FY 2022 Bridge Investment Program (BIP) Bridge Projects
Application Template
This FY 2022 BIP Application Template is provided to assist project sponsors who intend to apply for a Bridge Project FY 2022 BIP grant. Interested eligible applicants should read the FY
2022 BIP Notice of Funding Opportunity in its entirety and especially where noted in this application template to submit eligible and competitive applications.
Basic Project Information
Basic Project Information – Provide a narrative for the below items on basic details pertinent to the project, including project name, description, location, involved parties, etc. Items in this section will be used to determine grant program eligibility as detailed in Section C of the NOFO.
Project Name
Eligibility Criteria
Project Description
(Replacement, Rehabilitation, Preservation, or Protection projects, including bridge bundling and NBIS culvert replacement and rehabilitation)
Provide a concise description of the project, the transportation challenges that it is intended to address, and how it will address those challenges. This section should discuss the project’s history, including a description of any previously incurred costs. The applicant may use this section to place the project into a broader context of other infrastructure investments being pursued by the project sponsor.
For each bridge that is part of the project, please indicate whether it is on the National Bridge Inventory under 23 U.S.C. 144(b).
BIP Request Amount
(minimum grant award is $2.5 million)
Exact Amount in year-of-expenditure dollars: $____________
Total Project Cost (total project cost cannot exceed
$100 million for Bridge
Projects)
Estimate in year-of-expenditure dollars: $____________
Applicant: (Name and identify which eligible applicant category applies. Select from the below statutory eligible applicants:
1. A State or a group of States;
2. A metropolitan planning organization that serves an urbanized area
(as designated by the Bureau of the Census) with a population over
200,000;
3. A unit of local government or a group of local governments;
4. A political subdivision of a State or local government;
5. A special purpose district or a public authority with a transportation function;
6. A Federal land management agency;
7. A Tribal government or a consortium of Tribal governments; and
8. A multistate or multijurisdictional group of entities as described above in 1 – 7.)
Maintenance Commitment
Applicant must certify the completed project will be maintained, if a co-applicant will maintain the completed structure, the co-applicant provides the certification.
Bike and Pedestrian
Accommodation required by
23 U.S.C. 217(e)
Federal law provides that all projects with Federal financial participation that replace or rehabilitate a highway bridge deck are required to provide safe accommodation of pedestrians or bicyclists when two conditions are met. If bicyclists and pedestrians are allowed to operate at each end of the bridge, and the anticipated project will be for replacement or rehabilitation, the applicant must detail how bicyclist and pedestrian access is included in the project or provide FHWA with the information needed to determine whether or not such access can be provided at a reasonable cost.
Additional Project Information
State(s) in which project is located
Does the project serve an urban or rural community?
State whether the project serves an urban or rural community. In determining, the DOT will rely on the Census Bureau Census 2010 definition of Urbanized Area as an area that consists of densely settled territory that contains 50,000 or more people. Updated lists of UAs are available on the Census Bureau website at http://www2.census.gov/geo/maps/dc10map/UAUC_RefMap/ua/. For the purposes of the BIP program, Urbanized Areas with populations of less than 50,000 will be considered rural.
List all Project Co-Applicants.
Identify the Lead Applicant
(who will be also the applicant responsible for administration of BIP funds if application is selected and point of contact for the application.)
Was an application for
USDOT discretionary grant funding for this project previously submitted?
(If Yes, please include project title, applicable grant programs and year.)
http://www2.census.gov/geo/maps/dc10map/UAUC_RefMap/ua/
Is the project located (entirely or partially) in Federal or
USDOT designated areas?
Yes/No. If yes, please describe which of the four Federally designated community development zones in which your project is located.
Opportunity Zones: (https://opportunityzones.hud.gov/) Empowerment
Zones: (https://www.hud.gov/hudprograms/empowerment_zones)
Promise Zones:
(https://www.hud.gov/program_offices/field_policy_mgt/fieldpolicymgt
pz) Choice Neighborhoods:
(https://www.hud.gov/program_offices/public_indian_housing/program s/ph/cn)
National Bridge Inventory Data
National Bridge Inventory Data - For each bridge on the project, fill out the NBI data in the following form. For projects with multiple bridges, including those utilizing bridge bundling, this table should be duplicated and populated with data for each individual bridge. This data is used to support and verify statements made about the project in other sections in this application template as noted in Section D.2.d.II of the NOFO. Data, format and coding information can be downloaded from Download NBI ASCII files - National Bridge Inventory
- Bridge Inspection - Safety Inspection - Bridges & Structures - Federal Highway
Administration (dot.gov):
Identification
Item 1 – State Code & Name
Item 8 – Structure Number
Item 5A – Record Type
Item 3 – County Code & Name
Item 6 – Feature Intersected
Item 7 – Facility Carried
Item 16 - Latitude
Item 17 – Longitude
Classification
Item 112 – NBIS Bridge Length
Item 104 – Highway System of
Inventory
Item 26 – Functional
Classification
Item 110 – Designated National
Network
Item 21 – Maintenance
Responsibility
Item 22 – Owner
Age and Service
Item 27 – Year Built
Item 106 – Year Reconstructed
Item 42 – Type of Service
Item 28A – Lanes on the
Structure
Item 29 – Average Daily Traffic https://www.fhwa.dot.gov/bridge/nbi/ascii.cfm
Item 109 – Average Daily Truck
Traffic
Item 19 – Bypass, Detour
Length
Structure Type and Material
Item 43 – Structure Type, Main
Condition
Item 58 – Deck Condition
Item 59 – Superstructure
Condition
Item 60 – Substructure
Condition
Item 61 – Channel and Channel
Protection
Item 62 – Culverts
Geometric Data
Item 49 – Structure Length
Item 50 – Curd of Sidewalk
Widths
Item 51 – Bridge Roadway
Width, curb-to-curb
Item 52 – Deck Width, out-to-out
Item 32 – Approach Roadway
Width
Item 47 – Inventory Route, Total
Horizontal Clearance
Item 53 – Minimum Vertical
Clearance over Bridge Roadway
Item 54 – Minimum Vertical
Underclearance
Item 55 – Minimum Lateral
Underclearance on Right
Item 56 – Minimum Lateral
Underclearance on Left
Load Rating and Posting
Item 70 – Bridge Posting
Item 41 – Structure Open, Posted, or Closed to Traffic
Appraisal
Item 113 – Scour Critical
Bridges
Inspections
Item 90 – Inspection Date
Project Selection Criteria
Project Selection Criteria – Provide narrative response how the project responds to the project selection criteria in Section E.1.b of the NOFO. In responding to project selection criteria, refer to statutory selection criteria included in Section E of the NOFO and address them in the appropriate project selection criteria.
Criteria #1: State of Good Repair
This project contributes to the State of Good Repair criteria by…
For each bridge on the project, indicate the condition based on the NBI data provided.
Are the bridge(s) on the project in Fair condition? Yes/No.
If yes, please describe why the bridge(s) are at risk of falling into poor condition within the next three (3) years.
Criteria #2: Safety
This project contributes to the Safety criteria by…
Criteria #3: Mobility and Economic Competitiveness
This project contributes to the Mobility and Economic Competitiveness criteria by…
Criteria #4: Climate Change, Resiliency, and the Environment
This project contributes to the Climate Change, Resilience, and the Environment criteria by…
Criteria #5: Equity, Partnership, and Quality of Life
This project contributes to the Equity, Partnership, and Quality of Life criteria by…
Criteria #6: Innovation
This project contributes to the Innovation criteria by…
Project Costs
Project Costs – Provide information detailing the costs associated with the project. These costs will be used to determine eligible award amount, how the project supports financial goals of the program, and other factors. More information on this section can be found in Section
D.2.d.III of the NOFO.
BIP Request Amount Exact Amount in year-of-expenditure dollars: $____________
Estimated Total of Other
Federal funding
(excluding BIP Request)
Estimate in year-of-expenditure dollars: $____________
Estimated Other Federal funding (excluding BIP) further detail
(List each Federal Program and identify Formula or
Discretionary and the amount for each Federal Program, e.g.
Program:_____________________________
Amount:_____________________________, and repeat for each source)
Estimated non- Federal funding
(Identify each source of non-Federal funding and estimated amount, e.g.
Source:_____________________________
Amount:_____________________________, and repeat for each source)
Future Eligible Project
Cost (Sum of BIP request, Other Federal Funds, and non-Federal Funds, above.
Previously incurred project costs (if applicable)
Total Project Cost (Sum of
‘previous incurred’ and
‘future eligible’
If more than one bridge, will bridge bundling be used to deliver the
Project?
Yes or No. If yes, explain the intended benefits of bridge bundling for this set of bridges.
If proposed project utilizes bundling, Cost of
Unbundled Projects
Estimate in year of expenditure dollars: $
Amount of Future Eligible
Costs by Project Type
Indicate Improvement Type by Structure Number (Bridge
Replacement, Bridge Rehabilitation, Bridge Preservation, Bridge
Protection, or Culvert Replacement or Rehabilitation) and amount per bridge (if bundling, include the unbundled cost in brackets[$__]1) (Ex.
Bridge Replacement Str. 001: $20,000,000[$25,000,000]
Bridge Replacement Str, 002, $15,000,000[$18,000,000]
Bridge Rehabilitation Str. 003, $5,000,000)[$5,500,000]
1. Bridge __________ Str. ________: $___________ [$____]
1 Costs of unbundled project will be compared with bundled costs to determine potential amount of cost savings and as a factor in the ability to unbundle bridges for an award
2. Bridge __________ Str. ________: $___________ [$____]
3. Bridge __________ Str. ________: $___________ [$____]
4. Bridge __________ Str. ________: $___________ [$____]
5. Bridge __________ Str. ________: $___________ [$____]
6. Will request $_____________ of the amounts awarded to the entity to pay subsidy and administrative costs necessary to provide to the entity Federal credit assistance under 23 U.S.C.
chapter 6.2
Benefit-Cost Analysis
Benefit Cost Analysis– Submit the requested information in Section D.2.d.V for the DOT to conduct a review of the benefit-cost analysis for the project and provide a summary of the analysis.
The benefit cost analysis demonstrates . . .
Project Readiness and Environmental Risk
Project Readiness and Environmental Risk– Submit the requested information in Section
E.2.b.iii for the DOT to conduct a review of the project readiness and environmental risk criteria for the project and provide a summary. If project includes multiple bridges, indicate the information for each bridge included in the application and what impact would occur on the timeframes if the project were unbundled.
Other Federal Funding and
Non-Federal Funding
Secured
Yes/No
NEPA Status – Indicate if the determination will likely be the result of a
Categorical Exclusion
(CE), Environmental
Assessment (EA), or
Environmental Impact
Statement (EIS)
Planned or Actual Start of NEPA Date: ________________
Planned or Actual Completion of NEPA Date:___________
Final NEPA Determination or current status of NEPA process:
2 Receipt of a BIP award does not guarantee that an applicant will receive TIFIA credit assistance, nor does it guarantee that any award of TIFIA credit assistance will be equal to 49% of eligible project costs. Receipt of TIFIA credit assistance is contingent on the applicant’s ability to satisfy applicable creditworthiness standards and other
Federal requirements.
Is the project currently programmed in the:
• TIP
• STIP
• MPO Long
Range
Transportation
Plan
• State Long Range
Transportation
Plan
Yes/No
(please specify in which plans the project is currently programmed, the year in which the project is currently programmed and provide the identifying number if applicable)
Is right-of-way acquisition necessary?
Yes/No
If Yes, Planned or Actual Start of Right-of-Way Acquisition
Date:_______________
Planned or Actual Completion of Right-of-Way Acquisition
Date:
Right-of way acquisition considerations.
If right-of-way must be acquired for the project:
1. Would right-of-way acquisition require relocation of any people or businesses? Yes/No.
2. If yes, are people or businesses being relocated members of traditionally underserved and underrepresented populations
(Environmental Justice communities)? If yes, please describe.
Design Status Planned or Actual Start of Preliminary Design
Date:_______________
Planned or Actual Completion of Preliminary Design
Date:__________
Planned or Actual Start of Final Design Date:_______________
Planned or Actual Completion of Final Design Date:__________
Anticipated Construction
Start Date:
Date:___________________________
Anticipated Project
Completion Date:
Date:___________________________
The summary on project readiness and environmental risk demonstrates…
Project Priority Considerations
Project Priority Considerations: Does the application support any of the DOT Priority
Considerations – Bridge Projects listed in Section E.2.b of the NOFO? If the applications supports one or more of the considerations for the FY22 submissions, describe which consideration(s) is supports and how. In the discussion below, reference to previous sections in which additional information was detailed to support the consideration(s).
This application supports the following priority considerations by…