This is a detailed specification document for dockside repairs to the USCGC SPAR (WLB-206), a 225-foot Coast Guard buoy tender, covering a performance period from July 7 through September 14, 2026. The specification encompasses 38 distinct work items totaling comprehensive maintenance and modernization activities across multiple vessel systems and components.
The work items span fire prevention compliance, deck preservation, tank cleaning and inspection (fuel, potable water, grey water, and sewage systems), ventilation duct cleaning, hydraulic and mechanical equipment servicing, hull fitting inspections, structural repairs, and system modernizations. Key capital replacements include LED flood light installation (11 units at $619 each), sewage system piping renewal using 90/10 CuNi material, main reduction gear filter assembly replacement ($21,199.80), interior deck covering renewal across multiple spaces, watertight hatch renewal ($5,000), and installation of two Cla-Val pressure relief valves ($19,360 each) in the firemain system. The specification requires the contractor to furnish extensive government-furnished equipment including repair kits, hydraulic components, wire rope assemblies, and mechanical parts valued at over $160,000 collectively. Critical inspection items must be completed within the first 25% of the contract period and include cargo hatch, hydraulic chain stoppers, crossdeck winches, and davit systems. The work demands compliance with Surface Forces Logistics Center Standard Specifications for welding, preservation, auxiliary systems, ventilation cleaning, and temporary hull accesses, along with adherence to occupational safety standards for shipyard employment and comprehensive environmental protection requirements including spill prevention and hazardous waste management.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| SPAR (WLB 225B) DS FQ4 BGW 26R1.pdf | ||
| AMEND 00001 CGC SPAR.doc | DOC document | |
| ATTACHMENT 1 SPAR Pricing Schedule.xlsx | XLSX spreadsheet | |
| SPAR DS FY26 3MAR26.docx | DOCX document | |
| ATTACHMENT 4 Request For Clarification SPAR.docx | DOCX document | |
| ATTACHMENT 3 Past Performance Information SPAR.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
USCGC SPAR (WLB 206)
SPECIFICATION FOR DOCKSIDE REPAIRS
FY2026
Developed By: Bryan G Wright
(Rev-0, 16 December 2025)
USCGC SPAR (WLB-225B) DOCKSIDE AVAILABILITY FY2026
ii (Rev-0)
TABLE OF CONTENTS
TABLE OF CONTENTS ............................................................................................................................. ii Revisions Record ......................................................................................................................................... iii Consolidated List of References ................................................................................................................... iv Consolidated List of Government-furnished Property .............................................................................. viii Consolidated List of Critical Inspection Items ............................................................................................. xi Principal Characteristics ............................................................................................................................. xii General Requirements WORK ITEM 1: Fire Prevention Requirements - Dockside WORK ITEM 2: Buoy Cargo Hold Deck, Preserve 100% WORK ITEM 3: Tanks, MP Fuel Stowage and Overflow, Clean and Inspect WORK ITEM 4: Tanks, MP Fuel Service, Clean and Inspect WORK ITEM 5: Tanks, Potable Water, Clean and Inspect WORK ITEM 6: Hydraulically Operated Cargo Hatch, Inspect and Service WORK ITEM 7: Main Diesel Engine, MDE, Exhaust Piping, Commercial Clean WORK ITEM 8: Ship Service Diesel Generator, SSDG, Exhaust Piping, Commercial Clean WORK ITEM 9: Vent Ducts, Engine And Motor Room, All, Commercial Cleaning WORK ITEM 10: Vent Ducts, Galley and Pantry Room, All, Commercial Cleaning WORK ITEM 11: Vent Ducts, Laundry Exhaust, Commercial Cleaning WORK ITEM 12: Vent Ducts, All Other, Commercial Cleaning WORK ITEM 13: Potable Water Pneumatic Tanks, Clean and Inspect WORK ITEM 14: Hull Fittings (Weight Handling Rigging Hardware), Inspect and Test WORK ITEM 15: Hydraulic Chain Stoppers, Inspect And Service WORK ITEM 16: Crossdeck Winches, Inspect and Service WORK ITEM 17: Hydraulic Inhaul Winch, Inspect And Service WORK ITEM 18: Mechanical Chain Stoppers, Inspect and Service WORK ITEM 19: Warping Capstan, Inspect and Service WORK ITEM 20: Hull Fittings (Mooring and Towing), Inspect and Test WORK ITEM 21: Single Point Davit, Inspect and Service WORK ITEM 22: Commissary Hoist, Inspect and Service WORK ITEM 23: Buoy Crane, Appleton EB600-60-40, Inspect and Service WORK ITEM 24: Grey Water Holding Tanks, Clean and Inspect WORK ITEM 25: Sewage Holding Tanks, Clean and Inspect WORK ITEM 26: Grey Water Piping, Clean and Flush WORK ITEM 27: Sewage Piping, Clean and Flush WORK ITEM 28: Tanks (Sewage Holding), Preserve, 100 percent WORK ITEM 29: Non-Buoy Weather Deck LED Flood Lights, Replace WORK ITEM 30: Deck Covering, Interior, Wet and Dry, Renew WORK ITEM 31: Magazine Passageway Entry Flush Hatch, Renew WORK ITEM 32: Deck Covering (Electrical Matting), Renew WORK ITEM 33: Sewage System Piping, Renew WORK ITEM 34: SORS Cargo Rail Remove - TCTO WORK ITEM 35: Compressed Air Receivers and System Valves, All, Clean, Inspect, Hydro and Lift . 147 WORK ITEM 36: Main Reduction Gear Filter Assembly, Replace WORK ITEM 37: Hot Water Accumulator Tanks, Clean and Inspect WORK ITEM 38: TCTO (TM2100.0) Firemain CLA-VAL PRV, Install iii (Rev-0)
REVISIONS RECORD
This page is used to record specification revisions, which may have occurred subsequent to a Revision 0 (Rev-0) package. Information listed is intended to provide contractors and field unit personnel a means to ensure all the current specification revision pages are present when reviewing or utilizing this specification package.
DATE REV# WORK
ITEM#
CHANGES MADE
NOTE : All work item and paragraph numbers listed above for a given revision correspond to same numbers in the previous revision. This revised specification is self-contained with all of the above listed changes incorporated.
iv (Rev-0)
CONSOLIDATED LIST OF REFERENCES
The below-listed documents form a part of this specification to the extent specified herein. Approval/publication dates or revision dates/numbers are also identified, to ensure that same document versions are used at the time of specification writing and during contract execution.
All Coast guard drawings, sentat publications, and standard specifications will be provided to contractors by the Coast Guard at an appropriate time, or upon request, free of charge. Other Government documents may be accessed – free of charge – from links located on the SFLC website. Commercial sites provide access to their respective documents.
COAST GUARD DRAWINGS
Coast Guard Drawing 225 WLB 259-005, Rev C, Combustion Intake & Exhaust A&D Hull Block 940
Coast Guard Drawing 225 WLB 801-020, Rev B, Tank CAPACITY - 95% Curves
Coast Guard Drawing 225B WLB 541-007, Rev D; Incinerator Fuel Oil Service Tank
Coast Guard Drawing 225B WLB 573-001, Rev E, Buoy Handling System Arrangement
Coast Guard Drawing 225B WLB 259-001, Rev D, Combustion Intake & Exhaust Diagram
Coast Guard Drawing 225B WLB 259-005, Rev C, Combustion Intake & Exhaust A&D Hull Block 940
Coast Guard Drawing 225B WLB 259-006, Rev D, Combustion Intake & Exhaust A&D Hull Blocks 970 & 975
Coast Guard Drawing 225B WLB 512-001, Rev K, HVAC Diagram
Coast Guard Drawing 225B WLB 512-007, Rev B, HVAC A&D, Fr 66-92, Innerbttm & 1st Platform
Coast Guard Drawing 225B WLB 528-001, Rev G, Plumbing and Interior Deck Drains
Coast Guard Drawing 225B WLB 528-002, Rev D, Weather Deck Drains Diagram
Coast Guard Drawing 225B WLB 532-002, Rev D, Potable Water Sys Dia
Coast Guard Drawing 225B WLB 541-001, Rev G; Fuel Oil System Diagram
Coast Guard Drawing 225B WLB 549-001, Rev C, Onboard Lubrication Requirements
Coast Guard Drawing 225B WLB 556-001, Rev F, Hydraulic System Diagram
Coast Guard Drawing 225B WLB 556-005, Rev D, Aft Hydraulic System A/D, Fr 66 Aft, Block 950, 970
Coast Guard Drawing 225B WLB 573-002, Rev -, Weight Handling System Arrangement
Coast Guard Drawing 225B WLB 573-009, Rev E, Bi-Dir Ch Stopper With Retractable Roller Stopper
Coast Guard Drawing 225B WLB 573-012, Rev -, Rising Sheave Chain Stopper Ripout Incidental to Upgrade
Coast Guard Drawing 225B WLB 573-013, Rev B, Rising Sheave Chain Stopper Mechanical Mods Incidental to Upgrade
Coast Guard Drawing 225B WLB 573-014, Rev -, Rising Sheave Chain Stopper Hydraulic Mods Incidental to Upgrade
Coast Guard Drawing 225B WLB 573-11, Rev G, ATON Tie Downs
Coast Guard Drawing 225B WLB 582-001, Rev -, Mooring and Towing A & D
Coast Guard Drawing 225B WLB 593-001, Rev E, Sewage and Waste Water System
Coast Guard Drawing 225B WLB 593-009, Rev B, Sewage Holding Tank
Coast Guard Drawing 225B WLB 601-001, Rev M; General Arrangement Inboard and Outboard Profiles v (Rev-0)
Coast Guard Drawing 225B WLB 601-002, Rev L, Booklet off General Drawings
Coast Guard Drawing 225B WLB 672-001, Rev C, Storerooms, Cargo Stowage and Ship Store Arrangement and Details
Coast Guard Drawing 225B WLB 801-005, Rev A Tank CAPACITY - 95% Curves
Coast Guard Drawing 225B WLB 901-003, Rev A, Hull Block 901 Block Assembly
Coast Guard Drawing 225B-WLB 556-1, Rev B, Hydraulic System Diagram
Coast Guard Drawing 225B-WLB 573-1, Rev -, Buoy Handling System Arrangement
Coast Guard Drawing 225B-WLB 573-2, Rev -, Weight Handling System Arrangement
Coast Guard Drawing 225B-WLB 111-001, Rev A, Shell Expansion
Coast Guard Drawing 225B-WLB 801-013, Rev B, Midship Section & Typical Sections
Coast Guard Drawing 225B-WLB 801-015, Rev B, Scantling, Decks, & Platforms
Coast Guard Drawing 225B-WLB 801-016, Rev -, Scantlings, Watertight Bulkheads
Coast Guard Drawing 225B-WLB_330_002, Rev L, Lighting System Forward of FR. 30 Hill Block 910/901
Coast Guard Drawing 225B-WLB_330_007, Rev P, Lighting System 02 Level & Above Hull Block 960B/975 & 970 Partial
Coast Guard Drawing 225-WLB_330_002, Rev K, Lighting System Forward of FR. 30 Hill Block 910/901
Coast Guard Drawing 225-WLB_330_007, Rev V, Lighting System 02 Level & Above Hull Block 960B/975 & 970 Partial
Coast Guard Drawing 225B WLB 521-001, Rev F, Firemain System Diagram
Coast Guard Drawing 225B WLB 521-003, Rev -, Firemain CLA-VAL PRV Installation
Coast Guard Drawing 225B WLB 551-001, Rev G, Compressed Air System Diagram
Coast Guard Drawing 225B WLB 532-002, Rev D, Potable Water Sys Dia
Coast Guard Drawing 225-WLB-597-020, Rev B, SORS Hold Stowage and Rail System
Coast Guard Drawing 225B-WLB-597-051, Rev A, SORS Hold Stowage and Handling Fittings
Coast Guard Drawing FL 2605-031, Rev D, Mechanical Chain Stopper, 1-7/8" Buoy Chain
Coast Guard Drawing FL 2605-034, Rev D, Mechanical Chain Stopper Repair Kit: 1-7/8", 1-5/8" & 1- 1/4"
Coast Guard Drawing FL 7101-573, Rev L, Buoy Chain Winch Assy Model CW1
Coast Guard Drawing FL-1702-11, Rev -, Inspection of Sheaves
Coast Guard Fleet Drawing FL-2605-29, Rev H, Chain Stopper System – Rising Sheave Assembly
NAVSEA Drawing 167-7379842, Rev A, Procedure & Welding Sequence for Non-Ballistic, Watertight & Airtight Quick Acting or Individually Dogged Personnel Doors
COAST GUARD PUBLICATIONS
Coast Guard Commandant Instruction (COMDTINST) M10360.3, Jun 2006, Coatings and Colors Manual
Coast Guard Technical Publication (TP) 10512, Section 573-A, July 2018, Buoy Handling Crane – Model
EB600-60-40
Coast Guard Technical Publication (TP) 11101, SWBS 583, Section A (SWBS 583A), Davit, Single Point Slewing Arm Model - RAD30 - 15.5 (BMD-710)
Coast Guard Technical Publication (TP) 3498, Section A, Jul 2015, Buoy Chain Winch
Coast Guard Technical Publication (TP) 3558, Apr 2008, Manufacturer’s Instruction Book-SWBS Group(s) 573, Section B, Cross Deck Winch – Model BMD-471 vi (Rev-0)
Coast Guard Technical Publication (TP) 3559, Section 582B, Apr 2009, Aft Capstan, 21” - Model BMD-
Coast Guard Technical Publication (TP) 3562, Sep 2013, SWBS 589, Section C, Dumbwaiter, Model –F-
WK-806
Coast Guard Technical Publication (TP) 3717, Jun 2003, Hydraulic Cargo Hatch
Coast Guard Technical Publication (TP) 3749, 26-APR-05, 1-7/8 Inch ATON Mechanical Chain Stopper
Coast Guard Technical Publication (TP) 3750, SWBS 573-A, Dec 2012, Rising Sheave Chain Stopper
Coast Guard Technical Publication (TP) 3796, Section A, Aug 2006, Galley Hood – Model NBDL-60 (13’-4”)
Coast Guard Technical Publication (TP) IB-H2-0012-V0, 17-SEP-25, Manufacturer's Instruction Book- SWBS Group(s) 241-242
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General Requirements
Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2022, Welding and Allied Processes
Surface Forces Logistics Center Standard Specification 3020 (SFLC Std Spec 3020), 2022, Overhaul AC Electrical Motors
Surface Forces Logistics Center Standard Specification 3041 (SFLC Std Spec 3041), 2022, Shipboard Electrical Cable Test
Surface Forces Logistics Center Standard Specification 3042 (SFLC Std Spec 3042), 2022, Shipboard Electrical Cable Removal, Relocation, Splice, Repair, and Installation
Surface Forces Logistics Center Standard Specification 5000 (SFLC Std Spec 5000), 2022, Auxiliary Machine Systems
Surface Forces Logistics Center Standard Specification 5100 (SFLC Std Spec 5100), 2022, Clean Shipboard Ventilation Systems
Surface Forces Logistics Center Standard Specification 5550 (SFLC Std Spec 5550), 2022, Fire Prevention and Response
Surface Forces Logistics Center Standard Specification 5550 (SFLC Std Spec 5550), Latest Version, Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2022, Requirements for Preservation of Ship Structures
Surface Forces Logistics Center Standard Specification 6341 (SFLC Std Spec 6341), 2022, Install Interior Deck Covering Systems
Surface Forces Logistics Center Standard Specification 8636 (SFLC Std Spec 8636), 2022, Temporary Hull Accesses
OTHER REFERENCES
American National Standards Institute/American Water Works Association (ANSI/AWWA) C652, 2019, Disinfection of Water-Storage Facilities
American National Standards Institute/NSF International (ANSI/NSF) 61, 2015, Drinking Water System Components - Health Effects
ANSI/AWWA reference if work does not deal with potable water piping.
ASTM F683, if piping insulation renewal is not applicable.
ASTM F992, if valve label is not applicable.
ASTM International (ASTM) D1330, 2015, Standard Specification for Rubber Sheet Gaskets vii (Rev-0)
ASTM International (ASTM) D5363, 2024; Standard Specification for Anaerobic Single-Component Adhesives (An)
ASTM International (ASTM) F683, 2014, Standard Practice for Selection and Application of Thermal Insulation for Piping and Machinery
ASTM International (ASTM) F992, 2017, Standard Specification for Valve Label Plates
Code of Federal Regulations (CFR) Title 29, Part 1915, 2022, Occupational Safety and Health Standards for Shipyard Employment
Commercial Item Description (CID) A-A-59316, 2016, Abrasive Materials; for Blasting
Federal Specification (Fed Spec) DDD-C-95, Mar 1972, Carpets and Rugs, Wool, Nylon, Acrylic, Modacrylic
Federal Specification (Fed Spec) QQ-N-281, Oct 1985, Nickel-Copper Alloy Bar, Rod, Plate, Sheet, Strip, Wire, Forgings, and Structural and Special Shaped Sections
Manufacturers Standardization Society of the Valve and Fittings Industry (MSS), SP-58, 2018, Pipe Hangers and Supports – Materials, Design, Manufacture, Selection, Application and Installation
MIL PRF-16173E INT AMD 1, Sep 2006, Corrosion Prevention Compound, Solvent Cut Back, Cold Application
Military Standard MIL-S-19622/17D, Dec 1992, Stuffing Tube, Nylon, and Packing Assemblies, General Specification for
Military Standard MIL-STD-2003/3A (SH), Sep 2009, Electrical Plant Installation Standard Methods for Surface Ships and Submarines
MIL-PRF-24176 , Oct 2004, Cement, Epoxy, Metal Repair And Hull Smoothing (Metric)
MIL-S-45180, 1998; Sealing Compound, Gasket, Hydrocarbon Fluid and Water Resistant
NAVSEA Technical Publication T9074-AD-GIB-010/1688, (TP 1688), July 2012, Requirements for Fabrication, Welding, and Inspection of Submarine Structure
Society of Automotive Engineers (SAE) Aerospace Material Specification (AMS) C-6183B, 2019, Cork and Rubber Composition Sheet; for Aromatic Fuel and Oil Resistant Gaskets
The Society for Protective Coatings (SSPC) Surface Preparation Standard No. 11 (SSPC-SP 11), 2013, Power-Tool Cleaning to Bare Metal
The Society for Protective Coatings (SSPC)/NACE International (NACE) 2007, Joint Surface Preparation Standard SSPC-SP 10/NACE No. 2, Near-White Metal Blast Cleaning
The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation Standard SSPC-SP 10/NACE No.2, 2007, Near-White Blast Cleaning viii (Rev-0)
CONSOLIDATED LIST OF GOVERNMENT-FURNISHED PROPERTY
The following is a list of property, which the Government will furnish. This list supersedes any other material obligations indicated or implied by referenced drawings.
WORK
ITEM
MTI ITEM DESCRIPTION NSN/PN QTY ESTIMATED
COST
($/UNIT)
15 N Repair Kit, HYD
Chain Stopper Rising Sheave (for Para. 3.2, Tasks #2 and #3)
NSN: 2040-01-483-3947 2 ea. 2,631.46
15 N Cylinder, Actuating Linear
NSN: 3040-01-483-3373 2 ea. 1,777.71
16 N Hand Pump SS NSN: 4320-01-517-1444 1 ea 1,499.66 16 N Pressure Gauge -
Model BMD-471 NSN: 6685-01-437-2519 4 ea 43.79
16 N Wire Rope Assembly NSN: 4010-01-643-2077 4 ea 900.00 16 N Hydraulic Brake
Repair Kit - Model
BMD-471
NSN: 3950-01-526-9090 4 ea. 913.00
16 N Counterbalance Valve
- Model BMD-471
NSN: 4810-01-353-0586 4 ea. 150.00
16 N Shuttle Valve - Model
BMD-471
NSN: 4820-01-317-2748 4 ea. 35.00
16 N Hydraulic Motor Seal Kit - Model BMD-471
NSN: 5330-01-475-4566 8 ea. 84.00
16 N Clutch Shoe - Model
BMD-471
NSN: 4910-01-475-4125 4 ea. 56.90
16 N Drum Bushing - Model
BMD-471
NSN: 3950-01-631-0884 8 ea. 272.00
16 N Shaft Bushing - Model
BMD-471
NSN: 3950-01-631-0771 4 ea. 298.00
16 N Gearbox Seal Kit (For Winch Gearbox
Assemblies) - Model
BMD-471
NSN: 5330-01-687-3092
PN: YMD-8194-R
4 ea. 70.00
16 N Control Station Repair Parts. Kit
NSN: 6110-01-644-9898 4 ea. 438.00
16 N Flag Block Pivot Bearing
NSN: 3110-01-644-9905 4 ea. 675.00
16 N Flag Block Bearing Cup, Sheave
NSN: 3110-01-644-9670 4 ea. 231.00
16 N Flag Block Bearing Cone, Sheave
NSN: 3110-01-013-4036 4 ea. 182.00
16 N Seal NSN: 5330-01-287-2826 4 ea. 104.00 16 N Manifold Repair Kit NSN: 4820-01-680-9495
PN: YMD-8192-R
4 ea. 551.00
17 N Roller bearing Unit NSN: 3130-01-504-4363 2 ea. 4,012.00 17 N Grease seal NSN: 5330-01-462-5544 4 ea. 79.25 ix (Rev-0)
17 N Level wind pivot bushing
NSN: 3120-01-621-2293 1 ea. 1,139.00
17 N Level wind thrust bearing
NSN: 3120-01-621-2300 2 ea. 483.30
17 N Rexroth DCV NSN: 4810-01-507-0037 1 ea. 208.29 17 N Rexroth Sandwich
Flow Control NSN: 4810-01-505-9289 1 ea. 250.00
17 N Sun Sandwich Relief Valves
NSN: 4820-01-439-2451 2 ea. 900.00
17 Y Level Wind Hydraulic Cylinder
NSN: 3040-01-441-3721 1 ea. 7,423.00
17 N 3:1 Pilot Ratio, Vented Counterbalance Valve
Assembly
NSN: 4820-01-563-5841 1 ea 98.70
17 N Fully Adjustable Needle Valve
NSN: 4820-01-416-0579 1 ea 48.75
17 N Wire Rope Assembly NSN: 4010-01-646-6972 1 ea. 500.00 17 Y **Hydraulic Motor NSN: 4320-01-445-2248 1 ea 23,998 17 N **Pump, Hydraulic
Ram, Hand Driven NSN: 4320-01-286-4065 1 ea. 419.77
17 N Cylinder Pin NSN: 5315-01-515-9847 1 ea 500.00 17 N Cylinder Pin NSN: 5315-01-515-9912 1 ea 520.00 20 N Hardware Kit, Pins NSN: 2030-01-485-7209 2 ea. 528.47 20 N Hardware Kit, Mechanical NSN: 2030-01-485-7215 2 ea. 538.91
21 N Swing Brake Seal Kit NSN: 5330-01-390-3514 PN:
90-016-2011
2 ea 68.45
21 N Swing Brake Disc Kit NSN: 3010-01-464-1040 PN:
90-016-2131
2 ea 187.20
21 N Swing Holding Valve NSN: 4820-01-466-4918 PN:
CBEA-LHV-YHL (Sun
Hydraulics)
1 ea 251.50
21 N Wire Rope Assembly NSN: 4010-01-620-9604 PN:
JWCG062100PL
1 ea 660.00
23 N Main Fall Wire Rope NSN: 4010-01-486-0047 PN:
JWCG13001919PL
1 ea. 2,642.00
23 N Aux Fall Wire Rope NSN: 4010-01-594-2228 PN:
JWCG75200637PL
1 ea. 805.32
29 N Floodlight, LED*** NSN: 6210-01-661-5675 PN:
STL-HI-45-UNIV-10CG
11 ea. 619.00
31 N 30 in. x 30 in. Quick- Acting Watertight Hatch, Steel, (Raised 12 in coaming, 18in.
QAWTS (hinge fwd)
NA 1 ea. 5,000.00
36 N WLB MRG Filter Assembly
NSN: 4330-01-F21-6384 1 ea. 21,199.80
N
4” Cla-Val Model 50- 20 Pressure Relief
NSN:4820-01-722-8444 2 ea. $19,360.00 x (Rev-0)
Valve, Globe Pattern, CL150 NAB Bodied / Monel Internal Trim / 316 SST Pilot Equipped with KO-1 Anti-Cavitation Trim, CK2 Isolation Valves
*Government-loaned property, which shall be returned to the vessel upon completion of the availability.
**New or refurbished equipment that the Government may provide for installation in place of existing equipment.
***Government-furnished property, which is to be supplied by either the vessel or the C5I Service Center xi (Rev-0)
CONSOLIDATED LIST OF CRITICAL INSPECTION ITEMS
The following is a list of work items, which contain Critical Inspection reports, which the Contractor must complete within the first 25% of the availability contract period (see SFLC Std Spec 0000, paragraph 3.2.6.5 (Inspection report particulars)):
Work Item
Title
6 Hydraulically Operated Cargo Hatch, Inspect and Service
15 Hydraulic Chain Stoppers, Inspect and Service
16 Crossdeck Winches, Inspect and Service
17 Hydraulic Inhaul Winch, Inspect and Service
19 Warping Capstan, Inspect and Service
21 Single Point Davit, Inspect and Service
22 Buoy Crane, Appleton EB600-60-40, Inspect and Service
23 System Piping, Renew xii (Rev-0)
PRINCIPAL CHARACTERISTICS
225' WLB (B-CLASS)
PHYSICAL
Length overall 225' 0" Length between perpendiculars 206' 0" Maximum beam 46' Designed draft 13' 0" Full load displacement 1905.6 Long Tons SW Light ship displacement 1500.7 Long Tons SW Minimum operating displacement 1869.2 Long Tons SW Mast height (above 12' waterline) 67' 5" Anchor Two 4000 lb standard Navy stockless anchors, 8 shots each, port and starboard, 1-3/8 die lock chain
HULL
Bilge keels (port & starboard) Frames 42-79 Frame spacing FR 0 to 12 21" FR 12 to 30 22" FR 30 to 102 24"
MACHINERY
Main propulsion Diesel Reduction Diesel engines Two Caterpillar 3608, TA, 3100 BHP each @ 900 RPM Number of propellers 1 Number of blades 4 Diameter 10' Pitch Controllable
RPM 254
Ship's service diesel generators Two Caterpillar 3508 TA, 450 KW Emergency diesel generator One Caterpillar 3406 DITA, 280 KW Shore tie Two 450 VAC, 400 Amp, 3-wire Shaft bearing, forward Cooper Bearing 01-BCP-1400-EX-TL Shaft bearing, aft Water Lubricated Cutless Bearing
TANK CAPACITIES
Diesel oil 76,498 gal.
Fresh water capacity 8056 gal.
Hydraulic oil capacity 2785 gal.
Lube oil storage 764 gal.
Grey water tank 2700 gal.
Sewage holding tank 1700 gal.
1 (Rev-0)
00000_0725_FLT
REC_00000_FLT_Commercial Project @ CG Facility (0121)
General Requirements
1. SCOPE
1.1 Intent. This standard specification invokes general requirements for conducting vessel repairs performed by commercial contractors at a Coast Guard facility for Coast Guard vessels.
1.2 Term interchangeability. The terms 'Contractor', 'CG Yard', 'NAVSTA EVERETT', 'shipyard', 'Base', and 'Coast Guard Industrial' are used interchangeably in this specification. Where the primary service provider is Coast Guard personnel, references to contractor and other noted descriptors within this specification or within drawings, publications, SFLC Standard Specifications or other commercial and military references are deemed the same as prime service provider.
2. REFERENCES
COAST GUARD DRAWINGS
None
COAST GUARD PUBLICATIONS
Coast Guard Commandant Instruction (COMDTINST) M10360.3 (series), Coatings and Color Manual
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), Latest Version, General Requirements
Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), Latest Version, Welding and Allied Processes
Surface Forces Logistics Center Standard Specification 5550 (SFLC Std Spec 5550), Latest Version, Fire Prevention and Response
Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), Latest Version, Requirements for Preservation of Ship Structures
OTHER REFERENCES
Code of Federal Regulations (CFR) Title 29, Part 1915, Occupational Safety and Health Standards for Shipyard Employment
NAVSEA Technical Publication T9074-AD-GIB-010/1688, (TP 1688), July 2012, Requirements for Fabrication, Welding, and Inspection of Submarine Structure
2 (Rev-0)
3. REQUIREMENTS
3.1 General. The Contractor must conform to all requirements specified in SFLC Std Spec 0000 and in this item, as applicable, during the performance of this availability. The requirements in this WI applies to all work under the scope of this contract, whether explicitly stated in all following work items or not, and to all other work subsequently authorized by changes, modifications, or extensions to the contract.
3.1.1 The Contractor must conform to all requirements specified in SFLC Std Spec 5550 and in the Fire Protection and Response work item, as applicable, during the performance of this availability.
3.1.1.1 Fire Safety Plan submission. The Contractor must submit a copy of the CFR 1915, Subpart P, Fire Safety Plan with the Contractor’s bid when work will be conducted in a Contractor–owned facility. Include any MOA(s) with local firefighting facilities.
3.1.1.2 Fire Plan submission. The Contractor must submit a copy of the developed availability specific fire plan as requested in the Fire Protection and Response work item, with the Contractor’s bid.
NOTE
NAVSEA drawings listed will be available FOR INSPECTION ONLY from the Coast Guard Port Engineer post-award. SFLC will not redistribute NAVSEA documents.
Contractors can apply to NAVSEA headquarters directly for copies.
3.2 Contractor-provided fire extinguishers. The Contractor must provide portable fire extinguishers.
3.3 Preservation requirements. The Contractor must accomplish all preservation tasks, including touch-ups, in accordance with SFLC Std Spec 6310.
3.3.1 Brand name approval. Ensure that all contractor-furnished coatings are in accordance with SFLC Std Spec 6310, Appendix C (Authorized Coatings for Use on Cutters and Boats).
3.3.2 Coating colors and system color schemes. The Contractor must obtain a written KO authorization to deviate from any coatings required in SFLC Std Spec 6310 Appendix C before work.
3.3.3 In-process quality control measures. The Contractor must abide by all the safety, preservation, and quality control requirements specified in SFLC Std Spec 0000, paragraph 3.2.4.2 (In-process QC measures for “critical-coated surfaces”).
3.3.3.1 Quality control requirements. The Contractor must abide by the following when performing preservation related inspections. The following measurements must be randomly spaced throughout for the purposes of providing a representation of the entire prepared or coated surface.
3.3.3.1.1 Surface profile measurements. One surface profile measurement must be taken for every 200 square feet for the first 1000 square feet; for each additional 500 square feet or less, one profile measurement must be taken.
Profile measurements must be taken in accordance with SFLC Std Spec 6310, paragraph 3.1.8.3 (Surface profile measurements). A “measurement” for surface profile is defined as follows:
ASTM D4417, Method B: One profile measurement is the average (mean) of 10 individual readings.
ASTM D4417, Method C: One profile measurement is the average (mean) of 2 individual readings.
3.3.3.1.2 Soluble salt conductivity measurements. 5 conductivity measurements must be taken every 1000 square feet. For submerged (immersed) applications conductivity measurements must not exceed 30 microsiemens/cm.
3 (Rev-0)
For non-submerged (non-immersed) applications conductivity measurements must not exceed 70 microsiemens/cm. If a conductivity check fails, clean the surface in accordance with SFLC Std Spec 6310, paragraph 3.1.8.5 (Soluble salt removal).
3.3.3.1.3 Coating thickness measurements. Three area measurements must be taken for the first 1000 square feet;
for each additional 1000 square feet, perform an additional area measurement. A “measurement” for coating thickness is defined as follows:
SSPC-PA 2 defines an area measurement as 5 separate spot measurements randomly spaced throughout a 100 square foot area.
SSPC-PA 2 defines a spot measurement as 3 gage readings and each new gage reading the probe must be moved to a new location within a 1.5-inch diameter circle defining the spot.
3.4 Welding and brazing requirements. The Contractor must perform all welding and allied processes, and NDE in accordance with SFLC Std Spec 0740.
3.5 Environmental protection requirements. The Contractor must adhere to the following environmental protection requirements in accordance with the SFLC Stand Spec 0000:
3.5.1 USCG facilities. The Contractor must provide and maintain environmental protection as defined in SFLC Std Spec 0000 Appendix B, Requirements for Environmental Protection at USCG Facilities, during the performance of this availability. Contractor must plan for and provide environmental protective measures to control pollution that develops during normal practice, as well as plan for and provide environmental protective measures required to correct conditions that develop during the project. Contractor must comply with applicable Federal, state, and local laws, codes, ordinances, and regulations in their entirety. Any reference to a specific portion of a Federal, state, or local law, code, ordinance, or regulation in this or any other item must not be construed to mean that relief is provided from any other sections of the law, code, ordinance, or regulation.
3.5.1.1 USCG Generator status. The activity Generator Status for the Coast Guard Facility is Small Quantity, conditionally excempt.
3.5.1.2 Plans and permits. The CG Facility has unit specific permits including the following:
Spill Prevention Control and Countermeasures (SPCC) Plan: Unit has a SPCC Plan which requires certain unit-specific procedures be followed for the storage, inspection, and transfer of petroleum products in containers 55 gallons or greater.
National Pollutant Discharge Elimination System (NPDES) Storm Water (SW) Permit: Unit has an NPDES SW permit which requires unit-specific procedures be followed for the storage and inspection of equipment and materials which may contribute contaminants to storm water discharges.
Air Emission Permit: Unit has an Air Emission Permit which requires unit-specific procedures be followed for the emissions of VOCs and hazardous air pollutants.
3.5.2 Test and procedures. The Contractor is required to promptly conduct tests and procedures for the purpose of assessing whether operations are in compliance with applicable Environmental Laws. Analytical work must be done by qualified laboratories; and where required by law, the laboratories must be certified.
3.5.3 Regulatory notifications. The Contractor is responsible for all regulatory notification requirements in accordance with Federal, State and local regulations. In cases where the Coast Guard must also provide public notification, such as storm water permitting, the Contractor must coordinate with the Contracting Officer or COR, and if work is being performed at a USCG Facility, the local Facility Engineer or Engineering Officer. The Contractor must submit copies of all regulatory notifications to the Contracting Officer and the local Facility
4 (Rev-0)
Engineer or Engineering Officer prior to commencement of work activities. Regulatory notifications must be provided for including but not limited to demolition, renovation, National Pollutant Discharge Elimination System (NPDES) defined site work, and remediation of controlled substances such as asbestos, hazardous waste, and lead paint.
3.5.4 Environmental manager. The Contractor must appoint in writing an Environmental Manager for the project, who is responsible for coordinating Contractor compliance with Federal, State, local, and station environmental requirements. The Environmental Manager must ensure compliance with Hazardous Waste Program requirements, including hazardous waste handling, storage, manifesting, and disposal; implement the Contractors’ Environmental Management Plan; ensure that all environmental permits are obtained, maintained, and closed out;
ensure compliance with Storm Water Program Management requirements; ensure compliance with Hazardous Materials including storage, handling, and reporting requirements; as well as coordinate any remediation of regulated substances such as lead, asbestos, and polychlorinated biphenyl (PCB). This may be a collateral position; however the individual must be trained to accomplish the following duties; ensure waste segregation and storage compatibility requirements are met; inspect and manage Satellite Accumulation areas; ensure only authorized personnel add wastes to containers; ensure all Contractor personnel are trained in 40 CFR requirements and individual position requirements; coordinate removal of waste containers; and maintain the Environmental Records binder and required documentation, including environmental permits compliance and close-out.
3.5.5 HW disposal. Contractor must comply with SFLC Std Spec 0000 Appendix B, Requirements For Environmental Protection At USCG Facilities for HW disposal, and ensure that waste removals are conducted during normal business hours (0800-1600) on Monday through Friday (excluding holidays).
3.5.6 Additional Requirements. The Contractor must be aware of the following:
3.5.6.1 No Contractor or Subcontractor must have the authority to sign a Hazardous Waste Manifest using the Coast Guard facility’s EPA Generator ID Number or remove contract generated hazardous waste from the Coast Guard facility without COR or KO-approval.
3.5.6.2 Local environmental regulations at the Government facilities may be more stringent. As with all environmental regulations, the Contractor must prepare for and comply with local and state regulations.
3.5.6.3 Coast Guard facilities do not maintain Facilities Response Plans (FRPs) per 33 CFR 154. Contractor must furnish the FRP when required for over-the-water liquids transfers to and from vessels, and is required for oil/fuel transfers to/from vessels for 250 barrels (10,500 gallons) or more.
3.6 Local Policy. The Contractor must refer to site (e.g., Base) Regulations and Instructions for details regarding local policies (e.g., crane services, parking, or facility usage).
3.7 SFLC Standard Specification approved changes. Approved updates to the 2022 SFLC Standard Specifications will appear here.
3.7.1 SFLC Standard Specification 5550: Replace paragraph 3.11.3 to state, “Material supporting imminent work shall be brought on the cutter and stored where the work is being performed. Material that appreciably contributes to fire load shall be removed at the end of each work shift when personnel are not present. Trash, debris, and packaging materials shall be promptly removed from the vessel at the end of each work shift and not allowed to accumulate.” Advance the paragraph numbering of the Fire Prevention and Safety Inspection form to 3.11.4.
5 (Rev-0)
4. NOTES
4.1 QA inspection forms. QA inspection forms (QA-1 thru QA-5), required in SFLC Std Spec 6310 to be completed and submitted during preservation of “critical-coated surfaces”, are provided at the end of this document.
6 (Rev-0)
QA-1 - QUALITY ASSURANCE INSPECTION FORM
(PRESERVATION CHECKLIST)
VESSEL NAME HULL # WORK
ITEM #
WORK ITEM TITLE
LOCATION OF WORK (INCL. FRAME #’S) AREA (SQFT)
CHECKPOINT 1 – COATING SYSTEM COMPLIANCE
Ensure all coatings are in compliance with SFLC Std Spec 6310, Appendix C.
CHECKPOINT 2 - PAINT STORAGE
Ensure all coatings are kept at a temperature of 65 to 85°F at all times, unless otherwise specified by the coating mfg.
CHECKPOINT 3 - AMBIENT CONDITIONS
Ensure surface and surrounding temperatures are each between 50 and 90°F for water-containing coatings, and 35 and 95°F for other coatings, unless otherwise specified by the coating manufacturer(s).
Ensure maximum relative humidity (RH) is as follows, from surface preparations through final curing of topcoat: 50% for tanks, voids, and vent plenum; and 85% for all other areas, unless otherwise specified by manufacturer(s).
Ensure surface temperature is at least 5°F above the dew point, unless otherwise specified by the coating mfg.
CHECKPOINT 4 - PRE-SURFACE PREPARATION
Remove surface contaminants (soluble salts, loose rust, mud, and marine growth) with low pressure fresh water wash down (maximum 5,000 psi). If oil and grease are present, perform solvent cleaning, as per SSPC SP-1.
Verify equipment setup, blast media, and surface preparation methods match designated test coupon.
CHECKPOINT 5 - SURFACE PREPARATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure cleanliness of prepared surface is as per specification (i.e.: SSPC SP-11, SP-10, SP WJ-2…).
Verify surface anchor profile using ASTM D4417-Methods B or C against SFLC Std Spec 6310. Conduct profile readings at a minimum of 5 locations for the first 1000-sqft area, and 2 locations for each succeeding 1000-sqft area.
Measure soluble salt conductivity in accordance with SSPC-Guide 15. Conduct 5 measurements per each 1000-sqft area (max. threshold: 70 microsiemens/cm for non-submerged surfaces, 30 microsiemens/cm for submerged surfaces).
CHECKPOINT 6 - PRIMER COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Verify proper mixing and stand-in (induction) times.
Ensure no paint is applied when the temperature is expected to drop to freezing before the paint has dried.
Ensure surfaces are completely dry, unless otherwise allowed by the coating manufacturer(s).
Verify wet film thickness (WFT) at random, to prevent under or over application. Verify final DFT.
Brush out all runs, sags, drips, and puddles.
Perform visual inspection for holidays and other defects.
CHECKPOINT 7 – STRIPE COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure overcoating window is as per manufacturer’s instructions.
After primer coat (mist coat after inorganic zinc), brush-apply un-thinned coat of same primer paint over edges, weld seams, cut-outs, and areas of complex geometries @ 3-4 mils wet film thickness (WFT).
CHECKPOINT 8 – TOP COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure overcoating window is as per manufacturer’s instructions.
Verify proper mixing and stand-in (induction) times, as applicable.
Verify wet film thickness at random, to prevent under or over application.
Brush out all runs, sags, drips, and puddles.
CHECKPOINT 9 – FINAL INSPECTION
Verify final system dry film thickness. Conduct 5 sets of 3 readings for each of the first 3 100-sqft areas, followed by 5 sets of 3 readings for each succeeding 1000-sqft area.
Ensure that system cure is in accordance with manufacturer's recommendation for intended service.
Ensure potable water tank exhaust ventilation is maintained continuously from and during coating application through final system cure, to exhaust all solvent to the atmosphere and to prevent solvent entrapment.
For immersion coatings (including tank U/W body), record date and time of the following events:
Final coat application: _____/_____; Return to service or removal from environment controls: _____/_____
CHECKPOINT 10 – RECORD KEEPING
Complete, sign, and submit all provided QA Inspection Forms.
NAME OF QP-1/AMPP INSPECTOR SIGNATURE CERT. # DATE / TIME
NAME OF CG REPRESENTATIVE SIGNATURE UNIT DATE/TIME
7 (Rev-0)
QA-2 - QUALITY ASSURANCE INSPECTION FORM
(ENVIRONMENTAL READINGS)
VESSEL NAME HULL #
WORK
Use one sheet for each activity. Record conditions every four hours from before surface preparation to application of final coating system coat.
DATE
TIME
ACTIVITY (SURFACE
PREPARATION, PRIMER
COAT, BARRIER COAT, TOP
COAT, ETC…)
LOCATION (FRAME &
DECK, RELATION TO
EQUIPMENT, ETC.)
TEMPERATURE % REL.
HUMID-
ITY
DEW
PT.
SURFAC
E
AMBIEN
T
ΔT
| DP -
SURFACE |
8 (Rev-0)
QA-3a - QUALITY ASSURANCE INSPECTION FORM
(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-C)
VESSEL NAME HULL # WORK ITEM
LOCATION OF WORK (FRAME REFERENCES) AREA (SQFT)
SURFACE PREPARATION METHOD PROFILE ACHIEVED (MILS)
MIN MAX MEAN
SSPC-SP-10/AMPP No. 2
SSPC-SP WJ-2/AMPP WJ-2
SSPC-SP-3
SSPC-SP-11
SSPC-SP-11 (inaccessible area) Brush-blasting (non-metallic substrate)
ABRASIVE MANUFACTURER: ABRASIVE SIEVE SIZE:
PLACE SURFACE PROFILE REPLICA TAPES IN THE SPACES PROVIDED BELOW, TO SERVE AS
PERMANENT QA RECORD. MAINTAIN A SEPARATE LOG FOR EACH LOCATION. WHEN AN AREA IS
DIVIDED INTO SEPARATE SECTIONS, MAINTAIN A SEPARATE LOG FOR EACH SECTION.
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Reading (mils): Reading (mils): Reading (mils):
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Reading (mils): Reading (mils): Reading (mils):
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Reading (mils): Reading (mils): Reading (mils):
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Reading (mils): Reading (mils): Reading (mils):
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Reading (mils): Reading (mils): Reading (mils):
MEAN MIL READING (IAW ASTM D4417-METHOD C) FOR ABOVE 15 READINGS:
NAME OF QP-1/AMPP INSPECTOR SIGNATURE CERT. # DATE /
TIME
9 (Rev-0)
QA-3b - QUALITY ASSURANCE INSPECTION FORM
(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-B)
VESSEL NAME HULL # WORK ITEM
SURFACE PREPARATION METHOD PROFILE ACHIEVED (MILS)
MIN MAX MEAN
SSPC-SP-10/AMPP No. 2
SSPC-SP WJ-2/AMPP WJ-2
SSPC-SP-3
SSPC-SP-11
SSPC-SP-11 (inaccessible area) Brush-blasting (non-metallic substrate)
ABRASIVE MANUFACTURER: ABRASIVE SIEVE SIZE:
RECORD MEASUREMENTS TAKEN IN THE SPACES PROVIDED BELOW, TO SERVE AS PERMANENT
QA RECORD. MAINTAIN SEPARATE LOG FOR EACH LOCATION. WHEN AN AREA IS DIVIDED INTO
SEPARATE SECTIONS, MAINTAIN A SEPARATE LOG FOR EACH SECTION.
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Mean Mils Reading (IAW ASTM D4417-Method B for above 10 readings (by column):
Mean Reading (mils)
10 (Rev-0)
QA-4 - QUALITY ASSURANCE INSPECTION FORM
(SURFACE SOLUBLE SALT CONDUCTIVITY LOG)
VESSEL NAME HULL # WORK
SOLUBLE SALT CONDUCTIVITY MEASUREMENTS IAW SSPC-GUIDE 15.
DATE TEST LOCATIONS CONDUCTIVITY (MICROSIEMENS/CM)
11 (Rev-0)
QA-5 - QUALITY ASSURANCE DATA FORM
(COATING THICKNESS)
(Use one sheet for each sequence)
VESSEL NAME HULL #
WORK ITEM
COATING MFG PRODUCT NAME
BATC
H #
INDUCTI
ON TIME
COATING SYSTEM
SEQUENCE
(PRIMER/TOUCHUP/3RD
COAT, ETC.)
DRY FILM THICKNESS (DFT) MEASUREMENTS IAW SSPC-PA 2.
SPOT 1 2 3 4 5
AVERAGE
VALUE
*BASE METAL READING
(BMR)
*Required, If Magnetic Pull-Off (Type I/Banana) Gauge Is Used.
LOCATION (FRAME REFERENCE):
SPOT 1 2 3 4 5 OVERALL AVG. DFT ADJUSTMENTS
1 AVG. BMR DEVIATION
3 BEFORE ADJUSTMENTS AFTER ADJUSTMENTS
AVG.
LOCATION (FRAME REFERENCE):
SPOT 1 2 3 4 5 OVERALL AVG. DFT ADJUSTMENTS
1 AVG. BMR DEVIATION
3 BEFORE ADJUSTMENTS AFTER ADJUSTMENTS
AVG.
LOCATION (FRAME REFERENCE):
SPOT 1 2 3 4 5 OVERALL AVG. DFT ADJUSTMENTS
1 AVG. BMR DEVIATION
3 BEFORE ADJUSTMENTS AFTER ADJUSTMENTS
AVG.
APPLICATION METHOD (AIRLESS,
CONVENTIONAL SPRAY, ROLLED)
AVERAGE DFT
12 (Rev-0)
4.2 Tank and Void Assessment form.
13 (Rev-0)
14 (Rev-0)
55500_ACC_0323_IBCT
WORK ITEM 1: Fire Prevention Requirements - Dockside
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to minimize shipboard fire risk and to clarify the Contractors’ role in fire prevention and response.
NOTE
This work item is not separately priced. Factor fire prevention and response costs into bid of affected work items.
1.2 Government-furnished property.
None.
2. REFERENCES
COAST GUARD DRAWINGS
None
COAST GUARD PUBLICATIONS
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General Requirements
Surface Forces Logistics Center Standard Specification 5550 (SFLC Std Spec 5550), 2022, Fire Prevention and Response
OTHER REFERENCES
None
3. REQUIREMENTS
3.1 Fire Plan. The Contractor must develop and implement a written fire plan in accordance SFLC Std Spec 5550. The Contractors Fire Plan must address Fire Protection and Response specifics as required in this Work Item.
3.1.1 The availability’s specific Fire Plan must always address the following:
material condition and fire protection boundary obstruction mitigations inoperable fittings log
15 (Rev-0) fire alarms firefighting equipment disposition
3.1.2 The Fire Plan must also address the following:
fire protection system status communication links temporary services power disconnects fire prevention and safety inspections
3.2 Fire Prevention Responsible Party. The Contractor must appoint a Fire Prevention Responsible Party (FPRP) who acts as the Contractor’s Responsible Person for fire prevention concerns during the entire availability.
3.3 Fire Prevention and Response Conference. The Contractor must participate in the Fire Prevention and Response Conference as required in Std Spec 5550, paragraph 3.12. The participants must address the contents of SFLC Std Spec 5550, paragraph 3.12.1, as applicable.
3.4 Fire Responsibility Familiarization Tour and Initial Inspection. The Contractor must participate in the Fire Responsibility Familiarization Tour and Initial Inspection as required in Std Spec 5550, paragraphs
3.12.2 through 3.12.4.
3.5 Material Condition and Fire Protection Boundary Obstruction Mitigation Requirements. The Contractor must conform to all material condition and fire protection boundary obstruction mitigation requirements detailed in SFLC Std Spec 5550, paragraph 3.2.
3.6 Inoperable Fittings Log Requirements. The Contractor must conform to all inoperable fittings log requirements detailed in SFLC Std Spec 5550, paragraph 3.3.
3.7 Fire Prevention Service Particulars. The Contractor must conform to the below listed fire prevention service requirements, in accordance with SFLC Std Spec 5550.
TABLE 1 – FIRE PREVENTION SERVICE SELECTION
*SUB-PARAGRAPH TITLE Y/N
3.4 Fire prevention system status N
3.4.1 Temporary firefighting system proposal N
3.4.2 Emergent firefighting system inoperability approval and notification N
3.4.3 “Disabled equipment” signage for disabled initial responder equipment N
3.4.4 Firefighting system inoperability allowance for removed hazards N
3.4.5 Maintain sprinkling zone operability N
3.4.6 including all subparagaphs
Hazard mitigation for maintenance of fixed extinguishing systems N
3.4.7 Procedure implementation for enabling/disabling fire suppression systems
N
3.4.8 Portable water pumping requirement for vessels w/o installed capability N
3.4.9 Limitations on operation of major machinery while firefighting systems are offline N
16 (Rev-0)
*SUB-PARAGRAPH TITLE Y/N
3.4.10 Liquid fuel pumping requirement for operational permanent or temporary firefighting systems N
3.4.11 Mechanical AFFF equipment must be available to initial responders in compartments with risk of flammable/combustible liquid spillage
N
3.4.12 including all subparagraphs
Portable fire extinguisher requirements N
3.4.13 Hose and reel protection N
3.4.14 including all subparagraphs
Drydock firefighting requirements N
3.4.15 Fire protection system status in Fire Plan N
3.5 Fire response related communication links in Fire Plan N
3.6 Fire response related temporary services in Fire Plan N
3.6.1 Minimize downtime of fixed extinguishing systems N
3.6.2 through 3.6.10 Firemain and related equipment requirements N
3.6.11 Permanent lighting requirements Y
3.6.12 including all subparagraphs
Temporary lighting requirements Y
3.6.13 Electrical power, firefighting water, and lighting source location and testing identified in Fire Plan
N
3.7 including all subparagraphs
Fire alarm requirements Y
3.8 Shore power manual disconnect locations identified in Fire Plan Y
3.9 Other power manual disconnect locations identified in the Fire Plan N
3.10 including subparagraph
Vessel firefighting equipment placement and disposition info in Fire Plan
Y
3.11 Fire prevention and safety inspections in Fire Plan Y
3.11.1 Initial and daily inspection requirements Y
3.11.2 Additional details in fire inspection reports Y
*Each sub-paragraph number relates directly to the identical sub-paragraph number in SFLC Std Spec 5550.
3.5 Extended fire prevention services. If the performance period of the contract is extended by the KO, the contractor must continue to provide all fire prevention services as specified herein for the extension period.
This section is not applicable to this work item.
17 (Rev-0)
WORK ITEM 2: Buoy Cargo Hold Deck, Preserve 100%
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to preserve the deck surfaces of the Cargo Hold (2-30-0-AA), including the two 24” x 24” x 21” drain sumps.
1.2 Government-furnished property.
None.
2. REFERENCES
COAST GUARD DRAWINGS
Coast Guard Drawing 225B WLB 601-002, Rev K. Booklet of General Drawings
COAST GUARD PUBLICATIONS
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General Requirements
Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2022, Requirements for Preservation of Ship Structures
OTHER REFERENCES
None.
3. REQUIREMENTS
3.1 General.
3.1.1 CIR.
None.
3.1.2 Tech Rep.
Not applicable.
3.1.3 Protective measures. The Contractor must furnish and install all protective measures in accordance with SFLC Std Spec 0000, paragraph 3.3.3 (Vessel component, space, and equipment protection).
18 (Rev-0)
3.1.4 Interferences. The Contractor must handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences). Known interferences include, but are not limited to the below-listed:
Lockers.
Kick-pipes.
Grip downs.
Tank covers.
Bilge sensors.
Hydraulic lines and components.
Electrical wiring and controller.
Heat sensors.
Handrails.
3.2 Preservation particulars. The Contractor must prepare and coat the cargo hold deck surfaces, shown on Coast Guard Drawing 225B WLB 601-002, including flush deck tie-down fittings and machinery foundations, angle coaming area, and approximately six inches up all adjacent vertical surfaces (as applicable); use the system specified for “Weather Decks (Weather Deck, Buoy Tender Working Deck)”, in SFLC Std Spec 6310, Appendix A (Cutter and Boat Exterior Painting Systems). Select Gray (36231) inorganic zinc coating. Use Coast Guard Drawing 225 WLB 601-002 as guidance.
3.3 Substrate inspection. After completion surface preparation and before coating application, the Contractor must perform a visual inspection of the prepared substrate, and submit a CFR.
19 (Rev-0)
12300_ESD_1022_FLT
REC_12311_FLT_225’ WLB ‘B’ Class (ALL) (0121)
WORK ITEM 3: Tanks, MP Fuel Stowage and Overflow, Clean and Inspect
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to clean and inspect the following tank(s):
TYPE OF TANK LOCATION CAPACITY - 95%
(GALLONS)
LOW SUCTION
(GALLONS)
Diesel Fuel Storage 4-17-1-F 5,090 161
Diesel Fuel Storage 4-17-4-F 3,457 109
Diesel Fuel Storage 4-30-0-F 20,615 651
Diesel Fuel Storage 4-30-1-F 7,225 228
Diesel Fuel Storage 4-30-2-F 7,225 228
Cargo Diesel Fuel Storage
3-48-0-FF 5,549 175
Diesel Fuel Storage 3-48-1-F 7,813 247
Diesel Fuel Storage 3-48-2-F 7,813 247
Diesel Fuel Overflow
3-54-0-F 5,549 175
1.2 Government-furnished property.
None.
2. REFERENCES
COAST GUARD DRAWINGS
Coast Guard Drawing 225B WLB 541-001, Rev G; Fuel Oil System Diagram
20 (Rev-0)
Coast Guard Drawing 225B WLB 541-007, Rev D; Incinerator Fuel Oil Service Tank
COAST GUARD PUBLICATIONS
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General Requirements
Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2022, Welding and Allied Processes
OTHER REFERENCES
Federal Specification (Fed Spec) QQ-N-281, Oct 1985, Nickel-Copper Alloy Bar, Rod, Plate, Sheet, Strip, Wire, Forgings, and Structural and Special Shaped Sections
Society of Automotive Engineers (SAE) Aerospace Material Specification…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .