This document is a Statement of Work outlining the requirements for renovating the greenhouse cooling system at the USDA Agricultural Research Service National Clonal Germplasm Repository in Riverside, California. Key details include demolishing and replacing the existing cooling system across four greenhouse bays totaling 168 feet in length. The contractor will remove the existing evaporative cooling components and install new sidewall girts, flashing, seals, gutters, pads, distribution piping and intake shutters. Additional requirements involve replacing four rusted columns, cleaning eleven other columns, and waterproofing all columns. The contractor must protect plants from exterior elements during renovation and obtain inspection approval from USDA-APHIS before and after work. The contract also specifies quality control, temporary facilities, site cleanup procedures, training, warranties and other standard contract provisions.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

GH Cooling System

Renovation

USDA Agricultural Research Service

National Clonal Germplasm Repository, 1060 Martin Luther King Blvd., Riverside, CA

1. Project Title: “GH Cooling System Renovation”

2. Government Points of Contact

a. CONTRACTING OFFICER (CO):

Lam Pham

Albany, CA 94710

Phone: 510-559-6307

Email: lam.pham@usda.gov

b. RESEARCH PROGRAM REPRESENTATIVES (RPR):

Dr. Robert Krueger

Riverside, CA 92507

Phone: (951) 827-6980

Email: robert.krueger@usda.gov

c. ADMINISTRATIVE OFFICER (AO):

Nancy E. Knap

Riverside, CA 92507

Phone: (951) 369-4813

Email: nancy.knap@usda.gov

d. AREA SAFETY AND HEALTH MANAGER

Ken Cushman, Safety and Health Manager

Albany, California 94710

Phone: (510) 559-6002

Email: ken.cushman@ars.usda.gov

e. ENGINEERING PROJECT MANAGER (EPM)

Peter Lane

Albany, CA 94710

Phone: 559-6340

Email: peter.lane@usda.gov

f. LOCATION MONITOR

Dr. Robert Krueger

Riverside, CA 92507

Phone: 951-827-6980

Email: robert.krueger@usda.gov

3. Location: The site of work is located at the Agricultural Research Service National

Clonal Germplasm Repository, 1060 Martin Luther King Blvd., Riverside, CA. 92507.

4. Site Visit: A site visit and inspection tour is encouraged.

5. Program Need and Justification:

mailto:lam.pham@usda.gov mailto:robert.krueger@usda.gov mailto:nancy.knap@usda.gov mailto:ken.cushman@ars.usda.gov mailto:peter.lane@usda.gov mailto:robert.krueger@usda.gov

The Repository facilities include greenhouses that are used for plant propagation, maintenance, and pathogen-testing. The greenhouses are equipped with negative pressure evaporative cooling systems. The cooling system has degraded over the years and requires replacement.

Trees maintained in this structure are held under permits from USDA-APHIS and CDFA and must not be exposed to outside air during the renovation. Greenhouses are inspected for structural integrity on a monthly basis by USDA-APHIS.

6. Scope of Service: The contractor shall provide all professional services necessary for the accomplishment of the contract project and such required services shall be in accordance with requirements as described herein.

The Contractor shall provide services for the following tasks marked by an “X”.

[X] Provide a technical and cost proposal to complete the project as per project requirements.

[X] Provide and install all material to complete the project as per project requirements.

7. Background/Project Requirements:

The greenhouses were designed, manufactured, and installed by Conley Manufacturing and

Sales, Montclair, CA. The greenhouses have galvanized frames covered with clear polycarbonate corrugate. The greenhouses (bays A thru D) are contiguous, with a total length of 168 ft divided into separate rooms (4 bays) of 60, 24, 24, and 60 ft lengths. Width of the greenhouses is 36 ft with side walls 8 ft high at the walls, gabled to 15 ft. The cooling system is a negative pressure evaporative cooling system including approximately 144 LF of intake shutter filter medium and framing, 48 motorized intake shutters, and approximately 144 LF of evaporative cooling systems including metal flashings and seals, supported by sidewall girts and J channels at the bottom of the corrugated channels. The exterior of the cooling system is enclosed in a metal frame screened structure to exclude insects and exposure to exterior air.

8. Description of work:

Greenhouse cooling system: Greenhouse A thru D. (See attached photos of Cool

System)

• Demolish and remove existing cool cell system.

• Replace existing cooling system with equal size/capacity.

• Replace 4 columns that are rusted at the top of the footings. Remove surface rust from remaining 11 columns. Apply rubberized waterproofing to all columns to a height 6 in above the top of the evaporative cooling system.

• Install new sidewall girts; evaporative cooling system girts, flashings, seals, gutters (pvc), pads (4 in thick X 30 in high), distribution piping, top cap, and plumbing from cool pads to existing sumps.

• Install new 39 in motorized intake shutters, replace intake shutter filter frames, install new filter medium.

• Clean up work area as needed, recycling as much material as possible.

• Critical notes: Trees inside the greenhouses in each zone must be protected from contact with the outside air until the work is completed and the filter medium has been reinstalled.

Contractor to install plastic barrier wall inside of the greenhouse sections to protect plants from construction work and elements. Isolation of plants from exterior must be inspected and approved by USDA-APHIS before work may proceed.

• Installation must be inspected and approved by USDA-APHIS before final payment.

Inspection will be arranged by Repository personnel. Provide at least 1-week prior notice to arrange an APHIS inspection, for timely inspection.

• Invoices can be approved upon completion of inspection and acceptance by USDA-APHIS inspector.

9. References & Standards: All construction shall comply with ARS Facilities Design

Standards (ARS Manual 242.1, 5-01-12), ARS Energy, Water, and Sustainability Policy

(ARS Policy & Procedures 134.2, 11-12-13), ARS Energy, Water, and Sustainability

Policy Bulletin (ARS Policy & Procedures Bulletin 15-134.2), governing Building Codes, and all applicable local, regional, State, and Federal regulations. Where one or more

Codes or regulations conflict, the more stringent shall apply.

10. Permits: Where governing regulations and imposed codes and standards require notices, permits, licenses, inspections, tests, and similar items or actions in order to lawfully proceed with the required work, the Contractor shall obtain items and take those actions in accordance with the regulations of the governing authority. Special authority may be required for remediation and disposal of ACM, Contractor shall confirm this and obtain this authority. The costs of such permits, licenses, inspections, etc., are the obligation of the Contractor.

11. Existing Installations/Demolition:

a) Contractor shall modify existing installations as needed to accommodate the new installation. Where applicable contractor shall coordinate demolition or modification of existing installations with the Owner. All disturbances of existing systems shall be thoroughly coordinated with the Owner to prevent disconnecting equipment that may potentially jeopardize in-progress research.

b) The Owner reserves the right to retain any equipment or materials removed as part of this scope of work. The Contractor shall coordinate any equipment or materials to be retained with the Owner prior to starting demolition operations. The Contractor shall legally dispose all equipment or material removed that will not be retained.

c) The contractor shall divert project waste to recycle where practical. The Contractor shall track and document the amount of waste diverted to recycle. The contractor shall submit diversion documentation as part of closeout. If no waste is diverted to recycle, the contractor shall submit a letter stating so and why diversion was not practical.

12. Submittals:

a) Contractor shall provide other relevant illustrations, standard schedules, mix designs, electrical layout and plan, performance charts, instructions, brochures, diagrams, manufacturer descriptive literature, catalog data, etc. applicable to proposed material install.

b) Contractor shall provide a site-specific Safety Plan and an Asbestos

Abatement/Management Plan designed to protect the workers and occupants of the buildings during all phases of construction.

c) The descriptive literature shall be annotated/highlighted to show its conformance with contract requirements.

d) Submittals are required for all building materials and equipment and will be stamped and/or signed by the general contractor prior to submission to the

Government.

e) Contractor is responsible for any costs incurred for equipment ordered without prior approval

13. Quality Control: The work performed under this contract shall be subject to continuous audit by the COR. Quality control is the exclusive responsibility of the

Contractor.

14. Temporary Facilities:

a) Temporary utilities (water and electricity) may be furnished to the Contractor by the

Government, if so requested. The Contractor shall maintain and protect all such utilities during the course of construction and shall repair or replace any items damaged through its own negligence.

b) If wash-down facilities are constructed for abatement activities, Contractor shall dispose wastewater in accordance with State and local regulations.

c) Should the Contractor require any power or utility shutdowns during construction, the Contractor shall obtain approval for such shutdown from the Location Monitor three working days prior to the need

15. Site Cleanup: The construction site shall be kept clean and free of debris at all times.

Clearance air and surface samples shall be taken to verify complete remediation of

ACM. Restore areas disturbed as nearly as possible to the original appearance and condition. Upon completion of the project, and prior to final inspection, the Contractor shall remove from the premises all unused material, trash, and debris resulting from the work to the satisfaction of the COR.

16. O&M Manuals

a) O&M manuals shall be submitted upon completion and acceptance of the project.

17. Training/Start-up/Commissioning:

a) Contractor is responsible for start-up, testing, and commissioning of all installed systems.

b) Contractor shall provide user training to cover all safe operation and preventative maintenance actions/frequencies/schedules of equipment included in this solicitation.

18. Final Inspection: The Contractor shall notify the Contracting Officer and Owner in writing 10 days prior to the date that the project will be ready for final inspection. An inspection of the project will be made by the Contracting Officer and Contractor at a mutually agreed upon time. COR and contractor shall compile a “punch list” prior to final acceptance of the installation and submit completed warranty documentation to manufacturer.

19. Warranty: In addition to any other warranties set out elsewhere in this contract, the

Contractor warrants that work performed under this contract conforms to the contract requirements and is free of any defect of equipment, material or design furnished, or workmanship performed by the Contractor or any of his subcontractors or suppliers at any tier. Such warranty shall continue for a period of one year from the date of final acceptance of the project. Under this warranty, the Contractor shall remedy at his own expense any such failure to conform or any such defect. In addition, the Contractor shall remedy at his own expense any damage to Government owned or controlled real or personal property, when that damage is the result of the Contractor's failure to conform to contract requirements or any such defect of equipment, material, workmanship, or design.

The Contractor shall also restore any work damaged in fulfilling the terms of this clause.

The Contractor's warranty with respect to work repaired or replaced hereunder will run for one year from the date of such repair or replacement.

20. Notification and Compliance: The Government shall notify the Contractor in writing within a reasonable time after the discovery of any failure, defect, or damage. Should the

Contractor fail to remedy any failure, defect, or damage within a reasonable time after receipt of notice thereof, the Government shall have the right to replace or repair and have the cost billed to the Contractor.

21. Latent Defects: The Warranty specified herein shall not limit the Government’s rights with respect to latent defects, gross mistake, or fraud.

22. Acceptance: Upon satisfactory submittal of the above documents the Contracting Officer shall issue to the Owner a certificate recommending final acceptance of the project.

Minor unfinished items of work may be listed on the certificate and excepted from final acceptance. A sum sufficient to cover the cost of completing these unfinished items of work will be withheld by the Owner from the final payment. All other funds including retainage shall be due and payable upon receipt by the Owner of the Contracting Officer's certificate. Upon certification by the Contracting Officer that the items of work have been completed, all monies withheld by the Owner shall be due the Contractor

END