Attachment_2_-_Specifications_1.pdf
PDF 932 KB Posted
- Attached to
- BLM-CO Sand Gulch Campground Expansion Federal contract opportunity
- Solicitation number
- 140L1723R0022
About this file
This pre-solicitation announcement is for a campground expansion project located at the Bureau of Land Management's Sand Gulch Campground near Canon City, Colorado. The project includes expanding campsites, parking areas, and amenities between August and December 2023 with an estimated budget between $250,000 and $500,000. Interested offerors should ensure active SAM registration and familiarize themselves with FAR Part 15 for contracting by negotiation, FAR Part 36 for construction provisions, Davis-Bacon wage rates for Fremont County, Colorado, and total small business set-aside requirements. The solicitation will utilize firm fixed price contracts awarded based on a low price technically acceptable basis. The point of contact for the pre-solicitation is listed as the contracting officer.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Attachment_1_-_Design_1.pdf | ||
| Attachment_3_-_Schedule_of_Items_1.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
U.S. BUREAU OF LAND MANAGEMENT
SAND GULCH CAMPGROUND
IMPROVMENTS
U.S. BLM – ROCKY MOUNTAIN DISTRICT
ROYAL GORGE FIELD OFFICE
3028 E. MAIN ST
CANON CITY, CO 81212
Project Specifications
U.S. DEPARTMENT OF THE INTERIOR
BUREAU OF LAND MANAGEMENT
PREFACE
These Project Specifications are issued for the technical execution of work associated with the Sand Gulch Campground Improvements project in Fremont, Colorado. These Specifications have been compiled based on the Federal Highway Administration’s Standard Specifications for the Construction of Roads and Bridges on Federal Highway Projects (FP-14). Any work required for completion of the project and not specified in these documents shall be performed in accordance with FP-14. Certain sections of these Project Specifications have been revised per the Project Special Conditions.
Construction contracts of the BLM are also governed by the following regulations:
● Federal Acquisition Regulation (FAR), Title 48, Code of Federal Regulations, Chapter 1
Table of Contents
U.S. BUREAU OF LAND MANAGEMENT .......................................................... i
Section 101. — TERMS, FORMAT, AND DEFINITIONS
Section 103. — SCOPE OF WORK
Section 106. — ACCEPTANCE OF WORK
Section 109. — MEASUREMENT AND PAYMENT
Section 151. — MOBILIZATION
Section 152. — CONSTRUCTION SURVEY AND STAKING
Section 153. — CONTRACTOR QUALITY CONTROL
Section 154. — CONTRACTOR SAMPLING AND TESTING
Section 155. — SCHEDULES FOR CONSTRUCTION CONTRACTS
Section 156. — PUBLIC TRAFFIC
Section 157. — SOIL POLLUTION PREVENTION PLAN AND EROSION
AND SEDIMENT CONTROL
Section 201. — CLEARING AND GRUBBING
Section 203. — REMOVAL OF STRUCTURES AND OBSTRUCTIONS
Section 204. — EXCAVATION AND EMBANKMENT
Section 209. — STRUCTURE EXCAVATION AND BACKFILL
Section 211. — ROADWAY OBLITERATION
Section 251. — RIPRAP
Section 302. — MINOR CRUSHED AGGREGATE
Section 303. — ROAD RECONDITIONING
Section 602. — CULVERTS AND DRAINS
Section 619. —CATTLE GUARDS
Section 621. — MONUMENTS AND MARKERS
Section 624. — TOPSOIL
Section 624. — ROLLED EROSION CONTROL PRODUCTS (RECP) AND SEEDING
Section 703. — AGGREGATE
Section 705. — ROCK
Section 708. — PLASTIC PIPE
Section 800. — MIC MISCELLANEOUS
Various Manufacture Specs
Section 101
DIVISION 100
GENERAL
REQUIREMENTS
Section 101. — TERMS, FORMAT, AND DEFINITIONS
101.01 Specifications Format. These specifications are divided into 10 Divisions
Division 100 consists of general contract requirements for which no direct payment is made. The requirements contained in Division 100 are applicable to all contracts.
Division 150 consists of project contract requirements that are applicable to all contracts. Work under Division 150 is paid for directly or indirectly according to Subsection 109.05 and the Section ordering the work. When there is no pay item in the bid schedule, no direct payment is made.
Divisions 200 through 600 consist of construction contract requirements for specific items of work. Work under these Divisions is paid for directly or indirectly according to Subsection 109.05 and the Section ordering the work. When there is no pay item in the bid schedule, no direct payment is made.
Division 700 contains the material requirements for Divisions 150 through 600. No direct payment is made in Division 700. Payment for material is included as part of the work required in Divisions 150 through 600.
The first three digits of the pay item number in the bid schedule identify the Section under which the work is performed.
101.02 Abbreviations. Whenever these abbreviations are used in the contract, they represent the following:
FAR — Federal Acquisition Regulations (48 CFR Chapter 1)
ISO — International Organization for Standardization
JMF — Job-Mix Formula
MPI — Master Painters Institute
MSDS — Material Safety Data Sheet
MUTCD — Manual on Uniform Traffic Control Devices for Streets and Highways
SI — International System of Units
U.S. — United States of America
USC — United States Code
101.03 Definitions. The following definitions apply to this contract:
Backfill — Material used to replace or the act of replacing material removed during construction. Material placed or the act of placing material adjacent to structures.
Base — The layer or layers of material placed on a subbase or subgrade to support a surface course.
Bid Schedule — The prepared schedule included with the bid forms, containing the estimated quantities of pay items for which unit bid prices are invited. Also known as Schedule of Items.
Construction Limits — The limits of the project site disturbed by construction operations and beyond which no disturbance is permitted. Typically, the construction limits are the same as the clearing limits, except when additional clearing is required.
Contract — The written agreement between the Government and the Contractor setting forth the obligations of the parties for the performance of and payment for the prescribed work.
Contractor — Individual or legal entity contracting with Government for performance of prescribed work.
Contract Time — The specified time allowed for completion of contract work.
Cross-Section — A vertical section of the ground or structure at right angles to the centerline or baseline of the roadway or other work.
Day — A calendar day beginning and ending at midnight.
Density — Mass per unit volume of material. Specific gravity multiplied by the density of water.
Detour — A temporary rerouting of public traffic to avoid the work or part of the work.
Drawings — Design sheets or fabrication, erection, or construction details submitted to the government by the Contractor.
Government — The Government of the United States of America.
Lift — When placing and compacting soils, aggregates, or pavement; a lift is a single, continuous layer of material that receives the same compactive effort throughout during a single work operation. When installing culvert pipe the backfill material placed on both sides of the pipe is considered to be contained in the same lift when placed to the same elevation.
Material — Substances specified or necessary to satisfactorily complete the contract work.
Measurement — The process of identifying the dimensions, quantity, or capacity of a pay item. See Section 109 for measurement methods, terms, and definitions.
Pay Item — A specific item of work for which a unit and price is provided in the contract.
Plans — The contract plans furnished by the Government showing the location, type, dimensions, and details of the work.
Project — The specific work and work area for an individual task order.
Roadbed — The graded portion of a road prepared as a foundation for upper layers and shoulders.
Roadside — The area between the outside shoulder edge and the right-of-way limits.
Schedule of Items – A schedule in the contract listing construction items with description, units of measurement and estimate of quantities, included in the work, see “Bid Schedule”.
Shoulder — A portion of the roadway contiguous with the traveled way that accommodates pedestrians, bicycles, stopped vehicles, and emergency use; as well as lateral support of the subbase, base, and surface courses.
Specifications — The written requirements for performing work.
Station — A precise location along a survey line.
Structures — Bridges, culverts, catch basins, drop inlets, retaining walls, cribbing, manholes, endwalls, buildings, sewers, service pipes, underdrains, foundation drains, and other constructed features that may be encountered in the work.
Subbase — The layer or layers of material placed on a subgrade to support a base.
Subcontract — The written agreement between the Contractor and an individual or legal entity prescribing the performance of a specific portion of the work.
Subcontractor — An individual or legal entity with which the Contractor sublets part of the work. This includes subcontractors in all tiers.
Subgrade — The top surface of a roadbed upon which the pavement structure, shoulders, and curbs are constructed.
Substantial Completion — The point at which the project is complete such that it can be safely and effectively used by the public without further delays, disruption, or other impediments.
Suitable Material — Rock or earth material that will provide stable foundations, embankments, or roadbeds, and is free of organic matter, muck, frozen lumps, roots, sod, or other deleterious material. Suitable material may require drying or adding water, root picking, and other methods of manipulation before use.
Suitable material includes the classifications of material for which the project was designed.
Superintendent — The Contractor's onsite representative who has authority to act for the Contractor and is responsible for directing and supervising construction operations on behalf of the Contractor.
Traveled Way — The portion of the roadway designated for the movement of vehicles, exclusive of shoulders.
Unsuitable Material — Material not capable of creating stable foundations, embankments, or roadbeds.
Unsuitable material includes muck, sod, or soils with high organic contents.
Work — The furnishing of labor, material, equipment, and other incidentals necessary to complete the project according to the contract.
Section 103
Section 103. — SCOPE OF WORK
103.01 Intent of Contract. The intent of the contract is to award one contract for the items shown on the bid schedule for the base bid, the additive items are optional and the Government may or may not award one of more additives at the time of the award.
The precise details of performing the work are not described, except as considered essential for the successful completion of the work. Furnish labor, material, equipment, tools, transportation, and supplies necessary to complete the work according to the contract. All items and labor incidental to completing the work are to be included in the unit bid prices as shown on the Contractors Bid Schedule and will not be paid for separately. Estimates of quantities are provided for comparison to the Contractors estimates only and are to be fully verified by the Contractor.
103.02 Location of Project
Work under this Contract is located at the Bureau of Land Management Sand Gulch Campground in Canon City, Colorado. Sand Gulch Campground is 13.5 miles North of Canon City on County Road 9.
103.03 Summary of the Work
The project includes, but is not limited to, the following work:
A. Construction on Existing Roads and Campsites
• Clear Grade, Grade and Place 6” CDOT Class 6 aggregate on existing main road. This will include 2,300 ft of existing road and 600 ft of Necessary Rerouting. Main driving Roads shall be 18 ft in width and match road design
• Place and Grade 4” of CDOT Class 6 on 11 existing campsites. To include, adding two new accesses on two separate campsites. Existing campsites average in size 50 ft by 50 ft. Campsites shall not exceed 2% grade.
• Furnish and Place new ADA compliant Concrete picnic tables for campsites. (Model number 100S from Outdoor Creations Inc. With BLM Emblem embossed on both sides, or approved equal).
• Furnish and Place new ADA compliant Fire Rings for campsites. (Model number: FSW/SL-30 -/18-/AL- /S from Pilot Rock or approved equal) .
• Furnish and Place 1 ft -2 ft boulders to outline all campsites, parking and roads for erosion control.
• Furnish and Place concrete parking delineators in all parking stalls, campsites and group sites. Parking delineators shall follow drawings.
B. New Campsite Construction
• Clear, Grub and grade New Campsite Road. Place 6” of CDOT Class 6 on top of new road. Road shall meet design in included drawings.
• Clear, Grub and Grade 13 New Back-in Campsites. Campsites Shall be topped with 4” of CDOT Class 6 aggregate. Campsites shall be no closer than 50 ft at any given point. Campsites shall be built to design and be graded to no more than 2%. Edges shall have proper drainage and be daylighted back into existing surface at 3:1. (Of the 13 Sites, 4 Campsites will have a 70 ft extension to parking areas.
• Clear, Grub and Grade 3 New Pull through Campsites. Campsites Shall be topped with 4” of CDOT Class 6 aggregate. Campsites shall be no closer than 50 ft at any given point. Campsites shall be built to design and be graded to no more than 2%. Edges shall have proper drainage and be daylighted back into existing surface at 3:1.
• Clear, Grub and Grade 1 New Camp Host Campsite. Campsites Shall be topped with 4” of CDOT Class 6 aggregate. Campsites shall be no closer than 50 ft at any given point. Campsites shall be built with 40 ft by 40 ft living area, a 12 ft by 70 ft parking area and be graded to no more than 2%. Edges shall have proper drainage and be daylighted back into existing surface at 3:1.
• Furnish and Install a 1000 Gallon Holding Tank, piping, and RV connection in the Camp Host Campsite.
• Clear, Grub and Grade 2 Group sites. Both Sites will have a topper of 4” of CDOT Class 6 Aggregate.
Sites will be graded to no more than 2%. Edges shall have proper drainage and be daylighted back into existing surface at 3:1.
• Group Site A: 60 ft by 60 ft living space and 24 ft by 60 ft parking area with 4 parking stalls.
• Group Site B: 60 ft by 24 ft living space and a 24 ft by 60 ft parking area with 4 parking stalls.
• Furnish and Place new ADA compliant concrete picnic tables for campsites. (Model number 100S from Outdoor Creations Inc. With BLM Emblem embossed on both sides, or approved equal)
• Furnish and Place new ADA compliant Fire Rings for campsites. (Model number: FSW/SL-30 -/18-/AL- /S from Pilot Rock or approved equal.)
• Furnish and Place 1 ft -2 ft boulders to outline all campsites, parking and roads for erosion control.
• Furnish and Place concrete parking delineators in all parking stalls, campsites and group sites. Parking delineators shall follow drawings.
• Furnish and Install 24 ft cattle guard with precast concrete foundation. Refer to drawing included.
• Furnish and Install two double vault precast concrete toilets. Toilets will be installed according to manufacture specifications and have ADA compliant access. (MISSOULA) C. Parking Lot Construction
• Clear, Grub and Blade Gravel Parking Lots. Parking Lots will have a topper of 6” of CDOT Class 6 Aggregate. Sites will be graded to no more than 3%. Edges shall have proper drainage and be daylighted back into existing surface at 3:1.
• Main Parking Lot: 70 ft by 150 ft with 30 parking stalls spaced at 9 ft
• Overflow Parking Lot: 25 ft by 70 ft with 8 stalls spaced at 9 ft
• Furnish and Place concrete parking delineators in all parking stalls, campsites and group sites.
• Parking delineators shall follow drawings.
NOTE: Drawings and specifications prepared for the work may be modified to accommodate on-site and regional conditions by mutual agreement of BLM and the Contractor if beneficial to the outcome of the project.
103.04 Project Site Conditions:
A. General: Contractor shall have access to the immediate work area and facilities as needed to complete the work.
B. Work Hours: Work hours shall be 07:00 a.m. to 6:00 p.m., Monday through Friday unless otherwise approved by the Government. No work will be allowed on the weekends or holidays without written approval from the Government.
C. Environmental Considerations: The Contractor shall, to the extent feasible, keep the overall worksite clean and clutter free. Clean-up litter and discarded material generated by the construction and dispose of at an approved sanitary landfill or other location and manner approved by the Government.
D. Incidental Operations: Land administered by the Government may be used by the Contractor for incidental operations such as materials storage, project office, equipment parking and camping. These areas shall be approved in advance by the Government. Environmental considerations of the preceding paragraphs will apply.
E. Camping on-site may be permitted if requested by the Contractor and approved in writing by the
Government.
F. Protection of Existing Improvements and Natural features: Contractors shall protect existing improvements at the site and repair any damage that occurs due to site work at Contractors expense, this includes the structural improvements and the access roads. Contractor shall also protect the vegetative buffer along the arroyo as noted on the Conceptual Site Plan and surrounding natural features outside the limits of work.
G. Security: Security of Contractor equipment is the responsibility of the Contractor.
H. No construction or drinking water is available on site. No power is available on site.
103.05 Performance of the Work
All work shall be conducted in a safe and expedient manner and in conformance with the specifications and design plans. When applicable, traffic control shall be in accordance with standards set forth in the most current edition of the Manual on Uniform Traffic Control Devices (MUTCD). All work shall be conducted by personnel fully qualified to perform the tasks assigned and shall be supervised by a designated Contractor’s Representative. A pre-work meeting will be conducted for each task order to agree upon limits of work and methods.
103.06 Equipment
All equipment shall be in good repair, and capable of accomplishing assigned tasks in a safe and acceptable manner. Where applicable, all equipment shall be fitted with approved spark arrestors. All equipment shall be cleaned of earthen and vegetative materials that may contain weed seed prior to delivery onto Public Lands, equipment inspection may be required.
103.07 Equipment and Materials Storage & Staging
The Contracting Officer’s Representative (COR) shall designate areas on the BLM that will be made available for storage of equipment and/or materials during active construction and/or maintenance periods.
The Contractor shall be responsible for protection of items stored on Government property, and shall ensure adequate safety measures are maintained at such sites. At the request of the Contractor, camping may be permitted if approved by the Field Office.
103.08 Contract Time
The contract time will start 14 calendar days from the effective date of the Notice to Proceed.
103.09 Road Closures
Closure of the road during weekdays shall be allowed for periods of up to 4-hours, when required for the work, with appropriate notice to the Field Office. Road shall be open each weekend starting at 3PM on Friday until 10AM on Monday unless otherwise approved.
BLM will allow full day road closures, intermittently as needed, mid-week only (Tuesday through Thursday) provided a minimum of two week notice is provided and Contractor is actively working during closure. Road will be open to traffic before 7am and after 6pm every day and open from 3pm Friday to 10am on Mondays.
Section 106
Section 106. — ACCEPTANCE OF WORK
106.01 Conformity with Contract Requirements.
References to standard documents and test methods of AASHTO, ASTM, GSA, and other recognized standard authorities refer to the documents and methods in effect on the date of the Solicitation for Bids (IFB) or Request for Proposal (RFP).
Perform work to the lines, grades, cross-sections, dimensions, and processes or material requirements shown in the contract.
Incorporate manufactured material into the work according to the manufacturer’s recommendations or to these specifications, whichever is stricter.
Plan dimensions and contract specification values are the values to be strived for and complied with. Perform work and provide material that is uniform in character and reasonably close to the prescribed value or within the specified tolerance range.
The Government may inspect, sample, or test work before final acceptance of the project. If the Government tests work, copies of test reports are furnished to the Contractor upon request.
Acceptable work conforming to the contract will be paid for at the contract bid price. Three methods of determining conformity and accepting work are described in Subsections 106.02 through 106.04. The primary method of acceptance is specified in each Section of work, but work may be rejected if it is found not to comply with the contract.
Remove and replace work that does not conform to the contract, or to prevailing industry standards where no specific contract requirements are noted, at no cost to the Government.
As an alternative to removal and replacement, the Contractor may submit a written request to:
(a) Have the work accepted at a reduced price; or
(b) Perform corrective measures to bring the work into conformity.
Include supporting rationale and documentation in the request. Include references or data justifying the proposal based on an evaluation of test results, effect on service life, value of material or work, quality, aesthetics, and other tangible engineering basis. The Government will determine disposition of the nonconforming work.
106.02 Visual Inspection. Acceptance is based on visual inspection of the work for compliance with the contract and prevailing industry standards.
106.03 Certification. For material manufactured off-site, use a manufacturer with an ISO 9000 certification or an effective testing and inspection system. Require the manufacturer to clearly mark the material or packaging with a unique product identification or specification standard to which it is produced.
Section 106
Check certifications before incorporating the material into the work to ensure that the requirements of the contract have been met. Mark the certifications with the following information:
• Project number and name;
• Pay item number and description;
• Contractor’s signature; and
• Date.
Material accepted by certification may be sampled and tested. If material is determined not to conform with the contract, the material will be rejected whether in place or not.
106.04 Measured or Tested Conformance. Perform necessary measurements and tests to ensure work complies with the contract.
Use prevailing industry standards in the absence of contract requirements or tolerances.
Submit measurements, tests, and supporting data for acceptance.
106.05 Inspection at the Plant. Work may be inspected at the point of production or fabrication.
Manufacturing plants may be inspected for compliance with specified manufacturing methods. Material samples may be obtained for laboratory testing for compliance with quality requirements. Allow full entry at all times to the parts of the plant producing the work.
106.06 Partial and Final Acceptance. Maintain the work during construction and until the project is accepted. Repair damage caused by the Contractor before final acceptance of the entire project at no cost to the Government.
(a) Partial acceptance. When a segment of the project is completed, a final inspection of that segment may be requested. If the segment is complete and in compliance, it may be accepted. If accepted, the Government may relieve the Contractor of further responsibility for maintaining accepted work.
(b) Final acceptance. Notify the Government when the entire project is complete to schedule an inspection. If work is determined to be complete, the inspection will constitute the final inspection. The Contractor will be notified in writing of final acceptance as of the date of the final inspection. Final acceptance relieves the Contractor of further responsibility for the maintenance of the project.
If the inspection discloses unsatisfactory work, the Government will provide to the Contractor a list of the work that is incomplete or requires correction. Immediately complete or correct the work. Submit notification when the work has been completed as provided above.
Section 109. — MEASUREMENT AND PAYMENT
109.01 Measurement of Work. Take and record measurements and perform calculations to determine pay quantities for invoicing for work performed. Take or convert measurements of work according to U.S. Customary measure.
Unless otherwise specified, measure when the work is in-place and complete according to the contract.
Measure the actual work performed, except do not measure work outside the design limits or other adjusted or specified limits (staked limits).
Take measurements as described in Subsection 109.02 unless otherwise modified by the Measurement Subsection of the Section controlling the work being performed. Measurement of quantities for payment for the individual pay items will be based on the contract price for each pay item.
Remeasure quantities if it has been determined that a portion of the work is acceptable, but has not been completed to the lines, grades, and dimensions shown in the plans or established by the Government.
No work is to be performed beyond the quantities allowed for in the Contract unless a contract change allowing the additional work has been signed by the Government.
109.02 Measurement Terms and Definitions. Unless otherwise specified, the following terms are defined as follows:
(a) Acre (AC). 43,560 square feet . Make longitudinal and transverse measurements for area computations horizontally. Do not make deductions from the area computation for individual fixtures having an area of 500 square feet (50 square meters) or less.
(b) Contract quantity (CQ). The quantity to be paid is the quantity listed in the bid schedule. The contract quantity will be adjusted for authorized changes that affect the quantity or for errors made in computing this quantity. If there is evidence that a quantity specified as a contract quantity is incorrect, submit calculations, drawings, or other evidence indicating why the quantity is in error and request in writing that the quantity be adjusted PRIOR to incurring additional cost.
(c) Cubic yard (CY).
(1) Cubic yard in-place. Measure solid volumes by a method approved by the Government or by the average end area method as follows:
(a) Take cross-sections of the original ground and use design or staked templates to determine end areas. Do not measure work outside of the lines or slopes established by the Government.
(b) If a portion of the work is acceptable but is not completed to the established lines and slopes, retake cross-sections or comparable measurements of that portion of the work. Use the remeasurements to calculate new end areas; and
(c) Compute the quantity using the average end areas multiplied by the horizontal distance along a centerline or reference line between the end areas. Deduct quantities outside the designed or staked limits.
(d) Day. A calendar day beginning and ending at midnight. Round portions of a day up to the full day.
(e) Each (EA). One entire unit. Measure the actual number of units completed and accepted.
(f) Hour (HR). 60 minutes. Measure the actual number of hours ordered by the Government and performed by the Contractor. Round portions of an hour up to the next half hour. Measure time in excess of 40 hours per week at the same rate as the first 40 hours.
(g) Linear foot (LF). As applicable, measure the work along its length from end-to-end; parallel to the base or foundation; along the top; along the front face; or along the invert. Do not measure overlaps.
(h) Lump sum (LS). Do not measure directly. The bid amount is complete payment for all work described in the contract and necessary to complete the work for that pay item.
(i) Mile. 5,280 linear feet . Measure horizontally along centerline of roadway.
(l) Pound (LB). Measure according to Subsection 109.03. If sacked or packaged material is furnished, the net weight as packed by the manufacturer may be used.
(m) Square foot (SF) and Square yard (SY). 1 square yard equals 9 square feet. Measurements for area computations will be made horizontally or vertically to the surface being measured. No deductions will be made for individual fixtures having area of 9 square feet or less.
(n) Ton. 2,000 pounds. Measure according to Subsection 109.03.
109.03 Weighing Procedures and Devices.
When material is proportioned or measured and paid for by mass, provide one of the following:
(a) Commercial weighing system. Use permanently installed and certified commercial scales.
(b) Invoices. If bulk material is shipped by truck or rail and is not passed through a mixing plant, submit a supplier's invoice with net mass or volume converted to mass. Periodic check weighing may be required.
109.04 Receiving Procedures. When the method of measurement requires weighing or volume measurement in the hauling vehicle, furnish a person to direct the spreading and distribution of material and to record the location and placement of the material on the project. During the placement, maintain a record of each delivery and document it in an acceptable manner. Include the following as applicable:
(a) Project number and name;
(b) Pay item number and description;
(c) Location where placed;
(d) Date;
(e) Load number;
(f) Truck identification;
(g) Time of arrival;
(h) Mass or volume; and
(i) Spread person's signature.
Use an approved format for the delivery records. Submit the original records and a written certification of the delivery of the material at the end of each shift.
109.05 Scope of Payment. Payment for contract work is provided, either directly or indirectly, under the pay items listed in the bid schedule.
(a) Direct payment. Payment is provided directly under a pay item listed in the bid schedule when one of the following applies:
(1) The work is measured in the Measurement Subsection of the Section ordering the work and the bid schedule contains a pay item for the work from the Section ordering the work.
(2) The Measurement Subsection of the Section ordering the work, references another Section for measuring the work and the bid schedule contains a pay item for the work from the referenced Section.
(b) Indirect payment. Work for which direct payment is not provided is a subsidiary obligation of the Contractor. Payment for such work is indirectly included under other pay items listed in the bid schedule.
This includes instances when the Section ordering the work references another Section for performing the work and the work is not referenced in the Measurement Subsection of the Section ordering the work.
Compensation provided by the pay items included in the bid schedule is full payment for performing contract work in a complete and acceptable manner. Risk, loss, damage, or expense arising out of the nature or prosecution of the work is included in the compensation provided by the pay items.
Work measured and paid for under one pay item will not be paid for under other pay items.
The quantities listed in the bid schedule are approximate unless designated as a contract quantity. Limit pay quantities to the quantities staked, ordered, or otherwise authorized before performing the work. Payment will be made for the actual quantities of work performed and accepted or material furnished according to the contract. No payment will be made for work performed in excess of that staked, ordered, or otherwise authorized.
DIVISION 150
PROJECT
REQUIREMENTS
Section 151
Section 151. — MOBILIZATION
Description
151.01 This work consists of moving personnel, equipment, material, and incidentals to the project and performing work necessary before beginning work at the project site. This work also includes obtaining permits, insurance, and bonds. This work shall also include demobilization at end of project.
Measurement
151.02 Measure the Section 151 items listed in the bid schedule according to Subsection 109.02.
Payment
151.03 The accepted quantities will be paid at the contract price per unit of measurement for the Section 151 pay items listed in the bid schedule. Payment will be full compensation for the work prescribed in this Section. See Subsection 109.05.
Progress payments for mobilization by the lump sum will be paid as follows:
(a) Bond premiums will be reimbursed under Fixed-Price Construction Contracts, after receipt of the evidence of payment.
(b) When 5 percent of the original contract amount is earned from pay items (not including mobilization), 50 percent of the mobilization pay item, or 5 percent of the original contract amount, whichever is less, will be paid.
(c) When 10 percent of the original contract amount is earned from pay items (not including mobilization), 100 percent of the mobilization pay item, or 10 percent of the original contract amount, whichever is less, will be paid.
(d) Any portion of the mobilization pay item in excess of 10 percent of the original contract amount will be paid after final acceptance.
Section 152
Section 152. — CONSTRUCTION SURVEY AND STAKING
152.01 Description. This work consists of performing surveying, staking, calculating, and recording data for the control of work.
152.02 Qualifications. Provide technically qualified survey crews experienced in roadway construction survey and staking. Provide personnel capable of performing in a timely and accurate manner.
152.03 Submittals. Submit the following at the preconstruction conference:
(a) Technology statement. A written statement that includes:
(1) The manufacturer, model, and software version of the AMG equipment; and
(2) Certification that the final 3D data is compatible with the AMG equipment.
(b) Personnel qualifications.
(1) The name, authority, relevant experience, and qualifications of the person with overall responsibility for the AMG system.
(2) The names, authority, and relevant experience of personnel directly responsible for operating the AMG equipment.
(c) Contractor quality control plan. Comply with Section 153 and describe personnel qualifications, procedures for checking, mechanical calibration, and maintenance of both survey and construction equipment. Include the frequency and types of checks performed.
Include a price breakdown by individual tasks when construction survey and staking is paid by the lump sum for use in making progress payments and price adjustments.
152.04 General. Conform to the following:
(a) Personnel. Provide a crew supervisor on the project whenever surveying and staking is in progress.
(b) Equipment. Furnish survey instruments and supporting equipment capable of achieving the specified tolerances. Construction equipment controlled with a Global Positioning System (GPS) and Robotic Total Station (RTS) machine guidance system may be used in the construction of subgrade, subbase, and base aggregate courses, or other construction operations when approved.
(c) Material. Furnish acceptable tools and supplies of the type and quality suitable for roadway survey work. Furnish stakes and hubs of sufficient length to provide a solid set in the ground with sufficient surface area above ground for necessary legible and durable markings.
Include staking activities in the construction schedule required under Section 155. Include the dates and sequence of each staking activity.
The plans show available site horizontal and vertical control points, to be used by the Contractor for use in establishing control for completion of each element of the work.
The Contractor shall be responsible for calculating and staking all roadway horizontal and vertical alignment, theoretical slope stake catch points, and other field data necessary beyond that shown on the plans. Provide immediate notification of apparent errors in the information provided on the plans.
Record survey and measurement field data in an approved format. Submit survey and measurement data at least weekly. Field data and supporting documentation become the property of the Government upon completion of the work.
Discuss and coordinate the following with the Government before surveying or staking:
(1) Surveying and staking methods;
(2) Stake marking;
(3) Grade control for courses of material;
(4) Referencing;
(5) Field staking data;
(6) Localization of the GPS systems to the site control points; and
(7) Other procedures and controls necessary for the work.
Do not start work until staking or three-dimensional (3D) verification data for the affected work has been approved.
Preserve initial reference and control points. Notify the Government of missing control points or stakes at least 10 days before beginning construction. The Government will reestablish control points missing before the beginning of construction.
Acceptance of the construction staking does not relieve the Contractor of responsibility for correcting errors discovered during the work and for bearing additional costs associated with the error.
Maintain legibility of stake markings for the duration of the project or until notified in writing the stakes are no longer needed. Replace stakes if necessary to ensure markings are maintained.
Remove and dispose of flagging, paint, lath, stakes, and other staking material after the project is complete.
152.05 Survey and Staking Requirements. Perform survey, staking, recording of data, and calculations as necessary to construct the project from the initial layout to final completion. Survey and set stakes to the tolerances in Table 152-1. Reset stakes, refine 3D data, or both as many times as necessary to construct the work.
(a) Control points. Relocate initial horizontal and vertical control points in conflict with construction to areas that will not be disturbed by construction operations. Furnish the coordinates, elevations, and supporting documentation for the relocated points before the initial points are disturbed. Set durable monuments for survey control that uniquely identify the points.
Furnish the GPS localization results at least 7 days before beginning construction layout survey work. The Government may order the GPS localization calibration and associated 3D model to be broken into two or more zones to maintain the localized relationship between control points and original ground.
(b) Centerline establishment. Establish centerline at roadway design cross-section locations and as necessary to construct the work. Reestablish the centerline when construction survey and staking work does not meet the tolerances.
(c) Original ground topographic verification. Use an approved method to regenerate profile data in areas where theoretical and actual ground elevations do not meet a tolerance of plus or minus 0.5 feet (150 millimeters). Retake profile to verify existing ground topography to mapping. Submit data in electronic and printed format for approval.
(d) Slope and references stakes. Perform the following:
(1) AMG method. After clearing operations are completed, set centerline reference stakes and hubs on both sides of centerline at 100-foot (30-meter) intervals at the clearing limit locations.
Where clearing limits are greater than 10 feet (3 meters) vertically, 25 feet (8 meters) horizontally, or both from subgrade hinge point; provide an additional reference stake and hub as approved by the Government. Label each centerline reference stake with station, hub elevation, and offset from centerline.
Construct a 1000-foot (300-meter) long test section using AMG on the project at an approved location before beginning grading operations. Select a test location with superelevation and curve widening transitions if applicable. Notify the Government 10 days before beginning the test section. Demonstrate capability, knowledge, equipment, and experience to achieve work within tolerances. Allow 14 days to evaluate the test section. Do not start full grading operations until the test section is approved.
(2) Conventional survey methods. Verify and set slope stakes on both sides of centerline at the theoretical catch point. If the theoretical catch point is not within a tolerance of 0.5 feet (150 millimeters), perform original ground topographic verification according to Subsection 152.05(c). Set the slope stake at the actual intersection of the design roadway slope with the natural ground-line. Set reference stakes outside the clearing limits. Include reference points and slope-stake information on the reference stakes.
Establish slope stakes in the field as the actual point of intersection of the design roadway slope with the natural ground-line when theoretical catch point information is not available.
(e) Clearing and grubbing limits. Set clearing and grubbing limits on both sides of centerline based on the actual slope-stake locations.
(f) Grade-finishing stakes.
(1) AMG method. Construct a 1000-foot (300-meter) long test section using AMG on the project at an approved location before beginning grading operations. Select a test location with superelevation and curve widening transitions if applicable. Notify the Government 10 days before beginning the test section. Demonstrate the capability, knowledge, equipment, and experience to achieve work within tolerances. Allow 14 days to evaluate the test section. Do not start full grading operations until the test section is approved.
Verify the grade elevation and horizontal alignment of roadway grade-finishing operations. Use conventional survey methods at random locations specified by the Government, not to exceed 500-foot (150-meter) intervals. Submit 3D coordinates of grade-finishing quality control checks.
(2) Conventional survey methods. Set grade-finishing stakes for grade elevations and horizontal alignment, on centerline and on each shoulder at design roadway cross-section locations. Set stakes at the top of subgrade and the top of each aggregate course. Reset grade finishing stakes as many times as necessary to construct the subgrade and each aggregate course.
During turnout or pullout construction, set stakes on the centerline, on each normal shoulder, and on the shoulder of the turnout. In parking areas, set stakes at the center and along the edges of the parking area. Set stakes in ditches to be paved.
When the centerline curve radius is less than or equal to 250 feet (75 meters), use a maximum longitudinal spacing between stakes of 25 feet (8 meters). When the centerline curve radius is greater than 250 feet (75 meters), use a maximum longitudinal spacing between stakes of 50 feet (15 meters). Use a maximum transverse spacing between stakes of 20 feet (6 meters). Use brushes or guard stakes at each stake.
(g) Culverts. Verify and set culvert locations at the inlet, outlet, and inlet basin points according to the plans. Perform the following if culvert design does not fit field conditions:
(1) Survey and record the ground profile along the culvert centerline;
(2) Determine the slope catch points at the inlet and outlet;
(3) Set reference points and record information necessary to determine culvert length and end treatments;
(4) Plot to scale the profile along the culvert centerline. Show the natural ground, the flow line, the roadway section, and the culvert including end treatments and other appurtenances. Show elevations, grade, culvert length, and degree of elbow.
(a) For single skewed culverts, submit a plotted field-design cross-section normal to roadway centerline and at each end section. Plot the offset and elevation of natural ground at the end section and at proposed template break points between centerline and the end section. Ensure the template design embankment slope is not exceeded.
(b) For multiple skewed culverts, submit a plotted field design cross-section normal to roadway centerline and at the end sections (left and right) nearest to the shoulder. Plot the offset and elevation of natural ground at the end section and at proposed template break points between centerline and the end section. Ensure the template design embankment slope is not exceeded.
(c) Submit the plotted field-design cross-section for approval of final culvert length and alignment. Plot at a clear and readable scale.
(d) Set inlet, outlet, and reference stakes when the field design has been approved. Stake inlet and outlet ditches to make sure the culvert and end treatments (such as drop inlets) are functional; and
(e) Adjust slope, reference, and clearing stakes as necessary to provide for culvert inlet treatments in cut slopes. Readjust slope, reference, and clearing stakes as necessary when culvert inlets are moved from their plan locations. Review slope adjustments with the Government and obtain approval.
(k) Permanent monuments and markers. Perform survey and staking work necessary to reestablish monuments disturbed during the work.
(l) Miscellaneous survey and staking. Survey and stake other work (such as guardrail, curb and gutter, turf establishment, utilities, and excavation limits for structures) to the proper location and required tolerances. Propose staking increments for approval by the Government when not specified.
Table 152-1
Construction Survey and Staking Tolerances (1)
Staking Horizontal Vertical
Control points set from existing Government control points
±0.03 feet ±0.01 feet × N
Mapping, topography, and cross-section points
±0.20 feet ±0.20 feet
Centerline points (3) including (PC), (PT), (POT),(POC), and references
±0.30 feet ±0.20feet
Slope-stake and slope-stake references (4) ±0.50 feet ±0.30 feet
Culverts, ditches, and minor drainage structures stakes
±0.50 feet ±0.30 feet (Field adjust with
Government) Clearing and grubbing limit stakes ±2.00 feet –
Roadway subgrade finish stakes (6) ±0.30 feet ±0.20 feet
Roadway finish grade stakes (6) ±0.30feet ±0.20 feet
(1) At statistical 95 percent confidence level. Tolerances are relative to existing Government control points.
(2) N is the number of instrument setups.
(3) Centerline points: PC - point of curve, PT - point of tangent, POT - point on tangent, POC - point on curve.
(4) Take the cross-sections normal to the centerline ±1 degree.
152.06 Acceptance. Construction survey and staking will be evaluated under Subsections 106.02 and 106.04.
Survey notes will be evaluated under Subsection 106.02.
152.07 Measurement. Measure the Section 152 pay items listed in the bid schedule according to Subsection 109.02 and the following as applicable:
When measuring grade finishing, measure one time for the subgrade and one time for finished course.
Do not measure time spent in making preparations, traveling to and from the project site, performing calculations, plotting cross-sections and other data, processing computer data, and other efforts necessary to successfully accomplish construction survey and staking.
Do not measure re-establishing missing control points or stakes after construction operations have begun.
152.08 Payment. The accepted quantities will be paid at the contract price per unit of measurement for the Section 152 pay items listed in the bid schedule. Payment will be full compensation for the work prescribed in this Section. See Subsection 109.05.
Payment for lump sum pay items will be prorated based on the progress of the work under this Section.
Section 153
Section 153. — CONTRACTOR QUALITY CONTROL
153.01 This work consists of planning and implementing a construction quality process to ensure work conforms to the contract.
Construction Requirements
153.02 Qualifications. Submit the following for approval with the Quality Control Plan:
(a) Quality control manager (QCM). Provide a QCM as follows:
(1) Full-time, on-site QCM. Provide a QCM for oversight of the work to manage quality control with the following qualifications. QCM may also serve as site Project Manager or similar.
(a) One year experience managing quality control on construction projects of similar type and scope, and
(b) One of the following:
(1) Two years’ experience as a construction project manager or superintendent on construction projects of similar type and scope;
(2) Three years’ experience as a project engineer, resident engineer, foreman, construction inspector, or equivalent on construction projects of similar type and scope;
or
(3) National Institute for Certification in Engineering Technologies (NICET) Level III certification or equivalent in highway construction or highway material.
(b) Independent Third-Party testing. Provide a third party testing sub-contractor for on-site materials testing and laboratory tests as required by the specifications.
(c) Testers. Provide testers with at least one-year experience in the type of sampling and testing required, and with one of the following for the type of sampling and testing performed:
(1) NICET Level II certification in highway material or equivalent state or industry certification;
(2) Certification by a regional certification program (such as Western Alliance for Quality Transportation Construction (WAQTC), Northeast Transportation Technician Certification Program (NETTCP), Southeast Task Force for Technician Training and Qualification (STFTTQ), or Multi Regional Training and Certification (M-TRAC)); or
(3) At least one year employment by an AASHTO accredited laboratory performing equivalent sampling and testing.
153.03 Quality Control Plan (QCP). Develop a QCP addressing all contract work categories. A category consists of related work items performed in one operation(such as excavation, drainage, and paving).
Include the work of subcontractors, major material suppliers, and structural and geotechnical services suppliers.
For each category, include the following:
(a) Quality control personnel. Furnish the name, authority, responsibilities, and qualifications of the quality control manager and other personnel directly involved in inspection and testing. Conform to Subsection 153.02.
(b) Quality control procedures. Describe the inspection, testing, and other activities to be performed for each additive in Subsection 153.04. Include methods, schedules, equipment, and laboratory facilities. Conform to Subsections 153.04 and 153.05.
List the material to be tested by:
(1) Pay item;
(2) Applicable requirements of the Sampling, Testing, and Acceptance Requirements tables;
(3) Persons responsible for performing the sampling and testing;
(4) Laboratory testing facilities to be used for process control and project testing; and
(5) Proposed reporting formats.
As a minimum perform process control testing according to the Sampling, Testing, and Acceptance Requirements tables included at the end of each Section where applicable.
(c) Records. Describe the reporting format for inspection, testing, certification, and daily reports.
Conform to Subsections 153.06 and 153.07.
At least 14 days before the start of work, submit the QCP for approval. Do not perform work on a work category unless the quality control for that category is accepted.
This is the start of the file's text. The full file is on GovTribe.