This statement of work outlines requirements for replacing the engine in a 2007 Diamondback airboat located at southeast Louisiana refuges in Lacombe, Louisiana. The selected contractor must remove the existing engine, install a new 525HP LSX Big Block marine engine with accessories, and fine tune the new engine and propeller. The contractor must have extensive airboat engine experience and provide all necessary parts, labor, and a three-year/200-hour warranty. The boat will be delivered within 100 miles of Lacombe, Louisiana for the work to be completed within 90 calendar days of award. Interested parties can request boat details from the point of contact. The final product must be fully functional and free of leaks upon validation.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140FS323Q0166_Amd_0001.pdf | ||
| Attachment_2-_Past_Performance_Data.docx | DOCX document | |
| Attachment_4-_Current_motor.pdf | ||
| Sol_140FS323Q0166.pdf | ||
| Attachment_3-_Quote_Schedule.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
REPLACE ENGINE IN 2007
DIAMONDBACK AIRBOAT
SOUTHEAST LOUISIANA REFUGES
LACOMBE, LOUISIANA
SCOPE OF WORK:
Contractor shall provide all required parts and labor to replace engine in a 2007 Diamondback airboat. The contractor will be required to remove old engine from the boat and install new engine and fine tune the engine and the propeller. Contractor will be required to provide new hoses, wiring harness and other associated parts so the motor is fully functional and compatible with boat. All new equipment and work shall be compliant with industry standards.
PROJECT LOCATION:
Boat will be delivered to the prospective contractor’s shop within 100 miles of Lacombe Louisiana. Contractor is responsible for pick and delivery if further than 100 miles from Lacombe, Louisiana.
PERFORMANCE PERIOD:
This contract will have an initial period of performance of 90 calendar days from time of award.
CONTRACTOR PERSONNEL
The services shall be performed by contractor with appropriate license(s) and credentials.
HOURS OF OPERATION/WORK SCHEDULE
N/A
CONTRACTOR USE OF SITE
N/A
MEETINGS
Pre-bid site visit is not required but all interested bidders can request to see boat or pictures of the boat. For meeting schedule contact Pon Dixson 985-285-3613 or at pon_dixson@fws.gov
As soon as the Contractor receives the "Notice to Proceed" letter from the Contracting Officer, a pre-work meeting shall be schedule to discussion the installation schedule.
TECHNICAL REQUIREMENTS
Airboats are highly specialized and must meet specific performance parameters. The contractor must have an extensive knowledge of how airboats function and have the ability to fine tune engines and propellers. Motor will be fully functional
MINIMUM SPECIFICATIONS
• Marine 7.4 liter LSX Big Block 525HP engine
• Horsepower 525 @5600
• Torque 550 @4000
• Emissions Certified
• Multiport EFI
• High amperage alternator
• New gauges and wiring harness to meet engine specifications
• High Performance flywheel
• Heavy duty radiator with maximum cooling capacity with built-in oil cooler
• Custom built headers, tuned and balanced for best performance
• Upgraded motor mounts
• LSX lower drive unit shaft
• Three (3) year/200 hour warrantee
****The trade-in engine which is currently in the boat, is a 2007 big block GM Levitator with a displacement of 496 CID
GENERAL DEFINITIONS
QUALITY ASSURANCE. Actions taken by the Government to assure services meet contract requirements.
QUALITY CONTROL. Those actions taken by a Contractor to control the performance of services to ensure services meet the requirements of the SOW.
GENERAL INFORMATION
The Contractor shall furnish all labor, materials and equipment necessary to complete the scope of work.
CERTIFICATES/CREDENTIALS
Certifications/Credentials at a minimum should include all pertinent state and federal certifications held by the contracting company and individual technicians who will perform the work onsite.
Capability/Capacity at a minimum should describe the number and credentials of all credentialed employees involved in all aspects of the project.
PERFORMANCE REQUIREMENTS SUMMARY
The final product shall be validated once everything is fully functioning and free of water and oil leaks.
| SCOPE OF WORK: |
| PROJECT LOCATION: |
| PERFORMANCE PERIOD: |
| CONTRACTOR PERSONNEL |
| HOURS OF OPERATION/WORK SCHEDULE |
| CONTRACTOR USE OF SITE |
| MEETINGS |
| TECHNICAL REQUIREMENTS |
| GENERAL DEFINITIONS |
| GENERAL INFORMATION |
| CERTIFICATES/CREDENTIALS |
| PERFORMANCE REQUIREMENTS SUMMARY |
File details come from the government source that posted it. Updated .