Attachment 2 - Performance Work Statement.pdf
PDF 193 KB Posted
- Attached to
- Paxton Locks
- Solicitation number
- FA460825QS024
About this file
This Performance Work Statement (PWS) details the requirements for installing a Paxton Access Control System in Building 6000 at Barksdale Air Force Base. The project involves installing 15 Paxton Access Control Units (ACUs) and Net2 Plus POE keypads at specified door locations, along with electric strikes, using new parts compatible with the existing Paxton system. The contractor must be a Paxton certified installer with at least 3 years of experience and provide three references from similar completed jobs.
Key specifications include installing ACUs, keypads, and wiring at locations approved by the Facility Manager, using specific components like US Net2 Pro Software, US Net2 Plus with POE, US Proximity Keypad KP75, and HES 9600 Electric Strikes. The installation must be completed within 30 days after the award date, with work performed during normal duty hours (0700-1630, Monday-Friday). The project is a 100% small business set-aside under NAICS code 561621, with a small business size standard of $25.0M, and will be awarded by the Department of the Air Force Global Strike Command's 2nd Contracting Squadron.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Performance Work Statement Install Paxton Access Control in Security Forces Building (Bldg. 6000)
OBJECTIVE: Install turn-key Paxton Access Control System throughout Bldg 6000 as outlined below.
All parts shall be new, used or refurbished strictly prohibited. Parts and pieces must be compatible with existing Paxton system.
QUALIFICATIONS:
1. Paxton certified installer with minimum 3-years experience.
2. Provide (3) references from recently completed similar jobs.
SCOPE OF WORK:
1. Install (15) Paxton Access Control Units (ACU’s) and Net2 Plus POE keypads at door locations where Facility Manager deems necessary
2. Install Electric Strikes where needed
3. Proposed ACU locations will be discussed with facility manager prior to doing any installs.
MATERIALS
1. Parts to be used:
Nomenclature/Part# UI Qty US Net2 Pro Software (To be turned over to 2 SFS) EA 1 Cabling and Misc Hardware EA 15 US Net2 Plus with POE EA 15 US Proximity Keypad KP75 EA 15 Electric Strike HES 9600 EA 9 Electric Strike HES 9600 EA 6 Black Box Network Services EA 2
2. Submittals required on all parts and pieces.
3. An area will be provided on or near work site as required to store contractors LOM.
SPECIFICS:
1. Install ACU, keypad and wire to MLR trigger provided by customer at the Facility Manager’s requested locations.
2. Install ACU, keypad and wire to ET provided by customer at Facility Manager’s requested locations.
3. Cut-in electric door strikes (ES’) and install ACU, keypad and applicable wiring harness at Facility
Manager’s requested locations.
4. There’s no old equipment to be removed from new ACU install locations.
5. Facility ceilings are suspended type.
6. No computers required.
7. No UPS’s required.
8. No CAD design required.
INSTALLATION
1. Each ACU installation location shall be discussed and approved by the facility manager prior to install.
2. Installation will be done in a neat and professional manner, to include but not limited to the use of mounting hardware and cable management.
3. Any damage to the facility caused by the contractor will be repaired by the contractor in conjunction with 2 CES.
FA460825QS024
Attachment 2
INSPECTION, TESTING and CERTIFICATION:
1. Each install location will be tested by 2 SFS facility manager to verify 100 percent serviceability.
WORKSITE LOCATION:
1. 1200 Chappie James Rd
(B6000) Barksdale AFB, LA 71110
2. Contractor Working Days/Hours:
a. Normal duty time M-F, 0700-1630
b. Days and hours can be adjusted as required with prior approval from 2 CONS and 2
SFS 48 hrs prior to a proposed change.
2 SFS Shall:
1. Coordinate contractor base access as required to complete project.
PERMITS:
1. No permits required for this project.
PERIOD OF PERFORMANCE:
ompleted NLT thirty 30 2 CONS and contractor will determine award date when funding becomes available
FA460825QS024
ACRONYMS
1. POE Power over Ethernet
2. ES Electrified Strike
3. EL Electrified Lock
4. ET Electrified Trim
5. MLR Motorized Latch Retraction
FA460825QS024