Attachment 2 - Specifications.pdf
PDF 4 MB Posted
- Solicitation number
- W912P922C0019
About this file
This award notice announces a contract for the Canal Road Pump Stations Number 2 and 3 at Wood River Levee District project. The work includes installation of two pump stations and two relief wells to be 10 inches in diameter and approximately 65 feet deep. Additional features are pavement restoration, stone protection, chain link fencing, inlet channels, holding bays, trash racks, sluice gates, power distribution, pump control systems, station lighting, guardrail and canopies, grounding and lighting protection, and variable drives. The contract was awarded on September 28, 2022 to Magruder Construction Co. Inc. for $7,527,300. The awarding agency is the Department of the Army Corps of Engineers Engineering District St Louis.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Attachment 1 - Plans.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
US Army Corps of Engineers St. Louis District
DESIGN DEFICIENCY CORRECTIONS
FOR WOOD RIVER FLOOD
PROTECTION PROJECT
REACH 5 PUMP STATIONS
MISSISSIPPI RIVER
MADISON COUNTY, IL
CONSTRUCTION SPECIFICATIONS
CONTRACT NUMBER: W912P9-22-C-0019
SOLICITATION NUMBER: W912P9-22-R-0001
MAY 2022
PROJECT TABLE OF CONTENTS
DI VI SI ON 00 - PROCUREMENT AND CONTRACTI NG REQUI REMENTS
00 08 00 SPECIAL CONTRACT REQUIREMENTS
DI VI SI ON 01 - GENERAL REQUI REMENTS
01 11 00 SUMMARY OF WORK
01 11 30 ENVIRONMENTAL PROTECTION
01 13 20 PROJECT SCHEDULE
01 14 00 WORK RESTRICTIONS
01 15 00 TEMPORARY CONSTRUCTION FACILITIES
01 22 00.00 10 PRICE AND PAYMENT PROCEDURES
01 33 00 SUBMITTAL PROCEDURES
01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00.00 10 QUALITY CONTROL
01 45 00.15 10 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE(RMS CM)
01 78 00 CLOSEOUT SUBMITTALS
DI VI SI ON 02 - EXI STI NG CONDI TI ONS
02 41 00 DEMOLITION
DI VI SI ON 03 - CONCRETE
03 30 00 CAST-IN-PLACE CONCRETE
DI VI SI ON 05 - METALS
05 21 00 STEEL JOIST FRAMING
05 50 14 STRUCTURAL METAL FABRICATIONS
05 50 15 CIVIL WORKS FABRICATIONS
DI VI SI ON 06 - WOOD, PLASTI CS, AND COMPOSI TES
06 71 33 FIBERGLASS REINFORCED PLASTIC (FRP) LADDERS
06 82 14 FIBERGLASS REINFORCED PLASTIC (FRP) PIPE AND TUBE RAILINGS
DI VI SI ON 09 - FI NI SHES
09 97 02 PAINTING: HYDRAULIC STRUCTURES
DI VI SI ON 13 - SPECI AL CONSTRUCTI ON
13 34 19 METAL BUILDING SYSTEMS
DI VI SI ON 26 - ELECTRI CAL
26 00 00.00 20 BASIC ELECTRICAL MATERIALS AND METHODS
26 05 00.00 40 COMMON WORK RESULTS FOR ELECTRICAL
26 08 00 APPARATUS INSPECTION AND TESTING
26 20 00 INTERIOR DISTRIBUTION SYSTEM
26 29 23 VARIABLE FREQUENCY DRIVE SYSTEMS UNDER 600 VOLTS
26 41 00 LIGHTNING PROTECTION SYSTEM
DI VI SI ON 31 - EARTHWORK
31 06 00.00 09 GEOTEXTILE
PROJECT TABLE OF CONTENTS Page 1
31 11 00 CLEARING AND GRUBBING
31 21 40 CARE OF WATER
31 23 00.00 20 EXCAVATION AND FILL
31 23 23.33 FLOWABLE FILL
31 37 00.00 09 STONE PROTECTION
DI VI SI ON 32 - EXTERI OR I MPROVEMENTS
32 15 00 AGGREGATE SURFACING
32 31 13 CHAIN LINK FENCES AND GATES
32 92 19 SEEDING
DI VI SI ON 33 - UTI LI TI ES
33 26 00.00 10 RELIEF WELLS
33 40 00 STORM DRAINAGE UTILITIES
DI VI SI ON 35 - WATERWAY AND MARI NE CONSTRUCTI ON
35 20 16.53 VERTICAL LIFT GATES
35 45 02.00 10 SUBMERSIBLE PUMP, AXIAL-FLOW AND MIXED-FLOW TYPE
DI VI SI ON 40 - PROCESS I NTERCONNECTI ONS
40 05 13 PIPELINES, LIQUID PROCESS PIPING
40 95 00 PROCESS CONTROL
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 2
Amendment 0001
SECTION TABLE OF CONTENTS
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
SECTION 00 08 00
SPECIAL CONTRACT REQUIREMENTS
PART 1 GENERAL
1.1 SURVEYS
1.2 PAY REQUESTS
1.3 RIGHT-OF-WAY
1.4 PUBLIC UTILITIES AND PRIVATE IMPROVEMENTS
1.5 DAMAGE TO WORK
1.6 QUANTITY SURVEYS
1.7 PARTIAL PAYMENT
1.8 CERTIFICATES OF COMPLIANCE
1.9 PURCHASE ORDERS
1.10 SAFETY AND HEALTH REQUIREMENTS MANUAL EM 385-1-1
1.11 ACCIDENT INVESTIGATIONS AND REPORTING
1.12 ACCIDENT PREVENTION PROGRAM
1.13 DAILY INSPECTIONS
1.14 ENVIRONMENTAL LITIGATION
1.15 TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER
1.16 SUBCONTRACTS
1.17 REQUIRED INSURANCE - WORK ON A NON-GOVERNMENT INSTALLATION.
1.18 PROTECTION OF MATERIAL AND WORK
1.19 CONTAMINATION OF WATER
1.20 COMMERCIAL WARRANTY
1.21 ORDER AND COORDINATION OF WORK
1.22 SUBMITTALS
1.23 STONE SOURCES
1.24 CONTRACTOR PERFORMANCE EVALUATIONS
1.25 SECURITY REQUIREMENTS
PART 2 PRODUCTS
PART 3 EXECUTION
-- End of Section Table of Contents --
DOCUMENT 00 08 00 Page 1
SECTION 00 08 00
SPECIAL CONTRACT REQUIREMENTS
PART 1 GENERAL
1.1 SURVEYS
The work indicated on the drawings is determined from the latest available survey data. If any of the Contractor's pre-work field measurements indicate any substantial changes in the site condition which, in the opinion of the Contracting Officer, may require a revision in any design feature, drawings and supplementary specifications will be issued.
1.2 PAY REQUESTS
Pay requests authorized in the Contract Clause entitled "Payments Under Fixed-Price Construction Contracts", will be paid pursuant to the clause entitled "Prompt Payment for Construction Contracts". Pay requests shall be submitted on ENG Form 93 and 93a, "Payment Estimate-Contract Performance" and "Continuation", respectively. All information and substantiation required by the identified contract clauses shall be submitted with the ENG Form 93, and the required certification shall be included on the last page of the ENG Form 93a, signed by an authorized official of the Contractor and dated when signed. The designated billing office is the Office of the Area Engineer.
1.3 RIGHT-OF-WAY
Right-of-way for construction purposes will be furnished by the Government without cost to the Contractor. Where right-of-way for access to a work site is not available over existing public roads, access through private lands as shown on the contract drawings will be furnished by the Government without cost to the Contractor. The Contractor will be required at its own expense to do all work necessary to make such right-of-way suitable for traveling to and from the work site without interrupting the existing drainage. Upon completion of the contract work, any such access roadway and right-of-way furnished by the Government shall be left in a condition satisfactory to the Contracting Officer.
1.4 PUBLIC UTILITIES AND PRIVATE IMPROVEMENTS
a. Unless otherwise specified, shown on the drawings, or stated in writing by the Contracting Officer, the Contractor shall not move or disturb any public utilities or private improvements. Such removals, alterations, and/or relocations, where necessary, will be made by others. The locations shown on the drawings for underground utilities are approximate only. The exact locations of such utilities shall be determined by the Contractor in the field prior to commencing construction operations in their vicinity.
b. The attention of the Contractor is directed to the possibility that public utilities or private improvements may be encountered within the construction limits, some of which may be buried, and the existence of which is presently not known. Should any such utilities or improvements be encountered, the Contractor shall immediately notify the Contracting Officer so that a determination may be made as to whether they shall be removed, relocated, or altered. After such
DOCUMENT 00 08 00 Page 2 determination is made, the Contractor shall, if so directed by the Contracting Officer, remove, relocate, or alter them as required and an equitable adjustment will be made. In the event the Contracting Officer arranges for such removals, alterations, or relocations to be performed by others, the Contractor shall cooperate with such others during the latters' removal, alteration, or relocation operations.
1.5 DAMAGE TO WORK
a. The responsibility for damage to any part of the work to be performed under this contract shall be as set forth in the clause of the contract entitled "Permits and Responsibilities". However, if the cofferdam(s) is constructed in accordance with plans and progress schedules approved by the Contracting Officer, but is overtopped by flood and such flood causes damage to the cofferdam or if any part of the permanent work is damaged by flood or earthquake, which damage is not due to the failure of the Contractor to take reasonable precaution or to exercise sound engineering and construction practices in the conduct of the work, the Contractor shall make the repairs ordered by the Contracting Officer and full compensation for such repairs will be made at the applicable contract unit or lump sum prices as fixed and established in the contract. If, in the opinion of the Contracting Officer, there are no contract unit or job prices applicable to any part of such damaged work, an equitable adjustment pursuant to the Contract Clause entitled, "Changes", will be made as full compensation therefore.
b. The Contractor may, subject to approval of the Contracting Officer, or the Contracting Officer may order the Contractor to, flood or breach the cofferdam during a rise prior to, and in anticipation of, natural flooding due to overtopping. Such flooding or breach will be considered the same as though the cofferdam, if constructed in accordance with plans and progress schedules approved by the Contracting Officer, had been overtopped, in which event an equitable adjustment will be made for damages to the cofferdam and/or any part of the permanent work, as provided in (a) above.
1.6 QUANTITY SURVEYS
The Contractor shall have a Professional Land Surveyor registered in the state the work is being accomplished conduct original and final earthwork surveys. Surveys shall be performed in the presence of the Contracting Officer and all field survey notes be initialed by the Government Representative and furnished to the Government within 24 hours unless directed otherwise by the Contracting Officer.
1.7 PARTIAL PAYMENT
At the discretion of the Contracting Officer, partial payment will be made for equipment delivered and stored on site or off site providing such storage is in accordance with the provisions of these specifications and the Contractor furnishes satisfactory evidence that title to such equipment has been acquired and that it will be utilized on the work covered by these specifications. Partial payment is defined as the invoice amount plus shipping costs. If the equipment is stored off site, the Government shall have the right to inspect the equipment.
DOCUMENT 00 08 00 Page 3
1.8 CERTIFICATES OF COMPLIANCE
Any certificates required for demonstrating proof of compliance of materials with specification requirements shall include the signature and title of an official authorized to certify in behalf of the manufacturing company and shall contain the name and address of the Contractor, the project name and location, and the quantity and date or dates of shipment or delivery to which the certificates apply. Copies of laboratory test reports submitted with certificates shall contain the name and address of the testing laboratory and the date or dates of the tests to which the report applies. Certification shall not be construed as relieving the Contractor from responsibility for furnishing satisfactory material if, after tests are performed on selected samples, the material is found not to meet the specific requirements.
1.9 PURCHASE ORDERS
Two copies of all purchase orders for other than stock materials showing the firm names and addresses and list of material shall be furnished to the Contracting Officer or an authorized representative as soon as issued.
1.10 SAFETY AND HEALTH REQUIREMENTS MANUAL EM 385-1-1
The Safety and Health Requirements Manual EM 385-1-1 forms a part of these specifications. EM 385-1-1 and its changes are available at http://www.publications.usace.army.mil/USACEPublications/Engineer-Manuals/ .
Contractor shall be responsible for complying with the current edition and all changes posted on the web as of the effective date of this solicitation.
1.11 ACCIDENT INVESTIGATIONS AND REPORTING
Refer to EM 385-1-1, Paragraph 01.D. Accidents, involving contractor and/or subcontractor employees performing any work or related work on a USACE project, shall be investigated and reported immediately to the Contracting Officer or authorized Contracting Officer's representative.
This reporting requirement applies to on-site or off-site accidents. Upon receipt of the initial accident report notification, the Contracting Officer shall issue additional guidance concerning continuing project operations which may include a "cease work" directive. If a cease work directive is issued, the Contractor will not be allowed to resume work related to the accident until all conditions of the "cease work" directive are met. After the initial notification, the Contractor shall ensure a formal investigation is conducted and reports are completed by the immediate supervisor of the employee(s) involved and reported to the Contracting Officer or an authorized representative within one working day after the accident occurs. The accident Investigation report shall be made on ENG Form 3394.
1.12 ACCIDENT PREVENTION PROGRAM
Refer to Contract Clause FAR 52.236-13 entitled, "Accident Prevention".
Within 15 days after receipt of Notice of Award of the contract, and at least 7 days prior to the prework conference, the original and one copy of the Accident Prevention Program shall be submitted to the Contracting Officer for review. See EM 385-1-1 Appendix A (2014 Edition) and checklist included at the end of this section for guidance in creating the Accident Prevention Plan.
DOCUMENT 00 08 00 Page 4
The program shall also include a copy of company policy statement of accident prevention and any other guidance statements normally provided new employees. Each company employee shall be required to sign the company policy statement of accident prevention to verify that all employees have been informed of the safety program, and such signed statements shall be maintained at the project site.
When marine plant and equipment are in use under this contract, the requirements of EM 385-1-1, Section 19 shall be met.
The Contractor shall not commence physical work at the site until the program has been reviewed and found acceptable by the Contracting Officer, or an authorized representative. The Contractor shall submit for approval the Activity Hazard Analysis for each phase of construction prior to the beginning of work in each phase. Also refer to Section 1 of EM 385-1-1.
1.13 DAILY INSPECTIONS
The Contractor shall perform daily safety inspections and record them in RMS. Reports of daily inspections shall be maintained at the job site.
The reports shall be records of the daily inspections and resulting actions. Each report shall include, as a minimum, the following:
a. Phase(s) of construction underway during the inspection.
b. Locations of areas inspections were made.
c. Results of inspection, including nature of deficiencies observed and corrective actions taken, or to be taken, date, and signature of the person responsible for its contents.
1.14 ENVIRONMENTAL LITIGATION
a. If the performance of all or any part of the work is ordered by a court of competent jurisdiction to be suspended, delayed, or interrupted as a result of environmental litigation, as defined below, the Contracting Officer, at the request of the Contractor, shall determine whether the order is due in any part to the acts or omissions of the Contractor or a Subcontractor at any tier not required by the terms of this contract. If it is determined that the order is not due in any part to acts or omissions of the Contractor or a Subcontractor at any tier other than as required by the terms of this contract, such suspension, delay, or interruption shall be considered as if ordered by the Contracting Officer in the administration of this contract under the terms of the Contract Clause entitled "Suspension of Work".
b. The term "environmental litigation", as used herein, means a lawsuit alleging that the work will have an adverse effect on the environment or that the Government has not duly considered, either substantively or procedurally, the effect of the work on the environment.
1.15 TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER
a. This provision specifies the procedure for the determination of time extensions for unusually severe weather in accordance with the Contract Clause entitled, "Default (Fixed-Price Construction)". In order for the Contracting Officer to award a time extension under this
DOCUMENT 00 08 00 Page 5 clause, the following conditions must be satisfied:
(1) The weather experienced at the project site during the contract period must be found to be unusually severe, that is, more severe than the adverse weather anticipated for the project location during any given month.
(2) The unusually severe weather must actually cause a delay to the completion of the project. The delay must be beyond the control and without the fault or negligence of the Contractor.
b. Upon acknowledgement of the Notice to Proceed (NTP) and continuing throughout the contract, the Contractor shall record on the daily CQC report, the occurrence of adverse weather and resultant impact to normally scheduled work. Actual adverse weather delay days must prevent work on critical activities for 50 percent or more of the Contractor's scheduled work day. The delay must be beyond the control and without the fault or negligence of the Contractor. The number of actual adverse weather delay days shall include days impacted by actual adverse weather (even if adverse weather occurred in previous day), be calculated chronologically from the first to the last day of each month, and be recorded as full days. The Contracting Officer will convert any qualifying delays to calendar days, giving full consideration for equivalent fair weather work days, and issue a time extension modification in accordance with the FAR Clause 52.249-10 entitled "Default (Fixed Price Construction)".
1.16 SUBCONTRACTS
In accordance with the Contract Clause entitled "Subcontracts", the Contractor shall, within seven days after the award of any subcontract by the Contractor or a Subcontractor, deliver to the Contracting Officer an electronic copy of a completed Standard Form 1413 with the original signatures of both parties.
1.17 REQUIRED INSURANCE - WORK ON A NON-GOVERNMENT INSTALLATION.
a. The Contractor shall, at its own expense, provide and maintain during the entire performance period of this contract at least the kinds and minimum amounts of insurance required in the following schedule:
(1) Workmen's Compensation . Amounts required by applicable jurisdictional statutes.
(2) Employer's Liability Insurance . $100,000
(3) Comprehensive General Liability Insurance .
Bodily Injury - $500,000 per occurrence
(4) Comprehensive Automobile Insurance .
Bodily Injury - $200,000 each person $500,000 each accident Property Damage - $ 20,000 each accident
b. Within 15 days after receipt of Notice of Award and before commencing work under this contract, the Contractor shall notify the
DOCUMENT 00 08 00 Page 6
Contracting Officer in writing that the required insurance has been obtained. The policies evidencing required insurance shall contain an endorsement to the effect that any cancellation or any material change adversely affecting the Government's interest shall not be effective
(1) for such period as the laws of the State in which this contract is to be performed prescribe, or (2) until 30 days after the insurer or the Contractor gives written notice to the Contracting Officer, whichever period is longer.
c. The Contractor shall insert the substance of this clause, including this paragraph c, in subcontracts under this contract and shall require subcontractors to provide and maintain the insurance required in paragraph a above. The Contractor shall maintain a copy of all subcontractor's proofs of required insurance, and shall make copies available to the Contracting Officer upon request.
d. Statements of required insurance should be submitted to the following address:
Department of the Army St. Louis District, Corps of Engineers Central Area Office; CEMVS-EC-CA 1222 Spruce Street St. Louis, Missouri 63103
1.18 PROTECTION OF MATERIAL AND WORK
The Contractor shall at all times protect and preserve all materials, supplies, and equipment of every description (including property which may be Government-furnished or owned) and all work performed. All reasonable requests of the Contracting Officer to enclose or specially protect such property shall be complied with. If, as determined by the Contracting Officer, material, equipment, supplies, and work performed are not adequately protected by the Contractor, such property may be protected by the Government and the cost thereof may be charged to the Contractor or deducted from any payments due to the Contractor.
1.19 CONTAMINATION OF WATER
In addition to the requirements set forth in SECTION 01 11 30, paragraph Protection of Water Resources, the Contractor shall take positive protective measures to prevent spillage of potential pollutant materials such as fuel, emulsion materials, chemicals etc., from storage containers or equipment, into lakes or tributary waters. Such positive protective measures may include, but are not limited to, the following:
(1) A berm enclosure of sufficient capacity to contain such materials.
(2) Security measures to prevent acts of vandalism which could result in spillage of such materials (fences, guards, etc.).
(3) Storage of such materials in an area where the terrain would preclude leakage into lake or tributary waters.
(4) Utilization of secure Government storage areas if the Contracting Officer indicates such space is available. No storage past immediate needs (2 days) without the consent of the Contracting Officer.
The Contractor shall submit its proposals for implementing the above
DOCUMENT 00 08 00 Page 7 provisions in accordance with SECTION 01 11 30, paragraph Environmental Protection Plan.
1.20 COMMERCIAL WARRANTY
The Contractor agrees that the standard commercial equipment furnished under this contract shall be covered by the most favorable commercial warranties the manufacturer gives to any customer for such equipment, and that the rights and remedies provided herein are in addition to and do not limit any rights afforded to the Government by any other clause of this contract. The Contractor shall furnish 2 hard copies or an electronic copy of the warranties to the Contracting Officer.
1.21 ORDER AND COORDINATION OF WORK
a. Speed Limit. The Contractor shall be required to strictly adhere to all posted speed limits for all vehicles traveling over local, county and State of Illinois roads.
b. Coordination. The Contractor shall coordinate all activities with the local authorities and utility companies involved. Points of contact are as follows:
Wood River Drainage & Levee District (WRD&LD) Kevin Williams 543 W. Madison Ave.
Wood River, IL 62095 618/401-7226 kwilliams@wrleveedist.org
Ameren (New service, shielding, de-energizing) Brad Long C: 618-610-2896 O: 618-463-4030 blong@ameren.com
Roxana Water Department O: (618)-254-5513
Mayor of Hartford - Bill Robertson billrobertson@hartfordillinois.net
Mayor of Roxana - Marty Reynolds mreynolds@roxana-il.org
Village of Hartford Department of Public Woks Road Closure Coordination O: (618)-251-2694
c. Utilities. The Contractor shall provide potable water, electricity, and sanitary facilities required in the performance of this contract. The Contractor may obtain and utilize these utilities from sources approved by the Contracting Officer. The absence of Government utilities will not relieve the Contractor of his obligation to provide these services.
The Contractor shall field verify all utilities and ensure construction
DOCUMENT 00 08 00 Page 8 activities do not cause any disturbance or damage to the existing utilities. The Contractor is not authorized to undertake any additional work that would be at an additional cost at the direction of one of the POCs listed above. If coordination yields a requirement for additional work at an additional cost outside the scope of this contract, the Contractor shall communicate with the Contracting Officer. Necessary additional work will then be handled in accordance with Section 00700, Contract Clause entitled, "Changes".
Any overhead utility lines shall be protected during construction operations in the vicinity of the existing lines, and the Contractor shall coordinate construction activities with the Electric Utility and any other affected utilities. Installation of any temporary utility items or de-energizing of lines required shall be coordinated with the respective utilities involved. Any disturbance or damage to existing utilities caused by the Contractor shall require immediate notification to the utility owner, and such disturbance or damage shall be repaired by the Contractor or such repair paid for by the Contractor (should the utility require self-performance of such work) at no expense to the Government.
The Contractor will be required to furnish all required electrical construction power required for all construction activities including temporary electrical distribution equipment. The Contractor has the option of negotiating with the local power utility company to bring in temporary power lines, or using gasoline powered engine-generator sets, or both. The Contractor shall include with its bid all up-front and monthly costs for this service. Construction site power lines shall in no way interfere with site work or operations by the Wood River Levee District. All temporary power equipment shall be removed by the Contractor before completion of the contract.
The contractor shall notify the Roxanna Water Department prior to starting construction. The contractor shall always protect the integrity of the existing waterline by bracing, shoring, or some other acceptable means
d. Traffic Control. All traffic shall be handled by means of existing pavement, new temporary and permanent construction, and road closures.
The Contractor shall provide a minimum 30-day public notice to the WRD&LD and the Villages of Hartford and Roxana prior to implementing any road closures or detours. At the end of construction, the Contractor shall be responsible for obliterating any and all temporary roads and connections, and restore them to their pre-construction condition, unless specifically required otherwise. The Contractor shall additionally return existing roads impacted by construction to their pre-construction condition, unless specifically noted otherwise. The contractor shall maintain traffic control for the repairs to Canal Road at all times according to Illinois DOT Standard Specification, Section 701.
e. Sequence Restrictions.
(1) The Contractor shall coordinate with the WRD&LD for the location and restrictions of the Contractor's staging area provided by the local sponsors.
(2) The Contractor shall close Canal Road at the landside of the levee for no more than 7 days in order to install the Pump Station force main discharge pipes under the road. The Road closure shall be coordinated with the WRD&LD and the Villages of Hartford and Roxana.
DOCUMENT 00 08 00 Page 9
f. Sequence Restrictions.
(1) The Contractor shall drill Pilot Hole (PH-272-22) within 45-days after notice to proceed has been initiated. The pilot hole requirements are outlined within specification 33 26 00.00 10 - RELIEF WELLs.
g. Contractor Requirements. The Contractor is advised that the following requirement must be followed:
(1) The Contractor shall remove any and all debris and trash within the construction limits as shown on the drawings. The Contractor shall dispose of all debris and trash off site.
(2) The Contractor shall coordinate any and all dewatering/unwatering operations of the construction site with the WRD&LD. The Contractor's operations shall in no way inhibit or restrict the District's ability to operate the existing gatewell.
(3) The Contractor shall not install or allow the relief wells at PS No. 2 to become operational until PS No. 2 is in operation, or the contractor has another means to control the discharge flow from the relief wells so that it doesn't impact the work site or adjoining properties.
(4) A local storm in the Cahokia Creek watershed can cause the Cahokia Diversion Channel to rise quickly, but any adverse effect on construction operations on the riverside of the levee would be rare. On the interior of the levee, the ditch leading to the gravity drain begins to pond when the gravity drain is closed. Gate closing is heavily dictated by interior rain events at the gravity drains. The closure of the gate based on the flood event will be closed by the levee district between stages of 25 to 32 on The Mel Price gage. Accumulation of local runoff during a closed gravity situation may prevent construction operations if ponding exceeds the natural ground elevation at the construction site. The Contracting Officer will determine the extent of the delay to the work due to high exterior or interior water levels, and the time fixed for completion of the contract will be extended for the period of the time delay, in accordance with Section 00700, Contract Clause entitled, "Default".
1.22 SUBMITTALS
Additional submittals for this contract that are not listed within individual technical provisions are listed below. Government approval is required for submittals with a "G" designation; submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00 - SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Accident Prevention Program; G Statements of Required Insurance; G
SD-06 Test Reports
Ledge Testing; G
DOCUMENT 00 08 00 Page 10
1.23 STONE SOURCES
a. On the basis of information and data available to the Contracting Officer, stone meeting the quality requirements of these specifications has been produced from the sources listed at the end of these Special Clauses.
b. Stone may be furnished from any of the currently listed sources or, at the option of the Contractor, may be furnished from any other source designated by the Contractor and accepted by the Contracting Officer, subject to the conditions hereinafter stated.
c. It is the Contractor's responsibility to determine that the stone source or combination of sources selected are capable of supplying the quantities and gradation needed and at the rate needed to maintain the scheduled progress of the work.
d. After the award of the contract, the Contractor shall designate in writing only one source or one combination of sources from which stone will be furnished. If the Contractor proposes to furnish stone from a source not currently listed, only a single additional source for stone may be designated. Samples for acceptance testing shall be provided as required by SECTION 35 31 19. If a source for stone so designated by the Contractor is not accepted for use by the Contracting Officer, the Contractor may not propose other sources but shall furnish the stone from a source listed at no additional cost to the Government.
e. Acceptance of a source of stone is not to be construed as acceptance of all material from that source. The right is reserved to reject materials from certain localized areas, zones, strata, or channels when such materials are unsuitable for stone as determined by the Contracting Officer. Materials produced from a listed or unlisted source shall meet all the requirements of SECTION 35 31 19, of the Technical Provisions of these specifications.
f. If the Contractor proposes to furnish stone from a source or sources listed, he shall submit Department of transportation ledge testing information from within the past 12 months. Selected ledge or ledges for producing crushed stone shall meet the following MINIMUM requirements: Stone shall weigh more than 155 lbs/cubic foot. The stone shall also have an absorption less than 2 percent. The Contractor shall also schedule a site visit to the quarry to inspect the proposed ledge(s) that stone will be produced. The Government shall be included in the scheduling of the site visit and a minimum 72-hour notice shall be given.
1.24 CONTRACTOR PERFORMANCE EVALUATIONS
In accordance with the provisions of Subpart 36.201(Evaluation of Contractor Performance) of the Federal Acquisition Regulation (FAR), construction contractor's performance shall be evaluated throughout the performance of the contract. The United States Army Corps of Engineers (USACE) follows the procedures outlined in Engineering Regulation 415-1-17 to fulfill this FAR requirement. For construction contracts awarded at or above $100,000.00, the USACE will evaluate contractor's performance and prepare a performance report using the Contractor Performance Assessment Reporting System (CPARS), which is a web-based system. After an evaluation (interim or final) is written up by the USACE, the contractor will have the ability to access, review and comment on the evaluation for a period
DOCUMENT 00 08 00 Page 11 of 30 days. Accessing and using CPARS requires specific software, called PKI certification, which is installed on the user's computer. The certification is a Department of Defense requirement and was implemented to provide security in electronic transactions. The certification software could cost approximately $110 - $125 per certificate per year and is purchased from an External Certificate Authorities (ECA) vendor.
Current information about the PKI certification process and for contacting vendors can be found on the web site: http://www.cpars.navy.mil/. If the Contractor wishes to participate in the performance evaluation process, access to CPARS and PKI certification is the sole responsibility of the Contractor.
1.25 SECURITY REQUIREMENTS
The contractor and all associated sub-contractors shall receive a brief/training (provided by the RA) on the local suspicious activity reporting program. This locally developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the project manager, security representative or law enforcement entity. This training shall be completed within 30 calendar days of contract award and within 30 calendar days of new employees commencing performance with the results reported to the COR NLT 5 calendar days after the completion of the training.
The Contractor must pre-screen Candidates using the E-verify Program (http://www.uscis.gov/e-verify) website to meet the established employment eligibility requirements. The Vendor must ensure that the Candidate has two valid forms of Government issued identification prior to enrollment to ensure the correct information is entered into the E-verify system. An initial list of verified/eligible Candidates must be provided to the COR no later than 3 business days after the initial contract award.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
Not used.
-- End of Section --
DOCUMENT 00 08 00 Page 12
November 2021
STONE SOURCES
ST. LOUIS DISTRICT
Source
No. Producer MRM* Lat. Long.
1. Tower Rock Stone Co., Ste Genevieve MO. 127.6 38N 90W
2. Plattin Quarry, Ste. Genevieve, MO. 139.0 38N 90W
3. Mississippi Lime Quarry, Ste. Genevieve, MO. 155.0 38N 90W
4. Barnhart Limestone Inc., Barnhart, MO. 156.0 38N 90W
5. Bussen Quarry, St. Louis County, MO. 168.0 38N 90W
6. Bellefontaine Quarry, 8.0** 38N 90W
Fort Bellefontaine, MO.
7. Fort Belle Quarry, Ft. Bellefontaine, MO. 7.0** 38N 90W
8. Calhoun Quarry, Batchtown, IL. 241.0 38N 90W
9. Wayne Smith Quarry, Louisiana, MO. 281.0 39N 91W
10. Anna Quarry, Anna, IL. 37N 89W
11. Bussen Quarry, Eureka, MO. 38N 90W
12. Callender Quarry, Pittsfield, IL. 39N 90W
13. Central Stone Quarry #1, Huntington, MO. 39N 91W
14. Central Stone Quarry #9, Perry, MO. 39N 91W
15. Central Stone Quarry #33, Florence, IL. 39N 91W
16. Columbia Quarry Co. #15, Cypress, IL. 37N 89E
17. Char1eston Stone Co., Charleston, IL. 39N 88W
18. Columbia Quarry #1, Columbia, IL. 38N 90W
19. Columbia Quarry #9, Dupo, IL. 38N 90W
20. Falling Spring Quarry Co., Falling Springs, IL. 38N 90W
Source
No. Producer MRM* Lat. Long.
21. Magruder Quarry, Troy, MO. 38N 90W
22. Magruder Quarry, Foley, MO. 39N 90W
23. Fred Weber Inc., Winfield MO. 38N 90W
24. Bluff City Mineral, E. Alton, IL. 38N 90W
25. Columbia Quarry Co. #7, Waterloo, IL. 38N 90W
26. Seminole Ag. Lime Co., Dexter, MO. 37N 90W
27. S-S-S Inc., New London, MO. 39N 91W
28. Southeast Missouri Stone Co., Cape Girardeau, MO. 37N 89W
29. Base Rock Mineral, Bonne Terre, MO. 37N 90W
30. Williamsville Stone Co., Poplar Bluff, MO. 36N 90W
31. Nokomis Quarry, Nokomis, IL. 39N 89W
32. Brickeys Quarry, Bloomsdale, MO. 135.8 38N 90W
33. Martin Marietta Aggregate, Perryville, MO. 37N 89W
34. Ashley Quarry, Magruder Limestone, Troy, MO 39N 91W
35. Buncombe Quarry, Marion, IL 37N 88W
36. Cave-In-Rock Quarry, Cave in Rock, IL 37N 88W
37. Shawnee Stone, LLC, Cypress, IL 37N 89W
38. Heartland Materials, Jackson, MO 37N 89W
39. Cane Creek Stone LLC, Butler County, MO 36N 90W
40. Fruitland Quarry, Cape Girardeau County, MO 37N 89W
41. Arab Aggregates, LLC, Zalma, MO 37N 90W
42. Shook Quarry, Shook, MO 37N 89W
43. Lodi Quarry, Lodi, MO 37N 90W
44. Bussen Quarry, St. Genevieve, MO 38N 90W
* Mississippi River Mile
** Missouri River Mile
Item Description Yes No N/A
1. Signature sheet
a. Includes the name, signature, and title of the Plan Preparer (Qualmed person, i.e. corporate safety staff person, QC)
b. Includes the name, signature,and tiUe of the Plan Approver {e.g.
owner, company president, regional vice presiden
c. Includes the name{s), signature(s), and title{s) for Plan Concurrence (provide concurrence of other applicable corporate and project personnel(contractor))
2.Background information
a. Includes the Contractor Name.
b. Includes the Contract Number.
c. Includes the Project Name.
d. Includes the Brief Project Description.
e. Includes the Location of the Project {map).
f. Includes a means to evaluate the work being done (see AHA requirements in 01.A.13) and associated hazards involved.
g. Addresses the identified hazards involved and the control measures to be taken.
3. Statement of Safety and Health Policy detailing their commitment to providing a safe and healthfulworkplace for all employees.
4.Responsibilities and Lines of Authorities a.Includes the identification and job responsibilities of personnel responsible for safety - at both corporate and project level - including their resumes.
b.Includes the lines of authority.
5. Training- new hire SOH orientation training at the time of initial hire of each new employee and any periodic retraining/recertification requirements 6.Procedures for job site inspections - assignment of responsibilities and frequency CESO Checklist A-01,Sep 14
U.S.Army Corps of Engineers Safety Inspection Checklist
Abbreviated Accident Prevention Plan
Inspector Name (Print) Inspector Signature
This checklist serves as a guide only. It does not replace or eliminate the need to comply with the requirements set forth in Engineering Manual 385-1-1, Safety and Health Requirements Manual, dated XX September 2014.The references Included In this checklist correspond to the applicablesections of EM 385-1-1.
If service, supply and R&D contracts with limited scopes are awarded, the contractor may submit an abbreviated Accident Prevention Plan. This APP shall address the following areas at a minimum. If other areas of the EM 385-1-1 are pertinent to the contract, the contractor must assure these areas are addressed as well.
Remarks (Any NO or N/A Item)
Date of Inspection
Location (Plant or Facility) Contract Number
Contractor Name Project Name
Date of Inspection
7.Procedures for reporting man-hours worked and reporting and investigating any accidents as soon as possible but not more than 24 hours afterwards to the Contracting Officer/Representative
(CO/COR).
8.Emergency Planning. Employees working alone shall be provided an effective means of emergency communication. This may be cellular phone, two-way radio or other acceptable means. The selected means of communication must be readily available and must be in working condition.
9.Drinking Water provisions, toilet and washing facilities.
10.First Aid and CPR training (at least two employees on each shift shall be qualified/certified to administer first aid and CPR) and provision of first aid kit (types/size).
11.Personal Protective Equipment
a. Work Clothing - Minimum Requirements. Employees to wear clothing suitable for the weather; minimum requirements for work shall be short-sleeve shirt, long pants (excessively long or baggy pants are prohibited) and leather work shoes. If AHA determines safety-toed (or other protective) footwear is necessary (i.e., mowing, weed eating, chain saw use, etc), they shall be wom.
b.Eye and Face Protection. Eye and face protection shall be worn as determined by an analysis of the operations being performed HOWEVER, all involved in chain saw use, chipping,stump grinding, pruning operations, grass mowing, weed eating and blowing operations shall be provided safety eyewear (Z87.1) as a minimum.
c. Hearing Protection. Hearing protection must be worn by all exposed to high noise activities {includes grass mowing/trimming, chainsaw operations, tree chipping, stump grinding and pruning) d.Head Protection. Hard hats shall comply with ANSIZ89.1 and shall be wom by all workers when a head hazard exists. At a minimum, hard hats shall be worn when performing activities identified in {b) above e.High Visibility Apparel shall comply with ANSI/ISEA 107, Class 2 requirements at a minimum and shall be worn by all workers exposed to vehicular or equipment traffic.
f.Protective Leg chaps shall be wom by all chainsaw operators.
g. Gloves of the proper type shall be worn by persons involved in activities that expose the hands to cuts,abrasions, punctures, bums and chemicalirritants.
h. If work is being performed around water and drowning is a hazard, PFD's must be provided and worn as appropriate.
12.Machine Guards and safety devices. Lawn maintenance equipment must have appropriate guards and safety devices in place and operational.
CESO Checklist A-01,Sep 14
U.S.Army Corps of Engineers Safety Inspection Checklist
Abbreviated Accident Prevention Plan Remarks (Any NO or N/A item)
13. Hazardous Substances. When any hazardous substances are procured, used, stored or disposed, a hazard communication program must be in effect and MSDSs shall be available at the worksite. Employees shall have received training in hazardous substances being used. When the eyes or body of any person may be exposed to corrosives, irritants or toxic chemicals, suitable facilities for quick drenching or flushing of the eyes and body shall be provided within 10 seconds of the worksite.
14. Traffic control shall be accomplished in accordance with DOrs
MUTCD.
15. Control of Hazardous Energy (Lockout/Tagout). Before an employee perfonns any servicing or maintenance on any equipment where the unexpected unergizing or startup of the equipment could occur, procedures must be in place to ensure adequate control of
16. Driving, working on (i.e., working with equipmenUmowers) while on slopes, working from/in boats/skiffs, etc shall also be considered and dealt with accordingly.
Other Remarks
CESO Checklist A-01,Sep 14
Remarks (Any NO or N/A Item)
U.S.Army Corps of Engineers Safety Inspection Checklist
Abbreviated Accident Prevention Plan
1. Signature sheet
a. Includes the name, signature, and title of the Plan Preparer (Qualified person, i.e. corporate safety staff person, QC )
b. Includes the name, signature, and title of the Plan Approver (e.g. owner, company president, regional vice president ) (HTRW activities require approval of a Certified Industrial Hygienist, a Certified Safety Professional may approve the plan for operations involving UST removal where contaminants are known to be petroleum, oils, or lubricants).
c. Includes the name(s), signature(s), and title(s) for Plan Concurrence (provide concurrence of other applicable corporate and project personnel (contractor)) (e.g. Chief of Operations, Corporate Chief of Safety, Corporate Industrial Hygienist, project manager or superintendent, project safety professional, project
QC. )
2. Background information
a. Includes the Contractor Name.
b. Includes the Contract Number.
c. Includes the Project Name.
d. Includes the Brief Project Description.
e. Includes the Location of the Project (map).
f. Includes the Contractor Accident Experience (Copy of OSHA
g. Includes the Listing of Phases of Work and Hazardous Activities Requiring an Activity Hazard Analyses (AHA).
3. Statement of Safety and Health Policy. Includes a copy of the corporate safety policy. (In addition to the corporate policy statement, a copy of the corporate safety program may provide a portion of the information required by the accident prevention
4. Responsibilities and Lines of Authorities
a. Includes the identification and job responsibilities of personnel responsible for safety - at both corporate and project level – including their resumes.
b. Includes the lines of authority.
CESO Form A-02 Sep 13
Remarks (Any NO or N/A item)
Form A-02 U.S. Army Corps of Engineers
Accident Prevention Plan Checklist
Date of Inspection
Location (Plant or Facility) Contract Number
Contractor Name Project Name
Inspector Name (Print) Inspector Signature
This checklist serves as a guide only, it does not replace or eliminate the need to comply with the requirements set forth in Engineering Manual 385-1-1, Safety and Health Requirements Manual, dated XX Sept 2014. The references included in this checklist correspond to the applicable sections of EM 385-1-1.
5. Training
a. Includes the list of subjects to be discussed with employees at safety indoctrination.
b. Includes the list of mandatory training and certifications applicable to this project (e.g., explosive actuated tools, confined space entry, crane operator, diver, vehicle operator, HAZWOPER training and certification, PPE ) and any requirements for periodic retraining / recertification.
c. Includes the identity requirements for emergency response training.
d. Includes the outline requirements (who attends, when given, who will conduct, etc. ) for supervisory and employee safety
6. Safety and Health Inspections
a. Includes the name(s) of individual(s) responsible for conducting safety inspections. (e.g., PM, safety professional, QC, supervisors, employees )
b. Includes proof of inspector's training / qualifications.
c. Indicates when inspections will be conducted.
d. Furnished sample forms upon which inspections will be recorded.
e. Indicates deficiency tracking system and follow-up procedures.
f. Includes the names of competent and / or qualified person(s) and proof of competency / qualification to meet specific OSHA competent / qualified person(s) requirements.
g. Includes any external inspections / certifications which may be required. (e.g., US Coast Guard )
7. Safety and Health Expectations, Incentive Programs, and Compliance
a. Includes the company's written safety program goals, objectives, and accident experience goals.
b. Includes a brief description of the company's safety incentive programs (if any ).
c. Includes the policies and procedures regarding noncompliance with safety requirements (to include disciplinary actions for violation of safety requirements).
d. Includes the written company procedures for holding managers and supervisors accountable for safety.
8. Mishap Reporting
a. The plan identifies how, when, and who shall complete the Exposure data (man-hours worked).
b. The plan identifies how, when, and who shall complete mishap investigations, reports, and logs.
c. The plan identifies how, when, and who shall make immediate notification of major mishaps.
CESO Form A-02 Sep 13
Remarks (Any NO or N/A item)
Form A-02 U.S. Army Corps of Engineers
Accident Prevention Plan Checklist (cont’d)
9. Plans (Programs, Procedures) required by the Safety Manual
a. Fatigue Management Plan (01.A.20)
b. Emergency response plans:
(1) Procedures & Test (01.E.01)
(2) Spill Plans (01.E.01, 06.A.02)
(3) Fire Fighting Plan (01.E.01; 19.A)
(4) Posting of Emergency Telephone Numbers (01.E.05)
(5) Man overboard/abandon ship (19.A.04)
(6) Medical Support. Outline on-site medical support and off-site medical arrangements including rescue and medical duties for those employees who are to perform them, and the name(s) of on-site Contractor personnel trained in first aid and CPR. A minimum of two employees shall be certified in CPR and first-aid per shift/site (Section 03.A; 03.D)
c. Plan for prevention of alcohol and drug abuse (01.C.02)
d. Site Sanitation Plan (Section 02.B)
e. Medical Support Plan, (03.A.01; 03.A.06; 03.D)
f. Bloodborne Pathogen Plan (03.A.05)
g. Exposure Control Plan (03.A.05)
h. Site Layout Plan (04.A)
i. Access/Haul road Plan (04.B)
j. Hearing Conservation Program (05.C)
k. Respiratory Protection Plan (05.G)
l. Health Hazard Control Program (06.A)
m. Process Safety Management Plan (06.B.04)
n. Lead Abatement Plan (06.C & Specs)
o. Asbestos Abatement Plan (06.C & Specs)
p. Radiation Safety Program (06.F)
q. Abrasive Blasting Plan (06.I)
r. Heat/Cold Stress Monitoring Plan (06.J)
s. Indoor Air Quality Management Plan (06.L)
t. Mole Remediation Plan (06.L.04)
u. Chromium (VI) Exposure Evaluation (06.M)
v. Crystalline Silica Assessment (06.N)
w. Lighting Evaluation (07.A)
x. Lighting Plan for Night Operations (07.A.09) CESO Form A-02 Sep 13
Form A-02 U.S. Army Corps of Engineers
Accident Prevention Plan Checklist (cont’d)
Date of Inspection
Based on a risk assessment of contracted activities and on mandatory OSHA compliance programs, the Contractor shall address all applicable occupational risks and compliance plans. Using the EM 385-1-1 as a guide, plans may include but not be limited to:
9. Plans (Programs, Procedures) continued.
y. Traffic Control Plan (08.C.05)
z. Fire Prevention Plan (09.A.01)
aa. Wild Land Fire Management Plan (09.L)
bb. Arc Flash Hazard Analysis (11.B)
cc. Assured Equipment Grounding Control Program (AEGCP), (11.D.05, App D)
dd. Hazardous Energy Control Plan, (12.A.01)
ee. Standard Pre-Lift Plan (LHE) (16.A.03, 16.L.15)
ff. Critical Lift Plan – LHE (16.H)
gg. Naval Architectural Analysis (16.L)
hh. Contingency Plan for Severe Weather (19.A.03)
ii. Man Overboard/Abandon Ship (19.A.04)
jj. Float Plan (19.F.04)
kk. Fall Protection Program, (21.D);
ll. Demolition/Renovation Plan (to include engineering survey), (23.A.02)
mm. Rope Access Program, (24.H.02)
nn. Excavation/Trenching Plan, (25.A.01)
oo. Underground construction fire prevention and protection Plan, (26.D.01)
pp. Compressed Air Plan, (26.I.01)
qq. Formwork and Shoring Erection and Removal plan, (27.C)
rr. PreCast Concrete Plan, (27.D) ss Lift. slab plans, (27.E)
tt. Masonry Bracing Plan, (27.F.01)
uu. Steel Erection Plan, (28.B)
vv. Explosives Safety Site Plan (ESSP) (29.A)
ww. Blasting Plan, (29.A; 26.J)
xx. Underwater Dive Operations Plan, (30.A.14, 16, )
yy. Tree…
This is the start of the file's text. The full file is on GovTribe.