Attachment 2 - QASP.docx
DOCX document 47 KB Posted
- Attached to
- Court Reporter Services
- Solicitation number
- N6893622Q0211
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Attachment 3 - ELIN Matrix.xlsx | XLSX spreadsheet | |
| L-1 Past Performance Information Form.pdf | ||
| L-2 Contractor Performance Assessment Questionnaire.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Quality Assurance Surveillance Plan (QASP) For Court Reporter Services
1. Purpose
This Quality Assurance Surveillance Plan (QASP) is a Government developed and applied document used to make sure systematic quality assurance methods are used in the administration of the performance-based services under the planned contract. The intent is to ensure that the Contractor performs in accordance with the performance metrics and the Government receives the quality of services called for in the contract.
This contract requirement, as defined in the Performance Work Statement (PWS) is to provide Court Reporter services for the Naval Air Warfare Center Weapons Division, China Lake, CA.
This requirement will be met using a five-year, hybrid Firm Fixed Price (FFP) and Cost Reimbursement Indefinite Delivery Indefinite Quality (IDIQ) contract. A properly executed QASP will assist the Government in achieving the objectives of this procurement.
2. Authority
Authority for issuance of this QASP is provided in Section E - Inspection and Acceptance, which provides for inspection and acceptance of the services and documentation called for in service contracts, to be executed by the Contracting Officer or a duly authorized representative.
3. Scope
To fully understand the roles and responsibilities of the parties, it is important to first define the distinction in terminology between Quality Control Plan and the Quality Assurance Surveillance Plan. In the Quality Control Plan, the Contractor, not the Government, is responsible for management and quality control actions necessary to meet the quality standards set forth by the contract.
The QASP on the other hand, is put in place to provide Government surveillance oversight of the contractor’s efforts to assure that they are timely, effective and are delivering the results specified in the contract.
4. Government Resources
The following definitions for Government resources are applicable to this plan:
Contracting Officer - A person duly appointed with the authority to enter into (Procuring Contracting Officer) (PCO) contracts and make related determination and findings on behalf of the Government. The PCO for this contract is Code D240000. Contracting Officers are designated via a written warrant, which sets forth limitations of authority.
Contracting Officer’s Representative (COR) - An individual appointed in writing by the PCO to act as their authorized representative to assist in administering the contract. The COR will be appointed in the resulting contract. The limitations of authority are contained in a written letter of designation.
5. Responsibilities
The following Government resources shall have responsibility for the implementation of this QASP:
Contracting Officer – The Contracting Officer ensures performance of all necessary actions for effective contracting, ensures compliance with the terms of the contract and safeguards the interests of the United States in the contractual relationship. It is the Contracting Officer that assures the Contractor receives impartial, fair and equitable treatment under the contract. The Contracting Officer is ultimately responsible for the final determination of the adequacy of the Contractor’s performance.
Contracting Officer’s Representative (COR) – The COR is responsible for technical administration of the contract and assures proper Government surveillance of the contractor’s performance. The COR is not empowered to make any contractual commitments or to authorize any changes on the Government’s behalf. Any changes that the contractor deems may affect contract price, terms or conditions shall be referred to the Contracting Officer for action.
6. Methods of QA Surveillance
a. Contractor Performance Assessment Report System (CPARS) – The Government will perform an evaluation using CPARS format 1 month prior to the end of each period of performance. The Government will address the quality of the product or service, schedule, cost control, business relations, management, and other important areas. This evaluation will be one determinant in performance of each sequential period. The marketplace for curriculum development and financial training support services is very competitive; as such, the successful offeror has bested interest in the Government generated CPARS under this contract. As this information may affect future source selections throughout DoD, and future contracts, the semi-annual Government assessment will be used appropriately as an additional performance oversight and communication tool.
b. QASP – The below listed methods of surveillance shall be used by the COR in the technical administration of this QASP. In addition to the below instructions, the form to be used for documentation of quality assurance surveillance is the Surveillance Activity Checklist provided herein.
c. Observation, Feedback, and Review – Unscheduled observation of products and services provided by the contractor on site and recurring review of contractor submitted reports will be performed by the COR. Feedback from customers will be collected and used by the COR to document surveillance of technical performance.
7. Surveillance
Enclosures (1) sets forth the performance standards and surveillance methods for the contractor and COR while Enclosure (2) provides the checklist and means for the COR to document on a semi-annual basis the results of the surveillance and shall be provided to the Contracting Officer on a semi-annual basis.
8. Documentation
In addition to providing a semi-annual reports to the Contracting Officer, the COR will maintain a complete Quality Assurance file. The file will contain copies of all reports, evaluations, recommendations, and any actions related to the Government’s performance of the quality assurance function, including the originals of the Surveillance Activity Checklists. All such records will be maintained for the life of the contract. The COR shall forward these records to the Contracting Officer at termination or completion of the contract.
9. Enclosures
Enclosure (1) Performance Quality Standards Enclosure (2) Surveillance Activity Checklist
N68936-14-T-0001
SOURCE SELECTION INFORMATION-SEE FAR 2.101 AND 3.104, FOR OFFICIAL USE ONLY
Enclosure (1)
PERFORMANCE QUALITY STANDARDS
| Description |
| Performance Standards |
| Surveillance Method/ |
Measure
| General Requirements IAW PWS Para 3.1 |
| Contractor shall provide General Requirements support. Based upon feedback form the Government, the services provided are deemed comprehensive, timely, and technically acceptable. |
| 100% Inspection by the COR |
| Security IAW PWS Para 3.2 |
| Contractor personnel shall be able to perform work up to Controlled Unclassified Information (CUI). |
| 100% Inspection by the COR |
| Government Notification IAW PWS Para 3.3.1.1 |
| Contractor shall reasonably acknowledge Government notification of the date, time, location of the proceeding, and the name of the Government Trial Attorney (GTA) via return email or other means—deemed appropriate by the PCO—Contractor shall identify the selected Court Reporter 48 hours before the proceeding. |
| 100% Inspection by the COR |
| Arrival Time IAW PWS Para 3.3.1.2 |
| Contractor personnel shall report to the GTA, at least 15 minutes before the designated start time of the proceedings. |
| 100% Inspection by the COR |
| Reporting Method IAW PWS Para 3.3.1.3 |
| Court Reporter shall report everything spoken during a session while on the record and incorporate it into the transcript. |
| 100% Inspection by the COR |
| Signatures IAW PWS Para 3.3.1.4 |
| Court Reporter shall provide a signature page and any corrections to all parties promptly after it is received. |
| 100% Inspection by the COR |
| Virtual Depositions and other Proceedings IAW PWS Para 3.3.1.5 |
| The Contractor shall conduct, record, and provide transcripts and digital video records of all meetings. |
| 100% Inspection by the COR |
| Transcripts IAW PWS Para 3.3.1.6 |
| Contractor shall provide transcript as establish in the task order and a “Rough Draft” (if requested) shall be delivered to the GTR within 24 hours of the close of the proceeding. |
| 100% Inspection by the COR |
| Manuscripts IAW PWS Para 3.3.1.7 |
| The manuscript shall be a verbatim copy of the transcript, but in reduced format. |
| 100% Inspection by the COR |
| Exhibits IAW PWS Para 3.3.1.8 |
| At in-person proceedings, court reporter shall mark the exhibits as they are identified by the attorney doing the questioning |
| 100% Inspection by the COR |
| Accuracy of Transcripts IAW PWS Para 3.3.1.9 |
| Contractor shall be responsible for furnishing complete transcripts, Contractor shall correct errors and furnish the corrected transcript within five (5) calendar days from receipt of notification |
| 100% Inspection by the COR |
| Transcript Certification IAW PWS Para 3.3.10 |
| Court Reporter shall complete and the Contractor shall attach at the end of each proceeding transcript and certification of accuracy. |
| 100% Inspection by the COR |
| Legibility of Transcript Copies IAW PWS Para 3.3.1.11 |
| Contractor shall correct or replace the transcript with acceptable legible copies within one (1) calendar day after receipt of illegibility notification unless otherwise directed by the GTA |
| 100% Inspection by the COR |
| Retention of Notes and Recordings IAW PWS Para 3.3.1.12 |
| Contractor shall retain and properly safeguard all stenographic notes and electronic recording taken by the Court Reporter |
| 100% Inspection by the COR |
| Loss of Testimony IAW PWS Para 3.3.1.13 |
| Contractor shall provide the services necessary to retake and transcribe lost testimony without additional cost. |
| 100% Inspection by the COR |
| Proceedings Room IAW PWS Para 3.3.1.14 |
| If required, proceeding room shall be suitable for its intended purpose in accordance with the PWS, |
| 100% Inspection by the COR |
DATA PERFORMANCE STANDARDS
| Description |
| Standard |
| AQL |
| Surveillance |
Method/Measure
| Transcripts (A001) |
| Submission is in accordance with the CDRL. |
| 95% of required deliverable provided on time. No more than 1 report per year may be inaccurate or require a rewrite. |
| 100% Inspection by COR. |
| Manuscripts (A002) |
| Submission is in accordance with the CDRL. |
| 95% of required deliverable provided on time. No more than 1 report per year may be inaccurate or require a rewrite. |
| 100% Inspection by COR. |
| Exhibits (A003) |
| Submission is in accordance with the CDRL. |
| 95% of required deliverable provided on time. No more than 1 report per year may be inaccurate or require a rewrite. |
| 100% Inspection by COR. |
| Travel/Travel Report (A004) |
| Submission is in accordance with the CDRL. |
| 95% of required deliverable provided on time. No more than 1 report per year may be inaccurate or require a rewrite. |
| 100% Inspection by COR. |
Surveillance Activity Checklist
All tasks will be assessed on the following:
Quality of Product or Service – Assess the contractor’s effort to transform operational needs and requirements into an integrated solution. Areas of focus may include the planning and management of program efforts, the quality of support provided throughout all phases of contract execution, the integration of program management specialties, management of interfaces, and the management of a totally integrated effort of all program management concerns to meet cost, performance, and schedule objectives. Assess how successfully the contractor meets program quality.
Schedule – Assess the contractor’s adherence to the required delivery schedule by assessing the contractor’s efforts during the assessment period that contribute to or effect the schedule variance. Also address significance of scheduled events (i.e., design reviews), discuss causes, and assess the effectiveness of contractor corrective actions.
Cost Control – Assess the contractor’s effectiveness in forecasting, managing, and controlling contract cost. Is the contractor experiencing cost growth or underrun? If so, discuss the causes and contractor-proposed solutions for the cost overruns. For contracts where task or contract sizing is based upon contractor provided person-hour estimates, the relationship of these estimates to ultimate cost should be assessed. In addition, the extent to which the contractor demonstrates a sense of cost responsibility, through the efficient use of resources in each work effort should be assessed.
Business Relations – Assess the timelines, completeness and quality of problem identification, corrective action plans, proposal submittals, the contractor’s reasonable and cooperative behavior, effective business relations, and customer satisfaction.
Management – Assess the contractor’s success with timely award and management of subcontracts. Discuss the extent to which the contractor discharges its responsibility for integration and coordination of all activity needed to execute the contract; identifies and applies resources required to meet schedule requirements; assigns responsibility for tasks/actions required by contract; communicates appropriate information to affected program elements in a timely manner. Assess the contractor’s risk mitigation plans. If applicable, identify any other management areas that are unique to the contract.
Other Areas – Assess additional evaluation areas unique to the contract, or that cannot be captured elsewhere.
The evaluation ratings are as follows:
Performance Based Evaluation: The Government will evaluate contractor performance based on their ability to complete work specified in the scope and PWS paragraphs 3.3 through 3.3.1.15. The contractor shall be evaluated using the following ratings:
Exceptional Performance: Contractor’s performance of virtually all contract requirements consistently exceeds the acceptable standards and in addition provides numerous significant, tangible or intangible, benefits to the Government (e.g., improved quality, responsiveness, increased timeliness, or generally enhanced effectiveness of operations). The few areas for improvement are all minor. There are no recurring problems. Contractor’s management initiates effective corrective action whenever needed.
Very Good Performance: Contractor’s performance of most contract requirements is consistently above acceptable standards and provides significant tangible and intangible benefits to the Government (e.g., improved quality, responsiveness, increased timeliness, or generally enhanced effectiveness of operations). Although some areas require improvement, these areas are minor and are offset by better performance in other areas. Few, if any, recurring problems have been noted, and the contractor takes satisfactory corrective action.
Satisfactory Performance: Contractor’s performance of most contract requirements meets the acceptable standards with some tangible or intangible benefits to the Government (e.g., improved quality, responsiveness, increased timeliness, or generally enhanced effectiveness of operations). Although there are some areas of very good or excellent performance, these are more or less offset by unsatisfactory performance in other areas.
Marginal Performance: Performance does not meet contractual requirements. The contractual performance of the task and sub-task being assessed reflect a serious problem for which the contractor has not yet identified corrective actions. The contractor’s proposed actions appear only marginally effective or were not fully implemented.
Unsatisfactory Performance: Contractor’s performance of most contract requirements is inconsistent and frequently does not always meet acceptable standards. Quality, responsiveness, and timeliness in many areas require attention and action. Corrective actions have not been taken or are ineffective.
Enclosure (2)
SURVEILLANCE ACTIVITY CHECKLIST
Semi-Annual Surveillance Assessments shall be performed by the COR and documented using the SAC below, and any required CDRLs for the month as described in the PWS and this SAC, Enclosure (2).
| Description |
| Surveillance Method/ |
Measure
| Quality |
| Schedule |
| Cost Control |
| Business Relations |
Management
Other
| General Requirements IAW PWS Para 3.1 |
| 100% Inspection by the COR |
| Security IAW PWS Para 3.2 |
| 100% Inspection by the COR |
| Government Notification IAW PWS Para 3.3.1 |
| 100% Inspection by the COR |
| Arrival Time IAW PWS Para 3.3.2 |
| 100% Inspection by the COR |
| Reporting Method IAW PWS Para 3.3.3 |
| 100% Inspection by the COR |
| Signatures IAW PWS Para 3.3.4 |
| 100% Inspection by the COR |
| Virtual Depositions and other Proceedings IAW PWS Para 3.3.5 |
| 100% Inspection by the COR |
| Transcripts IAW PWS Para 3.3.6 |
| 100% Inspection by the COR |
| Manuscripts IAW PWS Para 3.3.7 |
| 100% Inspection by the COR |
| Exhibits IAW PWS Para 3.3.8 |
| 100% Inspection by the COR |
| Accuracy of Transcripts IAW PWS Para 3.3.9 |
| 100% Inspection by the COR |
| Transcript Certification IAW PWS Para 3.3.10 |
| 100% Inspection by the COR |
| Legibility of Transcript Copies IAW PWS Para 3.3.11 |
| 100% Inspection by the COR |
| Retention of Notes and Recordings IAW PWS Para 3.3..12 |
| 100% Inspection by the COR |
| Loss of Testimony IAW PWS Para 3.3.13 |
| 100% Inspection by the COR |
| Proceedings Room IAW PWS Para 3.3.14 |
| 100% Inspection by the COR |
Enclosure (2)
Semi-Annual Summary of Ratings For:
Requirements in accordance with the PWS and Contract Data Requirements List’s (CDRL’s) Form DD-1423.
| Quality of Product or Service | Schedule | |||
| Number of Exceptional | ____ | Number of Exceptional | ____ | |
| Number of Very Good | ____ | Number of Very Good | ____ | |
| Number of Satisfactory | ____ | Number of Satisfactory | ____ | |
| Number of Marginal | ____ | Number of Marginal | ____ | |
| Number of Unsatisfactory | ____ | Number of Unsatisfactory | ____ |
| Cost Control | Business Relations | |||
| Number of Exceptional | ____ | Number of Exceptional | ____ | |
| Number of Very Good | ____ | Number of Very Good | ____ | |
| Number of Satisfactory | ____ | Number of Satisfactory | ____ | |
| Number of Marginal | ____ | Number of Marginal | ____ | |
| Number of Unsatisfactory | ____ | Number of Unsatisfactory | ____ |
| Management | |
| Number of Exceptional | ____ |
| Number of Very Good | ____ |
| Number of Satisfactory | ____ |
| Number of Marginal | ____ |
| Number of Unsatisfactory | ____ |
| Other Areas | |
| Number of Exceptional | ____ |
| Number of Very Good | ____ |
| Number of Satisfactory | ____ |
| Number of Marginal | ____ |
| Number of Unsatisfactory | ____ |
Checklist Completed By: ____________________________
Date Completed: ____________________________
Contract Requirements in accordance with the Contract Data Requirements Lists (CDRLs) Form DD-1423
| Description |
| Surveillance Method/Measure |
| Quality |
| Schedule |
| Cost Control |
| Business Relations |
| Management |
| Other Areas |
| Transcripts (A001) |
| 100% Inspection by the COR |
| Manuscripts (A002) |
| 100% Inspection by the COR |
| Exhibits (A003) |
| 100% Inspection by the COR |
| Travel/Travel Report (A004) |
| 100% Inspection by the COR |
Annual Summary of Ratings For:
Requirements in accordance with the PWS and Contract Data Requirements List’s (CDRL’s) Form DD-1423.
| Quality of Product or Service | Schedule | |||
| Number of Exceptional | ____ | Number of Exceptional | ____ | |
| Number of Very Good | ____ | Number of Very Good | ____ | |
| Number of Satisfactory | ____ | Number of Satisfactory | ____ | |
| Number of Marginal | ____ | Number of Marginal | ____ | |
| Number of Unsatisfactory | ____ | Number of Unsatisfactory | ____ |
| Cost Control | Business Relations | |||
| Number of Exceptional | ____ | Number of Exceptional | ____ | |
| Number of Very Good | ____ | Number of Very Good | ____ | |
| Number of Satisfactory | ____ | Number of Satisfactory | ____ | |
| Number of Marginal | ____ | Number of Marginal | ____ | |
| Number of Unsatisfactory | ____ | Number of Unsatisfactory | ____ |
| Management | Other Areas | |||
| Number of Exceptional | ____ | Number of Exceptional | ____ | |
| Number of Very Good | ____ | Number of Very Good | ____ | |
| Number of Satisfactory | ____ | Number of Satisfactory | ____ | |
| Number of Marginal | ____ | Number of Marginal | ____ | |
| Number of Unsatisfactory | ____ | Number of Unsatisfactory | ____ |
Checklist Completed By: ____________________________
Date Completed: ____________________________
Annual Surveillance
The COR will perform an annual assessment of overall contract performance utilizing the CPARS evaluation rating definitions listed in Enclosure 2. This annual assessment will occur at the midpoint of each year following the award of the contract and cover the previous 12 months, except for the first year of the contract, which cover only the previous 6 months.
| Description |
| Surveillance Method/ |
Measure
| Date Planned |
| Date Completed |
| Summary Rating/Results |
| Quality of Product or Service |
| Review of Semi-annual Ratings. |
| Schedule |
| Review of Semi-annual Ratings. |
| Cost Control |
| Review of Semi-annual Ratings. |
| Business Relations |
| Review of Semi-annual Ratings. |
| Management |
| Review of Semi-annual Ratings. |
| Utilization of Small Business |
| Review of Semi-annual Ratings. |
| Other Areas |
| Review of Semi-annual Ratings. |
Annual Surveillance Completed By: ____________________________
Date Completed: ____________________________
SOURCE SELECTION INFORMATION-SEE FAR 2.101 AND 3.104, FOR OFFICIAL USE ONLY