Attachment 1:

1 | P a g e

Statement of Work (SOW) for Tracy Engineering Services– One Time Purchase

Department of Homeland Security (DHS) Federal Emergency Management Agency (FEMA)

PART 1: GENERAL

1.1 BACKGROUND

The Federal Emergency Management Agency (FEMA) is seeking to procure services for Professional Engineering report for a Spill Prevention Control and Countermeasures Plan (SPCC). Since FEMA is tasked with responding to disasters with minimal launch time, it is always essential that FEMA has the required warehouse operational equipment to move, load, and transport life-saving and life-sustaining disaster commodities during disaster operations.

1.2 SCOPE

FEMA is pursuing an engineering service. This particular service will provide a Professional Engineering report for a Spill Prevention Control and Countermeasures Plan (SPCC). The contract should allow FEMA to procure a new SPCC Plan to meet the current regulations per 40CFR, Part 112.

1.3 PERIOD OF PERFORMANCE

The period of performance shall be within 120 days from the Date of Award.

PART 2: CONTRACTOR DELIVERABLES

2.1 GENERAL

The contractor(s) shall provide service for Professional Engineering report for a Spill Prevention Control and Countermeasures Plan (SPCC)

PART 3: SPECIFIC TASKS

3.1 Service COMPONENTS

For the purposes of this Statement of Work (SOW), the breakdown of the required item below:

Item Name: CLIN 0001 Location Quantity Total Price Engineering Services DC Tracy 1

3.2 DELIVERY LOCATION

Attachment 1:

2 | P a g e

The Government will require engineering services to provide:

• Site visit for visual observation of the tanks, and the secondary containment systems currently existing.

• Prepare a new SPCC Plan to meet the current regulations per 40CFR, Part 112.

• Provide certification of the SPCC plan.

These services will be performed at the FEMA Distribution Center Tracy 1547 East Grant Line Road Tracy, CA 95304

Hours of Performance: Work hours 7:00am – 3:30pm

PART 4: TECHNICAL EVALUATION

4.1 TECHNICAL EVALUATION FACTORS

The proposals will be compared to the below specifications

4.1.1 Factor 1: Technical Acceptability

The technical quotation evaluation will be rated based on if the offeror can provide Lowest Price Technically Acceptable with the below servicing expectations.

The engineering services will include:

• Site visit for visual observation of the tanks, and the secondary containment systems currently existing.

• Prepare a new SPCC Plan to meet the current regulations per 40CFR, Part 112.

• Provide certification of the SPCC plan.

• These services will be performed at the FEMA Distribution Center Tracy 1547 East Grant Line Road

Tracy, CA 95304

PART 1: GENERAL
1.1 BACKGROUND
1.2 SCOPE
1.3 PERIOD OF PERFORMANCE
PART 2: CONTRACTOR DELIVERABLES
PART 3: SPECIFIC TASKS
PART 4: TECHNICAL EVALUATION
4.1 TECHNICAL EVALUATION FACTORS
4.1.1 Factor 1: Technical Acceptability