Attachment 2 - Pricing Schedule USCGC JAMES 70Z08526DLREP0002.xlsx
XLSX spreadsheet 28 KB Posted
- Attached to
- USCG JAMES DS FQ1 FY26
- Solicitation number
- 70Z08526DLREP0002
About this file
This file is a Pricing Schedule for the USCGC JAMES (WMSL-418) Dockside Availability in FY2026, prepared by 3MC Mobile & Mechanical Repair, LLC. The document details a comprehensive ship maintenance contract awarded by the US Coast Guard for $817,791.20, with services including grooming air conditioning plants, renewing side boat davits, inspecting fire detection systems, performing biennial maintenance on folding boom cranes, and cleaning/inspecting various tanks and systems.
The pricing breakdown includes 9 definite line items totaling $777,331.20 and 1 optional line item for tank preservation at $40,460.00. Labor rates are calculated at $95 per hour, with assumed overhead factors of 15% for G&A and 10% for profit. The contract covers multiple maintenance tasks across different ship systems, with work to be performed dockside and focusing on critical maritime vessel upkeep and repair services for the US Coast Guard.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOS&S
| PRICING SCHEDULE FOR: |
| USCGC JAMES (WMSL-418) DOCKSIDE AVAILABILITY FY2026 |
| ITEM | DESCRIPTION | UNIT PRICE | UNIT | QTY | EXTENDED PRICE |
| D-001 | Air Conditioning Plants, Groom | $239,941.20 | JOB | 1 | $239,941.20 |
| D-002 | Side Boat Davit, Renew | $217,872.00 | JOB | 1 | $217,872.00 |
| D-003 | Fire Detection System, Inspect and Test | $8,039.60 | JOB | 1 | $8,039.60 |
| D-004 | Folding Boom Cranes, Biennial Maintenance, Perform | $115,398.40 | JOB | 1 | $115,398.40 |
| D-005 | Potable Water Pneumatic Tank, Clean and Inspect | $7,040.00 | JOB | 1 | $7,040.00 |
| D-006 | Stern Boat Launch and Recovery, Level II | $154,580.00 | JOB | 1 | $154,580.00 |
| D-007 | Tanks (Aviation Fuel Service), Clean and Inspect | $7,820.00 | JOB | 1 | $7,820.00 |
| D-008 | Tanks (Aviation Fuel Stowage and Overflow), Clean and Inspect | $6,860.00 | JOB | 1 | $6,860.00 |
| D-009 | Tanks (Potable Water), Clean and Inspect | $8,800.00 | JOB | 1 | $8,800.00 |
| O-010 | Tanks (Potable Water), Preserve (Partial) - OPTIONAL | $40,460.00 | JOB | 1 | $40,460.00 |
| D-011 | Fire Prevention, Provide | $10,980.00 | JOB | 1 | $10,980.00 |
| O-00A | Composite Labor Rate | $95.00 | Hour | 0 | $0.00 |
| O-00Z | Laydays | Day | 0 | ||
| Total Price of Definite Items | $777,331.20 | ||||
| Total Price of Option Items | $40,460.00 | ||||
| Total Price of Definite and Optional Items | $817,791.20 |
3MC Mobile & Mechanical Repair, LLC PO Box 366 Hilliard, FL 32046
(9/15/2025)
Page &P of &N
CostEstimateBreakdowns
| Composite Labor Rate | 55 | |||||||||||||||||||||||
| Assumed G&A Factor | 15% | |||||||||||||||||||||||
| Assumed Profit Factor | 10% | Direct Labor | Direct Material/Subs Cost | |||||||||||||||||||||
| ITEM | DESCRIPTION | UNIT PRICE | Sub-Contracted (put a "1" in the blank) | Total Labor Hours | Total Material & Subs (cost + G&A + profit) | Eng Tech | Machinest/Pipe Fitter | Electrician | Shipfitter | Welder | Firewatch | Insulator/Lagger | Painter | Gen Labor/Helper/Rigger | Supt/QA/NDT | Mat/Sub Cost 1 | Mat/Sub Cost 2 | Mat/Sub Cost 3 | Mat/Sub Cost 4 | Lab Rate | Area | WorkItemID | WIFileID | LoadData |
| 62 | Baltimore, MD | |||||||||||||||||||||||
| 52 | Biloxi, MS | |||||||||||||||||||||||
| 56 | Boston, MA | |||||||||||||||||||||||
| 50 | Charleston, SC | |||||||||||||||||||||||
| 60 | Corpus Christi, TX | |||||||||||||||||||||||
| 51 | Hampton Roads | |||||||||||||||||||||||
| 64 | Honolulu, HI | |||||||||||||||||||||||
| 55 | Houston, TX | |||||||||||||||||||||||
| 56 | Los Angeles, CA | |||||||||||||||||||||||
| 55 | Median Rate | |||||||||||||||||||||||
| 49 | Miami | |||||||||||||||||||||||
| 50 | Narragansett Bay, RI | |||||||||||||||||||||||
| 55 | New London, CN | |||||||||||||||||||||||
| 45 | New Orleans | |||||||||||||||||||||||
| 62 | NYNY | |||||||||||||||||||||||
| 49 | Panama City, FL | |||||||||||||||||||||||
| 60 | Philadelphia, PA | |||||||||||||||||||||||
| 51 | Portland, ME | |||||||||||||||||||||||
| 57 | Portland, OR | |||||||||||||||||||||||
| 55 | San Diego, CA | |||||||||||||||||||||||
| 67 | San Francisco, CA | |||||||||||||||||||||||
| 55 | Santa Barbara, CA | |||||||||||||||||||||||
| 55 | SE North Carolina | |||||||||||||||||||||||
| 65 | Seattle, WA | |||||||||||||||||||||||
| 48 | Tampa-St. Petersburg | |||||||||||||||||||||||
| 60 | Wilmington, DE |
(09/28/2009)_x000D_ Page &P of &N
CostEstimateTemplate
File details come from the government source that posted it. Updated .