STATEMENT OF WORK
3-25 AVN REGT
M978 HEMTT Fueler Purge
Wheeler Army Airfield, HI 96786
3-25 AVN REGT M978 HEMTT Fueler Purge
PROJECT DESCRIPTION: Furnish all labor, equipment, and materials for performing the following requirements. To accomplish this objective, complete, capable and ready for operation under the provision section of the contract, the Unified Facilities Criteria (UFC) and the following sections of this contract, the Contractor shall:
Fully empty all fuel, fuel contaminants, debris, and water from the HEMTT main tank, and all associated pumps and lines
Fully purge the main tank and all associated pumps and lines with purging solution, so that no fuel, water, debris or other contaminants.
Written Records
After the award of the contract, the contractor shall provide a drop off, completion and pick up schedule for all vehicles.
GOVERNMENT REVIEW COMMENTS
Prior to the Notice to Proceed, the Contractor shall submit, for approval, a complete schedule. This will be updated as needed based on job completion.
Upon receipt of a submittal, the Government shall do a cursory check of quality and quantity. If submittal is lacking, it will be returned for correction and resubmission.
The review time will begin when the corrected submittal is received. If an otherwise satisfactory submittal is over one (1) day late in accordance with the latest design schedule, the Government review period may be extended up to seven (7) days.
After satisfactory submittal receipt, the Government will be allowed fourteen (14) days to review and agree.
The review will be for conformance with the contract. The Contractor shall respond to all comments in advance of the next scheduled submittal. The response shall identify action taken with citation of location within the relevant document.
Generalized statements of intention such as “will comply” or “will revise the specification” are not acceptable.
ANTITERRORISM/OPERATIONS SECURITY
1. AT Level I Training. This provision/contract text is for contractor employees with an area of performance within an Army controlled installation, facility or area. All contractor employees, to include subcontractor employees, requiring access Army installations, facilities and controlled access areas shall complete AT Level I awareness training within 45 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable. The contractor shall submit certificates of completion for each affected contractor employee and subcontractor employee, to the COR or to the contracting officer, if a COR is not assigned, within 30 calendar days after completion of training by all employees and subcontractor personnel. AT level I awareness training is available at the following website:
https://atlevel1.dtic.mil/at.
2. Access and General Protection/Security Policy and Procedures. This standard language text is for contractor employees with an area of performance within an Army controlled installation, facility or area. Contractor and all associated sub-contractors employees shall comply with applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative). The contractor shall also provide all information required for background checks to meet installation access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services or Security Office.
Contractor workforce must comply with all personal identity verification requirements as directed by DOD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any individual facility or installation change, the Government may require changes in contractor security matters or processes.
3. iWATCH Training. This standard language is for contractor employees with an area of performance within an Army controlled installation, facility or area. The contractor and all associated sub-contractors shall brief all employees on the local iWATCH program (training standards provided by the requiring activity ATO). This local developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the COR. This training shall be completed within 45 calendar days of contract award and within 20 calendar days of new employees commencing performance with the results reported to the COR NLT 45 calendar days after contract award.