Attachment 2. Specifications.pdf

PDF 434 KB Posted

Attached to
Vehicle Lifts Installation
Solicitation number
2441926Q0031
Issued by

About this file

This document is a specifications package for a federal construction contract to install vehicle lifts at Fort Simcoe Job Corps Civilian Conservation Center in White Swan, Washington. The project requires removal of existing vehicle lifts and installation of three government-furnished lifts in the Auto Repair Shop building, including concrete slab demolition and reinforced concrete installation per specifications, as well as modification or installation of electrical branch circuits, wiring, conduit, breakers, disconnects, pneumatic shop air system connections, anchors, and testing of new lifts. Work hours are 8:00 AM to 4:30 PM Monday through Friday, with a pre-construction conference required within 10 days of award and bonds due 10 days after award. The contract includes a single Base Item (B121 Install Government Furnished Lifts) measured as a lump sum, with action and informational submittals due 12 days after Notice to Proceed and weekly progress reports required thereafter. All work must comply with ICC codes, NFPA standards, ABA accessibility standards, and manufacturer instructions, with electrical work performed by state-licensed electricians or apprentices under direct supervision. The project is exempt from state permitting but requires third-party inspection by a state-licensed or ICC-certified inspector at the contractor's expense.

The specifications sections address general requirements, cutting and patching, selective demolition, cast-in-place concrete (Class C, 4500 psi minimum), general-service compressed-air piping (copper or galvanized steel with flexible connectors to lifts), and electrical work including raceways, conductors, and support installation. Lead paint considerations apply given the age of existing structures, requiring lead-safe work practices. Closeout procedures mandate substantial completion inspection, punch list completion, final cleaning, and contract release within 10 days of CO acceptance. The contracting officer will determine which deficiencies identified during inspection must be corrected. No optional items or set-asides are indicated, and all pricing must be provided for the specified work scope.

View the file

Other files

File Type Posted
Attachment 4. Wage Determination.pdf PDF
12441926Q0031.pdf PDF
Attachment 3. Drawings.pdf PDF
Attachment 1. Schedule of Items.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

VEHICLE LIFT INSTALLATIONS 010150 – 1

FORT SIMCOE JOB CORPS CCC GENERAL REQUIREMENTS

SECTION 010150

GENERAL REQUIREMENTS

PART 1 – SUMMARY OF WORK

1.1 DESCRIPTION

A. Work for this project requires the contractor to be responsible for supplying all labor, materials, equipment, utilities, miscellaneous items, freight and delivery and all necessary valid licenses for the work summarized as follows:

1. Remove existing vehicle lifts and install government furnished lifts. Demo concrete slab and install reinforced concrete per detail for new lift support (two-post lift). Furnish and install modification, extension, or new branch circuits (as applicable) for new lifts, including wiring, conduit, breakers, disconnects, connection to pneumatic (shop air) system as applicable, anchors, testing and adjusting of new lifts.

1.2 LOCATION

A. This project is located at the Fort Simcoe Job Corps Civilian Conservation Center located nine miles from White Swan, Washington in Yakima County. The address is 40 Abella Ln, White Swan, WA 98952. Driving instructions can be obtained from the Center by calling 509-874-8954.

1.3 WORK HOURS

A. Work hours for this project are between 8:00 AM-4:30 PM Monday through Friday.

1.4 USE OF PREMISES

A. Confine constructions operations to immediate area of work. Do not disturb portions of Project site beyond areas in which the Work is indicated.

B. Government will occupy site and buildings during entire construction period. Cooperate with Government during construction operations to minimize conflicts and facilitate Government usage. Perform the work so as not to interfere with Government's day-to-day operations.

C. Keep driveways, parking areas, loading areas and entrances to buildings clear and available to Government, Government's employees, and emergency vehicles at all times.

Do not use these areas for parking or storage of materials. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from Government.

VEHICLE LIFT INSTALLATIONS 010150 – 2

1.5 DEFINITIONS

A. The following terms in any combination relating to the installation of products/materials:

install, furnish, provide, or similar statements; mean that the contractor is responsible for the procurement and installation of the products unless it is specifically designated as either a government furnished item, supply only product, or spare.

1.6 INCIDENTAL CONSTRUCTION

A. Performance of the specific tasks indicated in the plans and specifications may require incidental construction including that is not specifically included in drawings and specification but not limited to: provision of temporary shoring or supports, installation and subsequent removal of temporary access points, removal and reinstallation or relocation of items not designated for replacement as required for work or equipment clearance or as a precautionary protective measure. Disconnection of supporting or interconnection equipment between different systems and reconnection to new equipment as applicable to specific project requirements; examples include but are not limited to:

fire alarm components and interconnection/control for HVAC air handling equipment, cleaning chemical equipment for dishwashers, electric bonding for conductive water piping replacement, etc. In all cases the contractor shall be responsible for removal of temporary works, reinstallation of temporarily relocated items, or reconstruction of items selectively demolished for incidental construction purposes in a neat workman like manner, that matches existing finishes, quality standards, and code requirements unless the Contracting Officer specifically authorizes incidental construction to be incorporated into the finished work or items removed for coordination purposes to not be re-installed or reconstructed. The Contractor shall provide turn-key fully operational and finished installations unless the drawings and specifications specifically indicate otherwise.

1.7 STANDARDS AND CODES

A. All contract work shall adhere to the most recent version of:

1. All the International Code Council Family of codes (ICC) e.g. International

Building Code (IBC), International Fire Code (IFC), and International Mechanical Code (IMC).

2. All National Fire Protection Association (NFPA) codes and Standards e.g. , NFPA 70: National Electrical Code (NEC), NFPA 1: Fire Code, and NFPA 101- Life Safety Code.

3. Architectural Barriers Act Standards (ABA or ABAAS).

4. Product Manufacturer’s installation instructions.

1.8 QUALIFICATIONS

A. When applicable to specific contract work items:

1. Electrical work shall be performed by journey level electricians licensed in the

State of contract performance or trainees/apprentices working under the direct supervision of State-licensed electrical supervisors (or State equivalent).

VEHICLE LIFT INSTALLATIONS 010150 – 3

1.9 ELECTRICAL INSPECTIONS

A. This Federal contract is exempt from State permitting requirements. However, electrical work must be inspected by a third-party Inspector who is either State-licensed or ICC-certified. The Contractor will arrange for the inspection and pay any fees required for the inspection and associated report; arrangement may include completion and submission of load calculations, permit applications, and any other required coordination. The Inspector does not have any jurisdictional authority on Federal projects. The USFS is the jurisdiction having authority. The inspection will be based on the most recent version of the NFPA 70 National Electric Code (NEC) and currently adopted State codes. A list of deficiencies with corresponding code reference is to be provided in a report signed by the inspector. The addressee in the report is to be the Job Corps Center. The Inspector will provide a copy of their current inspection credentials with the inspection report. The Contractor will submit the report to the COR. The CO will determine which deficiency/violations will be enforced for the Contractor to fix.

1.10 WORK RESTRICTIONS

A. Smoking is permitted on campus only in the designated smoking area.

1.11 SCHEDULE OF ITEMS

A. Schedule of Items:

1. Provide pricing for all items listed in the Schedule of Items.

2. Contract award will be made for all Base Items.

3. Optional Items may or may not be awarded, depending on funding availability.

B. Base Items (BI):

1. Base Item No. 1 –B121 Install Government Furnished Lifts

a. Measurement: This item is measured as a Lump Sum quantity.

b. Payment: The contract lump sum price as shown in the Schedule of Items includes all materials, equipment, labor and incidentals to install three government furnished vehicle lifts in the Auto Repair Shop building, including related work indicated in the plans.

c. Deficiencies: #NA.

VEHICLE LIFT INSTALLATIONS 010150 – 4

PART 2 – PROJECT SCHEDULE

2.1 PROJECT SCHEDULE

ITEM* REQUIRED DUE DATE (calendar days)

Pre-Construction Conference

Within 10 days of Award (virtually)

Bonds 10 days after Award

Notice To Proceed (NTP)

Issued after Pre-Construction Conference (insurance and bonds acceptance required prior to NTP)

Action and Informational Submittals

12 days after NTP (CORs have 12 days to return)

Progress Reports Every 7 days after NTP is issued.

Closeout Submittals

Prior to CO acceptance of project

Contract Release form and final pay request

10 days after CO acceptance of project

* All items above must be included in Contractor’s construction schedule

PART 3 – SUBMITTAL PROCEDURES

3.1 DEFINITIONS

A. Action Submittals: Written and graphic information that requires Government approval.

B. Informational Submittals: Written information that does not require Government approval. Submittals may be rejected for not complying with requirements.

VEHICLE LIFT INSTALLATIONS 010150 – 5

3.2 PROCEDURES

A. Contractor Responsibilities

1. Review each submittal and check for compliance with the Contract Documents.

2. Highlight, encircle, or otherwise identify deviations from the Contract Documents on submittals.

3. Include the following information on label or cover sheet for processing and recording action taken:

a. Project name.

b. Date.

c. Name and address of Contractor.

d. Name of manufacturer.

e. Unique identifier, including revision number.

f. Number and title of appropriate Specification Section.

g. Drawing number and detail references, as appropriate.

h. Date of Contractor’s approval.

i. Statement certifying that submittal has been reviewed, checked, and approved by the Contractor for compliance with the Contract Documents.

4. The Government will not review submittals that do not bear Contractor's approval and will return them without action.

5. Unless additional copies are required for final submittal, and unless the

Contracting Officer (CO) observes noncompliance with provisions of the Contract Documents, initial submittal may serve as final submittal.

6. Submittals must be submitted in electronic PDF format. Submit to CO via email or electronic file transfer site.

7. Only final submittals with mark indicating action taken by Government are to be used for construction.

8. Submittals not required by the Contract Documents will not be reviewed and may be discarded.

B. Processing Time: Time for review shall commence on CO's receipt of submittal.

1. Initial Review: Government will review initial submittal within 12 calendar days.

Additional time may be needed if processing must be delayed to permit coordination with subsequent submittals. CO will advise Contractor when a submittal being processed must be delayed for coordination.

2. Resubmittals: If resubmittal is necessary, it will be resubmitted within 3 calendar days, and reviewed by the Government within 3 calendar days.

3.3 ACTION SUBMITTALS

A. Prepare and submit Action Submittals required in the Technical Specifications in this contract, if applicable, and as indicated at the end of this subsection.

B. Collect information into a single submittal for each element of construction and type of product or equipment.

VEHICLE LIFT INSTALLATIONS 010150 – 6

1. Mark up each submittal to show which products and options are applicable.

2. Include the following information, as applicable:

a. Manufacturer's written recommendations.

b. Manufacturer's product specifications.

c. Manufacturer's installation instructions.

d. Manufacturer's catalog cuts.

e. Wiring diagrams showing factory-installed wiring.

f. Compliance with recognized trade association standards.

g. Compliance with recognized testing agency standards.

C. Required Action Submittals

1. Product Data: See Technical Specification Sections

3.4 INFORMATIONAL SUBMITTALS

A. Prepare and submit Informational Submittals required in the Technical Specifications in this contract, if applicable, and as indicated below:

B. Required Informational Submittals:

1. Accident Prevention Plan.

2. Construction Schedule.

3. Current licensure and/or certifications for individuals indicated in

QUALIFICATIONS paragraph above or as required in individual technical sections.

3.5 PROGRESS REPORTS

A. The contractor shall prepare and submit weekly progress reports during the course of construction. The reports shall include a narrative description of work in progress and completed during the week with a note on any delays not accounted for in the approved progress schedule. Photos of the work in place shall also be included; photos should consist of both macro (close up detail –e.g. to demonstrate finish quality or equipment data plate) and overview photos that demonstrate the construction phase, larger areas of work in the context of the surrounding area. Photos shall document key construction areas e.g. primary structural member installation, utilities that will be covered by later construction, any damage discovered or caused by the construction and shall be annotated with location information. A substantial completion report shall also be submitted documenting fulfillment of contract requirements. If a punchlist is created; the Contractor shall provide a punchlist completion report prior to contract closeout.

3.6 CLOSEOUT SUBMITTALS

A. Prepare and submit Closeout Submittals, as follows:

1. See Technical Specification Sections.

VEHICLE LIFT INSTALLATIONS 010150 – 7

2. One-Year Warranty on Entire Project as required by FAR 52.246–21

PART 4 – TEMPORARY FACILITIES AND CONTROLS

4.1 USE OF UTILITIES

A. Utilities: Use of Government existing facilities will be permitted without metering and without payment of use charges, as long as facilities are cleaned and maintained in an acceptable condition. At Substantial Completion, restore these facilities to condition existing before initial use. The following are available for use by the contractor: water, and electrical power services. The following are not available: telephone service. The contractor is expected to provide whatever phone service he deems necessary for the duration of the project.

4.2 SANITARY FACILITIES

A. Sanitary facilities are available for use by the Contractor. Facilities must be cleaned and maintained daily.

4.3 STAGING AND STORAGE

A. Coordinate on-site staging and storage requirements with the Center Point of Contact or the Contracting Officer Representative (COR).

4.4 CONSTRUCTION WASTE DISPOSAL FACILITIES

A. Provide waste-collection containers in sizes adequate to handle waste from construction operations. Containerize and clearly label hazardous, dangerous, or unsanitary waste materials separately from other waste. Use of Government waste containers will not be permitted.

4.5 SAFETY AND ENVIRONMENTAL PROTECTION

A. Environmental Protection: Contractor shall provide protection, operate temporary facilities, and conduct construction in ways and by methods that comply with environmental regulations and that minimize possible air, waterway, and subsoil contamination or pollution or other undesirable effects.

B. Due to the age of most Job Corps structures, any painted surfaces should be considered potentially lead painted; these facilities are not considered child occupied facilities subject to the RRP but contractors disturbing painted surfaces via cutting, sanding, grinding, and similar dust generating activities shall adhere to the principals of lead safe work practices including as applicable wetting surfaces before disturbance to minimize dust generation, capture with HEPA vacuum when dust generation can't be avoided, personal protective equipment use for employees, and prompt cleanup and disposal of waste generated by construction and demolitions activities.

VEHICLE LIFT INSTALLATIONS 010150 – 8

C. Barricades, Warning Signs, and Lights: Comply with the national or state Manual on Uniform Traffic Control Devices (MUTCD) for erecting structurally adequate barricades, paint with appropriate colors, graphics, and warning signs/lights to inform personnel, students, and the public of possible hazards.

D. Fire Protection.

1. Store combustible materials in containers in fire-safe locations.

2. Maintain unobstructed access to fire extinguishers, fire hydrants, fire-protection facilities, stairways, and other access routes for firefighting. Prohibit smoking in hazardous fire-exposure areas.

3. Supervise welding operations, combustion-type temporary heating units, and similar sources of fire ignition.

PART 5 – EXECUTION REQUIREMENTS

5.1 EXAMINATION

A. Before beginning work, examine areas and document existing conditions. Proceed with installation only after unsatisfactory conditions have been corrected. Proceeding with the Work indicates acceptance of surfaces and conditions.

B. Field verify all new and existing dimensions affecting the work of this contract before ordering products.

C. Immediately on discovery of the need for clarification of the Contract Documents, submit a request for information to CO. Include a detailed description of problem encountered, together with recommendations for changing the Contract Documents.

5.2 INSTALLATION

A. Locate the Work and components of the Work accurately, in correct alignment and elevation to fit with existing construction.

B. Make vertical work plumb and make horizontal work level.

C. Install per manufacturer's written instructions and recommendations.

5.3 PROGRESS CLEANING

A. Clean Project site and work areas daily, including common areas. Dispose of materials lawfully.

1. Comply with NFPA 241 requirements for removal of combustible waste materials and debris.

2. Do not hold materials more than 7 days during normal weather or 3 days if the temperature is expected to rise above 80 deg F (27 deg C).

VEHICLE LIFT INSTALLATIONS 010150 – 9

B. Burying or burning waste materials on-site will not be permitted. Washing waste materials down sewers or into waterways will not be permitted.

5.4 PROTECTION OF INSTALLED CONSTRUCTION

A. Provide protection and maintain conditions that ensure installed Work does not get damaged or deteriorated prior to Substantial Completion.

5.5 CORRECTION OF THE WORK

A. Repair or remove and replace defective construction. Restore damaged substrates and finishes.

1. Repairing includes replacing defective parts, refinishing damaged surfaces, touching up with matching materials, and properly adjusting operating equipment.

PART 6 – CLOSEOUT PROCEDURES

6.1 SUBSTANTIAL COMPLETION

A. Definition of Substantial Completion: The Date certified by the CO when construction is sufficiently complete, in accordance with the Contract Documents, so the Government can occupy or utilize the Work or designated portion thereof for the use for which it is intended, as expressed in the Contract Documents.

B. Preliminary Procedures: Before requesting inspection for determining date of Substantial Completion, complete the following. List items below that are incomplete in request.

1. Prepare a list of items to be completed and corrected (punch list), the value of items on the list, and reasons why the Work is not complete.

2. Advise the CO of pending insurance changeover requirements.

3. Submit specific warranties, workmanship bonds, final certifications, and similar documents.

4. Obtain and submit releases permitting Government unrestricted use of the Work and access to services and utilities.

5. Deliver tools, spare parts, extra materials, and similar items to location designated by Government. Label with manufacturer's name and model number where applicable.

6. Complete startup testing of systems.

7. Submit changeover information related to Government occupancy, use, operation, and maintenance.

8. Complete final cleaning requirements, including touchup painting.

9. Touch up and otherwise repair and restore marred exposed finishes to eliminate visual defects.

VEHICLE LIFT INSTALLATIONS 010150 – 10

C. Inspection: Submit a written request for inspection for Substantial Completion. On receipt of request, CO will either proceed with inspection or notify Contractor of unfulfilled requirements. CO will prepare the Certificate of Substantial Completion after inspection or will notify Contractor of items, either on Contractor's list or additional items identified by CO, that must be completed or corrected before certificate will be issued.

1. Reinspection: Request reinspection when the Work identified in previous inspections as incomplete is completed or corrected.

2. Results of completed inspection will form the basis of requirements for Final

Completion.

6.2 FINAL COMPLETION

A. Preliminary Procedures: Before requesting final inspection for determining date of Final Completion, complete the following:

1. Submit certified copy of CO’s Substantial Completion inspection list of items to be completed or corrected (punch list), endorsed and dated by CO. The certified copy of the list shall state that each item has been completed or otherwise resolved for acceptance.

2. Submit evidence of final, continuing insurance coverage complying with insurance requirements.

3. Instruct Government personnel in operation, adjustment, and maintenance of products, equipment, and systems.

B. Inspections: Submit a written request for final inspection for acceptance. On receipt of request, CO will either proceed with inspection or notify Contractor of unfulfilled requirements. CO will prepare a final Certificate for Payment after inspection or will notify Contractor of construction that must be completed or corrected before certificate will be issued.

1. Reinspection: Request reinspection when the Work identified in previous inspections as incomplete is completed or corrected.

6.3 LIST OF INCOMPLETE ITEMS (PUNCH LIST)

A. Preparation: Submit two copies of list. Include name and identification of each space and area affected by construction operations for incomplete items and items needing correction including, if necessary, areas disturbed by Contractor that are outside the limits of construction.

6.4 FINAL CLEANING

A. General: Provide final cleaning. Conduct cleaning and waste-removal operations to comply with local laws and ordinances and Federal and local environmental and antipollution regulations.

VEHICLE LIFT INSTALLATIONS 010150 – 11

B. Cleaning Agents: Use cleaning materials and agents recommended by manufacturer or fabricator of the surface to be cleaned. Do not use cleaning agents that are potentially hazardous to health or property or that might damage finished surfaces.

C. Complete the following cleaning operations before requesting inspection for certification of Substantial Completion for entire Project or for a portion of Project:

1. Clean Project site, yard, and grounds, in areas disturbed by construction activities, including landscape development areas, of rubbish, waste material, litter, and other foreign substances.

2. Remove tools, construction equipment, machinery, and surplus material from Project site.

3. Touch up and otherwise repair and restore marred, exposed finishes and surfaces.

Replace finishes and surfaces that cannot be satisfactorily repaired or restored or that already show evidence of repair or restoration.

D. Remove waste materials from Project site and dispose of lawfully.

END OF SECTION 010150

VEHICLE LIFT INSTALLATIONS 017329 - 1

FORT SIMCOE JOB CORPS CCC CUTTING AND PATCHING

SECTION 017329 – CUTTING AND PATCHING

PART 1 - GENERAL

1.1 RESPONSIBILITIES

A. If the Project involves a General Construction Contractor, the General Construction Contractor shall be responsible for the cutting of openings with area equal to or greater than thirty-six (36) square inches. The cutting of openings with area less than thirty-six (36) square inches shall be the responsibility of the Separate Prime Contractor whose work requires the cutting. The General Construction Contractor shall be responsible for all patching work, regardless of the size of the opening.

B. If the cutting of openings into newly constructed walls, partitions, floors, or ceilings is required due to lack of coordination between Separate Prime Contractors, or due to ill-timed or defective work by one or more Separate Prime Contractors, the Separate Prime Contractor primarily responsible for the lack of coordination or the ill-timed or defective work shall bear all costs involved in cutting and patching. The Government may direct the General Construction Contractor to actually perform the cutting and patching.

C. If the Project does not involve a General Construction Contractor, cutting and patching shall be the responsibility of the Separate Prime Contractor whose work requires the cutting. The Contractor shall employ competent individuals, approved by the Government, to do the cutting and patching.

1.2 SUBMITTALS

A. When cutting and patching procedures are required to be approved prior to the work, the Contractor shall submit a plan for cutting and patching well in advance of the work. The submittal shall describe the procedures and request approval to proceed. The submittal shall include the following, as applicable and be submitted per 010150 Submittal procedures.

1. A description of the limits of cutting and patching required, how it is to be performed, and why it cannot be avoided.

2. A description of the anticipated results in terms of changes to existing construction, including changes to structural elements and operating components as well as changes in the building's appearance and other significant visual elements.

3. A listing of products to be used and firms or entities that will perform work.

4. Identification of the dates when cutting and patching is to be performed.

5. Identification of any utilities that will be distributed or affected, including those that will be relocated and those that will be temporarily out of service, and an indication of how long service will be disrupted.

6. Where cutting and patching involves addition of reinforcement to structural elements, details and engineering calculations to show how reinforcement is integrated with the original structure.

VEHICLE LIFT INSTALLATIONS 017329 - 2

B. Approval by the Government to proceed with cutting and patching does not waive the right of the Government to later require complete removal and replacement of any part of the work found to be unsatisfactory.

1.3 MATERIALS

A. Materials used shall be identical to existing materials.

B. If identical materials are not available or cannot be used where exposed surfaces are involved, materials used shall match existing adjacent surfaces to the fullest extent possible with regard to visual effect.

C. All materials used shall have installed performance equal or greater than that of existing materials.

D. All materials used shall be compatible with adjacent existing materials and shall have no deleterious effect on the existing construction.

1.4 INSPECTION

A. Before cutting existing surfaces, the Contractor shall examine surfaces to be cut and patched and conditions under which cutting and patching are to be performed.

B. The Contractor shall avoid any unsafe or unsatisfactory conditions, and if unsafe or unsatisfactory conditions are encountered, corrective action shall be taken before proceeding.

1.5 PREPARATION

A. Work to be cut shall be provided with temporary support.

B. Existing construction shall be protected during cutting and patching to prevent damage by cutting and patching operations.

C. Protection from adverse weather conditions shall be provided for portions of the project that might be exposed during cutting and patching operations.

D. Cutting and patching operations shall be conducted so as to avoid interference with use of adjoining areas or interruption of free passage to adjoining areas.

E. The Contractor shall take all precautions necessary to avoid cutting existing pipe, conduit, or ductwork that serve the facility and are scheduled to be removed or relocated, until provisions have been made for bypass installations.

VEHICLE LIFT INSTALLATIONS 017329 - 3

1.6 PERFORMANCE, GENERAL

A. Skilled workmen shall be employed to perform cutting and patching.

B. Cutting and patching shall be undertaken at the earliest feasible time and completed without delay.

C. Cutting, fitting, and patching for installation of components or the performance of other construction activities shall be performed so as to restore surfaces to their original condition.

D. Openings shall be temporarily covered when not in use.

E. Where excavating and backfilling are required, the Contractor shall comply with requirements of applicable sections of the Technical Specifications.

F. For utility services shown or required to be removed, relocated, or abandoned, the Contractor shall ensure the utility service is shut off or not active prior to performing any work on the system. If the utility service requires continued operation during the Work, the Contractor shall by-pass the service before cutting service pipe or conduit. Any pipe or conduit that is to remain shall be sealed with a cap, valve, or plug to prevent entrance of moisture or other foreign matter.

1.7 PERFORMANCE, CUTTING

A. Cutting of existing construction shall be performed using methods least likely to damage elements to be retained or adjoining construction. Where possible, proposed procedures shall be reviewed with the original installer and shall comply with the original installer's recommendations.

B. Where cutting is required, hand or small power tools designed for sawing or grinding shall be used. Hammering and chopping shall not be done. Holes and slots shall be cut neatly to the size required with minimum disturbance of adjacent surfaces.

C. To avoid marring existing finished surfaces, cutting or drilling shall be done from the exposed or finished side into concealed surfaces.

D. A cutting machine such as a carborundum saw, or diamond core drill shall be used to cut through concrete and masonry.

1.8 PERFORMANCE, PATCHING

A. Patching shall be performed with durable seams that are as invisible as possible. Patching shall meet specified tolerances.

B. Where feasible, patched areas shall be inspected and tested to demonstrate integrity of the installation.

C. Exposed finishes of patched areas shall be restored, and finished restoration shall be extended into retained adjoining construction in a manner that will eliminate evidence of patching and refinishing.

VEHICLE LIFT INSTALLATIONS 017329 - 4

D. Where patching occurs in a smooth painted surface, the final paint coat shall be extended over entire wall plane (wall corner to corner) containing the patch. The patched area itself shall receive a primer and second coat.

E. Where the removal of walls or partitions extends from the new space into another existing space, the floor and wall surfaces in the new space shall be patched and repaired to provide an even surface of uniform color and appearance. If uniform color and appearance cannot be achieved, the existing floor and wall coverings in the existing space shall be removed and replaced with new materials.

F. Existing ceilings shall be patched, repaired, or re-hung as necessary to provide an even plane surface of uniform appearance.

1.9 COORDINATION

A. Structural elements shall not receive any cutting and patching that would reduce their load-carrying capacity or load-deflection ratio. Structural elements include:

1. Foundation construction

2. Bearing and retaining walls

3. Structural concrete

4. Structural steel

5. Lintels

6. Structural decking

7. Stair systems

8. Miscellaneous structural metals

9. Exterior curtain wall construction

10. Equipment supports.

11. Piping, ductwork, vessels, and equipment

12. Structural systems of Special Construction in the Technical Specifications

B. Safety-related components and operating elements shall not receive cutting and patching in a manner that would result in reducing their capacity to perform as intended, result in increased maintenance, or result in decreased operational life or safety. For those components and elements covered by a warranty, the Contractor shall coordinate cutting and patching with the warranting party, and the cutting and patching shall not void the warranty. Safety-related components and operating elements include:

1. Shoring, bracing, and sheeting.

2. Primary operational systems and equipment

3. Air or smoke barriers

4. Water, moisture, or vapor barriers

5. Membranes and flashings

6. Roofing systems and membranes

7. Fire protection systems

8. Noise and vibration control elements and systems

9. Control systems

10. Communication systems

11. Conveying systems

12. Electrical wiring systems

13. Special Construction specified in the Technical Specifications

VEHICLE LIFT INSTALLATIONS 017329 - 5

C. Visually-exposed components and construction that is exposed on the exterior or exposed in occupied spaces shall not receive cutting and patching in a manner that will reduce the building's aesthetic qualities or result in visual evidence of cutting and patching. If possible, the original installer or fabricator shall be retained to cut and patch the following categories of exposed work:

1. Processed concrete finishes.

2. Ornamental metal

3. Matched-veneer woodwork.

4. Window wall system

5. Stucco and ornamental plaster

6. Acoustical ceilings

7. Carpeting

8. HVAC enclosures, cabinets, or covers.

9. If it is not possible to engage the original installer or fabricator, another recognized, experienced, and specialized firm shall be engaged.

10. For those components and construction covered by a warranty, the Contractor shall coordinate cutting and patching with the warranting party, and the cutting and patching shall not void the warranty.

D. The General Construction Contractor shall be responsible for removing, storing, and replacing removable ceilings where work is to be provided above an existing removable ceiling not indicated for replacement.

1.10 CLEANING AND RESTORATION

A. Thorough cleaning shall be performed for areas and spaces where cutting and patching is performed or used as access.

B. Paint, mortar, oils, putty, and items of similar nature shall be completely removed.

C. Piping, conduit, and similar features shall be thoroughly cleaned before painting or other finishing is applied.

D. Pipe covering and insulation damaged incidental to cutting and patching shall be restored to its original condition.

PART 2 - PRODUCTS

2.1 (NOT USED)

PART 3 - EXECUTION

3.1 (NOT USED)

END OF SECTION 017329

VEHICLE LIFT INSTALLATIONS

FORT SIMCOE JOB CORPS CCC

024119 - 1

SELECTIVE DEMOLITION

SECTION 024119 - SELECTIVE DEMOLITION

PART 1 - GENERAL

1.1 SUMMARY

A. The Work of this Section Includes:

1. Demolition and removal of selected portions of exterior or interior of building or structure and site elements.

2. Removal of existing items for reinstallation.

B. Related Requirements:

1. Section 010150 "General Requirements" for restrictions on use of the premises, Government-occupancy requirements, and phasing requirements.

2. Section 017329 "Cutting and Patching" for cutting and patching procedures.

1.2 MATERIALS OWNERSHIP

A. Unless otherwise indicated, demolition waste becomes property of Contractor.

1.3 INFORMATIONAL SUBMITTALS

A. Survey of Existing Conditions: Submit survey.

B. Proposed Protection Measures: Submit report, including Drawings, that indicates the measures proposed for protecting individuals and property, for environmental protection, for dust control and, for noise control. Indicate proposed locations and construction of barriers.

C. Schedule of selective demolition activities with starting and ending dates for each activity.

1.4 FIELD CONDITIONS

A. Government will occupy portions of building immediately adjacent to selective demolition area.

Conduct selective demolition so Government's operations will not be disrupted.

B. Conditions existing at time of inspection for bidding purpose will be maintained by Government as far as practical.

C. Notify Contracting Officer of discrepancies between existing conditions and Drawings before proceeding with selective demolition.

D. Hazardous Materials:

1. It is not expected that hazardous materials will be encountered in the Work.

024119 - 2

SELECTIVE DEMOLITION

a. If materials suspected of containing hazardous materials are encountered, do not disturb; immediately notify Contracting Officer.

E. On-site sale of removed items or materials is not permitted.

PART 2 - PRODUCTS

2.1 PERFORMANCE REQUIREMENTS

A. Regulatory Requirements: Comply with governing EPA notification regulations before beginning selective demolition. Comply with hauling and disposal regulations of authorities having jurisdiction.

B. Standards: Comply with ANSI/ASSP A10.6 and NFPA 241.

PART 3 - EXECUTION

3.1 EXAMINATION

A. Verify that utilities have been disconnected and capped before starting selective demolition operations.

B. Survey of Existing Conditions: Record existing conditions by use of preconstruction photographs or video.

1. Inventory and record the condition of items to be removed for salvage or reinstallation.

Photograph or video conditions that might be misconstrued as damage caused by removal.

2. Photograph or video existing conditions of adjoining construction including finish surfaces, that might be misconstrued as damage caused by selective demolition operations or removal of items for salvage or reinstallation.

3.2 PREPARATION

A. Temporary Shoring: Design, provide, and maintain shoring, bracing, and structural supports as required to preserve stability and prevent movement, settlement, or collapse of construction and finishes to remain, and to prevent unexpected or uncontrolled movement or collapse of construction being demolished.

B. Temporary Protection: Provide temporary barricades and other protection required to prevent injury to people and damage to adjacent buildings and facilities to remain.

C. Existing Items to Remain: Protect construction indicated to remain against damage and soiling during selective demolition. When permitted by Contracting Officer, items may be removed to a suitable, protected storage location and reinstalled in their original locations after selective demolition operations are complete.

024119 - 3

SELECTIVE DEMOLITION

3.3 UTILITY SERVICES AND BUILDING SYSTEMS

A. Existing Services/Systems to Remain: Maintain utilities and building systems and equipment to remain and protect against damage during selective demolition operations.

B. Existing Services/Systems to Be Removed, Relocated, or Abandoned: Locate, identify, disconnect, and seal or cap off utilities and building systems serving areas to be selectively demolished.

1. Arrange to shut off utilities with utility companies.

2. If disconnection of utilities and building systems will affect adjacent occupied parts of the building, provide temporary services/systems that bypass area of selective demolition and that maintain continuity of services/systems to those parts of the building.

3. Demolish and remove existing building systems, equipment, and components indicated on Drawings to be removed.

a. Piping to Be Removed: Remove portion of piping indicated to be removed and cap or plug remaining piping with same or compatible piping material.

b. Ducts to Be Removed: Remove portion of ducts indicated to be removed and plug remaining ducts with same or compatible ductwork material.

c. Equipment to Be Removed: Disconnect and cap services and remove equipment and components.

4. Abandon existing building systems, equipment, and components indicated on Drawings to be abandoned in place.

a. Piping to Be Abandoned in Place: Drain piping and cap or plug piping with same or compatible piping material and leave in place.

b. Ducts to Be Abandoned in Place: Cap or plug ducts with same or compatible ductwork material and leave in place.

5. Remove and reinstall/salvage existing building systems, equipment, and components indicated on drawings to be removed and reinstalled or removed and salvaged:

a. Equipment to Be Removed and Reinstalled: Disconnect and cap services and remove, clean, and store equipment and components; when appropriate, reinstall, reconnect, and make equipment operational.

b. Equipment to Be Removed and Salvaged: Disconnect and cap services and remove equipment and components and deliver to Government’s designated representative.

3.4 SALVAGE/REINSTALL

A. Removed and Reinstalled Items:

1. Clean and repair items to functional condition adequate for intended reuse.

2. Reinstall items in locations indicated. Comply with installation requirements for new materials and equipment. Provide connections, supports, and miscellaneous materials necessary to make item functional for use indicated.

024119 - 4

SELECTIVE DEMOLITION

3.5 SELECTIVE DEMOLITION, GENERAL

A. General: Demolish and remove existing construction only to extent required by new construction and as indicated. Use methods required to complete the Work within limitations of governing regulations and as follows:

1. Neatly cut openings and holes plumb, square, and true to dimensions required. Use cutting methods least likely to damage construction to remain or adjoining construction.

Use hand tools or small power tools designed for sawing or grinding, not hammering and chopping. Temporarily cover openings to remain.

2. Cut or drill from the exposed or finished side into concealed surfaces to avoid marring existing finished surfaces.

3. Do not use cutting torches until work area is cleared of flammable materials. At concealed spaces, such as duct and pipe interiors, verify condition and contents of hidden space before starting flame-cutting operations. Maintain portable fire-suppression devices during flame-cutting operations.

4. Maintain fire watch during and for at least 1 hours after flame-cutting operations.

5. Locate selective demolition equipment and remove debris and materials so as not to impose excessive loads on supporting walls, floors, or framing.

B. Site Access and Temporary Controls: Conduct selective demolition and debris-removal operations to ensure minimum interference with roads, streets, walks, walkways, and other adjacent occupied and used facilities.

3.6 DISPOSAL OF DEMOLISHED MATERIALS

A. Remove demolition waste materials from Project site and dispose of them in an EPA-approved construction and demolition waste landfill acceptable to authorities having jurisdiction.

1. Do not allow demolished materials to accumulate on-site.

2. Remove and transport debris in a manner that will prevent spillage on adjacent surfaces and areas.

B. Burning: Do not burn demolished materials.

3.7 CLEANING

A. Clean adjacent structures and improvements of dust, dirt, and debris caused by selective demolition operations. Return adjacent areas to condition existing before selective demolition operations began.

END OF SECTION 024119

033000 - 1

CAST-IN-PLACE

CONCRETE

SECTION 033000 - CAST-IN-PLACE CONCRETE

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Concrete standards.

2. Concrete materials.

3. Admixtures.

4. Fiber reinforcement.

5. Vapor retarders.

6. Floor and slab treatments.

7. Curing materials.

8. Accessories.

9. Repair materials.

10. Concrete mixture materials.

11. Concrete mixture class types.

12. Concrete mixing.

B. Related Requirements:

1.2 ACTION SUBMITTALS

A. Product data.

B. Design Mixtures: For each concrete mixture, include the following:

1. Mixture identification.

2. Compressive strength at 28 days or other age as specified.

3. Compressive strength required at stages of construction.

4. Durability exposure classes for Exposure Categories F, S, W, and C.

5. Maximum w/cm ratio.

6. Calculated equilibrium and fresh density for lightweight concrete.

7. Slump or slump flow limit.

8. Air content.

9. Nominal maximum aggregate size.

10. Steel-fiber reinforcement content.

11. Synthetic microfiber content.

12. Synthetic macrofiber content.

13. Intended placement method.

14. Submit adjustments to design mixtures when characteristics of materials, Project conditions, weather, test results, or other circumstances warrant changes.

033000 - 2

CAST-IN-PLACE

CONCRETE

1.3 INFORMATIONAL SUBMITTALS

A. Testing Agency: Include documentation indicating compliance with ASTM E329 or ASTM C1077 and copies of applicable ACI certificates for testing technicians or ACI Concrete Construction Special Inspector - MH, ASCC.

B. Material certificates.

C. Material test reports.

D. Field quality-control reports.

1.4 QUALITY ASSURANCE

A. Laboratory Testing Agency Qualifications: A testing agency qualified in accordance with ASTM C1077 and ASTM E329 for testing that performs duties on behalf of the Architect/Engineer.

B. Field Quality-Control Testing Agency Qualifications: An independent agency, qualified in accordance with ASTM C1077 and ASTM E329 for testing indicated.

PART 2 - PRODUCTS

2.1 CONCRETE STANDARDS

A. ACI Publications: Comply with ACI 301 unless modified by requirements in the Contract Documents.

2.2 CONCRETE MATERIALS

A. Cementitious Materials:

1. Portland Cement: ASTM C150/C150M, Any of the following: Type I, Type II, Type III, Type V.

2. Pozzolans: ASTM C618, Class C, F, or N.

3. Slag Cement: ASTM C989/C989M, Grade 100 or 120.

4. Ground Glass Pozzolan: ASTM C1866/C1866M, Type GS or GE.

5. Silica Fume: ASTM C1240.

B. Normal-Weight Aggregates:

1. Coarse Aggregate: ASTM C33/C33M, Class 3S, Class 3M, or Class 1N.

2. Maximum Coarse-Aggregate Size: 1-1/2 inches nominal.

3. Fine Aggregate: ASTM C33/C33M.

033000 - 3

CAST-IN-PLACE

CONCRETE

2.3 ADMIXTURES

A. Air-Entraining Admixture: ASTM C260/C260M.

B. Chemical Admixtures: Do not use calcium chloride or admixtures containing calcium chloride.

1. Water-Reducing Admixture: ASTM C494/C494M, Type A.

2. Retarding Admixture: ASTM C494/C494M, Type B.

3. Water-Reducing and -Retarding Admixture: ASTM C494/C494M, Type D.

4. High-Range, Water-Reducing Admixture: ASTM C494/C494M, Type F.

5. High-Range, Water-Reducing and -Retarding Admixture: ASTM C494/C494M, Type G.

6. Admixtures with special properties, with documentation of claimed performance enhancement, ASTM C494/C494M, Type S.

C. Mixing Water for Concrete Mixtures and Water Used to Make Ice: ASTM C1602/C1602M.

Include documentation of compliance with limits for alkalis, sulfates, chlorides, or solids content of mixing water from Table 2 in ASTM C1602/C1602M.

2.4 VAPOR RETARDERS

A. Sheet Vapor Retarder, Class C: ASTM E1745, Class C; not less than 10 mils thick.

2.5 CURING MATERIALS

A. Water: Potable water that does not cause staining of the surface.

B. Clear, Waterborne, Membrane-Forming, Curing and Sealing Compound: ASTM C1315, Type 1, Class A.

2.6 REPAIR MATERIALS

A. Repair Overlayment: Cement-based, polymer-modified, self-leveling product that can be applied in thicknesses from 1/4 inch and that can be filled in over a scarified surface to match adjacent floor elevations.

2.7 CONCRETE MIXTURE MATERIALS

A. Prepare design mixtures for each type and strength of concrete, proportioned on the basis of laboratory trial mixture or field test data, or both, in accordance with ACI 301.

1. Use a qualified testing agency for preparing and reporting proposed mixture designs, based on laboratory trial mixtures.

B. Cementitious Materials: Limit percentage, by weight, of cementitious materials other than portland or hydraulic cement in concrete assigned to Exposure Class F3 as follows:

1. Fly Ash or Other Pozzolans: 25 percent by mass.

2. Slag Cement: 50 percent by mass.

033000 - 4

CAST-IN-PLACE

CONCRETE

3. Silica Fume: 10 percent by mass.

4. Total of Fly Ash or Other Pozzolans, Slag Cement, and Silica Fume: 50 percent by mass, with fly ash or pozzolans not exceeding 25 percent by mass and silica fume not exceeding 10 percent by mass.

5. Total of Fly Ash or Other Pozzolans and Silica Fume: 35 percent by mass with fly ash or pozzolans not exceeding 25 percent by mass and silica fume not exceeding 10 percent by mass.

2.8 CONCRETE MIXTURE CLASS TYPES

A. Class C: Normal-weight concrete used for interior slabs-on-ground.

1. Exposure Class: ACI 318 Class F0, S0, W0, C1.

2. Minimum Compressive Strength: 4500 psi at 28 days.

3. Maximum w/cm Ratio : 0.50.

4. Limit water-soluble, chloride-ion content in hardened concrete to 0.30 percent by weight of cement.

2.9 CONCRETE MIXING

A. Ready-Mixed Concrete: Measure, batch, mix, and deliver concrete in accordance with ASTM C94/C94M and furnish delivery ticket.

PART 3 - EXECUTION

3.1 EXAMINATION

A. Before placing concrete, verify that installation of concrete forms, accessories, reinforcement, and embedded items is complete and that required inspections have been performed.

B. Do not proceed until unsatisfactory conditions have been corrected.

3.2 TOLERANCES

A. Comply with ACI 117.

3.3 INSTALLATION OF VAPOR RETARDERS

A. Sheet Vapor Retarders: Place, protect, and repair sheet vapor retarder in accordance with ASTM E1643 and manufacturer's written instructions.

033000 - 5

CAST-IN-PLACE

CONCRETE

3.4 INSTALLATION OF CAST-IN-PLACE CONCRETE

A. Before placing concrete, verify that installation of formwork, reinforcement, embedded items, and vapor retarder is complete and that required inspections are completed.

B. Notify Contracting Officer and testing and inspection agencies 24 hours prior to commencement of concrete placement.

C. Water addition in transit or at the Project site must be in accordance with ASTM C94/C94M and must not exceed the permitted amount indicated on the concrete delivery ticket.

D. Deposit concrete continuously in one layer or in horizontal layers of such thickness that no new concrete is placed on concrete that has hardened enough to cause seams or planes of weakness.

E. Deposit and consolidate concrete for floors and slabs in a continuous operation, within limits of construction joints, until placement of a panel or section is complete.

3.5 APPLICATION OF FINISHING FLOORS AND SLABS

A. Float Finish:

1. When bleedwater sheen has disappeared and concrete surface has stiffened sufficiently to permit operation of specific float apparatus, consolidate concrete surface with power-driven floats or by hand floating if area is small or inaccessible to power-driven floats.

2. Repeat float passes and restraightening until surface is left with a uniform, smooth, granular texture and complies with ACI 117 tolerances for conventional concrete.

3. Apply float finish to surfaces to receive trowel finish.

B. Trowel Finish:

1. After applying float finish, apply first troweling and consolidate concrete by hand or power-driven trowel.

2. Continue troweling passes and restraighten until surface is free of trowel marks and uniform in texture and appearance.

3. Grind smooth any surface defects that would telegraph through applied coatings or floor coverings.

4. Do not add water to concrete surface. Use of an approved finishing aid is acceptable.

5. Do not apply troweled finish to concrete, which has a total air content greater than

3 percent.

6. Apply a trowel finish to surfaces exposed to view.

7. Finish surfaces to the following tolerances, in accordance with ASTM E1155, for a randomly trafficked floor surface:

3.6 APPLICATION OF CONCRETE CURING

A. Protect freshly placed concrete from premature drying and excessive cold or hot temperatures.

1. Comply with ACI 301 for cold weather protection during curing.

2. Comply with ACI 301 and ACI 305.1 for hot-weather protection during curing.

033000 - 6

CAST-IN-PLACE

CONCRETE

B. Curing Unformed Surfaces: Comply with ACI 308.1 as follows:

1. Begin curing after finishing concrete.

2. Interior Concrete Floors:

a. Floors To Receive Curing and Sealing Compound:

1) Apply uniformly to floors and slabs indicated in a continuous operation by power spray or roller in accordance with manufacturer's written instructions.

2) Recoat areas subjected to heavy rainfall…

This is the start of the file's text. The full file is on GovTribe.