The provided document is a Data Item Description (DID) for a Performance and Cost Report. This report is required as part of a federal contract opportunity for the Naval Surface Warfare Center Carderock Division Total Ship Survivability Trial Engineering Services.

The Performance and Cost Report details the contractor's progress, including man-hours expended, funds spent, and percentage of work completed by task. The report must be provided in a machine-readable format and contain specific details such as cumulative totals, variances, and an assessment of whether sufficient resources remain to complete the tasks. This report is used by the government to evaluate the contractor's progress on the contract.

View the file

Other versions and copies of DI-FNCL-80912A

File Revision Posted Attached to
DI-FNCL-80912.pdf Revision not stated CODE 102 B575 GRINDING ROOM VENTILATION
DI-FNCL-80912.pdf Revision not stated 3D METAL ADDITIVE UPGRADE LAB
DI-FNCL-80912.PDF Revision not stated 500 AREA TEMPORARY TRAILERS
ATTACH_B_DI-FNCL-80912.pdf Revision not stated Aviation Maintenance Management

Who attaches DI-FNCL-80912A

Other files

File Type Posted
N0016724Q0179 0001.pdf PDF
N0016724Q0179 conformed to 0001.pdf PDF
Attachment 1- CDRL A001 - MGMT_TSST_SRC.pdf PDF
N0016724Q0179.pdf PDF

On GovTribe

Work with this file

  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DATA ITEM DESCRIPTION

Title: Performance and Cost Report

Number: DI-FNCL-80912A Approval Date: 20190812

AMSC Number: 10075 Limitation: N/A

DTIC Applicable: No GIDEP Applicable: No

Preparing Activity: MI Project Number: FNCL-2019-003

Applicable Forms:

Use/relationship: The Performance and Cost Report provides current status and projected requirements of funds, man-hours, and work completion. The report is used for evaluation of contractor progress.

a. This Data Item Description (DID) contains the format, content, and intended use information for the data deliverable resulting from the work task described in the solicitation.

b. This DID supersedes DI-FNCL-80912.

Requirements:

1. Reference Documents. None.

2. Format. The Performance and Cost Report format shall be in contractor format and machine readable by the Government.

3. Content. The Performance and Cost Report shall contain the following:

3.1 Man-hours. Total man-hours expended by technical categories or program tasks, cumulative total man-hours to date, and percentages of total man-hours spent to date. State whether or not remaining hours are sufficient to complete the task.

3.2 Funds. Total funds expended, by task, for the month; cumulative total funds spent to date; and percentage of total contract funds spent to date. State whether or not remaining funds are sufficient to complete the task. The report shall include cost variance.

3.3 Work completion. Percentage of work completed, by tasks during the month and cumulative percentage of total contract work completed to date.

End of DI-FNCL-80912A.