickness of Protective Coating Systems by Destructive, Cross-Sectioning Means ASTM International (ASTM) D5363, 2003, Standard Specification for Anaerobic Single Component

Adhesives x (Rev-1)

ASTM International (ASTM) D5363, 2016, Standard Specification for Anaerobic Single-Component Adhesives (AN)

ASTM International (ASTM) E797, 2005, Standard Practice for Measuring Thickness by Manual Ultrasonic Pulse-Echo Contact Method

ASTM International (ASTM) F992, 2006, Standard Specification for Valve Label Plates ASTM International (ASTM) F992, 2017, Standard Specification for Valve Label Plates ASTM International (ASTM), D3951, Re-approved 2004, Standard Practice for Commercial Packaging Commercial Item Description (CID) A-A-59316, Abrasive Materials for Blasting Commercial Item Description (CID) A-A-59588, 2013, Rubber Silicone Commercial Item Descriptions (CID) A-A-59323 A, 2005, Cloths, Cleaning, Low-Lint Federal Specification (Fed Spec) DDD-C-95, Mar 1972, Carpets and Rugs, Wool, Nylon, Acrylic, Modacrylic Federal Specification (Fed Spec) HH-P-151, Mar 1991, Packing; Rubber-Sheet, Cloth-Insert Federal Specification (Fed Spec) HH-P-151, Mar 1991, Packing; Rubber-Sheet, Cloth-Insert Federal Specification (Fed Spec) QQ-N-281, Oct 1985, Nickel-Copper Alloy Bar, Rod, Plate, Sheet, Strip, Wire, Forgings, and Structural and Special Shaped Sections Federal Standard (FED-STD) 595, 2008, Colors Used in Government Procurement Institute of Electrical and Electronic Engineers (IEEE), Standard 45, 2002, Recommended Practice for

Electrical Installations on Shipboard International Organization for Standardization (ISO) 484/2, 1981, Shipbuilding - Ship Screw Propeller -

Manufacturing tolerances - Part 2: Propellers of Diameter Between 0.80 and 2.50m, Inclusive International Standard Organization (ISO) 4406, 1999, Hydraulic Fluid Power – Fluids – Method for

Coding Level of Contamination by Solid Particles Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-61, 2013 Edition, Pressure Testing Of Steel Valves Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-67, 2017 Edition, Butterfly Valves Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-72, 2018 Edition, Ball Valves with Flanged or Butt-Welding Ends for General Service Manufacturers' Standardization Society of the Valve and Fittings Industry (MSS) SP-80, 2003 Edition, Bronze Gate, Globe, Angle and Check Valves Manufacturers' Standardization Society of the Valve and Fittings Industry (MSS) SP-80, 2013 Edition, Bronze Gate, Globe, Angle and Check Valves MIL-A-22262, Mar 1996, Abrasive Blasting Media Ship Hull Blast Cleaning MIL-A-24456, Jun 1979, Adhesive for Plastic-Vibration Damping Tile MIL-D-16791, Jan 1993, Detergents, General Purpose (Liquid, Nonionic) MIL-DTL-1222, Dec 2000, Studs, Bolts, Screws and Nuts for Applications Where a High Degree of

Reliability Is Required MIL-G-6032D(1), Grease, Plug Valve, Gasoline and Oil Resistant, NATO Code #G-636 MIL-PRF-16173, Sep 2006, Corrosion Preventive Compound, Solvent Cutback, Cold-Application MIL-PRF-24613, Dec 1990, Deck Covering Materials, Interior, Cosmetic Polymeric MIL-PRF-24635, 2009, Coating Systems, Weather-Resistant, Exterior Use MIL-PRF-24647, Jan 2018, Paint System, Anticorrosive and Antifouling, Ship Hull MIL-PRF-24667C, May 2008, Coating System, Non-Skid, for Roll, Spray, or Self-Adhering Application xi (Rev-1)

MIL-S-45180, 1998, Sealing Compound, Gasket, Hydrocarbon Fluid and Water Resistant MIL-S-8660C(2), Silicone Compound, NATO Code # S-736 MIL-STD-2148, Oct 1989, Vibration Damping Materials MIL-STD-2148, Oct 1989, Vibration Damping Materials, Procedures for Installation, Maintenance, and

Repairs Naval Sea Systems Command (NAVSEA) Underwater Ship Husbandry Manuals (UWSH) S0600-AA-

PRO-160, Jan 2011, Chapter 16, Cofferdams Naval Ships Systems Command Drawing 803-2145518, Rev G, Sprayshields for Mechanical Joints NAVSEA Drawing 803-921865, Rev P; Cathodic Protection Hull Zinc Anodes QPL-24667, May 2008, Qualified Product List (Military) of Products Qualified Under Detail

Specification MIL-PRF-24667, Coating System, Non-Skid, for Roll, Spray, or Self-Adhering Application

Society of Automotive Engineers (SAE) Aerospace Material Specification (AMS) C6183, 2019, Cork and Rubber Composition Sheet; for Aromatic Fuel and Oil Resistant Gaskets

Society of Automotive Engineers (SAE) Aerospace Material Specification (AMS) C6183, 2019, Cork and Rubber Composition Sheet; For Aromatic Fuel And Oil Resistant Gaskets

Society of Automotive Engineers (SAE) Aerospace Material Specification (AMS) C-6183B, 2019, Cork and Rubber Composition Sheet; for Aromatic Fuel and Oil Resistant Gaskets

Society of Automotive Engineers (SAE) Aerospace Material Specification (AMS) G-6032, 2014 Grease, Plug Valve, Gasoline and Oil Resistant, NATO Code Number G-363, Metric

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2020, General Requirements, 2018, General Requirements

The Society for Protective Coatings (SSPC) Surface Preparation Specification No.1 (SSPC-SP 1), 2004, Solvent Cleaning

The Society for Protective Coatings (SSPC) Surface Preparation Specification No.1 (SSPC-SP 1), 2016, Solvent Cleaning

The Society for Protective Coatings (SSPC) Surface Preparation Specification No.11 (SSPC-SP 11), 2004, Power Tool Cleaning to Bare Metal

The Society for Protective Coatings (SSPC) Surface Preparation Specification No.11 (SSPC-SP 11), 2012, Power-Tool Cleaning to Bare Metal

The Society for Protective Coatings (SSPC) Surface Preparation Specification No.3 (SSPC-SP 3), 2004, Power Tool Cleaning

The Society for Protective Coatings (SSPC), January 2015, Paint Application Specification No. 2 (PA-2), Procedure for Determining Conformance to Dry Coating Thickness Requirements

The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation Standard SSPC-SP 10/NACE No.2, 2004, Near-White Blast Cleaning

The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation Standard SSPC-SP 12/NACE No.5, 2002, Surface Preparation and Cleaning of Metals by Waterjetting Prior to Recoating

The Society for Protective Coatings (SSPC)/NACE-International (NACE) Joint Surface Preparation Standard SSPC-SP 10/NACE No. 2, 2007, Near-White Metal Blast Cleaning

Vosper Thornycroft Technical Bulletin No. 49, Jul 1992, Procedure for Fitting New Tiller Rod Eye Bearings to Actuators and Removing Redundant Grease Hose On BMS Island Class USCG Cutters xii (Rev-1)

CONSOLIDATED LIST OF GOVERNMENT-FURNISHED PROPERTY

The following is a list of property, which the Government will furnish. This list supersedes any other material obligations indicated or implied by referenced drawings.

WORK

ITEM

MTI ITEM DESCRIPTION NSN/PN QTY ESTIMATED

COST

($/UNIT)

5 N Shaft seal assembly kit NSN: 5330-01-497-8095 2 ea. 859.48 5 N Shaft seal assembly NSN: 4320-01-497-8057 2 ea. 3,111.84 5 N Emergency Shaft Seal

Inflator Kit NSN: 5330-01-497-9866 2 ea. 175.00

6 Y John Deere Genset Port engine

NSN: 6115-01-539-8540 1 ea. 44,433.00

6 Y John Deere Genset Starboard engine

NSN: 6115-01-540-3513 1 ea. 44,901.00

6 N 110' Soft Patch Kit NSN: 2040-01-469-1629 1 ea. 1,700.00 6 N Meter, Time Totalizing NSN: 6645-01-588-4890 2 ea. 47.39

17 Y *Transducer Cover Plate

N/A 1 ea. 50.00

26 N **Port spray ring NSN: 2990-01-475-9621 1 ea. 1,584.00 26 N **Starboard spray ring NSN: 2990-01-475-9620 1 ea. 1,584.00 26 N **Port 8" flapper valve NSN: 4810-01-475-8648 1 ea. 2,072.00 26 N **Starboard 8" flapper valve NSN: 4810-01-475-8415 1 ea. 2,072.00

26 N MDE gasket kit NSN: 5330-01-475-8157 2 ea. 389.45 26 N MDE gasket kit NSN: 5330-01-475-8169 2 ea. 312.52 26 N Exhaust gasket kit NSN: 5330-01-475-8804 4 ea. 128.24 26 N Turbo Charger gasket NSN: 5330-01-424-6806 2 ea 283.01 26 N Expansion bellows and flower pot to bellows NSN 5330-01-394-8528 6 ea 96.84

29 N **Transmitter, Liquid Quantity

NSN: 6680-01-233-9518 1 ea. 1,458.91

29 N **Non-Return Flapper Valve

NSN: 4820-01-217-8241 1 ea. 40.54

41 Y **Propeller, LH NSN: 2010-01-222-2440 1 ea. 23,445.00 41 Y **Propeller, RH NSN: 2010-01-222-2441 1 ea. 22,800.00 43 Y **Rudder NSN: 2040-01-223-2674 2 ea. 25,000.00 43 N **Lower Rudder

Bearing NSN 3120-01-477-8696 2 ea. 1,364.00

61 Y **Kraissl 2 ½” Duplex strainer

NSN: 4730-01-394-9731 4 ea. 3,900.00

61 Y **Kraissl 4” duplex strainer

NSN: 4730-01-173-1413 2 ea. 4,700.00

61 Y **Kraissl 1 ½” Duplex strainer for RO

PN:72-38F 1 ea. 600.00

*Government-loaned property, which shall be returned to the vessel upon completion of the availability.

**New or refurbished equipment that the Government may provide for installation in place of existing equipment.

***Government-furnished property, which is to be supplied by either the vessel or the C4IT ServiceCenter xiii (Rev-1)

CONSOLIDATED LIST OF CRITICAL INSPECTION ITEMS

The following is a list of work items, which contain Critical Inspection reports, which the Contractor must complete within the first 25% of the availability contract period (see SFLC Std Spec 0000, paragraph 3.2.6.5 (Inspection report particulars)):

Work Item Title

47 Impressed Current Cathodic Protection System, Inspect And Maintain

61 Sea Strainers - Duplex (All Sizes), Overhaul xiv (Rev-1)

PRINCIPAL CHARACTERISTICS

110’ WPB (A-CLASS)

PHYSICAL

Length overall 110' 0" or 113' if stern flap present Length between perpendiculars 104' 1/2" Depth 10' 1/2" Beam, molded 21' 1" Depth, molded 10' 11-1/4" Full load draft 6' 5-3/4" Height of highest projection 55' Full load displacement 165.1 long tons Anchor FX 125 Fortress with 400 ft of line Shore tie voltage requirements 450VAC 400A 3PH 60Hz ungrounded

HULL

Hull BS-4360, GR 43A Steel Main weatherdeck & superstructure 5086 Aluminum Alloy Frame spacing Various Bulkheads Seven watertight transverse Fin stabilizers Frame 22-1/2

MACHINERY

Main Propulsion Two Paxman Type 16 RP200M (Valenta) V-16 Diesel; 2880 BHP each @ 1500 RPM

(max) Reduction Gears Two ZF Model BW 1500 reversible reduction gearboxes; 1.839:1 ratio

Number of Propellers 2 Number of Blades 5 Diameter of Propeller 49.6" Pitch 61.4"

RPM N/A

Shaft AQUAMET 17 Shaft Diameter 4" Shaft Seal Johnson Duramax split face seal Shaft Bearings Rubber Cutless or Thordon Rudders Twin underslung type, 5 sq ft each Ship's Service Generators Northern Lights M1066A1-130KW

TANK CAPACITIES

Fuel Oil (95%) 10,317 gal.

Fresh Water (100%) 1,760 gal.

Lubricating Oil (95%) 115 gal.

xv (Rev-1)

1 (Rev-1)

00000_0220_FLT

REC_00000_FLT_Commercial Project @ Contractor’ Facility (1212)

General Requirements

1. SCOPE

1.1 Intent. This standard specification invokes general requirements for conducting vessel repairs performed at a commercial contractor’s facility for Coast Guard vessels.

1.2 Term interchangeability. The terms 'Contractor', 'CG Yard', 'NAVSTA EVERETT', 'shipyard', 'Base', and 'Coast Guard Industrial' are used interchangeably in this specification. Where the primary service provider is Coast Guard personnel, references to contractor and other noted descriptors within this specification or within drawings, publications, SFLC Standard Specifications or other commercial and military references are deemed the same as prime service provider.

2. REFERENCES

COAST GUARD DRAWINGS

None

COAST GUARD PUBLICATIONS

Coast Guard Commandant Instruction (COMDTINST) M10360.3 (series), Coatings and Color Manual Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2020, General

Requirements, 2018, General Requirements Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2020, Welding and

Allied Processes Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2020, Requirements for Preservation of Ship Structures

OTHER REFERENCES

None

3. REQUIREMENTS

3.1 General. The Contractor shall conform to all requirements specified in SFLC Std Spec 0000 and in this item, as applicable, during the performance of this availability.

NOTE

The requirements of paragraph 3.1 (General) applies to all work under the scope of this contract, whether explicitly stated in work items or not, and to all other work subsequently authorized by changes, modifications, or extensions to the contract.

2 (Rev-1)

3.2 Contractor-provided fire watch personnel. The Contractor shall provide fire watch personnel and equipment.

3.3 Preservation requirements. The Contractor shall accomplish all preservation tasks, including touch-ups, in accordance with SFLC Std Spec 6310.

3.3.1 Brand name approval. Ensure that all contractor-furnished coatings are in accordance with SFLC Std Spec 6310, Appendix C (Authorized Coatings for Use on Cutters and Boats).

3.3.2 Coating colors and system color schemes. Ensure that all colors and color coat/paint schemes are in accordance with COMDTINST M10360.3, Chapter 6 (Cutter and Boat Colors Exterior and Interior).

NOTE

Unless a waiver has been granted (in writing) by the KO, deviations from authorized coatings (listed in Appendix C of SFLC Std Spec 6310) and colors and color schemes (provided in Chapter 6 of COMDTINST M10360.3) are strictly prohibited.

3.4 Welding and brazing requirements. The Contractor shall perform all welding and allied processes, and NDE in accordance with SFLC Std Spec 0740.

3.5 Environmental protection requirements. The Contractor shall adhere to the following environmental protection requirements in accordance with the SFLC Stand Spec 0000:

3.5.1 Contractor operated (non USCG) facilities. The Contractor shall provide and maintain environmental protection as defined in SFLC Std Spec 0000 Appendix A, Requirements for Environmental Protection at Contractor Operated (Non USCG) Facilities, as applicable, during the performance of this availability. Contractor shall plan for and provide environmental protective measures to control pollution that develops during normal practice, as well as plan for and provide environmental protective measures required to correct conditions that develop during the project. Contractor shall comply with applicable Federal, state, and local laws, codes, ordinances, and regulations in their entirety. Any reference to a specific portion of a Federal, state, or local law, code, ordinance, or regulation in this or any other item shall not be construed to mean that relief is provided from any other sections of the law, code, ordinance, or regulation.

3.5.2 Test and procedures. The Contractor shall be required to promptly conduct tests and procedures for the purpose of assessing whether operations are in compliance with applicable Environmental Laws. Analytical work shall be done by qualified laboratories; and where required by law, the laboratories shall be certified.

3.5.3 Regulatory notifications. The Contractor shall be responsible for all regulatory notification requirements in accordance with Federal, State and local regulations. In cases where the Coast Guard must also provide public notification, such as storm water permitting, the Contractor must coordinate with the Contracting Officer or COR, and if work is being performed at a USCG Facility, the local Facility Engineer or Engineering Officer. The Contractor shall submit copies of all regulatory notifications to the Contracting Officer and the local Facility Engineer or Engineering Officer prior to commencement of work activities. Regulatory notifications shall be provided for including but not limited to demolition, renovation, National Pollutant Discharge Elimination System (NPDES) defined site work, and remediation of controlled substances such as asbestos, hazardous waste, and lead paint.

3.5.4 Environmental manager. The Contractor shall appoint in writing an Environmental Manager for the project, and shall be responsible for coordinating Contractor compliance with Federal, State, local, and station environmental requirements. The Environmental Manager shall ensure compliance with Hazardous Waste Program requirements, including hazardous waste handling, storage, manifesting, and disposal; implement the Contractors’ Environmental Management Plan; ensure that all environmental permits are obtained, maintained, 3 (Rev-1) and closed out; ensure compliance with Storm Water Program Management requirements; ensure compliance with Hazardous Materials including storage, handling, and reporting requirements; as well as coordinate any remediation of regulated substances such as lead, asbestos, and polychlorinated biphenyl (PCB). This may be a collateral position; however the individual must be trained to accomplish the following duties; ensure waste segregation and storage compatibility requirements are met; inspect and manage Satellite Accumulation areas;

ensure only authorized personnel add wastes to containers; ensure all Contractor personnel are trained in 40 CFR requirements and individual position requirements; coordinate removal of waste containers; and maintain the Environmental Records binder and required documentation, including environmental permits compliance and close-out.

3.5.5 HW disposal. Contractor shall comply with SFLC Std Spec 0000 Appendix A, Requirements For Environmental Protection At Contractor Operated (Non USCG) Facilities for HW disposal.

3.6 Local Policy. None.

3.7 SFLC Standard Specification approved changes. The Contractor shall be aware that the following are approved changes to published SFLC 2018 Edition Standard Specifications and supersede published content:

None.

4. NOTES

4.1 QA inspection forms. QA inspection forms (QA-1 thru QA-5), required in SFLC Std Spec 6310 to be completed and submitted during preservation of “critical-coated surfaces”, are provided at the end of this document.

4 (Rev-1)

QA-1 - QUALITY ASSURANCE INSPECTION FORM

(PRESERVATION CHECKLIST)

VESSEL NAME HULL # WORK ITEM

WORK ITEM TITLE

LOCATION OF WORK (INCL. FRAME #’S) AREA (SQFT)

CHECKPOINT 1 – COATING SYSTEM COMPLIANCE

Ensure all coatings are in compliance with SFLC Std Spec 6310, Appendix C.

CHECKPOINT 2 - PAINT STORAGE

Ensure all coatings are kept at a temperature of 65 to 85°F at all times, unless otherwise specified by the coating mfg.

CHECKPOINT 3 - AMBIENT CONDITIONS

Ensure surface and surrounding temperatures are each between 50 and 90°F for water-containing coatings, and 35 and 95°F for other coatings, unless otherwise specified by the coating manufacturer(s).

Ensure maximum relative humidity (RH) is as follows, from surface preparations through final curing of topcoat: 50% for tanks, voids, and vent plenum; and 85% for all other areas, unless otherwise specified by manufacturer(s).

Ensure surface temperature is at least 5°F above the dew point, unless otherwise specified by the coating mfg.

CHECKPOINT 4 - PRE-SURFACE PREPARATION

Remove surface contaminants (soluble salts, loose rust, mud, and marine growth) with low pressure fresh water wash down (maximum 5,000 psi). If oil and grease are present, perform solvent cleaning, as per SSPC SP-1.

Verify equipment setup, blast media, and surface preparation methods match designated test coupon.

CHECKPOINT 5 - SURFACE PREPARATION

Verify environmental conditions (see CHECKPOINT 3).

Ensure cleanliness of prepared surface is as per specification (i.e.: SSPC SP-11, SP-10, SP WJ-2…).

Verify surface anchor profile using ASTM D4417-Methods B or C against SFLC Std Spec 6310. Conduct profile readings at a minimum of 5 locations for the first 1000-sqft area, and 2 locations for each succeeding 1000-sqft area.

Measure soluble salt conductivity in accordance with SSPC-Guide 15. Conduct 5 measurements per each 1000-sqft area (max. threshold: 70 microsiemens/cm for non-submerged surfaces, 30 microsiemens/cm for submerged surfaces).

CHECKPOINT 6 - PRIMER COAT APPLICATION

Verify environmental conditions (see CHECKPOINT 3).

Verify proper mixing and stand-in (induction) times.

Ensure no paint is applied when the temperature is expected to drop to freezing before the paint has dried.

Ensure surfaces are completely dry, unless otherwise allowed by the coating manufacturer(s).

Verify wet film thickness (WFT) at random, to prevent under or over application. Verify final DFT.

Brush out all runs, sags, drips, and puddles.

Perform visual inspection for holidays and other defects.

CHECKPOINT 7 – STRIPE COAT APPLICATION

Verify environmental conditions (see CHECKPOINT 3).

Ensure overcoating window is as per manufacturer’s instructions.

After primer coat (mist coat after inorganic zinc), brush-apply un-thinned coat of same primer paint over edges, weld seams, cut-outs, and areas of complex geometries @ 3-4 mils wet film thickness (WFT).

CHECKPOINT 8 – TOP COAT APPLICATION

Verify environmental conditions (see CHECKPOINT 3).

Ensure overcoating window is as per manufacturer’s instructions.

Verify proper mixing and stand-in (induction) times, as applicable.

Verify wet film thickness at random, to prevent under or over application.

Brush out all runs, sags, drips, and puddles.

CHECKPOINT 9 – FINAL INSPECTION

Verify final system dry film thickness. Conduct 5 sets of 3 readings for each of the first 3 100-sqft areas, followed by 5 sets of 3 readings for each succeeding 1000-sqft area.

Ensure that system cure is in accordance with manufacturer's recommendation for intended service.

Ensure potable water tank exhaust ventilation is maintained continuously from and during coating application through final system cure, to exhaust all solvent to the atmosphere and to prevent solvent entrapment.

For immersion coatings (including tank U/W body), record date and time of the following events:

Final coat application: _____/_____; Return to service or removal from environment controls: _____/_____

CHECKPOINT 10 – RECORD KEEPING

Complete, sign, and submit all provided QA Inspection Forms.

NAME OF QP-1/NACE INSPECTOR SIGNATURE CERT. # DATE / TIME

5 (Rev-1)

QA-2 - QUALITY ASSURANCE INSPECTION FORM

(ENVIRONMENTAL READINGS)

VESSEL NAME HULL # WORK ITEM

# WORK ITEM TITLE

Use one sheet for each activity. Record conditions every four hours from before surface preparation to application of final coating system coat.

DATE

TIME

ACTIVITY (SURFACE

PREPARATION, PRIMER COAT,

BARRIER COAT, TOP COAT,

ETC…)

LOCATION (FRAME &

DECK, RELATION TO

EQUIPMENT, ETC.)

TEMPERATURE % REL.

HUMID-

ITY

DEW

PT.

SURFACE AMBIENT ΔT

| DP -

SURFACE |

NAME OF QP-1/NACE INSPECTOR SIGNATURE CERT. # DATE / TIME

6 (Rev-1)

QA-3A - QUALITY ASSURANCE INSPECTION FORM

(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-C)

VESSEL NAME HULL # WORK ITEM

SURFACE PREPARATION METHOD PROFILE ACHIEVED (MILS)

MIN MAX MEAN

SSPC-SP-10/NACE No. 2

SSPC-SP WJ-1/NACE WJ-1

SSPC-SP WJ-2/NACE WJ-2

SSPC-SP WJ-3/NACE WJ-3

SSPC-SP WJ-4/NACE WJ-4

SSPC-SP-3

SSPC-SP-11

SSPC-SP-11 (inaccessible area) Brush-blasting (non-metallic substrate)

ABRASIVE MANUFACTURER: ABRASIVE SIEVE SIZE:

PLACE SURFACE PROFILE REPLICA TAPES IN THE SPACES PROVIDED BELOW, TO SERVE AS

PERMANENT QA RECORD. MAINTAIN A SEPARATE LOG FOR EACH LOCATION. WHEN AN AREA IS

DIVIDED INTO SEPARATE SECTIONS, MAINTAIN A SEPARATE LOG FOR EACH SECTION.

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Reading (mils): Reading (mils): Reading (mils):

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Reading (mils): Reading (mils): Reading (mils):

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Reading (mils): Reading (mils): Reading (mils):

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Reading (mils): Reading (mils): Reading (mils):

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Reading (mils): Reading (mils): Reading (mils):

MEAN MIL READING (IAW ASTM D4417-METHOD C) FOR ABOVE 15 READINGS:

NAME OF QP-1/NACE INSPECTOR SIGNATURE CERT. # DATE /

TIME

7 (Rev-1)

QA-3B - QUALITY ASSURANCE INSPECTION FORM

(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-B)

VESSEL NAME HULL # WORK ITEM

SURFACE PREPARATION METHOD PROFILE ACHIEVED (MILS)

MIN MAX MEAN

SSPC-SP-10/NACE No. 2

SSPC-SP WJ-1/NACE WJ-1

SSPC-SP WJ-2/NACE WJ-2

SSPC-SP WJ-3/NACE WJ-3

SSPC-SP WJ-4/NACE WJ-4

SSPC-SP-3

SSPC-SP-11

SSPC-SP-11 (inaccessible area) Brush-blasting (non-metallic substrate)

ABRASIVE MANUFACTURER: ABRASIVE SIEVE SIZE:

RECORD MEASUREMENTS TAKEN IN THE SPACES PROVIDED BELOW, TO SERVE AS PERMANENT QA

RECORD. MAINTAIN SEPARATE LOG FOR EACH LOCATION. WHEN AN AREA IS DIVIDED INTO

SEPARATE SECTIONS, MAINTAIN A SEPARATE LOG FOR EACH SECTION.

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Mean Reading (mils)

Mean Reading (mils) IAW ASTM DD4417).

8 (Rev-1)

QA-4 - QUALITY ASSURANCE INSPECTION FORM

(SURFACE SOLUBLE SALT CONDUCTIVITY LOG)

VESSEL NAME HULL # WORK ITEM

SOLUBLE SALT CONDUCTIVITY MEASUREMENTS IAW SSPC-GUIDE 15.

DATE TEST LOCATIONS CONDUCTIVITY (MICROSIEMENS/CM)

9 (Rev-1)

QA-5 - QUALITY ASSURANCE DATA FORM

(COATING THICKNESS)

(Use one sheet for each sequence)

VESSEL NAME HULL # WORK ITEM

# WORK ITEM TITLE

COATING MFG PRODUCT NAME BATC

H #

INDUCTI

ON TIME

COATING SYSTEM

SEQUENCE

(PRIMER/TOUCHUP/3RD

COAT, ETC.)

DRY FILM THICKNESS (DFT) MEASUREMENTS IAW SSPC-PA 2.

SPOT 1 2 3 4 5 AVERAGE

VALUE

*BASE METAL READING

(BMR) Required, If Magnetic Pull-Off (Type I/Banana) Gauge Is Used.

LOCATION (FRAME REFERENCE):

SPOT 1 2 3 4 5 OVERALL AVG. DFT ADJUSTMENTS

1 AVG. BMR DEVIATION

3 BEFORE ADJUSTMENTS AFTER ADJUSTMENTS

AVG.

1 AVG. BMR DEVIATION

1 AVG. BMR DEVIATION

APPLICATION METHOD (AIRLESS,

CONVENTIONAL SPRAY, ROLLED)

AVERAGE DFT

10 (Rev-1)

24360_DFM_0320_110WPB

WORK ITEM 1: Mechanical Shaft Seal Assemblies, Overhaul

1. SCOPE

1.1 Intent. This work item describes the requirements for the Contractor to overhaul the mechanical shaft seal assemblies on the port and starboard propeller shafts.

1.2 Government-furnished property.

MTI ITEM DESCRIPTION NSN/PN QTY ESTIMATED

COST

($/UNIT)

N Shaft seal assembly kit NSN: 5330-01-497-8095 2 ea. 859.48 N Shaft seal assembly NSN: 4320-01-497-8057 2 ea. 3,111.84

N Emergency Shaft Seal Inflator Kit NSN: 5330-01-497-9866 2 ea. 175.00

**New or refurbished equipment that the Government may provide for installation in place of existing equipment.

2. REFERENCES

COAST GUARD DRAWINGS

Coast Guard Drawing 110C WPB 161-005, Rev G, Stern Tube Installation Details

COAST GUARD PUBLICATIONS

Coast Guard Technical Publication (TP) 3495, May 2002, Chapter 243, Installation Duramax

Shaft Seal System Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2020, General Requirements, 2018, General Requirements Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2020, Requirements for Preservation of Ship Structures

OTHER REFERENCES

None

3. REQUIREMENTS

3.1 General.

3.1.1 CIR.

11 (Rev-1)

None.

3.1.2 Tech Rep.

Not applicable.

3.1.3 Protective measures. The Contractor shall furnish and install all protective coverings to seal off and protect all non-affected vessel's components, equipment, and spaces near the work area against contamination during the performance of work. Upon completion of work, the Contractor shall remove all installed protective measures, inspect for the presence of contamination, and return all contaminated equipment, components, and spaces to original condition of cleanliness.

3.1.4 Interferences. The Contractor shall handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences). Known interferences include, but are not limited to the following:

• Deck plate.

• Deck plate framing.

• Propulsion shaft.

3.2 Seal overhaul particulars. The Contractor shall accomplish the following for each shaft seal assembly, using TP-3495 as a guide:

• Disassemble and remove the shaft seal assembly and emergency shaft seal inflator system.

• Clean all components free of marine growth.

• Perform visual inspection of cleaned components. Submit CFR.

• Renew all seal components with Government-furnished shaft seal assembly kit and emergency shaft seal inflator.

• Renew shaft seal cooling flex hoses.

• Reassemble and reinstall the seal assembly.

CAUTION

Do not rotate shaft during overhaul tasks.

NOTE

The seal inflator adaptor is of universal length and will require adjustments.

3.2.1 The Contractor shall measure, cut, and fit the inflator adaptor to the length required to achieve a depth that passes into the center chamber of the inflator but not touch the inside wall of the interior diameter. The seal inflator adaptor end shall be rounded following the cutting to length, to prevent rubbing/chaffing. When installed and the seal inflation cycled, the seal must return to a fully relaxed position with no visible bulging or protrusion in the seal inflator adaptor area.

3.2.2 Prior to installing the mechanical shaft seal assembly on the cutter, the Contractor shall perform NDT testing of the newly installed shaft seal inflator. Install a 4-inch stub shaft into the emergency shaft seal of similar or better surface finish of the propulsion shaft. Inflate the emergency shaft seal inflator to a pressure of 15 psi to engage seal, maximum 40 psi. Visually inspect the seal to ensure that it inflates uniformly around the shaft and is not bulging or otherwise displaying signs of mechanical derangement or seal compromise. Leave the emergency shaft seal inflated with the stub shaft installed and submerge the

12 (Rev-1) system in water for 5-minutes. Inspect for signs of air leaks from the emergency shaft seal inflation tube or Schraeder valve assembly. Remove the emergency shaft seal inflator and stub shaft from the water and orient the inflator with the mounting flange facing up. Fill the cavity between the stub shaft and seal housing with water up to the mounting flange. After 5-minutes have elapsed, inspect the water level in the seal housing for signs of leakage. No visible air or water leaks are permitted. Make repairs as necessary to obtain a leak free condition. Submit a CFR.

3.2.3 After the propulsion shafts have been installed and coupled to the reduction gear output flanges, the Contractor shall perform a clearance measurement between the propulsion shaft and the shaft seal adapter flange thru the emergency inflator boss across the vertical and horizontal planes; make any adjustments necessary to re-center the seal around the shaft. Submit a CFR.

NOTE

Minor relocating of the shaft seal adapter flange within the mechanical limits of the pilot grooves is authorized to achieve the Duramax running clearance tolerances between the propulsion shaft to shaft seal adapter flange. It is IMPORTANT that upon installation of the Duramax Marine Shaft Seal System that the propeller shaft is as close to the center of the friction ring as possible. Failure to center the shaft could cause it to hit the inside of the friction ring. If this happens the seal faces could separate and drip.

3.3 Government right to change out seal assembly. The Contractor shall be aware that the Government reserves the right to furnish up to two new shaft seal assemblies in lieu of overhauling the seals, at no additional cost to the Government.

3.4 Seal venting. After launching the cutter and in the presence of the Coast Guard Inspector, the Contractor shall remove the cooling water injection lines from both seals and allow the stern tube and seal assemblies to flood with water, in accordance with the manufacturer’s guidance in TP 3495 and CG Drawing 110C WPB 161-005. When the air is vented from the seal assemblies re-connect the injection lines.

WARNING

Do not rotate shaft until the stern tubes have been vented.

3.5 Operational test, post repairs. After completion of work and in the presence of the Coast Guard Inspector, the Contractor shall thoroughly test and demonstrate the equipment listed below to be in satisfactory operating condition. Submit a CFR.

• Shaft seal assembly

NOTE

Pay special attention to water leaks, abnormal noises, and any binding in normal shaft operation.

3.6 Touch-up preservation. The Contractor shall prepare and coat all new and disturbed surfaces to match existing adjacent surfaces in accordance with SFLC Std Spec 6310, paragraph 3.1.13 (Touch-ups and minor coating repairs).

13 (Rev-1)

4. NOTES

4.1 Coast Guard personnel. Coast Guard personnel will operate all equipment and machinery.

14 (Rev-1)

31100_ENV_0230_110WPB

WORK ITEM 2: Ship Service Diesel Generator(s) (John Deere), Renew

1. SCOPE

1.1 Intent. This work item describes the requirements for the Contractor to renew the port and starboard ships service diesel generators, including diesel engines.

1.2 Government-furnished property.

MTI ITEM DESCRIPTION NSN/PN QTY ESTIMATED

COST

($/UNIT)

Y John Deere Genset Port engine NSN: 6115-01-539-8540 1 ea. 44,433.00

Y John Deere Genset Starboard engine NSN: 6115-01-540-3513 1 ea. 44,901.00

N 110' Soft Patch Kit NSN: 2040-01-469-1629 1 ea. 1,700.00 N Meter, Time Totalizing NSN: 6645-01-588-4890 2 ea. 47.39

*Government-loaned property, which shall be returned to the vessel upon completion of the availability.

**New or refurbished equipment that the Government may provide for installation in place of existing equipment.

***Government-furnished property, which is to be supplied by either the vessel or the C4IT Service Center.

2. REFERENCES

COAST GUARD DRAWINGS

Coast Guard Drawing 110 WPB 183-003, Rev B, Generator Foundations Modifications Coast Guard Drawing 110 WPB 201-003, Rev -, Machinery Arrangement Coast Guard Drawing 110 WPB 259-002, Rev -, Genset Exhaust Piping System Coast Guard Drawing 110 WPB 320-001, Rev D, Ships Service Power 1-Line Diagram

COAST GUARD PUBLICATIONS

Surface Forces…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .