This document is a Performance Work Statement (PWS) and a Federal Contract Opportunity for a Hazardous Fuel Reduction and Invasive Species Control Project within the Savannah Coastal Refuges Complex at the Pinckney National Wildlife Refuge in Beaufort County, South Carolina.

The PWS outlines the scope of work, which includes 645 acres of mechanical fuel reduction treatments using forestry mulching machines, forestry whole tree chipping crews, and other Service-approved operations. The goal is to reduce fuel loads by 95%, remove non-merchantable pines and Chinese tallow trees, and promote an understory of at least 75% native warm-season grasses. The performance period is from contract award through April 30, 2025.

The related Federal Contract Opportunity is a Request for Quotation (RFQ) that is 100% Small Business Set-Aside, with a North American Industry Classification System (NAICS) code of 115310 (Support Activities for Forestry) and a $34 Million size standard. Quotes are due by August 14, 2024, and a site visit is scheduled for August 6, 2024. Award will be made as a firm-fixed-price contract based on the best value to the government, considering technical, past experience, and price factors.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

United States Department of the Interior

US Fish and Wildlife Service Savannah Coastal Refuges Complex

694 Beech Hill Lane Hardeeville, SC 29927

Scope of Work and Performance Work Statement

Hazard Fuel Reduction and Invasive Species Control Project (2024-2025)

Primary POC: Shaw Davis, Deputy Project Leader shaw_davis@fws.gov

843-784-9911 (office) 912-312-5227 (mobile)

Alternate POC: Wayne Harris, Wildlife Biologist billy_harris@fws.gov 912-660-0779 (mobile)

Chuck Hayes, Supervisory Wildlife Biologist chuck_hayes@fws.gov 912-210-7366 (mobile)

Project summary:

The project is located on Pinckney Island National Wildlife Refuge (NWR) (Beaufort County, SC) (Map 1). Completion of this project will result in everlasting improvements in hazard fuel reduction, invasive species control, and habitat management.

Summary of mechanical treatments (2024-2025)

- 645 acre treatment area of mechanical fuel reduction using forestry mulching machines, forestry whole tree chipping crews, and/or other Service approved mechanical operations on Pinckney Island NWR (Map 2)

- a minimum of 200 acres of the entire area will be treated, not to exceed total project budget

Scope of Work

Overview:

mailto:shaw_davis@fws.gov mailto:billy_harris@fws.gov mailto:chuck_hayes@fws.gov

This treatment is needed to reduce overly dense fuel loads by 95%, remove all non-merchantable pines and Chinese tallow tree where practical, promote an understory dominated by at least 75% coverage of native warm-season grasses, and improve the efficacy of prescribed burns that minimize catastrophic wildfire hazard.

Once completed, the resulting native forest communities should be suitable for management with herbicide applications, under-planting of longleaf pine, and frequent, low intensity prescribed fires. This schedule should maintain biological diversity and resiliency into perpetuity.

Stand specific treatment (2024-2025):

Mechanical operations will be completed on suitable sites located throughout the treatment area as the first major step in hazard fuel reduction. Forestry mulching machines and/or forestry whole tree chipping equipment will be employed to reduce fuel loads in selected areas containing little to no merchantable pines, to clear areas of loblolly and slash pine advanced regeneration, and to create sufficiently open conditions for future longleaf pine planting. All treated vegetation, other than scattered logs totaling at least 1 ton per acre where available, will be mulched to soil level and/or chipped and hauled off site.

• All areas of desirable live oak and other hardwood and cabbage palm dominated hammocks scattered across the project site are to be excluded from all mechanical operations.

• The existing longleaf pine stand is only to be treated for Chinese tallow, sweetgum, and other invasive hardwoods.

• All Chinese tallow tree, regardless of diameter, encountered during mechanical operations will be mulched/chipped to soil level.

• Contractor is responsible for transport of all equipment to and from the project site.

• Refuge Biologists will provide a shapefile defining the boundaries of the project.

• Equipment operators will avoid all wetlands that are scattered across the project area.

• All contracted personnel will pay close attention to avoid harm to curious Refuge visitors that may wander into the area of operations. Contractor should place orange cones adjacent to daily operation areas along established trails.

• Equipment operators will avoid all identified cultural resources near or within the project area. If previously unidentified and/or potential cultural resources are discovered during project operations, contractor shall pause work and contact Refuge Manager or designee for consultation with USFWS archeological program staff.

• Operations will be suspended if weather conditions are such to cause excessive rutting and/or damage to access roads.

• Refuge Biologists and Refuge Managers have the authority to halt operations anytime for unfavorable weather, damage to non-target vegetation, or non-cooperative operators.

• Contractor shall be responsible for repairing any damage done by field crews to gates, fences, access roads, signs, structures, and any other infrastructure.

• Refuge Biologists and Refuge Managers shall monitor all operations with frequent, on-site inspections.

• No littering will be tolerated and all garbage, including empty containers of hydraulic fluid, engine oil, and other materials must be removed daily.

• All bids should be based on a treatment price per acre on a minimum of 200 acres, not to exceed the total project budget.

• All equipment used by the contractor will be clean of off-site soil and plant material, prior to entering the Refuge. If equipment leaves the work site for any reason it will be cleaned prior to re-entering the Refuge. This requirement is to limit the potential for spread of exotic and invasive plants onto the Refuge.

• Contractor shall take every precaution necessary to prevent damage to leave trees.

• All operations should follow South Carolina’s Best Management Practices for

Forestry as minimum standards for environmental protection (best-management-practices-manual.pdf (scfc.gov)).

Period of Performance:

All mechanical treatments should be completed by April 30, 2025, pending the finalization of all Endangered Species Act Section 7 consultation, National Environmental Policy Act Compliance, National Historic Preservation Act Section 106 consultation, and other legal requirements for active fuels and habitat management on federal lands. This period may be extended due to unforeseen circumstances related to weather and other variables, as approved by the Refuge Manager or Wildlife Biologist and contracting officer.

https://www.scfc.gov/wp-content/uploads/2021/03/best-management-practices-manual.pdf https://www.scfc.gov/wp-content/uploads/2021/03/best-management-practices-manual.pdf