Attachment 2- Specification.pdf
PDF 3 MB Posted
- Attached to
- USCGC MANOWAR DRYDOCK REPAIRS Federal contract opportunity
- Solicitation number
- 70Z08026QPBPL0026
About this file
This is a detailed Specification for Drydock Repairs for USCGC MANOWAR (WPB 87330) during FY2026, developed January 9, 2026. The specification encompasses 47 work items organized across hull preservation, structural repairs, system modifications, and equipment renewals, with an estimated performance period from June 17, 2026 to August 19, 2026. Key preservation work includes 100% underwater body preservation using MIL-PRF-24647 anticorrosive and ablative coating systems, 100% freeboard preservation with polysiloxane finishes, main deck surface preparation and slip-resistant sheet installation, and superstructure aluminum preservation. Critical structural and mechanical work encompasses propulsion shaft renewal with comprehensive alignment surveys, rudder assembly renewal with bearing replacement, stern tube interior preservation, intermediate and aft water-lubricated bearing renewal, intermediate and aft bearing carrier renewal, and propeller renewal with blue-fitting verification. System-critical work includes sewage system modification installing Jets vacuum toilets, seawater cooling piping/valve renewal, fire main bleed line modification, electrical system upgrades (24VDC distribution system and intrusion detection system replacement), and unmanned space ventilation modifications. Additional requirements include drydocking operations with pre-award calculations, underwater hull inspection board participation, tank cleaning and inspection (fuel, dirty oil, oily water, grey water, sewage), comprehensive electrical thermographic inspection of power distribution, and sea trial support with dock trial completion. Government-furnished property totals over $120,000 including propellers, shafts, rudders, alternators, electrical components, and various bearings and seals. The specification mandates compliance with SFLC Standard Specifications for preservation, welding, electrical work, and drydocking procedures, with critical inspection items requiring reports within the first 25% of contract performance and extensive quality control documentation throughout all preservation and coating operations.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 70Z08026QPBPL00260001_US KO signed.pdf | ||
| 70Z08026QPBPL0026_0_US.pdf | ||
| Attachment 1-Schedule of Services CGC MANOWAR DD Repairs.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
USCGC MANOWAR (WPB 87330)
SPECIFICATION FOR DRYDOCK REPAIRS
FY2026
Developed By: Daniel Domenech Diaz
(Rev-0, 9 January 2026)
USCGC MANOWAR (WPB-87) DRYDOCK AVAILABILITY FY2026
ii (Rev-0)
TABLE OF CONTENTS
Revisions Record .......................................................................................................................................... iv Consolidated List of References .................................................................................................................... v Consolidated List of Government-furnished Property .................................................................................. x Consolidated List of Critical Inspection Items .......................................................................................... xiii Principal Characteristics ............................................................................................................................. xiv General Requirements WORK ITEM 1: Hull Plating (Side Scan), Ultrasonic Testing WORK ITEM 2: Ultrasonic Thickness Measurements, Perform WORK ITEM 3: U/W Body, Preserve, 100 percent WORK ITEM 4: Hull Plating Freeboard, Preserve, 100 Percent WORK ITEM 5: Tank, Dirty Oil, Clean and Inspect WORK ITEM 6: Tank, Oily Water, Clean and Inspect WORK ITEM 7: Tanks, MP Fuel Service, Clean and Inspect WORK ITEM 8: Decks, Exterior (Main Deck), Preserve WORK ITEM 9: Superstructure, Preserve, 100% WORK ITEM 10: Capastic Fairing, Depth Sounder, Renew WORK ITEM 11: Watertight Closures, Assess WORK ITEM 12: Mast, Preserve (“100%”) – Contractor Interference Removal WORK ITEM 13: Intermediate Water-Lubricated Propulsion Shaft Bearings, Renew WORK ITEM 14: Aft Water-Lubricated Propulsion Shaft Bearings, Renew WORK ITEM 15: Intermediate Bearing Carriers, Renew WORK ITEM 16: Aft Bearing Carriers, Renew WORK ITEM 17: Propulsion Shafts, Renew WORK ITEM 18: Stern Tube Interior Surfaces, Preserve, 100 Percent WORK ITEM 19: Propellers, Renew WORK ITEM 20: Electrical Power Distribution System, Thermographic Inspection, 450 VAC And
Below WORK ITEM 21: Fathometer Transducer, Renew WORK ITEM 22: Speed Log, Skin Valve, Renew WORK ITEM 23: Ventilation System, Engine Room Supply and Exhaust Fan Assemblies, Clean and
Inspect WORK ITEM 24: Ducting, HVAC System, Clean WORK ITEM 25: Sea Water System, Perform Maintenance WORK ITEM 26: Rudder Assemblies, Renew WORK ITEM 27: Stern Launch Door, Remove, Inspect and Reinstall WORK ITEM 28: Grey Water Holding Tanks, Clean and Inspect WORK ITEM 29: Sewage Holding Tanks, Clean and Inspect WORK ITEM 30: Grey Water Piping, Clean and Flush WORK ITEM 31: Sewage Piping, Clean and Flush WORK ITEM 32: Cathodic Protection/Zinc Anodes, Renew WORK ITEM 33: Drydock WORK ITEM 34: Temporary Services, Provide - Cutter WORK ITEM 35: Sea Trial Performance, Support, Provide
WORK ITEM 36: SEWAGE SYSTEM (TOILET), MODIFY
WORK ITEM 37: Frames and Brackets, Engine Room, Renew WORK ITEM 38: Watertight Closure, Renew WORK ITEM 39: Windows, Pilothouse, Renew WORK ITEM 40: Critical Coated Surface(s), Preserve iii (Rev-0)
WORK ITEM 41: Interior Deck Covering System And Jointer Deck, Renew WORK ITEM 42: 24VDC Distribution System, Upgrade WORK ITEM 43: Intrusion Detection System, Replace WORK ITEM 44: Unmanned Space Ventilation Modify WORK ITEM 45: Fire Main Bleed Line, Modify WORK ITEM 46: Sewage Air Compressor, Remove WORK ITEM 47: Seawater Cooling Piping/Valves, Renew iv (Rev-0)
REVISIONS RECORD
This page is used to record specification revisions, which may have occurred subsequent to a Revision 0 (Rev-0) package. Information listed is intended to provide contractors and field unit personnel a means to ensure all the current specification revision pages are present when reviewing or utilizing this specification package.
DATE REV# WORK
ITEM#
CHANGES MADE
NOTE : All work item and paragraph numbers listed above for a given revision correspond to same numbers in the previous revision. This revised specification is self-contained with all of the above listed changes incorporated.
v (Rev-0)
CONSOLIDATED LIST OF REFERENCES
The below-listed documents form a part of this specification to the extent specified herein. Approval/publication dates or revision dates/numbers are also identified, to ensure that same document versions are used at the time of specification writing and during contract execution.
All Coast guard drawings, technical publications, and standard specifications will be provided to contractors by the Coast Guard at an appropriate time, or upon request, free of charge. Other Government documents may be accessed – free of charge – from links located on the SFLC website. Commercial sites provide access to their respective documents.
COAST GUARD DRAWINGS
1. Drawings 87 WPB 321-001, 321-002, and 302-001 are applicable to all hulls.
2. Drawing 87 WPB 310-005 is applicable only to CGC GANNET. Drawing 87 WPB 310-011 is applicable only to CGC SEA HORSE. 87 WPB 310-001 is applicable to all others. Retain only the drawing that is applicable and delete the other two.
APM:
Coast Guard Drawing 87 WPB 085-001, Rev -, Tank Capacity Curves
Coast Guard Drawing 87 WPB 085-011, Rev C, Lifting Slings
Coast Guard Drawing 87 WPB 085-012, Rev A, Lifting Cradle
Coast Guard Drawing 87 WPB 085-013, Rev B, Docking Plan
Coast Guard Drawing 87 WPB 111-001, Rev H, Shell Expansion
Coast Guard Drawing 87 WPB 111-050, Rev A, Updates to DWG 87-WPB-111-001 Exhaust Port Insert
Plate Installation and Details
Coast Guard Drawing 87 WPB 113-001, Rev G, Platform Plating & Framing
Coast Guard Drawing 87 WPB 113-002, Rev B, Galley/Mess Deck Access
Coast Guard Drawing 87 WPB 116-001, Rev -, Longitudinal Girders & BHD’s
Coast Guard Drawing 87 WPB 117-001, Rev G, Transverse Sections
Coast Guard Drawing 87 WPB 122-001, Rev C, Watertight Bulkheads
Coast Guard Drawing 87 WPB 131-001, Rev J, Deck Construction Plan
Coast Guard Drawing 87 WPB 151-001, Rev L, Superstructure Details
Coast Guard Drawing 87 WPB 163-001, Rev H, Sea Chest Details
Coast Guard Drawing 87 WPB 165-001, Rev F, Transducer Details
Coast Guard Drawing 87 WPB 167-002, Rev C, CG Schedule of Doors, Manholes, Windows & Hatches
Coast Guard Drawing 87 WPB 167-002, Rev C, CG Schedule of Doors, Manholes, Windows, and
Hatches.
Coast Guard Drawing 87 WPB 167-003, Rev -, Weather Tight Door for Fuel Station Access
Coast Guard Drawing 87 WPB 167-004, Rev H, W.T. Doors and Hatches
Coast Guard Drawing 87 WPB 171-001, Rev W, Mast Details
Coast Guard Drawing 87 WPB 185-001, Rev AP, Auxiliary Foundation Booklet
Coast Guard Drawing 87 WPB 186-001, Rev -, Foundations for Install of Jets Vacuum System
Coast Guard Drawing 87 WPB 243-003, Rev -, Propulsion Shaft Details vi (Rev-0)
Coast Guard Drawing 87 WPB 245-003, Rev A, Propeller Details
Coast Guard Drawing 87 WPB 256-001, Rev AC, Seawater Cooling Piping
Coast Guard Drawing 87 WPB 302-001, Rev W, Misc. Controls Wiring Diagram
Coast Guard Drawing 87 WPB 302-003, Rev -, Jets Vacuum Toilet Electrical Details
Coast Guard Drawing 87 WPB 310-001, Rev H, Ship’s Service One-Line Diagram
Coast Guard Drawing 87 WPB 310-001, Rev J, Ship’s Service One-Line Diagram
Coast Guard Drawing 87 WPB 310-005, Rev -, Ships Service 60HZ AC Power One Line Diagram
Coast Guard Drawing 87 WPB 310-007, Rev A, Unmanned Spaces Ventilation modification Electrical
Coast Guard Drawing 87 WPB 310-011, Rev -, PowerGen One Line SSDG One Line
Coast Guard Drawing 87 WPB 313-001, Rev R, DC System
Coast Guard Drawing 87 WPB 321-001, Rev K, Power System Deck Plan
Coast Guard Drawing 87 WPB 321-002, Rev AM, Power & Lighting Circuit Details & V.D. Calculations
Coast Guard Drawing 87 WPB 423-001, Rev W, Speed Log & Depth Sounder System
Coast Guard Drawing 87 WPB 433-001, Rev M, General Announcing & Alarm Sys Wiring Diagram
Coast Guard Drawing 87 WPB 436-001, Rev G, Fire Detection System
Coast Guard Drawing 87 WPB 436-002, Rev A, Intrusion Detection System, Replace
Coast Guard Drawing 87 WPB 514-001, Rev M, HVAC Duct & Piping System
Coast Guard Drawing 87 WPB 514-001, Rev M, HVAC Duct & Piping Systems
Coast Guard Drawing 87 WPB 514-005, Rev E, Ventilation Mods to Unmanned Spaces
Coast Guard Drawing 87 WPB 521-002, Rev -, Fire Main Bleed Line Mod
Coast Guard Drawing 87 WPB 526-001, Rev J, Scuppers & Deck Drains Piping
Coast Guard Drawing 87 WPB 561-001, Rev M, Steering System Details
Coast Guard Drawing 87 WPB 562-001, Rev A, Rudder Details
Coast Guard Drawing 87 WPB 583-001, Rev W, RIB Deployment Structure
Coast Guard Drawing 87 WPB 583-001, Rev Y, RIB Deployment Structure
Coast Guard Drawing 87 WPB 593-001, Rev L, Sewage Piping
Coast Guard Drawing 87 WPB 593-004, Rev B, Sewage System Modifications Jets Vacuum System
Coast Guard Drawing 87 WPB 593-005, Rev -, Air Compressor, Removal
Coast Guard Drawing 87 WPB 601-001, Rev R, Outboard Profile & General Arrangements
Coast Guard Drawing 87 WPB 602-001, Rev F, Visual ID and Draft Mark Plan
Coast Guard Drawing 87 WPB 621-001, Rev K, Joiner Work Details
Coast Guard Drawing 87 WPB 621-001, Rev K, Jointer Work Details
Coast Guard Drawing 87 WPB 631-001, Rev P, Ship’s Painting Schedule
Coast Guard Drawing 87 WPB 633-001, Rev A, Cathodic Protection
Coast Guard Drawing 87 WPB 634-001, Rev G, Deck Covering and Details
Coast Guard Drawing 87 WPB 640-001, Rev P, Interior Furnishings
Coast Guard Drawing 87WPB 431-001, Rev T, IC Panel Board Wiring Diagram
Coast Guard Drawing 87WPB 432-001, Rev L, Dial Telephone Wiring Diagram
Coast Guard Fleet Drawing FL 2804-12, Rev -, U.S.C.G. Emblem
Coast Guard Fleet Drawing FL 2804-22, Rev A, Consolidated Visual ID for Cutters vii (Rev-0)
COAST GUARD PUBLICATIONS
Coast Guard Commandant Instruction (COMDTINST) M10360.3, Jun 2006, Coatings and Colors
Manual
Coast Guard Commandant Instruction (COMDTINST) M5530.1C, Physical Security and Force
Protection Program
Coast Guard Technical Publication (TP) 4499, Jun 2018, SWBS 243, Stern Tube Seal-Model 442C
Coast Guard Technical Publication (TP) 4500, September 2017, SWBS 233, Engine Change-Out Guide –
Waterborne Main Diesel
Coast Guard Technical Publication (TP) 4506, Wartsila TM-EL-68839, Issue A, Mar 2005, Rudderstock
Seal Type EL
Coast Guard Technical Publication (TP) 4511, SWBS 430, Jun 2019, Alarm Panel & Tank Level
Indication (TLI) System
Coast Guard Technical Publication (TP) 4525, SWBS 202, 2003, Main Diesel Engine Control System
Schematics
Coast Guard Technical Publication (TP) 4533, SWBS 233, 2002, Propulsion Internal Combustion
Engines, Maintenance Manual
Coast Guard Technical Publication (TP) 4559, SWBS 513, Oct 2019, Ventilation System, Engine Room
Coast Guard Technical Publication (TP) 4564A, Electronic Steering System
Coast Guard Technical Publication (TP) 9115, SWBS 593, March 2016, Jets Vacuum Sewage System
Coast Guard Technical Publication (TP) E-424-013, SWBS 424, July 2007, CDOH-EML500 Speedlog
User’s Manual
Fire Prevention and Response
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2018, General
Requirements
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2020, General
Requirements
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General
Requirements
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), Latest Version, General Requirements
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std. Spec 0000), 2022, General
Requirements
Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2018, Welding and
Allied Processes
Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2022, Welding and
Allied Processes
Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), Latest Version, Welding and Allied Processes
Surface Forces Logistics Center Standard Specification 3041 (SFLC Std Spec 3041), 2022, Shipboard
Electrical Cable Test
Surface Forces Logistics Center Standard Specification 3042 (SFLC Std Spec 3042), 2022, Shipboard
Electrical Cable Removal, Relocation, Splice, Repair, and Installation
Surface Forces Logistics Center Standard Specification 5100 (SFLC Std Spec 5100), 2022, Clean
Shipboard Ventilation Systems
Surface Forces Logistics Center Standard Specification 5550 (SFLC Std Spec 5550), Latest Version, viii (Rev-0)
Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2018, Requirements for Preservation of Ship Structures
Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2022, Requirements for Preservation of Ship Structures
Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), Latest Version, Requirements for Preservation of Ship Structures
Surface Forces Logistics Center Standard Specification 6310 (SFLC Std. Spec 6310), 2022, Requirements for Preservation of Ship Structures
Surface Forces Logistics Center Standard Specification 6341 (SFLC Std Spec 6341), 2022, Install Interior
Deck Covering Systems
Surface Forces Logistics Center Standard Specification 8634 (SFLC Std Spec 8634), 2022, Drydocking
Surface Forces Logistics Center Standard Specification 8635 (SFLC Std Spec 8635), 2020, Temporary
Services
OTHER REFERENCES
American Society for Nondestructive Testing (ASNT) SNT-TC-1A, 2016, Recommended Practice for
Personal Qualification and Certification in Nondestructive Testing
American Society for Nondestructive Testing, SNT-TC-1A: Personnel Qualification and Certification in
Nondestructive Testing, 2016
AN/SPS-73V Surface Search Radar (SSR), Sep 1998, Operation, Maintenance, and Installation Manual
ASTM International (ASTM) D1330, 2010, Standard Specification for Rubber Sheet Gaskets
ASTM International (ASTM) D1330, 2015, Standard Specification for Rubber Sheet Gaskets
ASTM International (ASTM) F992, 2006, Standard Specification for Valve Label Plates
Code of Federal Regulations (CFR) Title 29, Part 1915, Occupational Safety and Health Standards for
Shipyard Employment
Commercial Item Description (CID) A-A-59313, Nov 2003, Thread Compound; Antiseize, Zinc Dust-
Petrolatum
Commercial Item Descriptions (CID) A-A-59316, Nov 2016 Abrasive Materials for Blasting
Federal Standard (FED-STD) 595, 2008, Colors Used in Government Procurement
MIL-A-18001, Dec 2015, Anodes, Sacrificial Zinc Alloy (Commercially Accepted - ASTM B418)
MIL-A-22262, Mar 1996, Abrasive Blasting Media Ship Hull Blast Cleaning
MIL-A-22262, Mar 1996; Abrasive Blasting Media Ship Hull Blast Cleaning
MIL-A-46106b, Jun 1992, Adhesive-Sealants, Silicone, RTV, One-Component
MIL-D-16791, Jan 1993, Detergents, General Purpose (Liquid, Non-ionic)
MIL-HDBK-299, Oct 1991, Cable Comparison Handbook – Data Pertaining to Electric Shipboard Cable
MIL-PRF-24139, Mar 1987, Grease, Multipurpose, Water Resistant.
MIL-PRF-24613A, Nov 2007, Deck Covering Materials, Interior, Cosmetic Polymeric
MIL-PRF-24635, 2009, Coating Systems, Weather-Resistant, Exterior Use
MIL-PRF-24647, Jan 2018, Paint System, Anticorrosive and Antifouling, Ship Hull
MIL-STD-2003, Sep 2009, Electrical Plant Installation Standard Methods for Surface Ships &
Submarines
NAVSEA Technical Publication T9074-AD-GIB-010/1688, (TP 1688), July 2012, Requirements for
Fabrication, Welding, and Inspection of Submarine Structure ix (Rev-0)
Raytheon Marine Company, Jan 1992, Technical Manual, Radar Set Model R40X/R41X, AN/SPS-69, RMC Document Number G261404
Society of Automotive Engineers (SAE) Aerospace Material Specification (AMS) C6183, 2013, Cork and
Rubber Composition Sheet; for Aromatic Fuel and Oil Resistant Gaskets
Society of Automotive Engineers (SAE) Aerospace Material Specification (AMS) C6183, 2019, Cork and
Rubber Composition Sheet; for Aromatic Fuel and Oil Resistant Gaskets
The Society for Protective Coatings (SSPC) Surface Preparation Specification No.1 (SSPC-SP 1), 2016, Solvent Cleaning
The Society for Protective Coatings (SSPC) Surface Preparation Specification No.11 (SSPC-SP 11), 2012, Power-Tool Cleaning to Bare Metal
The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation
Standard SSPC-SP 12/NACE No.5, 2002, Surface Preparation and Cleaning of Metals by
Waterjetting Prior to Recoating
The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation
Standard SSPC-SP WJ-2/NACE WJ-2, 2012, Waterjet Cleaning of Metals – Very Thorough
Cleaning
The Society for Protective Coatings (SSPC)/NACE-International (NACE) Joint Surface Preparation
Standard SSPC-SP 10/NACE No. 2, 2007, Near-White Blast Cleaning
The Society for Protective Coatings (SSPC)/NACE-International (NACE) Joint Surface Preparation
Standard SSPC-SP 10/NACE No. 2, 2007, Near-White Metal Blast Cleaning x (Rev-0)
CONSOLIDATED LIST OF GOVERNMENT-FURNISHED PROPERTY
The following is a list of property, which the Government will furnish. This list supersedes any other material obligations indicated or implied by referenced drawings.
WORK
ITEM
MTI ITEM DESCRIPTION NSN/PN QTY ESTIMATED
COST
($/UNIT)
8 N Slip Resistant Sheets NSN: 7220-01-F11-2238 1 KT 5,352.24
13 N Thordon bearing, Grade
Orange (5.5" OD x 4"
ID x 7.87" (200mm)
LG)
PN: F54615-02-8-1 NSN:
3120-21-914-2012
2 ea. 525.03
14 N Thordon bearing, Grade
Orange (5.5" OD x 4"
ID x 11.41" (290mm)
LG)
PN: F54615-02-8-0 NSN:
3120-21-914-2011
2 ea. 558.05
15 N **Intermediate bearing carrier
NSN: 3130-01-F11-2388 P/N:
87 WPB 243-001, Item 17
2 ea. 591.86
16 N **Aft bearing carrier NSN: 3130-01-F11-2200 PN:
87 WPB 243-001, Item 14
2 ea. 1931.31
17 Y Propeller Shaft NSN: 2010-01-458-9175 2 ea. 10,195.95
17 N Seal Assembly, Shaft NSN: 4320-01-670-5724 PN:
388725
2 ea. 6801.00
17 N Kit Rebuild, Inflatable
Seal
NSN: 5330-01-F18-5385 PN:
390831
2 ea. 1381.00
17 Y *Alignment Kit N/A 1 set 5000.00
19 Y Starboard Propeller
(RH)
PN: 706-3351.00 RH NSN:
2010-01-457-0573
1 ea. 9153.07
19 Y Port Propeller (LH) PN: 706-3350.00 LH NSN:
2010-01-459-0421
1 ea. 9542.05
19 N *Propeller Nut Wrench N/A 1 ea. 200.00
19 N Propeller Nut PN: 5317350 NSN: 2010-01-
458-9217
2 ea. 322.07
19 N Propeller Nut, Locking PN: 5317355 NSN: 5310-01-
458-9125
2 ea. 285.10
19 N Anode, Propeller Nut PN: 87WPB243001ITEM39
NSN: 5342-01-481-8403
2 ea. 153.06
21 N Transducer, sonar PN: SS60SLD NSN: 5845-01-
618-8996
1 ea. 328.72
22 N 3" Ball Valve NSN: 4810-01-517-8110 PN:
LV071A
1 ea. 5625.00
22 N **Doppler Speed Log
Measurement Rod
NSN: 6605-01-470-1266 1 ea. 4984.63
23 N **Fan, Tube Axial NSN: 4140-01-598-0425 1 ea. 2,223.72
23 N **Fan, Tube Axial NSN: 4140-01-598-1549 1 ea. 3,091.15
25 N Iron body/ Stainless steel stem/ bronze disk
(flanged) 8 inch
PN: J022929-512431A NSN:
4820-01-613-5021
2 ea. 563.25
25 N Iron body/ Stainless PN: 22929-112431A NSN: 2 ea. 521.46 xi (Rev-0) steel stem/ bronze disk
(wafer) 8 inch
4820-01-615-9571
25 N Iron body/ Stainless steel stem/ bronze disk
(flanged) 3 inch
PN: 22925-5124 NSN: 4820-
01-650-0975
2 ea. 226.51
25 N Iron body/ Stainless steel stem/ bronze disk
(wafer) 3 inch
PN: 22925-1124316 NSN:
4820-01-332-6811
2 ea. 214.14
26 Y Rudder Assembly, port NSN: 2040-01-461-1944 1 ea. 6113.36
26 Y Rudder Assembly, starboard
NSN: 2040-01-461-1943 1 ea. 5971.93
26 N Upper Roller Bearing NSN: 3110-01-512-5534 2 ea. 287.43
26 N Wartsila EL Seals Kit PN: H75492-01 NSN: 2040-01-
565-9776
2 ea. 7243.42
26 N Lower Bearing PN: TBF113090 NSN: 3120-
20-000-7677
2 ea. 405.81
27 N **Valve, Counterbalance
PN: CBCA-LAN/AP NSN:
4820-01-687-1295
4 ea. 291.50
27 N **Manifold, Valve PN: YVY NSN: 4730-01-687-
2 ea. 134.30
32 N Anode, corrosion preventive
PN: 899Y105 NSN: 5342-00-
813-6058
15 ea 57.37
33 Y *Transducer Cover
Plate
N/A 2 ea. 50.00
36 N Sewage installation kit:
Jets 610SS Toilets, Vacuum Pump, controller and Vacuum
Accumulator
NSN: 4510-01-F16-4844 PN:
CUSTVU15-TO610
1 ea. $13,957
38 N Door, QAWT, 26―X54―R.H.
(Main Deck Office
Access)
NSN: 2040-01-F14-3674 1 ea. 10,250.90
39 N Window, marine (Pos
3)
NSN: 2090-21-920-3186 1 3,084.93
39 N Window, Marine (Pos
6)
NSN: 2090-21-914-8549 1 3,138.86
39 N Window, marine (Pos
8, 11)
NSN: 2090-21-914-9450 1 2,565.38
41 N **Panel, Deck, 5/8"x48"x96", Aluminum 5052-H32
Core, 1/4" Cell, 0.063"
6061-T6 Face Sheets, Natural Mill Finish
NSN: 2040-01-F19-5621 PN:
SPXC-1000-1000D
1 Ea. $654.00
42 N Panel Bridge 24 V NSN: 6110-01-F18-5605 1 ea. 2,548.00
42 N Alternator NSN: 6125-01-020-2950 2 ea. 14,668.79
42 N Regulator Voltage NSN: 5963-01-623-3549 2 ea. 350.00
42 N Resistor Thermal NSN: 5905-01-662-5504 2 ea. 35.00 xii (Rev-0)
42 N Harness, Wiring NSN: 5995-01-661-5659 2 ea. 75.00
42 N Seal Plain NSN: 5330-12-314-3403 2 ea. 56.32
42 N Coupling Half NSN: 4730-12-408-7920 2 ea. 1,572.87
42 N Coupling, Flex NSN: 3010-01-255-4200 2 ea. 480.44
42 N Insert, Flexible
Coupling
NSN: 3010-12-332-3557 2 ea. 830.23
42 N Screw Machine NSN: 5305-01-384-3454 12 ea. 3.71
42 N Washer, Spring
Tension
NSN: 5310-12-125-7798 12 ea. 2.44
42 N Nut, Plain Hexagon NSN: 5310-12-156-4982 12 ea. 2.33
42 N Guard Plate NSN: 2920-12-408-7817 2 ea. 941.45
42 N Plate, Mounting NSN: 5340-12-333-7085 2 ea. 75.00
42 N Screw, Cap, Hexagon NSN: 5305-01-240-1274 14 ea. 4.53
42 N Washer, Spring
Tension
NSN: 5310-01-195-9000 14 ea. 1.81
42 N Screw Cap Hexagon NSN: 5305-12-142-8243 4 ea. 7.92
42 N Screw, Cap NSN: 5305-12-142-8236 4 ea. 3.64
42 N Washer, Flat NSN: 5310-12-149-4352 8 ea. 2.35
42 N Bracket NSN: 2815-12-408-5547 4 ea. 130.18
43 N Sensaphone Eapress II ACN: 6320-01-F21-6407 1 $1300
43 N IDS Relay Panel ACN 6320-01-F21-6406 1 $1400
43 N Switch, 3 position, Key
Lock, ACN 6320-01-F21-6408 1 $13.00
43 N Holder, switch ACN 6320-01-F21-6409 1 $2.00
43 N Contact Block, NC ACN 6320-01-F21-6410 3 $5.00
43 N Sensor, Optical ACN 6320-01-F21-6411 6 $44.00
43 N Mounting Bracket, 90 deg
ACN 5340-01-F21-6412 2 $7.00
43 N Mounting Bracket, straight
ACN 5340-01-F21-6413 4 $7.00
*Government-loaned property, which shall be returned to the vessel upon completion of the availability.
**New or refurbished equipment that the Government may provide for installation in place of existing equipment.
***Government-furnished property, which is to be supplied by either the vessel or the C4IT ServiceCenter xiii (Rev-0)
CONSOLIDATED LIST OF CRITICAL INSPECTION ITEMS
The following is a list of work items, which contain Critical Inspection reports, which the Contractor must complete within the first 25% of the availability contract period (see SFLC Std Spec 0000, paragraph 3.2.6.5
(Inspection report particulars)):
Work
Item Title
3 U/W Body, Preserve, 100 percent
7 Tanks, MP Fuel Service, Clean and Inspect
17 Propulsion Shafts, Renew
25 Sea Water System, Perform Maintenance
26 Rudder Assemblies, Renew
27 Stern Launch Door, Remove, Inspect and Reinstall
33 Drydock
36 SEWAGE SYSTEM (TOILET), MODIFY
40 Critical Coated Surface(s), Preserve xiv (Rev-0)
PRINCIPAL CHARACTERISTICS
87' WPB
PHYSICAL
Length overall 87'
Length between perpendiculars 81' 7"
Depth 10' 11"
Maximum beam 19.4'
Draft, mean to design waterline 5' 9"
Height of highest projection 50.2'
Full load displacement 93.5 long tons
Minimum operating displacement 83.9 long tons
Displacement, light ship 77.9 long tons
Framing Longitudinal
Bulkheads Four watertight bulkheads located below the Main Deck
Anchor 40 lb Fortress with 480 ft. 3 strand 5/8" dia. Line stayset
HULL
Hull/main weatherdeck material ABS Grade AH 36
Superstructure 5086 Aluminum
MACHINERY
Main propulsion Two MTU 8V396TE94, sequential turbo-charged diesels
Reduction gears Two ZF Type BW 255
Propulsion shaft Two AQUAMET 22, 101.6mm
Shaft diameter 4"
Shaft seal Two John Crane mechanical seals
Shaft bearing, intermediate Thordon Elastomeric Bearing
Shaft bearing, aft Thordon Elastomeric Bearing
Number of propellers 2
Number of blades 5
Diameter of propeller 1040mm
Pitch 1230 mm fixed
Shaft RPM 828
Rudders Two 316L Stainless Steel
Ship's service generators Two Man Model D08241F01 diesel with Stanford 60KW Generator
TANK CAPACITIES
3-9-1-f (fuel oil) 1402 gal
3-9-2-f (fuel oil) 1402 gal
3-12-2-f (waste oil) 86 gal
3-12-1-f (oily water) 86 gal
3-7-0-q (sewage collection) 352 gal
3-7-1-q (grey water) 52 gal
3-12-1-w (fresh water) 200 gal
3-12-2-w (fresh water) 200 gal
1 (Rev-0)
00000_0824_FLT
REC_00000_FLT_Commercial Project @ Contractor’ Facility (0121)
General Requirements
1. SCOPE
1.1 Intent. This standard specification invokes general requirements for conducting vessel repairs performed at a commercial contractor’s facility for Coast Guard vessels.
1.2 Term interchangeability. The terms 'Contractor', 'CG Yard', 'NAVSTA EVERETT', 'shipyard', 'Base', and
'Coast Guard Industrial' are used interchangeably in this specification. Where the primary service provider is
Coast Guard personnel, references to contractor and other noted descriptors within this specification or within drawings, publications, SFLC Standard Specifications or other commercial and military references are deemed the same as prime service provider.
2. REFERENCES
COAST GUARD DRAWINGS
None
COAST GUARD PUBLICATIONS
Coast Guard Commandant Instruction (COMDTINST) M10360.3 (series), Coatings and Color Manual
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), Latest Version, General Requirements
Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), Latest Version, Welding and Allied Processes
Surface Forces Logistics Center Standard Specification 5550 (SFLC Std Spec 5550), Latest Version, Fire Prevention and Response
Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), Latest Version, Requirements for Preservation of Ship Structures
OTHER REFERENCES
Code of Federal Regulations (CFR) Title 29, Part 1915, Occupational Safety and Health Standards for
Shipyard Employment
NAVSEA Technical Publication T9074-AD-GIB-010/1688, (TP 1688), July 2012, Requirements for
Fabrication, Welding, and Inspection of Submarine Structure
2 (Rev-0)
3. REQUIREMENTS
3.1 General. The Contractor must conform to all requirements specified in SFLC Std Spec 0000 and in this item, as applicable, during the performance of this availability. The requirements in this WI applies to all work under the scope of this contract, whether explicitly stated in all following work items or not, and to all other work subsequently authorized by changes, modifications, or extensions to the contract.
3.1.1 The Contractor must conform to all requirements specified in SFLC Std Spec 5550 and in the Fire
Protection and Response work item, as applicable, during the performance of this availability.
3.1.1.1 Fire Safety Plan submission. The Contractor must submit a copy of the CFR 1915, Subpart P, Fire Safety
Plan with the Contractor’s bid when work will be conducted in a Contractor–owned facility. Include any MOA(s) with local firefighting facilities.
3.1.1.2 Fire Plan submission. The Contractor must submit a copy of the developed availability specific fire plan as requested in the Fire Protection and Response work item, with the Contractor’s bid.
NOTE
NAVSEA drawings listed will be available FOR INSPECTION ONLY from the Coast
Guard Port Engineer post-award. SFLC will not redistribute NAVSEA documents.
Contractors can apply to NAVSEA headquarters directly for copies.
3.1.1.3 SFLC-PBPL Availabilities (87 WPB, 110 WPB, & 154 WPC). The Contractor must conform to SFLC
Std Spec 5550 with the following amendments and supplements:
• For contracts executed at a Contractor’s facility, submit (pre-award) the facility’s Fire Safety Plan document described in 29 CFR 1915.502 – “Fire Safety Plan”. For planning assume that Coast Guard personnel will not be available to fight a fire.
• For all contracts at all facilities, submit the following information pre-award, taking into consideration how the maintenance/repairs specified in the work items will affect uninterrupted operation of the subject systems; make all necessary amendments to this submission after discussions with the COR at the arrival conference and during contract execution as emerging conditions warrant:
o Describe all anticipated needs for fire detection/alarm, fire-fighting, and shipboard lighting and communication systems supplementation (see below) and a description of the proposed remedies/solutions
(include pricing for maintaining capability in pre-award quote).
o Describe how any required temporary/supplemental fire detection/alarm systems will notify fire responders.
o Describe all anticipated breaches of the cutter’s Fire Protection Boundaries and the proposed temporary solutions that will minimize impact on the Fire Protection Boundary’s proper function (e.g. removal of cables/hoses/etc. at the end of work day or installation of quick disconnects, installation of temporary fire curtains, etc.).
• Whenever maintenance/repairs described in work items or Change Requests necessitate securing, or making inoperable, all or part of the vessel’s fire detection or fire alarm system, submit a proposal to the COR/KO describing an equivalent method(s) for temporarily maintaining all lost functionality of the system(s). Select the
3 (Rev-0) most economical option(s) available (i.e. for extended loss of service of the entire system the temporary fire detections/alarm system described in SFLC Std Spec 5550 may be the best option, for shorter durations temporary watch standers may be more economical, etc.). After the COR has agreed to the proposal, maintain the capability of these systems for the duration of the contract to the greatest practicable extent.
• Whenever maintenance/repairs described in work items or Change Requests necessitate securing, or making inoperable, all or part of the vessel’s firefighting (e.g. fire main system, P100 and other dewatering systems, halon systems, portable fire extinguishers, etc.), lighting, and communications systems, submit a proposal to the COR/KO describing equivalent method(s) for temporarily maintaining all lost functionality of the system(s). Select the most economical option(s) available. After the COR has agreed to the proposal, maintain fire detection/alarm/fighting and lighting/communications capability for the duration of the contract to the greatest practicable extent.
• All Fire Protection Boundaries must be left intact and functional at all times to the greatest practicable extent. Notify the COR in writing whenever a breached Fire Protection Boundary will be left unattended outside of normal working hours (e.g. a door/hatch is made un-closable/un-securable due to repair work, an access cut is made into deck/bhd that is part of a Fire Protection Boundary, etc.). When a Fire Protection Boundary must be breached to facilitate contract work, minimize the impact using industry-standard methods (e.g. fire curtains, quick-disconnect fittings, etc.)
3.2 Fire watch requirements. The Contractor must refer to 3.3.1.3 (Fire watch requirements) of SFLC Std Spec
0000, in accomplishing the following task:
• Provide portable fire extinguishers for Coast Guard fire watch personnel. Coast Guard fire watch is in lieu of contractor personnel during the hours of 0800-1600, Monday through Friday, and limited to two Coast Guard fire watch personnel.
• Provide fire watch personnel and fire extinguishers for the duration of the availability period, during and beyond noted Coast Guard fire watch support.
3.3 Preservation requirements. The Contractor must accomplish all preservation tasks, including touch-ups, in accordance with SFLC Std Spec 6310.
3.3.1 Brand name approval. Ensure that all contractor-furnished coatings are in accordance with SFLC Std Spec
6310, Appendix C (Authorized Coatings for Use on Cutters and Boats).
3.3.2 Coating colors and system color schemes. The Contractor must obtain a written KO authorization to deviate from any coatings required in SFLC Std Spec 6310 Appendix C before work.
3.3.3 In-process quality control measures. The Contractor must abide by all the safety, preservation, and quality control requirements specified in SFLC Std Spec 0000, paragraph 3.2.4.2 (In-process QC measures for “critical-coated surfaces”).
3.3.3.1 Quality control requirements. The Contractor must abide by the following when performing preservation related inspections. The following measurements must be randomly spaced throughout for the purposes of providing a representation of the entire prepared or coated surface.
3.3.3.1.1 Surface profile measurements. One surface profile measurement must be taken for every 200 square feet for the first 1000 square feet; for each additional 500 square feet or less, one profile measurement must be taken.
Profile measurements must be taken in accordance with SFLC Std Spec 6310, paragraph 3.1.8.3 (Surface profile measurements). A “measurement” for surface profile is defined as follows:
• ASTM D4417, Method B: One profile measurement is the average (mean) of 10 individual readings.
4 (Rev-0)
• ASTM D4417, Method C: One profile measurement is the average (mean) of 2 individual readings.
3.3.3.1.2 Soluble salt conductivity measurements. 5 conductivity measurements must be taken every 1000 square feet. For submerged (immersed) applications conductivity measurements must not exceed 30 microsiemens/cm.
For non-submerged (non-immersed) applications conductivity measurements must not exceed 70 microsiemens/cm. If a conductivity check fails, clean the surface in accordance with SFLC Std Spec 6310, paragraph 3.1.8.5 (Soluble salt removal).
3.3.3.1.3 Coating thickness measurements. Three area measurements must be taken for the first 1000 square feet;
for each additional 1000 square feet, perform an additional area measurement. A “measurement” for coating thickness is defined as follows:
• SSPC-PA 2 defines an area measurement as 5 separate spot measurements randomly spaced throughout a 100 square foot area.
• SSPC-PA 2 defines a spot measurement as 3 gage readings and each new gage reading the probe must be moved to a new location within a 1.5-inch diameter circle defining the spot.
3.4 Welding and brazing requirements. The Contractor must perform all welding and allied processes, and NDE in accordance with SFLC Std Spec 0740.
3.4.1 HY-130 material substitution. The Contractor must be aware that HY-130 steel plating is no longer commercially available. For the purpose of performing flight deck repairs on US Coast Guard WMEC-270 “B-
Class” cutters, Weldox 900 steel plating has been approved as a replacement for HY-130. Due to the similarity in material properties and weldability of HY-130 and Weldox 900, all welding procedures and welder qualifications for welding Weldox 900 must be the same as those outlined in NAVSEA TP 1688 as applicable for welding HY-
130.
3.4.2 Standard spec modification. For any welding involving HY-130 on the flight deck of WMEC-270 “B-Class” cutters, perform all welding and allied processes, and non-destructive evaluation (NDE) in accordance with
NAVSEA TP 1688. The Contractor must be aware that the welding requirements specified in this document take precedence over paragraph 3.3.6 of SFLC Standard Spec 0000 for the purpose of welding involving HY-130.
3.4.3 Approval to weld HY-130. To obtain Coast Guard approval to weld on HY-130 steel for WMEC-270 “B-
Class” cutters, the Contractor must provide written Performance Qualification Records (PQR’s) for each process to be used. The PQR’s must be approved by one of the regulatory agencies affirming that the WPS meets the welding requirements of NAVSEA TP 1688. In addition, the Contractor must ensure that all subcontractors, prior to performing welding operations, have qualified procedures by meeting all the requirements set forth in this document.
NOTE
NAVSEA approval is NOT required for welding procedures submitted but the procedures must be reviewed and shown to satisfy the requirements set forth in
NAVSEA TP 1688, by a welding regulatory agency. The requirements for welding
Weldox 900 are considered the same as those for welding HY-130.
3.5 Environmental protection requirements. The Contractor must adhere to the following environmental protection requirements in accordance with the SFLC Stand Spec 0000:
3.5.1 Contractor operated (non USCG) facilities. The Contractor must provide and maintain environmental protection as defined in SFLC Std Spec 0000 Appendix A, Requirements for Environmental Protection at
Contractor Operated (Non USCG) Facilities, as applicable, during the performance of this availability. Contractor
5 (Rev-0) must plan for and provide environmental protective measures to control pollution that develops during normal practice, as well as plan for and provide environmental protective measures required to correct conditions that develop during the project. Contractor must comply with applicable Federal, state, and local laws, codes, ordinances, and regulations in their entirety. Any reference to a specific portion of a Federal, state, or local law, code, ordinance, or regulation in this or any other item must not be construed to mean that relief is provided from any other sections of the law, code, ordinance, or regulation.
3.5.1.1 USCG Generator status. The activity Generator Status for the Coast Guard Facility is _________.
3.5.1.2 Plans and permits. The CG Facility has unit specific permits including the following:
• Spill Prevention Control and Countermeasures (SPCC) Plan: Unit has a SPCC Plan which requires certain unit-specific procedures be followed for the storage, inspection, and transfer of petroleum products in containers 55 gallons or greater.
• National Pollutant Discharge Elimination System (NPDES) Storm Water (SW) Permit: Unit has an
NPDES SW permit which requires unit-specific procedures be followed for the storage and inspection of equipment and materials which may contribute contaminants to storm water discharges.
• Air Emission Permit: Unit has an Air Emission Permit which requires unit-specific procedures be followed for the emissions of VOCs and hazardous air pollutants.
3.5.2 Test and procedures. The Contractor is required to promptly conduct tests and procedures for the purpose of assessing whether operations are in compliance with applicable Environmental Laws. Analytical work must be done by qualified laboratories; and where required by law, the laboratories must be certified.
3.5.3 Regulatory notifications. The Contractor is responsible for all regulatory notification requirements in accordance with Federal, State and local regulations. In cases where the Coast Guard must also provide public notification, such as storm water permitting, the Contractor must coordinate with the Contracting Officer or COR, and if work is being performed at a USCG Facility, the local Facility Engineer or Engineering Officer. The
Contractor must submit copies of all regulatory notifications to the Contracting Officer and the local Facility
Engineer or Engineering Officer prior to commencement of work activities. Regulatory notifications must be provided for including but not limited to demolition, renovation, National Pollutant Discharge Elimination System
(NPDES) defined site work, and remediation of controlled substances such as asbestos, hazardous waste, and lead paint.
3.5.4 Environmental manager. The Contractor must appoint in writing an Environmental Manager for the project, who is responsible for coordinating Contractor compliance with Federal, State, local, and station environmental requirements. The Environmental Manager must ensure compliance with Hazardous Waste Program requirements, including hazardous waste handling, storage, manifesting, and disposal; implement the Contractors’
Environmental Management Plan; ensure that all environmental permits are obtained, maintained, and closed out;
ensure compliance with Storm Water Program Management requirements; ensure compliance with Hazardous
Materials including storage, handling, and reporting requirements; as well as coordinate any remediation of regulated substances such as lead, asbestos, and polychlorinated biphenyl (PCB). This may be a collateral position; however the individual must be trained to accomplish the following duties; ensure waste segregation and storage compatibility requirements are met; inspect and manage Satellite Accumulation areas; ensure only authorized personnel add wastes to containers; ensure all Contractor personnel are trained in 40 CFR requirements and individual position requirements; coordinate removal of waste containers; and maintain the Environmental
Records binder and required documentation, including environmental permits compliance and close-out.
3.5.5 HW disposal. Contractor must comply with SFLC Std Spec 0000 Appendix A, Requirements For
Environmental Protection At Contractor Operated (Non USCG) Facilities for HW disposal.
6 (Rev-0)
3.6 Local Policy. The Contractor must refer to site (e.g., Base) Regulations and Instructions for details regarding local policies (e.g., crane services, parking, or facility usage).
3.7 SFLC Standard Specification approved changes. Approved updates to the 2022 SFLC Standard Specifications will appear here.
3.7.1 None.
4. NOTES
4.1 QA inspection forms. QA inspection forms (QA-1 thru QA-5), required in SFLC Std Spec 6310 to be completed and submitted during preservation of “critical-coated surfaces”, are provided at the end of this document.
7 (Rev-0)
QA-1 - QUALITY ASSURANCE INSPECTION FORM
(PRESERVATION CHECKLIST)
VESSEL NAME HULL # WORK ITEM
WORK ITEM TITLE
LOCATION OF WORK (INCL. FRAME #’S) AREA (SQFT)
CHECKPOINT 1 – COATING SYSTEM COMPLIANCE
Ensure all coatings are in compliance with SFLC Std Spec 6310, Appendix C.
CHECKPOINT 2 - PAINT STORAGE
Ensure all coatings are kept at a temperature of 65 to 85°F at all times, unless otherwise specified by the coating mfg.
CHECKPOINT 3 - AMBIENT CONDITIONS
Ensure surface and surrounding temperatures are each between 50 and 90°F for water-containing coatings, and 35 and 95°F for other coatings, unless otherwise specified by the coating manufacturer(s).
Ensure maximum relative humidity (RH) is as follows, from surface preparations through final curing of topcoat: 50% for tanks, voids, and vent plenum; and 85% for all other areas, unless otherwise specified by manufacturer(s).
Ensure surface temperature is at least 5°F above the dew point, unless otherwise specified by the coating mfg.
CHECKPOINT 4 - PRE-SURFACE PREPARATION
Remove surface contaminants (soluble salts, loose rust, mud, and marine growth) with low pressure fresh water wash down (maximum 5,000 psi). If oil and grease are present, perform solvent cleaning, as per SSPC SP-1.
Verify equipment setup, blast media, and surface preparation methods match designated test coupon.
CHECKPOINT 5 - SURFACE PREPARATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure cleanliness of prepared surface is as per specification (i.e.: SSPC SP-11, SP-10, SP WJ-2…).
Verify surface anchor profile using ASTM D4417-Methods B or C against SFLC Std Spec 6310. Conduct profile readings at a minimum of 5 locations for the first 1000-sqft area, and 2 locations for each succeeding 1000-sqft area.
Measure soluble salt conductivity in accordance with SSPC-Guide 15. Conduct 5 measurements per each 1000-sqft area (max. threshold: 70 microsiemens/cm for non-submerged surfaces, 30 microsiemens/cm for submerged surfaces).
CHECKPOINT 6 - PRIMER COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Verify proper mixing and stand-in (induction) times.
Ensure no paint is applied when the temperature is expected to drop to freezing before the paint has dried.
Ensure surfaces are completely dry, unless otherwise allowed by the coating manufacturer(s).
Verify wet film thickness (WFT) at random, to prevent under or over application. Verify final DFT.
Brush out all runs, sags, drips, and puddles.
Perform visual inspection for holidays and other defects.
CHECKPOINT 7 – STRIPE COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure overcoating window is as per manufacturer’s instructions.
After primer coat (mist coat after inorganic zinc), brush-apply un-thinned coat of same primer paint over edges, weld seams, cut-outs, and areas of complex geometries @ 3-4 mils wet film thickness (WFT).
CHECKPOINT 8 – TOP COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure overcoating window is as per manufacturer’s instructions.
Verify proper mixing and stand-in (induction) times, as applicable.
Verify wet film thickness at random, to prevent under or over application.
Brush out all runs, sags, drips, and puddles.
CHECKPOINT 9 – FINAL INSPECTION
Verify final system dry film thickness. Conduct 5 sets of 3 readings for each of the first 3 100-sqft areas, followed by 5 sets of 3 readings for each succeeding 1000-sqft area.
Ensure that system cure is in accordance with manufacturer's recommendation for intended service.
Ensure potable water tank exhaust ventilation is maintained continuously from and during coating application through final system cure, to exhaust all solvent to the atmosphere and to prevent solvent entrapment.
For immersion coatings (including tank U/W body), record date and time of the following events:
Final coat application: _____/_____; Return to service or removal from environment controls: _____/_____
CHECKPOINT 10 – RECORD KEEPING
Complete, sign, and submit all provided QA Inspection Forms.
NAME OF QP-1/AMPP INSPECTOR SIGNATURE CERT. # DATE / TIME
NAME OF CG REPRESENTATIVE SIGNATURE UNIT DATE/TIME
8 (Rev-0)
QA-2 - QUALITY ASSURANCE INSPECTION FORM
(ENVIRONMENTAL READINGS)
VESSEL NAME HULL #
WORK ITEM
Use one sheet for each activity. Record conditions every four hours from before surface preparation to application of final coating system coat.
DATE
TIME
ACTIVITY (SURFACE
PREPARATION, PRIMER COAT,
BARRIER COAT, TOP COAT,
ETC…)
LOCATION (FRAME &
DECK, RELATION TO
EQUIPMENT, ETC.)
TEMPERATURE % REL.
HUMID-
ITY
DEW
PT.
SURFACE AMBIENT ΔT
| DP -
SURFACE |
9 (Rev-0)
QA-3a - QUALITY ASSURANCE INSPECTION FORM
(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-C)
VESSEL NAME HULL # WORK ITEM
LOCATION OF WORK (FRAME REFERENCES) AREA (SQFT)
SURFACE PREPARATION METHOD PROFILE ACHIEVED (MILS)
MIN MAX MEAN
SSPC-SP-10/AMPP No. 2
SSPC-SP WJ-2/AMPP WJ-2
SSPC-SP-3
SSPC-SP-11
SSPC-SP-11 (inaccessible area)
Brush-blasting (non-metallic substrate)
ABRASIVE MANUFACTURER: ABRASIVE SIEVE SIZE:
PLACE SURFACE PROFILE REPLICA TAPES IN THE SPACES PROVIDED BELOW, TO SERVE AS
PERMANENT QA RECORD. MAINTAIN A SEPARATE LOG FOR EACH LOCATION. WHEN AN AREA IS
DIVIDED INTO SEPARATE SECTIONS, MAINTAIN A SEPARATE LOG FOR EACH SECTION.
Place Surface Profile
Replica Tape Here
Place Surface Profile
Replica Tape Here
Place Surface Profile
Replica Tape Here
Reading (mils): Reading (mils): Reading (mils):
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Reading (mils): Reading (mils): Reading (mils):
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Reading (mils): Reading (mils): Reading (mils):
Place Surface Profile
Replica Tape Here
Place Surface Profile
Replica Tape Here
Place Surface Profile
Replica Tape Here
Reading (mils): Reading (mils): Reading (mils):
Place Surface Profile
Replica Tape Here
Place Surface Profile
Replica Tape Here
Place Surface Profile
Replica Tape Here
Reading (mils): Reading (mils): Reading (mils):
MEAN MIL READING (IAW ASTM D4417-METHOD C) FOR ABOVE 15 READINGS:
NAME OF QP-1/AMPP INSPECTOR SIGNATURE CERT. # DATE /
TIME
10 (Rev-0)
QA-3b - QUALITY ASSURANCE INSPECTION FORM
(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-B)
VESSEL NAME HULL # WORK ITEM
SURFACE PREPARATION METHOD PROFILE ACHIEVED (MILS)
MIN MAX MEAN
SSPC-SP-10/AMPP No. 2
SSPC-SP WJ-2/AMPP WJ-2
SSPC-SP-3
SSPC-SP-11
SSPC-SP-11 (inaccessible area)
Brush-blasting (non-metallic substrate)
ABRASIVE MANUFACTURER: ABRASIVE SIEVE SIZE:
RECORD MEASUREMENTS TAKEN IN THE SPACES PROVIDED BELOW, TO SERVE AS PERMANENT QA
RECORD. MAINTAIN SEPARATE LOG FOR EACH LOCATION. WHEN AN AREA IS DIVIDED INTO
SEPARATE SECTIONS, MAINTAIN A SEPARATE LOG FOR EACH SECTION.
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Mean Mils Reading (IAW ASTM D4417-Method B for above 10 readings (by column):
Mean Reading
(mils)
11 (Rev-0)
QA-4 - QUALITY ASSURANCE INSPECTION FORM
(SURFACE SOLUBLE SALT CONDUCTIVITY LOG)
VESSEL NAME HULL # WORK ITEM
SOLUBLE SALT CONDUCTIVITY MEASUREMENTS IAW SSPC-GUIDE 15.
DATE TEST LOCATIONS CONDUCTIVITY (MICROSIEMENS/CM)
12 (Rev-0)
QA-5 - QUALITY ASSURANCE DATA FORM
(COATING THICKNESS)
(Use one sheet for each sequence)
VESSEL NAME HULL #
WORK ITEM
COATING MFG PRODUCT NAME
BATC
H #
INDUCTI
ON TIME
COATING SYSTEM
SEQUENCE
(PRIMER/TOUCHUP/3RD
COAT, ETC.)
DRY FILM THICKNESS (DFT) MEASUREMENTS IAW SSPC-PA 2.
SPOT 1 2 3 4 5
AVERAGE
VALUE
*BASE METAL READING
(BMR)
*Required, If Magnetic Pull-Off (Type I/Banana) Gauge Is Used.
LOCATION (FRAME REFERENCE):
SPOT 1 2 3 4 5 OVERALL AVG. DFT ADJUSTMENTS
1 AVG. BMR DEVIATION
3 BEFORE ADJUSTMENTS AFTER ADJUSTMENTS
AVG.
LOCATION (FRAME REFERENCE):
SPOT 1 2 3 4 5 OVERALL AVG. DFT ADJUSTMENTS
1 AVG. BMR DEVIATION
3 BEFORE ADJUSTMENTS AFTER ADJUSTMENTS
AVG.
LOCATION (FRAME REFERENCE):
SPOT 1 2 3 4 5 OVERALL AVG. DFT ADJUSTMENTS
1 AVG. BMR DEVIATION
3 BEFORE ADJUSTMENTS AFTER ADJUSTMENTS
AVG.
APPLICATION METHOD (AIRLESS,
CONVENTIONAL SPRAY, ROLLED)
AVERAGE DFT
13 (Rev-0)
4.2 Tank and Void Assessment form.
14 (Rev-0)
15 (Rev-0)
11000_NET_0523_87WPB
WORK ITEM 1: Hull Plating (Side Scan), Ultrasonic Testing
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to perform thickness measurements of the underwater (u/w) body and freeboard by ultrasonic side scan method.
1.2 Government-furnished property.
None.
2. REFERENCES
COAST GUARD DRAWINGS
Coast Guard Drawing 87 WPB 085-013, Rev B, Docking Plan
Coast Guard Drawing 87 WPB 111-001, Rev H, Shell Expansion
Coast Guard Drawing 87 WPB 111-050, Rev A, Updates to DWG 87-WPB-111-001 Exhaust
Port Insert Plate Installation and Details
COAST GUARD PUBLICATIONS
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General Requirements
OTHER REFERENCES
American Society for Nondestructive Testing (ASNT) SNT-TC-1A, 2016, Recommended
Practice for Personal Qualification and Certification in Nondestructive Testing
3. REQUIREMENTS
3.1 General.
3.1.1 CIR.
None.
3.1.2 Tech Rep.
Not applicable.
16 (Rev-0)
3.1.3 Protective measures. The Contractor must furnish and install all protective measures in accordance with SFLC Std Spec 0000, paragraph 3.3.3 (Vessel…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .