This is a Project-Specific Terms and Conditions document for a Federal Railroad Administration (FRA) grant agreement with the City of Eau Claire, Wisconsin, for the Galloway Street Vehicular and Pedestrian Rail Crossing Elimination Program. The project involves eliminating two at-grade crossings at the intersection of Galloway Street and Union Pacific Railroad (UPRR) line by constructing a new grade-separated overpass. The project will connect two segments of the Chippewa River Regional Trail, improve travel time for vehicle commuters and pedestrians, eliminate crossing accidents, reduce idling emissions, and accommodate future freight and commuter rail traffic. The project is located in downtown Eau Claire, with an estimated substantial completion date of February 15, 2028.
The total project cost is $12,499,500, with the FRA contributing $9,999,600 (80%) and the City of Eau Claire providing $2,499,900 (20%) in non-federal funds. The funding source is the Infrastructure Investment and Jobs Act, with the grant awarded through the FY 2022 Railroad Crossing Elimination Program. The project will involve project administration, environmental review, final design, and construction, including utility relocations, real estate acquisition, and road realignment. The overpass will provide 23 feet of vertical clearance and be a single span 80 ft long prestressed concrete girder bridge. Performance measurements will track average daily traffic, vehicle speeds, and pedestrian/bicycle usage before and after project completion.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Galloway Street Overpass Design Services.PDF | ||
| Attachment 3 - Affected Area.PDF | ||
| Attachment 1 - Narrative.PDF |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Version Date: April 30, 2025
Attachment 2
PROJECT-SPECIFIC
TERMS AND CONDITIONS
Project-Specific Terms and Conditions
Table of Contents
ARTICLE 1: PROJECT-SPECIFIC DESIGNATIONS
1.1 Recipient
1.2 Project and Purpose
1.3 Program Designations
ARTICLE 2: SPECIAL TERMS AND CONDITIONS
ARTICLE 3: ADMINISTRATIVE INFORMATION
3.1 Application
3.2 FRA Awarding Official
3.3 Federal Award Date
3.4 Program Name and Assistance Listings Number
3.5 Recipient’s Unique Entity Identifier
3.6 Federal Award Identification Number
ARTICLE 4: STATEMENT OF WORK
4.1 General Project Description
4.2 Project Location
4.3 Project Scope
4.4 Implement Required Environmental Commitments
ARTICLE 5: AWARD DATES AND ESTIMATED PROJECT SCHEDULE
5.1 Award Dates
5.2 Estimated Project Schedule
ARTICLE 6: AWARD AND PROJECT FINANCIAL INFORMATION
6.1 Award Amount
6.2 Federal Obligation Information
6.3 Federal Authorization and Funding Source
6.4 Funding Availability
6.5 Approved Project Budget
6.6 Pre-Award Costs
6.7 Phased Funding Agreement
ARTICLE 7: PERFORMANCE MEASUREMENT INFORMATION
ARTICLE 8: ENVIRONMENTAL COMPLIANCE
ARTICLE 9: LABOR AND WORK
9.1 Efforts to Support Good-Paying Jobs and Strong Labor Standards
9.2 Supporting Narrative
ARTICLE 1: PROJECT-SPECIFIC DESIGNATIONS
1.1 Recipient
This Agreement (Agreement) is between the Federal Railroad Administration (FRA) and the City of Eau
Claire, WI (the Recipient).
1.2 Project and Purpose
The purpose of this award is to fund a Fiscal Year (FY) 2022 Railroad Crossing Elimination Program grant for the Galloway Street Vehicular and Pedestrian Rail Crossing Eliminations and Construction of Galloway
St. Rail Overpass (the Project), as described in Article 4 of this Attachment 2, to help achieve the goals identified in the Notice of Funding Opportunity for Railroad Crossing Elimination Program, 87 Fed. Reg.
40335, July 6, 2022, that solicited applications for Federal financial assistance. FRA and the Recipient will accomplish that purpose by timely completing the Project and ensuring that this award does not substitute for non-Federal investment in the Project, except as proposed in the Application.
1.3 Program Designations
(a) Research and Development. This award not for research and development.
(b) Project Size. This award is for a non-Major Project as that term is defined in FRA Guidance on Development and Implementation of Railroad Capital Projects, January 11, 2023 (Railroad
Capital Projects Guidance).
(c) Phased Funding. This award is not a phased funding agreement as further discussed in
Section 6.7 of this Attachment 2.
(d) Grant or Cooperative Agreement. This award is made as a Grant Agreement
(e) Security Risk. This award is for a Project that has a low security risk.
(f) Rural Area. This award not for a Project in a Rural Area.
ARTICLE 2: SPECIAL TERMS AND CONDITIONS
Pursuant to the court’s preliminary injunction order in State of California v. Duffy, 1:25-cv-00208-JJM-PAS
(D.R.I.) (June 19, 2025), DOT will not impose or enforce the challenged immigration enforcement condition* or any materially similar terms and conditions, to any grant funds awarded, directly or indirectly, to Plaintiff States or local government entities within those States (collectively referred to as
“Plaintiff State Entities”), or otherwise rescind, withhold, terminate, or take other adverse action, absent specific statutory authority, based on the challenged immigration enforcement condition while DOT is subject to an injunction. DOT will not require Plaintiff State Entities to make any certification or other representation related to compliance the challenged immigration enforcement condition nor will DOT construe acceptance of funding from DOT as certification as to the challenged immigration enforcement condition.
*The challenged immigration enforcement condition:
“[T]he Recipient will cooperate with Federal officials in the enforcement of Federal law, including cooperating with and not impeding U.S. Immigration and Customs Enforcement (ICE) and other Federal offices and components of the Department of Homeland Security in the enforcement of Federal immigration law.”
ARTICLE 3: ADMINISTRATIVE INFORMATION
3.1 Application
Application Title: Galloway Street Vehicular and Pedestrian Rail Crossing Eliminations and Construction of
Galloway St. Rail Overpass and Connections to Trail and Ball Street in a Qualified Census Tract
Neighborhood
Application Date: October 10, 2022
3.2 FRA Awarding Official
FRA Office of Railroad Development
Federal Railroad Administration
1200 New Jersey Ave, SE
Washington, DC 20590
FRA-Grants@dot.gov
3.3 Federal Award Date
The “Federal Award Date” is the effective date of this Agreement, as defined under Section 25.2 of
Attachment 1 of this Agreement.
3.4 Program Name and Assistance Listings Number
For the FY 2022 Railroad Crossing Elimination Program, the Assistance Listings Number is 20.327 and the
Assistance Listings Title is Railroad Crossing Elimination.
3.5 Recipient’s Unique Entity Identifier
The Recipient’s Unique Entity Identifier, as defined at 2 C.F.R. § 25.415, is listed in Section 1B on the
Agreement cover sheet.
3.6 Federal Award Identification Number
The Federal Award Identification Number is listed in Section 2 on the Agreement cover sheet as the
“Agreement Number.”
ARTICLE 4: STATEMENT OF WORK
4.1 General Project Description
The Recipient will complete project development, final design, right-of-way acquisition, and construction for the elimination of two at-grade crossings, a vehicle crossing (USDOT Crossing Inventory Number:
921335H) and a pedestrian trail crossing (USDOT Crossing Inventory Number: 183949E), at the intersection of Galloway Street (St) and Union Pacific Railroad (UPRR) line. The project development work will only consist of National Environmental Policy Act (NEPA) work. The Recipient will replace the existing at-grade highway crossing as well as the pedestrian at-grade crossing with a new, grade-separated overpass. The new overpass will also make for a seamless connection between two segments of the
Chippewa River Regional Trail, which is currently divided by Galloway Street. This grade separation will eliminate a significant rail crossing in the downtown area and improve travel time for both vehicle commuters and pedestrians, eliminate accidents at the crossing, reduce idling emissions, eliminate vehicular traffic bottlenecks, and provide accommodation for expected future demand for both freight and commuter rail and vehicular traffic.
4.2 Project Location
The project is located in the downtown area of the City of Eau Claire, Wisconsin and is located east of
Banbury Place and Boyd Park pedestrian bridge, where Galloway Street has an at-grade UPRR rail crossing.
Galloway Street is the primary connecting route between downtown Eau Claire and the River Prairie development in the adjacent community of Altoona. The average daily traffic along Galloway Street is over 4,400 vehicles as of August 30, 2021. Galloway Street eventually connects with U.S. Highway 53, a well-used regional highway moving vehicular and truck traffic into the north and northwestern rural reaches of Wisconsin. The rail crossing is most accurately described as occurring at Latitude 44.8151540 degrees and at 91.4832950 Longitudinal degrees.
4.3 Project Scope
The Recipient will notify FRA in writing of any requested changes in Project Scope and will not proceed with the changed scope unless approved by FRA in writing. If approved, changes to Project Scope may require additional environmental review or an amendment to this Agreement.
Task 1: Project Administration and Management
Subtask 1.1: Project Administration
The Recipient will perform all tasks required for the Project through a coordinated process, which will involve affected railroad owners, operators, and funding partners, including:
• Eau Claire County
• Wisconsin Department of Transportation (WisDOT)
• Union Pacific Railroad (UPRR)
• FRA
The Recipient will facilitate the coordination of all activities necessary for implementation of the Project.
The Recipient will:
• complete necessary steps to hire a qualified consultant/contractor to perform required Project work, as necessary;
• hold regularly scheduled Project meetings with FRA;
• inspect and approve work as it is completed; and
• participate in other coordination, as needed.
The Recipient will demonstrate to FRA that it is carrying out the project benefits in the most cost-efficient manner.
Subtask 1.2: Project Management Plan
The Recipient will prepare a Project Management Plan (PMP), that describes how the Project will be implemented and monitored to ensure effective, efficient, and safe delivery of the Project on time and within budget. The PMP will describe, in detail, the activities and steps necessary to complete the tasks outlined in this Statement of Work.
The PMP will include a Project Schedule and Project Budget for the work to be performed under this
Agreement. The Project Schedule will be consistent with the Estimated Project Schedule in Section 5.2 of this Attachment 2 but provide a greater level of detail. Similarly, the Project Budget should be consistent with the Approved Project Budget in Section 6.5 of this Attachment 2 but provide a greater level of detail.
The Recipient will submit the PMP to FRA for review and approval. The Recipient will implement the
Project as described in the approved PMP. The Recipient will not begin work on subsequent tasks until
FRA has provided written approval of the PMP, unless FRA has provided pre-award authority for such work under Section 6.6 of this Attachment 2. FRA will not reimburse the Recipient for costs incurred in contravention of this requirement.
FRA may require the Recipient to update the PMP. The Recipient will submit any such updates to FRA for review and approval, and FRA will determine if updates to the PMP require an amendment to this
Agreement. The Project Budget and Project Schedule may be revised consistent with Article 5 of
Attachment 1 of this Agreement without amending this Agreement.
The Recipient will identify agreements governing the construction, operation, and maintenance of the
Project in the PMP. If requested by FRA, the Recipient will provide FRA the final, executed copies of any agreements within ten business days of the request.
The PMP will be consistent with the FRA Guidance on Development and Implementation of Railroad
Capital Projects (Railroad Capital Projects Guidance) and 49 U.S.C. § 22903, as applicable.
Subtask 1.3: Project Closeout
The Recipient will submit a Final Performance Report as required by Section 7.2 of Attachment 1 of this
Agreement, which should describe the cumulative activities of the Project, including a complete description of the Recipient’s achievements with respect to the Project objectives and milestones.
Task 1 Deliverables:
Deliverable ID Subtask Deliverable Name
1.1 1.2 Project Management Plan
1.2 1.3 Final Performance Report
Task 2: Environmental Review
The Recipient will develop environmental documentation as directed by FRA and in accordance with 23
CFR 771, 23 CFR 774, Section 106 of the National Historic Preservation Act (54 U.S.C. § 306108; 36 C.F.R.
part 800), and all other applicable federal environmental planning requirements. The anticipated National
Environmental Policy Act (NEPA) Class of Action (CoA) for this project is a Categorical Exclusion (CE). The
CoA is subject to change at FRA’s discretion. The Recipient will use qualified environmental and cultural resource professionals to evaluate the Project’s impacts on environmental and cultural resources; this may include but is not limited to performing literature and desktop reviews and field reconnaissance, preparing reports, facilitating public and/or agency review as required based on the CoA, requesting information from relevant resource or regulatory agencies, drafting consultation letters, participating in meetings with project partners, stakeholders and/or the public, and drafting NEPA documentation. The
Recipient will use and/or follow any existing FRA forms, templates, and/or guidance. The Recipient will identify potential environmental/cultural resources concerns early on and will coordinate with FRA to identify necessary studies and consultations in accordance with FRA’s NEPA regulations and other relevant environmental review requirements.
Task 2 Deliverables:
Deliverable ID Deliverable Name
2 Draft & Final Environmental Documentation
Task 3: Final Design
The Recipient shall not commence work on Task 3: Final Design, until FRA has approved all necessary documentation and FRA has given the Recipient notice to proceed to the final design.
The Recipient will prepare or cause to be prepared a final design (FD) package showing, as applicable, design plans, specifications, and estimates necessary to demonstrate the effectiveness, feasibility, and readiness of the Project to be bid and/or constructed by a contractor or in-house personnel. The FD package must include an engineer’s schedule, construction estimate, and documentation showing approval of the plan by the City of Evansville and other stakeholders impacted by the proposed Project as needed. FRA will review the FD package for acceptance.
Task 3 Deliverables:
3.1 Final Design Package
Task 4: Construction
The Recipient shall not commence work on Task 4: Construction related activities, including any right of way acquisition activities, until FRA has accepted the FD documents described in Task 3: Final Design, and
FRA has given the Recipient notice to proceed to construction.
The Recipient will complete or cause to be completed construction related activities, including right of way acquisition, as specified in the final design package accepted by FRA under Task 3: Final Design. Task
4 includes right of way acquisition, the procurement of materials, sitework, and any construction engineering related activities to accomplish the Project described in Article 4.1 of this agreement.
The Recipient is responsible for coordinating several utility relocations and completing real estate acquisition to connect Ball Street and Galloway Street. The Recipient will also complete road realignment at Galloway Street which will provide 23 feet of vertical clearance, providing clearance between the top of the tracks and the new bridge. The Recipient will construct a single span 80 ft long prestressed concrete girder bridge over the center line of tracks.
Task 4 Deliverables:
N/A N/A
Additional Task:
None.
4.4 Implement Required Environmental Commitments
The Recipient will consult FRA if it intends to perform ground-disturbing activities (i.e., geotechnical boring, trenching, tree clearing, vegetation removal, etc.) in support of design prior to the completion of the environmental review for the Project. The Recipient must not proceed with such activities until FRA has reviewed and provided in writing a notice to proceed. FRA will comply with all applicable federal laws and regulations including but not limited to Section 106 of the National Historic Preservation Act and
Section 7 of the Endangered Species Act.
The Recipient will implement any environmental commitments, Section 106 Programmatic Agreement
(PA), or Memorandum of Agreement (MOA), or any other documents or correspondence associated with the environmental review for the Project identified through the NEPA process conducted under Task 2:
Environmental Review.
ARTICLE 5: AWARD DATES AND ESTIMATED PROJECT SCHEDULE
5.1 Award Dates
Budget Period End Date: January 31, 2029
Period of Performance End Date: January 31, 2029
5.2 Estimated Project Schedule
Milestones associated with this Agreement are identified in Table 5-A: Estimated Project Schedule. The
Recipient will complete these milestones to FRA’s satisfaction by the Schedule Date, subject to Article 5 of Attachment 1 of this Agreement. The Recipient will notify FRA in writing when it believes it has achieved the milestone.
Table 5-A: Estimated Project Schedule
Milestone Schedule Date
NEPA Completion December 15, 2025
Final Design Completion February 11, 2026
Construction Substantial Completion February 15, 2028
ARTICLE 6: AWARD AND PROJECT FINANCIAL INFORMATION
6.1 Award Amount
Agreement Federal Funds: $9,999,600
6.2 Federal Obligation Information
Federal Obligation Type: Single
6.3 Federal Authorization and Funding Source.
Authorizing Statute: Sections 22104 and 22305 of the Infrastructure Investment and Jobs Act, Public Law
117-58 (November 15, 2021); 49 U.S.C. § 22909
Appropriation: Infrastructure Investment and Jobs Act, Division J, Title VIII (Public Law 117-58 (2021))
6.4 Funding Availability
Program funding that is obligated under this Agreement remains available until expended.
6.5 Approved Project Budget
The estimated total Project cost under this Agreement is $12,499,500.
FRA will contribute a maximum of 80 percent of the total Project cost, not to exceed the Agreement
Federal Funds in Section 6.1 of this Attachment 2. FRA will fund the Project at the lesser amount of the
Agreement Federal Funds or the FRA maximum contribution percentage of total Project costs.
The Recipient will contribute $2,499,900 in Agreement Non-Federal Funds. Recipient’s Agreement Non-
Federal Funds are comprised of cash contributions.
The Recipient will complete the Project to FRA’s satisfaction within the Approved Project Budget, subject to Article 5 of Attachment 1 of this Agreement.
Table 6-A: Approved Project Budget by Task
Task
Task Title Agreement
Federal Funds Agreement Non-
Federal Funds Total
Project Administration and Management
$80,000 $20,000 $100,000
Environmental Determination
$80,000 $20,000 $100,000
3 Final Design $1,194,240 $298,560 $1,492,800
4 Construction $8,645,360 $2,161,340 $10,806,700
Total $9,999,600 $2,499,900 Total Project Cost:
$12,499,500
Table 6-B: Approved Project Budget by Source
Funding Source Total Amount Percentage of Total
Project Cost
Federal Share $9,999,600 80%
Agreement Federal Funds - FRA FY22 RCE $9,999,600 80%
Agreement Non-Federal Funds $2,499,900 20%
City of Eau Claire $2,499,900 20%
6.6 Pre-Award Costs
None. Consistent with 2 C.F.R. part 200, costs incurred before the date of this Agreement are not allowable costs under this award. FRA will neither reimburse those costs under this award nor consider them as a non-Federal cost-sharing contribution to this award.
6.7 Phased Funding Agreement
Not applicable.
ARTICLE 7: PERFORMANCE MEASUREMENT INFORMATION
Table 7-A: Performance Measurement Table identifies the performance measures that this Project is expected to achieve. These performance measures will enable FRA to assess the Recipient’s progress in achieving grant program goals and objectives. The Recipient will report on these performance measures in accordance with the frequency and duration specified in Table 7-A.
Upon Project completion, the Recipient will submit reports comparing the actual Project performance of the new and or improved asset(s) against the pre-Project (baseline) performance and expected post-
Project performance as described in Table 7-A. The Recipient will submit the performance measures report to the Project Manager in accordance with Table 7-A.
Table 7-A: Performance Measurement Table
Goal Objective
Performance
Measure
Description of
Measure Measurement Reporting
Average
Daily
Traffic
Comparison of actual Average
Daily Traffic (ADT) post-construction versus the baseline
ADT pre-construction on
Galloway, Birch, and Main Streets
ADT Counts on
Galloway Street
Measure ADT yearly on Galloway pre and post overpass construction to determine if downtown commuters are avoiding residential routes and using improved
Galloway Street overpass
Pre-Project (Baseline) Performance as of Jan 2023:
Galloway St –
UPRR Crossing
ADT is 4,400
Frequency:
Annual
Expected Post- Project Performance:
Increased commuter traffic on Galloway and less ADT on Main
& Birch Streets
Duration:
For three years after the Performance
Period end date
Expected Post- Project Performance:
40-50 pedestrians and 20 bicyclists daily
Duration:
Three years after the Performance Period end date
Average
Vehicle
Speeds
Increased average speeds for vehicles on Galloway Street
Measure traffic volume and speed along
Galloway Street in both directions before and after construction of the overpass and crossing elimination.
Comparison of traffic speeds before and after construction
Pre-Project (Baseline) Performance as of August 2024:
30 miles per hour (MPH)
Frequency:
Annual
Expected Post- Project Performance:
35 miles per hour (MPH)
Duration:
Three years after the Performance Period end date
The Recipient will prepare a Project Outcomes Report pursuant to Section 8.3 of Attachment 1 of this
Agreement.
ARTICLE 8: ENVIRONMENTAL COMPLIANCE
In accordance with the National Environmental Policy Act (NEPA; 42 U.S.C. § 4321 et seq.), other environmental statutes, related regulatory requirements, and FRA’s NEPA-implementing regulations (23
C.F.R. part 771), FRA has determined that the actions funded under this Agreement as described in this
Attachment 2, Section 4.3, Task 2, are categorically excluded from detailed environmental review pursuant to 23 C.F.R. § 771.116 (c) (1), (3), and (8). In accordance with Section 106 of the National Historic
Preservation Act (54 U.S.C. § 306108; 36 C.F.R. part 800), FRA has also determined that the actions funded under this Agreement have no potential to cause effects to historic properties. The actions do not require the use of property protected by Section 4(f) of the Department of Transportation Act (49 U.S.C. § 303;
23 C.F.R. part 774).
Categorical exclusion (CE) means a category of actions that a Federal agency has determined normally do not have a significant impact on the quality of the human environment and therefore do not require either an environmental assessment (EA) or environmental impact statement (EIS). 42 U.S.C. § 4336e(1). In analyzing the applicability of a CE, FRA also considered whether unusual circumstances are present that would warrant a more detailed environmental review through the preparation of an EA or EIS. In accordance with 23 C.F.R. § 771.116 (a) and (b), FRA has further concluded that no unusual circumstances exist with respect to development of the activities funded under this grant that might trigger the need for a more detailed environmental review.
The Recipient will consult FRA if it intends to perform ground-disturbing activities (i.e., geotechnical boring, trenching, tree clearing, vegetation removal, etc.) in support of design prior to the completion of the environmental review for the Project. The Recipient must not proceed with such activities until FRA has reviewed and provided in writing a notice to proceed. FRA will comply with all applicable federal laws and regulations including but not limited to Section 106 of the National Historic Preservation Act and
Section 7 of the Endangered Species Act.
Should conditions or the scope of the action change, the Recipient must notify FRA and receive written response and notice to proceed before proceeding. FRA will evaluate whether this determination remains applicable or if additional environmental review is necessary.
The obligation of funds for Final Design (FD) does not predetermine or prejudice the outcome of the NEPA process for the project. The Recipient cannot commence any FD or construction activities until FRA has issued a written notice to proceed that will be informed by the final NEPA document, 23 CFR §
771.113(a)(1). As appropriate, FRA may require an amendment to this Agreement for consistency with its final NEPA decision.
In addition, all FD and/or construction activities must be supported by, and be consistent with, a final FRA-approved NEPA document (i.e., CE, FONSI, or ROD). If the project leads to/involves work outside of that considered by FRA in making its NEPA determination that may affect the environment, the Recipient must not allow the work to begin until the Recipient has informed FRA of such work and received a written notice to proceed from FRA. Before providing such notice to proceed to Recipient, FRA will determine what, if any, additional environmental review is required.
ARTICLE 9: LABOR AND WORK
9.1 Efforts to Support Good-Paying Jobs and Strong Labor Standards
This Section identifies the Recipient’s efforts to support good-paying jobs and strong labor standards related to the Project. The Recipient certifies that rows marked with “X” in the following table are accurate:
The Recipient or a project partner promotes robust job creation by supporting good-paying jobs directly related to the project with free and fair choice to join a union. (Describe robust job creation and identify the good-paying jobs in the supporting narrative below.)
The Recipient or a project partner will invest in high-quality workforce training programs such as registered apprenticeship programs to recruit, train, and retain skilled workers, and implement policies such as targeted hiring preferences.
The Recipient or a project partner will partner with high-quality workforce development programs with supportive services to help train, place, and retain workers in good-paying jobs or registered apprenticeships including through the use of local and economic hiring preferences, linkage agreements with workforce programs, and proactive plans to prevent harassment.
The Recipient or a project partner will partner with communities or community groups to develop workforce strategies.
The Recipient or a project partner has taken other actions related to the Project to create good-paying jobs with the free and fair choice to join a union and incorporate strong labor standards.
The Recipient or a project partner has not yet taken actions related to the Project to create good-paying jobs with the free and fair choice to join a union and incorporate strong labor standards but, before beginning construction of the Project, will take relevant actions described below.
X The Recipient or a project partner has not taken actions related to the Project to improve good-paying jobs and strong labor standards and will not take those actions under this award.