Attachment 2 Performance Requirements Summary Table.pdf

PDF 279 KB Posted

Attached to
DARTS Engineering Services SBIR Phase III Federal contract opportunity
Solicitation number
N6660421R0100
Issued by
Department of the Navy Naval Sea Systems Command

About this file

This document contains a performance requirements summary table and details of a related federal contract opportunity. The performance requirements summary table outlines technical requirements for engineering services to support the Data Analysis Reporting Tool Set (DARTS) program. Requirements include adapting, testing, installing, operating and maintaining the DARTS system aboard submarines and at test sites. Acceptable performance standards and quality levels are defined for each requirement.

The related federal contract opportunity is a sole source award to Progeny Systems for DARTS engineering services as a follow-on to previous Small Business Innovative Research funding. The five-year indefinite delivery, indefinite quantity contract valued at 258,330 man-hours will be issued by the Naval Undersea Warfare Center Division, Newport. The work involves developing and maintaining DARTS hardware and software variants to collect and analyze submarine non-propulsion electronic system data for test and evaluation reporting.

View the file

Other files for this federal contract opportunity

Other files attached to DARTS Engineering Services SBIR Phase III, newest first.
File Type Posted
Attachment 3 Requiring GFP Memo.pdf PDF
Exhibit A. CDRLs -_Redacted.pdf PDF
N6660421R0100.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Performance Requirements Summary Table

PR Number: 1300759772

Requirement (Task number and title from

SOW/PWS)

CDRL

(if applicable)

Performance Objective Performance Standard

Acceptable

Quality

Level

(AQL)

Monitoring Method

4.1

DARTS

DEVELOPMENT

Adapt the DARTS system as required to support installation on board USS VIRGINIA and in-service submarines being constructed or going through a post shakedown availability (PSA).

Changes are technically/operationally sound and compatible with platforms.

Standard is met 90% of the time.

Government feedback from Project

Managers upon review and execution of services provided.

Upgrade the DARTS hardware and software as needed for NPES or C3I

Systems.

Modifications and upgrades provide improvement.

Interfaces function properly.

Standard is met 90% of the time.

Government feedback from Project

Managers upon review and execution of services provided.

4.2

TEST

PREPARATION

Identify the data collection requirements for test events and prepare a DARTS variant to support those test events.

Services provided are technically accurate, complete, and are provided in accordance with all approved schedules.

Standard is met 90% of the time.

Government feedback from Project

Maintain Configuration Management of each DARTS variant in use.

Database is accurate and complete.

Standard is met 95% of the time.

Government feedback from Project

Conduct DARTS demonstrations at specified facilities in preparation for test events.

Services provided are technically accurate, complete, and are provided in accordance with all approved schedules.

Standard is met 90% of the time.

Government feedback from Project

Deliver test plans and procedures prior to each at-sea test.

Services provided are technically accurate, complete, and are provided in accordance with all approved schedules.

Standard is met 90% of the time.

Government feedback from Project

Managers upon review and execution of services provided.

4.3

INSTALLATION

AND REMOVAL

Install DARTS on specified submarines.

Services provided are technically accurate, complete, and are provided in accordance with all approved schedules.

Standard is met 90% of the time.

Government feedback from Project

Coordinate TEMPALT’s as needed to support installation and removal of

DARTS.

No installation delays.

Platform approvals made in advance.

Standard is met 90% of the time.

Government feedback from Project

Accommodate DARTS removal and shipping.

Classified Security and all approved schedules maintained.

Standard is met 90% of the time

Government feedback from Project

Managers upon review and execution of services provided.

4.4

TEST

CONDUCT

Conduct testing of DARTS during dockside and at-sea test periods, to include training NUWC Test Team members on DARTS operation and maintenance.

Services provided are technically accurate, complete, and are provided in accordance with all approved schedules.

Standard is met 90% of the time.

Government feedback from Project

Prepare, setup, and operate Mobile office that will accommodate remote

DARTS maintenance, calibration, and upgrades.

Budget constraints maintained. Full functionality provided.

Standard is met 90% of the time.

Government feedback from Project

Managers upon review and execution of services provided.

4.5

DATA

MANAGEMENT,

ANALYSIS AND

REPORTING

Maintain two databases for test data.

Databases contain required

System data completely and accurately.

Standard is met 95% of the time.

Government feedback from Project

Maintain accountability for all test data.

Mandated System data is recorded and is correct.

Standard is met 95% of the time.

Government feedback from Project

Deliver test reports after each at-sea test.

Reports are delivered according to schedule and provide mandated metrics.

Standard is met 95% of the time.

Government feedback from Project

Managers upon review and execution of services provided.

4.6

MAINTENANCE

AND STORAGE

Provide DARTS maintenance services including Systems updates.

Engineering services provided are technically accurate.

Standard is met 90% of the time.

Government feedback from Project

Provide for off-hull storage of the

DARTS system when it is not in operational use.

Accountability for equipment maintained.

Standard is met 95% of the time.

Government feedback from Project

Mobile office at test sites will accommodate all DARTS system maintenance.

Budget constraints maintained. Full functionality provided.

Standard is met 90% of the time.

Government feedback from Project

Managers upon review and execution of services provided.

5.0

PROGRESS

REPORTS

Submit a Monthly Report documenting technical progress and tracking program milestones.

Deliverable products are technically accurate and customer acceptable.

Standard is met 90% of the time.

Government feedback from Project

File details come from the government source that posted it. Updated .