This Statement of Work (SOW) details a water slide removal and installation project at the Barksdale Air Force Base Main Base Pool located at 335 Daedalus Ave #301, Barksdale AFB, LA. The contractor will remove existing water slides and install three new 4 Flum Pacific Ocan Slides with varying lengths (18', 16', and 12') and a deck height of 18ft. Each slide will have a 30" flume diameter. The project is part of a renovation to update pool facilities' safety and appearance, with the contractor responsible for removing and disposing of old slides, installing new slides using existing hardware, and ensuring the installation meets OSHA standards.
The SOW includes comprehensive security requirements for base entry, including visitor pass procedures, vehicle access restrictions, and conduct guidelines. Contractors must complete a 2SFS/SFA Form 74 for base access, comply with base traffic regulations, and are prohibited from carrying weapons. Additional requirements include maintaining a safety plan, providing personal protective equipment, reporting accidents, and managing records in accordance with Air Force instructions. The contractor must also safeguard government property and secure facilities at the end of each work period.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work
MAIN BASE POOL WATER SLIDE REMOVAL/INSTALLATION
PREPARED BY 2 FSS BARKSDALE AFB, LA
06 MARCH 2025
FA460825QS018
Attachment 2- Statement of Work
1. Description of work:
1.1. Scope of Work. Contractor will be removing the existing water slides from the pool and then installing new waterslides in their place.
1.2. Place of Performance. At the Barksdale Air Force Base Main Base Pool: 335
Daedalus Ave #301, Barksdale AFB, LA.
2. Background: Barksdale AFB is completing a renovation to update the existing pool facilities to update the safety and appearance of the existing pool.
3. Discussion: Contractor will be removing the current water slides from the pool deck and installing new waterslides in their place to ensure the installation meets OSHA standards.
3.1. Removal of Existing Slides: Contractor will be responsible for the removal and disposal of the existing slides.
3.2. Installation of New Slides: The new slides will be installed into the existing hardware on the pool deck. Contractor will be responsible for ensuring the existing hardware is in good condition and replacing any hardware as needed.
3.3. Equipment and Supplies: The contractor shall provide all personnel, equipment, tools, supervision, and other items and/or services necessary for water slide removal and installation.
3.3.1. Slide Replacement: Contractor will provide and install a new 4 Flum Pacific Ocan Slide. The deck height of the slides is 18ft and the slides’ flume diameters are each 30”. Slide 1 is 18’, slide 2 is 16’, and slide 3 is 12’.
4. Security Requirements:
4.1. Visitor Passes: To receive a visitor, pass the contactor much complete a 2SFS/SFA
Form 74, and fax that form to the Contract Administrator. This form will be sent to the successful offer or upon request. This information will be reviewed and forwarded to the passing office. If a pass is approved, the Commercial Visitor Control Center will issue a SFMIS AF Form 75 (Visitor Pass) to the contractor and his/her employees upon completion of screening process for the duration of the contract. The screening process takes time, and the contractor shall visit the Commercial Visitor Control Center prior to expecting base entry to receive the required forms and instruction on the application process (to include estimated time of receiving the visitor pass). Although contractors will not be issued vehicle passes, vehicles will be subject to search while on the installation. Employee privately owned vehicles will not be allowed access to the restricted/controlled areas without a free zone being established. Company vehicles will be allowed access to restricted/controlled areas. All Contactor vehicles should have marking with the company name for quick identification of ownership and notification if they are involved in an incident. Conduct Requirements: The contractor shall ensure
FA460825QS018
that his/her employees comply with all base traffic regulations and properly conduct themselves while on the base.
4.2. Retrieving Identification Media: The Contractor shall be responsible for retrieving all identification media including vehicle passes from employees who depart for any reason before the contract expires (e.g., terminate for cause, retirement, etc.).
4.3. Traffic compliance: The contractor and contractor employees shall comply with base traffic regulations.
4.4. Weapons, Firearms, Ammunition: Contractor employees are prohibited from possessing weapons, firearms, and ammunition on themselves or within their contractor or privately owned vehicles while on base.
4.5. Safeguarding government property and materials: The Contractor shall be responsible for safeguarding all government property, and controlled forms provided for contractor use. At the end of each work period, Contractor shall secure all Government facilities, equipment, and materials.
4.6. Records Management: The Contractor shall manage all data created for Government use or legally controlled by the Government, in support of the functional activity or required by AF publication, IAW with the AF Records Management procedures in Air Force Instruction (AFI) 33-322, Air Force Manual (AFMAN) 33-363 and Air Force Instruction (AFI) 33-364 (or their subsequent replacements)
5. Safety: The Contractor shall have a safety plan for their employees. The Contractor shall instruct each employee in the recognition and avoidance of unsafe conditions and regulations to his or her work environment to control or eliminate any hazards or other exposure to illness or injury. The Contractor shall provide their employees appropriate Personal Protective Equipment (PPE) and mandate proper wear.
6. Accident/Incident Reporting and Investigation. Contractor shall record and report to the Main Base Pool POC all available facts relating to each instance of accidental damage to Government property or injury to either Contractor or Government personnel. The Contractor shall secure the accident scene and wreckage until released by the accident investigative authority through the Main Base Pool POC. If the Government elects to investigate the incident, the Contractor shall cooperate fully and assist the Government personnel until the investigation is completed.