Attachment 1 - Statement of Work UVIS.pdf
PDF 100 KB Posted
- Attached to
- UVIS Refurbish and Re-install Federal contract opportunity
- Solicitation number
- FA9101-24-Q-B023
About this file
This document outlines a sole source procurement by the Air Force Test Center at Arnold Air Force Base to refurbish and reinstall an Under Vehicle Inspection System (UVIS). The statement of work details the required repairs and replacement of specific UVIS components by Global Grab Technologies, Inc., including cameras, lights, sensors and completing functional testing once reinstalled. Upon award of the firm-fixed price purchase order, Global Grab Technologies will refurbish the UVIS at their facility and then reinstall the system at Gate 2 of Arnold AFB by the period of performance completion date. As the market research identified Global Grab Technologies as the only vendor that can meet the specifications, this will be a sole source award in accordance with FAR Part 13 Simplified Acquisition Procedures.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| FA9101-24-Q-B023 - Notice of Intent to Sole Source-Final.pdf | ||
| FA9101-24-Q-B023_single source justification - FINAL_Redacted.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work To
Repair Under Vehicle Inspection System (UVIS) At Gate # 2, Arnold AFB, TN. 37389
Title Task: UVIS repair (Gate #2)
1. Purchase Type Service repair.
2. Requirements
1. Repair Under Vehicle Inspection System to factory recondition, replace the following items:
- OEM single board gige camera
- Center/Stitch camera lens
- VI-150 light cover set
- 4” and 6” LED light strip replacement
- Presence sensor module address 1 &2 (front and back)
2. Re-install the refurbished UVIS ramp assembly back into the Gate 2 roadway then re-terminate all wiring that is existing. The parts listed above are all the parts that the factory will be using to refurb the old unit.
3. Techs will also replace the front and rear vehicle sensors that initiate the inspection scan process which are still currently installed. This also includes resealing the new sensors with the correct factory recommended sealant.
4. Once the unit has been completely installed, the techs will power the system back up and complete a full function test of the system.
3. Delivery Instructions Re-install the refurbished the UVIS ramp assembly back into the gate 2 roadway at Arnold AFB, TN. 37389
4. Period of Performance Full function test once the system has been installed.
File details come from the government source that posted it. Updated .