Attachment_2_-Statement_of_Work_0001.pdf
PDF 98 KB Posted
- Attached to
- 2022 CFO TEST HOLES
- Solicitation number
- 140L0622Q0040
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
TITLE: Test Holes for Avalon Lake Mineral Materials Report
SOW PART A – GENERAL INFORMATION
A.1 INTRODUCTION
Excavate, re-fill 6 – 6ft x 6ft mineral material test holes (max depth ~20ft) with a contracted trackhoe on acreage north of Carlsbad, NM.
A.2 BACKGROUND
The City of Carlsbad has approached the BLM with interest in purchasing approximately 550 acres just north of Carlsbad, NM for the purpose of building low-income housing. The Solid Minerals Department of the Bureau of Land Management's Carlsbad Field Office is therefore required to create a Mineral Materials Report for approximately 550 acres on the north side of Carlsbad, NM.
A.3 SCOPE OF WORK
The proposed action (PA) is to dig 6 test holes at points across the area to assess mineral material potential and value on the sale acreage. The contractor shall dig the test holes no larger than 6 ft. x 6 ft. and will be up to 20 ft. deep. To accomplish this, a trackhoe shall enter from the George Shoup Relief Route and proceed southward along the roads. Test holes have been positioned along pre-existing lease roads for ease of access and to minimalize disturbance. All holes shall be filled in and leveled once measurements are complete. Equipment tracks will be leveled as necessary.
SOW PART B – WORK REQUIREMENTS
TECHNICAL REQUIREMENTS
B.1 IDENTIFY TASK 1
B.2 QUALIFICATIONS
Minimum qualification is Contractor is in the business of excavation and in the possession of a trackhoe that can dig up to 20ft deep.
DELIVERABLES
B.3 TASK 1 DELIVERABLE
SOW PART C – SUPPORTING INFORMATION
C.1 PLACE OF PERFORMANCE
The northern access road to the acreage is located approximately 1.8 miles east of the intersection of Highway 285 and the George Shoup Relief Route.
C.2 PERIOD OF PERFORMANCE
Performance to be completed within 30 days of award.
C.3 SPECIAL CONSIDERATIONS
C.3.1 GOVERNMENT-FURNISHED MATERIALS AND SERVICES
No government-furnished property will be provided to the contractor
C.4 KEY PERSONNEL
Contractor
The contractor shall identify, by name, the key management, technical, and/or instructor personnel who will work under this contract. Substitutions of key personnel shall be made only as directed by the Key Personnel clause of this contract.
File details come from the government source that posted it. Updated .