Attachment 1 - Statement of Work - Specifications - Photos.pdf
PDF 4 MB Posted
- Solicitation number
- 127EAX26Q0018
- Issued by
-
Department of Agriculture Forest Service
About this file
This is a Statement of Work and Specifications document for a federal construction contract issued by the US Department of Agriculture (USDA) Forest Service for site maintenance and minor construction work at abandoned mine sites in Arizona and New Mexico during 2026.
The Arizona scope of work encompasses three mine sites within the Coronado National Forest: Lead Queen Mine, Blue Nose Mine, and Marstellar Mine. Work at Lead Queen includes removing and disposing of approximately 416 linear feet of existing wire fence, 27 T-posts, 6 steel and concrete corner posts, and 2 wood gate posts at an off-site facility, with the existing ranch gate to be set aside on-site. At Blue Nose Mine, the contractor must install a bat-compatible closure at the remaining mine adit (approximately 5.2 ft x 5.75 ft), featuring an adjustable bat-friendly grate design with steel bars allowing bat ingress and egress while protecting the public. At Marstellar Mine, work consists of dry seeding at approximately 0.5 acres adjacent to the mine repository and installing erosion control fabric. The New Mexico scope involves the Nacimiento Mine on the Cuba Ranger District of the Santa Fe National Forest, requiring replacement of dilapidated barbed wire fencing with new barbed wire fencing and installation of a new pedestrian gate. Fencing work includes approximately 1,330 linear feet across three sides with approximately 88 new steel tee posts, with specific spacing and material specifications provided. The gate installation involves a 4-foot heavy-duty Agstar Gate (Model 40120042) with associated signage and concrete-set posts.
Performance periods differ by location: Arizona sites must be completed between October 1, 2026 and March 1, 2027 to comply with Mexican Spotted Owl breeding season restrictions, with separate Notice to Proceed (NTP) issuance. New Mexico sites have 180 calendar days from NTP. The contractor must provide mobilization and bonding, obtain all necessary permits and insurance, and develop a comprehensive work plan including health and safety, erosion control, and fire plans. Additional requirements include equipment cleaning protocols to prevent noxious weed spread, emergency spill kits, construction reporting with photographic documentation, and restoration of all disturbed areas. Payment for mobilization is structured as a lump sum with progressive disbursement tied to overall contract progress. All work must comply with FP-14 (Federal Highway) specifications as modified by supplemental specifications provided in the document, with visual inspection as the primary acceptance method.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Attachment 2 - Schedule of Items.xlsx | XLSX spreadsheet | |
| Attachment 3 AZ Wage Determination AZ20260007.pdf | ||
| 127EAX26Q0018 Site Maintenance and Minor Construction.pdf | ||
| Attachment 4 NM Wage Determination NM20260041.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Arizona & New Mexico Site Maintenance and Minor Construction 2026
US Department of Agriculture (USDA)
Schedule of Items, Statement of Work, Specifications
DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK
Arizona Sites
Description of Work. The Contractor shall furnish all labor, materials, equipment, and supervision for site maintenance and minor construction of project areas within the Coronado National Forest.
The project areas are mine waste repository areas and former mine sites remediated under CERCLA Activities onsite will include soil decompaction, dry seeding, installing erosion control fabric, removal of existing fencing, and a mine feature closure.
Project Location.
There are three project areas, Lead Queen Mine, Marstellar Mine, and Blue Nose Mine.
Lead Queen: The Lead Queen Mine is located on the Coronado National Forest. Access to the Site is east from Tucson on Interstate 10 about 23 miles to Exit 281, and south on State Highway 83 for about 26 miles to State Highway 82 for 13 miles to the town of Patagonia. Take McKeown Avenue east near the Patagonia Post Office and the road turns into Harshaw Road. Travel south on Harshaw Road about 5.2 miles and turn right on Forest Road 4649. Take this road about 0.6 miles and turn right on Forest Road 4684. Take route 4684 about 1.5 miles and park the vehicle. Travel by foot about 0.4 miles over desert terrain to reach the north dump site. Roads are minimally maintained by the Forest Service and may only be accessed by 4-wheel drive vehicles.
The legal description is Township 22 S, Range 16 E, NW ¼ in Section 33. The latitude is 31.484815 and longitude is -110.718891.
Blue Nose Mine: Blue Nose Mine is located south of the Marstellar Mine approximately 800 feet west of Harshaw Road at latitude 31.448608, longitude -110.731460, and elevation of 5283 feet amsl. The Site is accessed via an 800-foot, decommissioned road. Before remediation, the mine consisted of six mine adits, one mine shaft and numerous tailings and waste rock stockpiles located adjacent or near the mine shafts and mine adits.
Marstellar Mine: The Marstellar Mine is located approximately 1,022 feet west of Harshaw road at latitude 31.454282632, longitude -110.732718839, and elevation 5,235 feet amsl. The Site is accessed via a 750-foot, decommissioned road that can be driven with a high clearance vehicle.
The decommissioned road has natural barriers like slash and logs in place to deter public access.
These barriers need to be moved for vehicle access. The barriers must be put back in place after on-site activities.
Arizona Project Tasks
Lead Queen
1. Remove and dispose of approximately 416 LF of existing wire fence, 27 T- posts, 6 steel and concrete corner posts, 2 wood gate posts, at an appropriate off-site facility. The existing ranch gate shall be set aside on-site.
Blue Nose Mine
1. Install bat compatible closure at the remaining mine adit. Adit dimensions are approximately 5.2 ft x 5.75 ft.
Marstellar Mine
1. Perform dry seeding at the slope area adjacent to the Marstellar Mine Repository and install erosion control fabric, approximately 0.5 acres.
New Mexico Sites
Scope of Work
Work consists of furnishing and installing barbed wire fencing and furnishing and installing a new gate.
Location
The Nacimiento Mine is located on the Cuba Ranger District of the Santa Fe National Forest, in Sandoval County, New Mexico. It is located approximately 5 miles southeast of Cuba, New Mexico, adjacent to State Highway 126.
Pay Item 1 Mobilization and Bonding
Work-This work consists of moving personnel, equipment, material, and incidentals to the project and performing work necessary before beginning work at the project site. This work also includes obtaining permits, insurance, and bonds.
Measurement and Payment-The accepted quantity will be paid for as a lump sum at the contract price.
Pay Item 2 Fencing
Work-This work consists of replacing dilapidated barbed wire fencing with new barbed wire fencing utilizing existing steel tee posts and installing new steel tee posts where needed to maintain a maximum spacing of 10 feet between tee posts. Existing steel tee post spacing is about 16 feet on average, so new tee posts will need to be installed midway between existing steel tee posts. Some existing steel tee posts are too short and will need to be replaced with new steel tee posts. Approximately 580 linear feet of fence including approximately 40 new steel tee posts will be installed on the south side, approximately 550 linear feet of fence will be installed on the west side including approximately 36 new tee posts, and 200 linear feet of fence will be installed on the north side including approximately 12 new tee posts. Exact locations of new fencing will be designated by the Forest Service Representative.
Material- Barbed and smooth wire shall be of two twisted strands of 12.5-gauge wire. The wire shall have a Class III galvanization coating. Line posts shall be steel tees, 6’ long weighing not less than 1.3 lbs. per lineal foot and shall have an anchor plate sufficient to resist movement. Posts shall be painted with weather resistant green paint color #14109, Federal Standard #595A. Fence stays shall be double strand, twisted, 9 ½ gauge galvanized wire. Fence ties shall be minimum 12 ½ gauge galvanized wire.
Installation- Remove and properly dispose of all existing wire from fence to be replaced. Existing steel tee posts in good shape and properly driven into ground can be reused in new fence. Line post spacing shall be a minimum of 6 feet to a maximum of 10 feet.
All corner or end posts shall be braced. Corner posts, with braces, shall be placed at all changes in alignment or grade in excess of 20 degrees. Repair or replace existing corner or end posts as necessary.
Perform minor clearing of sagebrush and tree limbs as needed to emsure clear path for wire.
Fence shall have three strands of barbed wire spaced at 48 inches, 36 inches, and 26 inches above the ground. Fence shall have one strand of double twisted smooth wire installed 16 inches above the ground.
Every strand of wire shall be tied to each post in accordance with standard practice. Wrap wire around outside of post on all corner, end, gate, and intermediate brace posts. Install fence stays midway between line posts.
Sag weights, where necessary, will be 9-gauge galvanized wire with at least 50 lb. stone.
Remove and dispose of old fence wire and discarded posts off site.
Measurement and Payment- Measurement will be by the liner foot as measured along the centerline of the fence. The accepted quantity will be paid at the contract unit price for each linear foot furnished and installed.
Pay Item 3 Gate
Work-The work includes furnishing and installation of a new pedestrian gate along with gate posts and associated signage. Work also consists of removing and disposing existing squeeze gate including steel angle posts set in concrete.
Materials
New gate shall be a 4-foot-long heavy duty Agstar Gate manufactured by Behlen Country Model Number 40120042 or approved equal. Gate is furnished with two hinges, two bolt hooks, and painted green.
Gate posts shall be 2-inch diameter round steel tubing 8 feet in length with a minimum thickness of 0.25 inches. Two gate posts are required. Gate posts shall be primed and painted green.
Signs shall have the legend “Please Cose the Gate” with a minimum letter height of one inch and a maximum letter height of 2 inches. Sign material shall be aluminum with a minimum thickness of 0.063 inches. Sign mounting hardware shall be galvanized or stainless steel and a minimum of 3/8-inch diameter.
Installation-Bottom of gate shall be set approximately 6 inches above trail surface. Bottom of posts shall be set 30” below ground level in an 18” diameter hole that is backfilled with concrete. Posts shall be set plumb and at the proper distance for gate operation. Insert hook bolts into gate post per gate manufacturer’s directions. Install two “Please Close the Gate signs, one on each side of the gate.
Measurement and Payment-The accepted quantity will be paid for as a lump sum at the contract price.
Period of Performance.
Arizona Sites:
October 1, 2026 and March 1, 2027 to comply with Mexican Spotted Owl (MSO) breeding season restrictions as directed by the Forest Service biologist.
New Mexico Sites:
180 Calendar Days from Notice to Proceed (NTP).
***Note: Two separate NTP’s will be issued, one for the Arizona Sites and one for the New Mexico sites due to the above-mentioned restrictions. ***
In addition, the contractor shall comply with the following requirements:
(1) Hours of operation: sunrise to sunset.
(2) Noise: The use of horns and Jake brakes shall be avoided to the extent practicable.
Submittals. The following list of submittals will be required for this project. This list is not considered to be all inclusive and additional submittals may be requested by the USDA Forest Service.
Work Plan: The Contractor shall submit a Work Plan which includes the Erosion Control Plan and Site Health and Safety Plan.
Site Health and Safety Plan: The Contractor shall submit and comply with a site-specific Health and Safety Plan.
Certifications: The Contractor shall furnish samples and/or certifications as described in the Specifications. The items requiring certification include, but are not limited to: re-vegetation seed mixtures, and weed free certifications for erosion control materials.
Fire Plan. The Contractor shall submit a Fire Plan to outline measures to comply with fire restrictions, if applicable, on the National Forest. The COR shall provide any fire restrictions that may be in effect during construction and the Forest Fire Plan for each Forest.
Erosion Control Plan: The Contractor shall submit an Erosion Control Plan to identify the locations of erosion control measures such as the straw wattles.
Restoration by the Contractor. All areas disturbed by the Contractor’s operation such as, but not limited to, temporary access roads, staging areas, temporary haul roads, loading operations, and disposal operations shall be restored by grading and seeding. During the course of the work the Contractor shall periodically, or as directed by the COR, repair disturbed areas, remove and dispose of all surplus construction materials and debris and keep the project area reasonably clean. Upon completion of the work, the Contractor shall remove temporary construction facilities, debris, and unused materials, leaving the project site in a neat and clean condition. All debris shall be disposed off-site in a state-licensed waste management facility.
Control of Work. When required for execution of the work, the Contractor shall establish local survey points for locating the principal components of work. The Contractor shall stake or flag clearing limits, staging areas, and all other features of the work and receive approval from the Forest Service’s COR or Project Inspector before proceeding with the work on these items. Staking and surveying by the Contractor is considered incidental to other work items and no separate measurement or payment for this item will be made.
C - 2 – GOVERNMENT FURNISHED PROPERTY
There will be no government furnished property for this project.
C - 3 - STANDARD PROJECT SPECIFICATIONS
“Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects”, Publication No. FHWA-FLH-14-001” (FP-14 customary units) is included in this contract by reference. The requirements contained in these Specifications are hereby made a part of this contract. Copies of the “Standard Specifications for Construction of Roads and Bridges on Federal
Highway Projects” are available from the SUPERINTENDENT OF DOCUMENTS, U.S. GOVERNMENT PRINTING OFFICE, internet: bookstore.gpo.gov, phone: toll free (866) 512-1800.
C - 4 - SUPPLEMENTAL SPECIFICATIONS
Supplemental Specifications are applicable to the following items and are included in their entirety in this section. Within these Supplemental Specifications, standard specifications are referenced.
This reference is not intended to exclude other sections of the standard specifications. All standard specifications not referenced are still applicable.
Table of Contents
SECTION C – DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK
C - 2 – GOVERNMENT FURNISHED PROPERTY
C - 3 - Standard PROJECT SPECIFICATIONS
C - 4 - SUPPLEMENTAL SPECIFICATIONS
Preface
101 - Terms¸ Format¸ and Definitions
101.01 Meaning of Terms
101.03 Abbreviations
101.04 Definitions
102 - Bid¸ Award¸ and Execution of Contract
Delete Section 102
103 - Scope of Work
Delete Subsections 103.02, 103.03, 103.04, 103.05
104 - Control of Work
Delete Subsections 104.01, 104.02, 104.04
104.06 Use of Roads by Contractor
105 - Control of Material
105.05 Use of Material Found in the Work
106 - Acceptance of Work
106.01 Conformity with Contract Requirements
106.02 Visual Inspection
107 - Legal Relations and Responsibility to the Public
Delete Subsection 107.05
108 - Prosecution and Progress
Delete Section 108
109 - Measurement and Payment
Delete Subsections 109.06, 109.07, 109.08, 109.09
109.01 Measurement of Work
109.02 Measurement Terms and Definitions
151 – Mobilization and Bonding
153 - Contractor Quality Control
153.07 Records and control charts
155 - Schedules for Construction Contracts
155 Delete
155 - Schedules for Construction Contracts
Delete Section 155
203 – Removal of Structures and Obstructions
625 – Turf Establishment
713 – Roadside Improvement Material
SPS 170 - Water
SPS 719 – Construction Report
SPS 720 – Bat Compatible Closure
Preface Preface_wo_03_27_2023
Delete all but the first paragraph and add the following:
The Forest Service, US Department of Agriculture has adopted FP-14 for construction of National Forest System Roads.
101 - Terms¸ Format¸ and Definitions
Add the following paragraph to Subsection 101.01:
101.01 Meaning of Terms.
101.01 _National_11_9_2016
Delete all references to the TAR (Transportation Acquisition Regulations) in the specifications.
Add the following to Subsection 101.03:
101.03 Abbreviations.
(a) Acronyms.
AGAR — Agriculture Acquisition Regulations AFPA
— American Forest and Paper Association FSAR —
Forest Service Acquisition Regulations MSHA —
Mine Safety and Health Administration NESC —
National Electrical Safety Code
WCLIB — West Coast Lumber Inspection Bureau
(f) Miscellaneous unit abbreviations.
MP — milepost location ppm — parts per million volume
STA station location
Make the following changes to Subsection 101.04:
101.03_National_11_9_2016
101.04_National_1_22_2020
101.04 Definitions.
Delete these definitions and replace the following:
Bid Schedule — The Schedule of Items.
Bridge — A structure, including supports, erected over a depression or an obstruction such as water along a road, a trail, or a railway and having a deck for carrying traffic or other loads.
Contractor — The individual or legal entity contracting with the Government for performance of prescribed work. In a timber sale contract, the contractor is the “Purchaser”.
Culvert — Any structure with a bottom, regardless of fill depth, depth of invert burial, or presence of horizontal driving surface, or any bottomless (natural channel) structure with footings that will not have wheel loads in direct contact with the top of the structure.
Drawings — (Public Works Contracts) Design sheets or fabrication, erection, or construction details submitted to the CO by the Contractor according to FAR Clause 52.236-21 Specifications and Drawings for Construction. Also refers to submissions and submittals.
Notice to Proceed — (Public Works Contracts) Written notice to the Contractor to begin the contract work.
Right-of-Way — A general term denoting (1) the privilege to pass over land in some particular line (including easement, lease, permit, or license to occupy, use, or traverse public or private lands), or (2) Real property necessary for the project, including roadway, buffer areas, access, and drainage areas.
Solicitation—(Public Works Contracts) The complete assembly of documents (whether attached or incorporated by reference) furnished to prospective bidders.
Add the following definitions:
Adjustment in Contract Price — “Equitable adjustment,” as used in the Federal Acquisition Regulations, or “construction cost adjustment,” as used in the Timber Sale Contract, as applicable.
Change — “Change” means “change order” as used in the Federal Acquisition Regulations, or “design change” as used in the Timber Sale Contract.
Forest Service — The United States of America, acting through the Forest Service, U.S. Department of Agriculture.
Neat Line — A line defining the proposed or specified limits of an excavation or structure.
Pioneer Road — Temporary construction access built along the route of the project.
Purchaser — The individual, partnership, joint venture, or corporation contracting with the Government under the terms of a Timber Sale Contract and acting independently or through agents, employees, or subcontractors.
Protected Streamcourse — A drainage shown on the plans or timber sale area map that requires designated mitigation measures.
Road Order — An order affecting and controlling traffic on roads under Forest Service jurisdiction. Road Orders are issued by a designated Forest Officer under the authorities of 36 CFR, part 260.
Shop Drawings — (Timber and Stewardship Contracts) Referred to as “Drawings” in FP-14, include drawings, diagrams, layouts, schematics, descriptive literature, illustrations, lists or tables, performance and test data, and similar materials furnished by Purchaser to explain in detail specific portions of the work required by the contract.
Utilization Standards —
The minimum size and percent soundness of trees described in Public Works contract specifications or Timber Sale and IRTC contract provisions to determine merchantable timber.
Add Figure 101-1—Illustration of road structure terms:
102 - Bid¸ Award¸ and Execution of Contract 102.00_National_11_9_2016
Delete Section 102 in its entirety.
Delete Section 102.
103 - Scope of Work
Delete all of Section 103 except Subsection 103.01 Intent of Contract.
Delete Subsections 103.02, 103.03, 103.04, 103.05.
103.00_National_11_9_2016
104 - Control of Work
Delete Subsections 104.01, 104.02, and 104.04.
Delete Subsections 104.01, 104.02, 104.04.
104.00_National_11_9_2016
Add the following to Subsection 104.06:
104.06 Use of Roads by Contractor.
104.06_National_11_9_2016
The Contractor is authorized to use roads under the jurisdiction of the Forest Service for all activities necessary to complete this contract, subject to the limitations and authorizations designated in the Road Order(s) or described in the contract, when such use will not damage the roads or national forest resources, and when traffic can be accommodated safely.
105 - Control of Material
105.05_National_6_29_2020
105.05 Use of Material Found in the Work.
Delete 105.05 (a) and (b) and the last sentence of the second paragraph and substitute the following:
Materials produced or processed from Government lands in excess of the quantities required for performance of this contract are the property of the Government. Place excess material safely at government-approved location, at no additional cost to government.
106 - Acceptance of Work
Delete Subsection 106.01 and replace with the following:
106.01 Conformity with Contract Requirements.
Follow the requirements of FAR Clause 52.246-12 Inspection of Construction.
106.01 _National_7_18_2017
References to standard test methods of AASHTO, ASTM, GSA, and other recognized standard authorities refer to the methods in effect on the date of solicitation for bids.
Perform all work to the lines, grades, cross-sections, dimensions, and processes or material requirements shown on the plans or specified in the contract.
Incorporate manufactured materials into the work according to the manufacturer’s recommendations or to these specifications, whichever is more strict.
Plan dimensions and contract specification values are the values to be strived for and complied with as the design values from which any deviations are allowed. Perform work and provide material that is uniform in character and reasonably close to the prescribed value or within the specified tolerance range.
The purpose of a tolerance range is to accommodate occasional minor variations from the median zone that are unavoidable for practical reasons.
When standard manufactured items are specified (such as fence, wire, plates, rolled shapes, pipe conduits, etc., that are identified by gauge, unit mass, section dimensions, etc.), the identification will be considered to be nominal masses or dimensions. Unless specific contract tolerances are noted, established manufacturing tolerances will be accepted.
The Government may inspect, sample, or test all work at any time before final acceptance of the project.
When the Government tests work, copies of test reports are furnished to the Contractor upon request.
Government tests may or may not be performed at the work site. If Contractor testing and inspection is verified by the Government, the Contractor’s results may be used by the Government to evaluate work for acceptance. Do not rely on the availability of Government test results for process control.
Acceptable work conforming to the contract will be paid for at the contract unit bid price. Four methods of determining conformity and accepting work are described in Subsections 106.02 to 106.05 inclusive. The primary method of acceptance is specified in each Section of work. However, work may be rejected at any time it is found by any of the methods not to comply with the contract.
Remove, repair, or replace work that does not conform to the contract, or to prevailing industry standards where no specific contract requirements are noted. Removing, repairing, or replacing work; providing temporary traffic control; and any other related work to accomplish conformity will be at no cost to the Government.
(a) Disputing Government test results. If the accuracy of Government test results is disputed, promptly inform the CO. If the dispute is unresolved after reasonable steps are taken to resolve the dispute, further evaluation may be obtained by written request. Include a narrative describing the dispute and a proposed resolution protocol that addresses the following:
1. Sampling method;
2. Number of samples;
3. Sample transport;
4. Test procedures;
5. Testing laboratories;
6. Reporting;
7. Estimated time and costs; and
8. Validation process.
If the evaluation requires additional sampling or testing be performed, mutually agree with the Government on witnessing procedures and on sampling and testing by a third party laboratory. Use a third party laboratory accredited by the AASHTO accreditation program. Provide proof of the laboratory’s accreditation for the test procedures to be used. Do not use the same laboratory that produced the disputed Government test results or that produced the test results used as a basis for the dispute.
The CO will review the proposed resolution protocol and may modify it before final approval and execution.
The Government will use the approved resolution protocol test results to determine the validity of the disputed testing. If the Government test results are validated, the Contractor will be responsible for all costs associated with developing and performing the resolution protocol. If the Government test results are not validated, the Government will be responsible for all costs associated with developing and performing the resolution protocol. If the validity of the Government test results cannot be determined, the Contractor and Government will equally share all costs associated with developing and carrying out the resolution protocol.
(b) Alternatives to removing and replacing non-conforming work. As an alternative to removal and replacement, the Contractor may submit a written request to:
1. Have the work accepted at a reduced price; or
2. Be given permission to perform corrective measures to bring the work into conformity.
The request must contain supporting rationale and documentation. Include references or data justifying the proposal based on an evaluation of test results, effect on service life, value of material or work, quality, aesthetics, and other tangible engineering basis. The CO will determine disposition of the nonconforming work.
106.02 _National_11_9_2016
Delete Subsection 106.02 and replace with the following:
106.02 Visual Inspection.
Acceptance is based on visual inspection of the work for compliance with the specific contract requirements. Use prevailing industry standards in the absence of specific contract requirements or tolerances.
107 - Legal Relations and Responsibility to the Public 107.05_National_7_18_2017
Delete Subsection 107.05.
Delete Subsection 107.05.
108 - Prosecution and Progress
Delete Section 108 in its entirety.
Delete Section 108.
108.00_National_11_9_2016
109 - Measurement and Payment
Delete Subsections 109.06, 109.07, 109.08, and 109.09:
Delete Subsections 109.06, 109.07, 109.08, 109.09.
109.00_National_11_9_2016
109.01 _National_2_22_2019
Delete the third paragraph and Table 109-1 of Subsection 109.01 and replace with the following:
109.01 Measurement of Work.
Take measurements as described in Subsection 109.02 unless otherwise modified by the Measurement Subsection of the section controlling the work being performed. Table 109-1 indicates the accuracy required for quantities of the various pay units used in the Schedule of Items. Use this guide to determine the decimal placement in the final payment.
Table 109-1
Decimal Accuracy of Quantities for Final Payment
Pay Item Level of Precision Linear Foot 1
Exception--Timber, Steel, and concrete Piles 0.1 Station 0.1 Mile 0.01 Square Foot 0.1 Square Yard 0.1 Each 1 Acre 0.01 Gallon 1 M-Gals. 0.1 Cubic Yard 1 Exception--Structure Excavation; Sheathing Materials;
Bedding, Bed Course, and Backfill Materials; Gabions;
0.1
Exception--Concrete; Masonry 0.01 Pound 1 Ton 0.1 Exception--Calcium Chloride; Sodium Chloride; Hydrated Lime; Bituminous Materials; Pavements; Bed Course Materials
0.01
Hour 0.1
MFBM 0.01
Station Yard 1 Cubic Yard Mile 1 Ton Mile 1
109.02 _National_11_9_2016
Add the following sentence to Subsection 109.02(b):
109.02 Measurement Terms and Definitions.
(b) Contract quantity.
Contract quantities will be adjusted only when there are errors in the original design of 15% or more.
Arizona & New Mexico Site Maintenance and Minor Construction
151 – Mobilization and Bonding
151 – MOBILIZATION AND BONDING
151.01 Mobilization
Description
151.01 This work consists of moving personnel, equipment, material, and incidentals to the project and performing work necessary before beginning work at the project site. This work also includes obtaining permits, insurance, and bonds. Work at all sites is expected to be completed in succession or concurrently, therefore only one mobilization will be paid.
Add the following:
If the contractor elected to camp near the site, the contractor is responsible for arranging a camping site off the project site. The contractor may camp on NFS lands with FS approval. The contractor shall be responsible for keeping the camping area clean and free from all debris and food waste. Contractor will be required to provide sanitary facilities for the camp. No solid waste (trash) will be left on the forest. No security will be provided by the Forest Service at the site. The Contractor is responsible for any items, equipment or property left unattended or overnight at the Site.
Noxious Weed Control Requirements:
Clean all construction equipment prior to entry onto the project area. Remove all dirt and plant parts and material that could carry noxious weed seeds into the project area.
Only construction equipment so cleaned and inspected by the COR will be allowed to operate within the project area. Treat all subsequent move-ins of construction equipment in the same manner as initial move-ins. “Construction equipment” does not include personal vehicles or support equipment that remains on the main travel route.
To reduce the risk or spread of noxious and invasive weed species, standard equipment inspection and cleaning protocols will be utilized for all work involving off road travel consistent with the following technical guides: Inspection and Cleaning Manual for Equipment and Vehicles to Prevent the Spread of Invasive Species (Bureau of Reclamation Technical Memorandum No. 86-68220-07-05, June 2012), Invasive Plant Prevention Guidelines (Center for Invasive Plant Management, September, 2003), and Preventing the Spread of Invasive Plants: Best Management Practices for Land Managers, 3rd Edition (California Invasive Plant Council, 2012).
Emergency Spill Kit. Keep enough quantities of absorbent materials on the project site to absorb accidental fuel, hydraulic oil, or other petroleum product spills. Use absorbent materials that are biodegradable, non-water absorbing and designed specifically for the types of spills associated with the Contractor’s operation.”
A field meeting is required with the On-Scene-Coordinator (COR)/PI prior to developing the Work Plan. The Work Plan outlines the plans to complete the project within the contract time and in compliance with the Statement of Work and Specifications. It includes the timeline to complete the project (Gantt chart), including key milestones and activities; and strategies to complete milestones and activities. The Work Plan includes the Health and Safety Plan. One (1) Work Plan is required for the entire project.
151.02 Measure the Section 151 items listed in the bid schedule according to Subsection 109.02.
Payment
151.03 The accepted quantities will be paid at the contract price per unit of measurement for the Section 151 pay items listed in the bid schedule. Payment will be full compensation for the work prescribed in this Section. See Subsection 109.05.
Progress payments for mobilization lump sum will be paid as follows:
(a) Bond premiums will be reimbursed according to FAR Clause 52.232-5 Payments Under Fixed-Price Construction Contracts, after receipt of the evidence of payment.
(b) When 5 percent of the original contract amount is earned from other bid items, 50 percent of the mobilization item, or 5 percent of the original contract amount, whichever is less, will be paid.
(c) When 10 percent of the original contract amount is earned from other bid items, 100 percent of the mobilization item, or 10 percent of the original contract amount, whichever is less, will be paid.
(d) Any portion of the mobilization item in excess of 10 percent of the original contract amount will be paid after final acceptance.
153 - Contractor Quality Control
153.07 Records and control charts
Maintain complete testing and inspection records by pay item number and make them accessible to the CO and COR.
155 - Schedules for Construction Contracts
155 Delete.
Delete Section 155 in its entirety.
156 – PUBLIC TRAFFIC
Delete Section 156 in its entirety and replace with the following:
156.01 This work consists of controlling and protecting public traffic adjacent to and within the project.
Material
156.02 Conform to the MUTCD and the following Sections and Subsections:
Permanent Traffic Control 633 Traffic Signing and Marking Material 718 Concrete Barriers and Precast Guardwalls 618 Temporary Plastic Fence 710.11
Construction Requirements
156.03 General. Accommodate traffic according to MUTCD, approved traffic control plan and this section. Perform work in a manner that ensures safety and convenience of the public.
Except for roads with a valid Road Closure Order, keep existing roads open to all traffic during road improvement work, and maintain them in a condition that will adequately accommodate traffic. Accommodate public traffic on roads adjacent to and within the project until the project is accepted according to Subsection 106.07(b).
Submit traffic control plan at least 30 days prior to intended use. Perform no work that interferes or conflicts with traffic or existing access to the roadway surface until a traffic control plan has been approved.
Post construction signs and traffic control devices in conformance with MUTCD and Forest Service EM 7100-15. All required signs will be in place and approved prior to beginning work on project.
Delete Section 156.05. Add the following:
156.05 Temporary Closures. Road segments may be closed incidentally, no more than 15 minutes at each closing. Maintain traffic control devices and use flaggers during closure periods. Appropriate barricades and signs will be erected and maintained as shown in the traffic control plan or as otherwise designated.
Delete Section 156.09 in its entirety.
Delete Section 156.10 and replace with the following:
156.10 Acceptance. Public traffic work will be evaluated under Subsection 106.02.
Measurement and Payment
Delete Section 156.11 and replace with the following:
156.11 Do not measure Public Traffic for payment. Compensation for this item shall be incidental to Section 151 Mobilization.
155 - Schedules for Construction Contracts 155.00_National_11_9_2016
Delete Section 155 in its entirety.
Delete Section 155.
203 – Removal of Structures and Obstructions
Description 203.01 This work consists of removing, hauling, and disposing off-site of the existing range fence and components at the former Lead Queen Mine.
Corner posts and braces shall be removed entirely or cut at the footer Care shall be taken that no sharp ends of remaining posts remain Existing gate shall be set aside on-site
Measurement
203.10 Measure the Section 203 pay items listed in the bid schedule according to Subsection
203.11 The accepted quantities will be paid at the contract price per unit of measurement for the Section 203 pay items listed in the bid schedule. Payment will be full compensation for the work prescribed in this Section. See Subsection 109.05.
625 – Turf Establishment
625.01 This work consists of soil preparation, watering, fertilizing, mulching, seeding, and rolled erosion control product installation.
625.03 General
625.05 Seed Bed Preparation. Seed bed preparation refers to work necessary to prepare the soil surface to receive hand seed and/or hydromulch.
Use FP-14 Specifications and add:
The surfaces of areas to be seeded shall be decompacted to a depth of 6-10” perpendicular to the natural flow of water. Scarification/decompaction equipment (ripping tines, chain harrow, hand tools) will be used in such a manner that scarification furrows are no further than 6-9inches apart and, where possible, equipment will travel across the site in perpendicular directions (cross-hatched pattern). However, the contractor shall take care not to disturb existing vegetation established at the site.
Once decompaction has occurred the soil surface should appear roughened, such that obvious furrows are eliminated. The contractor shall take care to not re-compact the topsoil. Conduct scarification/decompaction activities no more than two days before seeding.
625.06 Watering. Moisten seeding areas before seeding.
625.08 Seeding. Apply seed to the Marstellar Mine
(a) Dry method. Apply the seed with approved power-driven seeders, drills, or other mechanical equipment. Hand-operated seeding methods are satisfactory on areas inaccessible to mechanical equipment.
Coronado Seed Mix – Perenial Graminoid Seed Mix Seed Variety
(Common Name) Seed Variety
(Scientific Name) Rate/ acre
(PLS – pure live seed) Sideoats grama Bouteloua curtipendula 4
Hairy grama or Blue Grama Bouteloua Hirisuta or Bouteloua gracilis
Plains bristlegrass Setaria vulpiseta 1
Cane beardgrass Bothriochloa barbinodis 1
Green sprangletop Leptochloa dubia 2
Plains lovegrass Erograstis intermedia 3
Section 629. — Rolled erosion control products and cellular confinement systems
Refer to FP-14 and add the following:
(a) Erosion Control Netting will be placed on the east facing slope of the Marstellar Mine
Area after seeding activities are completed. The contractor shall furnish an erosion control netting composed of certified weed free processed all-natural fibers (i.e. coir, excelsior, jute) mechanically bound between two all-natural fiber nettings to form a continuous matrix with a minimum dry weight of 0.4 pounds per square yard according to ASTM D 6475. U-shaped wire staples with 12 inch long legs and No. 11 diameter or of sufficient hardiness to facilitate installation without bending shall also be used.
Installation shall follow the manufacturer’s instructions. The Contractor shall limit the amount of traffic over the netting once it has been installed.
625.11 Measure the Section 625 items listed in the bid schedule according to Subsection
Measure the Section 625 items listed in the bid schedule according to Subsection 109.02
713 – Roadside Improvement Material
713.04 Seed. Conform to the Federal Seed Act, the Federal Plant Protection Act, and applicable state and local seed and noxious weed laws. Do not use wet, moldy, contaminated, or damaged seed. Provide each seed type in separate sealed containers. Clearly label each container with the following:
(a) Name and type of seed;
(b) Lot number;
(c) Net mass;
(d) Percent of purity, germination, and hard seed;
(e) Percent of maximum weed seed content;
(f) Seed origin;
(g) Noxious weeds present;
(h) Other crop seed;
(i) Inert matter;
(j) Name and address of seed distributor; and
(k) Mixture percent of each component.
Contractor will furnish and apply the following Seed Mix for vegetation for erosion control. The list below states the requirements for the pounds of pure live seed (PLS) per acre for each individual grass species in the mix. All seed mixes must be certified weed free. The seed mix will be applied by hand broadcasting.
All seed purchased will be certified to be free of the noxious weed seeds from weeds listed on the current ‘All States Noxious Weeds List’. Test results from a certified seed analyst and seed analysis labels attached to the bags will be provided to the COR.
SPS 170 - Water
SPECIAL PROJECT SPECIFICATION 170 – WATER
170.01 This work consists of developing an acceptable water supply, furnishing, hauling, and applying water.
Materials
170.02 Conform to the following subsection.
Water 725.01
170.03 Development of Supply & Access. Develop water supplies and access to the water supplies as required. The Contractor is responsible for finding an appropriate water source. Before using water sources, obtain all necessary permissions (i.e. rancher, tribe, private landowner, etc.), water rights, and permits. Provide a copy of permissions to the
COR.
170.04 Equipment. Provide mobile watering equipment with watertight tanks of known capacity. Provide for positive control of water application from the driver’s position.
170.05 Application. Apply water uniformly without ponding or washing.
170.06 Acceptance. Developing water supplies and watering will be evaluated under
Subsections 106.02 and 106.04.
Measurement
170.07 Measure the Section 170 items listed in the bid schedule according to Subsection
170.08 This pay item is incidental to other pay items in the Schedule of Items in Section 204.
SPS 719 – Construction Report
719.01 This work consists of furnishing qualified personnel to prepare a construction report for the Arizona and New Mexico Sites.
Personnel shall conform to the following:
(a) Personnel. Furnish technically qualified personnel experienced in preparing construction reports. Provide personnel capable of performing in a timely and accurate manner.
Personnel shall take photos as the project progresses and prepare technical notes and reports throughout the project.
Requirements
719.02 General. Before commencing the project, photos shall be taken of the existing topography and Site setting. Photos shall be taken at all key aspects of the project.
The final construction report shall consist of the following outline:
TABLE OF CONTENTS
1.0 INTRODUCTION
1.1 BACKGROUND
1.2 PROJECT BACKGROUND
1.3 SCOPE OF WORK
2.0 PROJECT ACTIVITIES
2.1 EXECUTIVE SUMMARY OF FIELDWORK
2.2 LESSONS LEARNED
3.0 REFERENCES
Appendix A – Photographic Log Appendix B – Materials Source Certifications
Project Activities includes a detailed description of all key aspects of the project, i.e. type of equipment used throughout the project, key onsite personnel, any submittal certifications, digital photographs, subcontractors, and any other key information. Draft construction report shall be submitted to the COR at 100% fieldwork completion. All photo files shall be included in a flash drive in .jpg format, separate from the report. Photos shall be taken throughout the progress of the project. Final report shall be submitted in flash drive and hard copy within 10 days of COR approval of Draft.
The Final report should include the required information for all sites. The Final Report shall be submitted 10 days after acceptance of the Draft Report.
719.03 Acceptance. Report will be evaluated under Subsections 106.02 and 106.04.
719.04 Measurements shall be evaluated based on the content and detail of the requirements listed in 719.02. The Contractor shall submit a FINAL report within 14 days of receipt of the comments on the draft report from the COR.
719.05 The accepted quantities will be paid at the contract price per unit of measurement for the Special Project Specification 719 pay item listed in the bid schedule. Payment will be full compensation for the work prescribed in this Section.
SPS 720 – Bat Compatible Closure
720.01 This work consists of furnishing qualified personnel to furnish materials, install and construct the physical safety closures at the Blue Nose Mine
720.02 General
Requirements Install physical safety hazards within the project as shown on the Drawings and as follows:
720.03 Closure with Adjustable Bat-friendly Grates and Bat Cupolas
This work will consist of fabricating and installing a special grate consisting of steel bars allowing for bat ingress and egress while providing protection for the public.
720.03 a) Closure with Adjustable Bat-friendly Grates for Adits. This design is adjustable for both height and width. Drawings provided indicate a 2ft upright footing supporting a main upright 4’-6” in length. This combination provides height adjustment from 4’-6” to 6’-0” with a 6” penetration of the main upright into the upright footing.
Drawings provided indicate a 48” main crossbar with 18” spacers. This combination provides a width adjustment from 4’-0” to ‘-0” with a 6” penetration of the main crossbar and the spacer. Drawings are provided to illustrate the design, construction, and installation of the adjustable bat-friendly grate structure.
Main Components of the adjustable bat-friendly grate design are:
a. Upright footing- 3 ½” x 3 ½” x 3/8” Hollow Structural Section (HSS); Refer to Illustration Upright Footing
b. Main Upright- 2 ½” x 2 ½” x 5/16” HSS; Refer Illustration Upright Footing
c. Rock Bolts- 5/8” round steel 12” long; Refer to Illustration Upright Footing
d. Pipe- 2” diameter steel pipe; Refer to Illustration Removable Bar and Lock
The proposed design shall accommodate a typical adit with dimensions less than or equal to 6’x6’ but greater than 4’x4’. When building multiple grates in the same vicinity, the height of the upright footing and the length of the main crossbar shall be chosen so that the total amount of adjustment will accommodate the largest number of installations. However, the following design adjustments must be observed:
a . For main crossbar widths of 8’ a third upright assembly (upright footing and main upright) must be installed and for every additional 4’ in length thereafter b . For main crossbar widths of 8’ a third upright assembly (upright footing and main upright) must be installed and for every additional 4’ in length thereafter c . Main crossbars may extend in length of up to 8’. For main crossbars of 8 feet or greater, crossbars shall be constructed of 48” lengths joined at each upright assembly
d. Only one section of removable bar is required per installation
Upright assembly installation:
a. Determine the position of the upright footings and pre-drill holes for rock bolt installation. Rock bolt locations must be on the mine-side of the grate
b. Slide the main upright into the upright footing and stand the upright assembly in place
c. The main upright must be placed so that when the hangers are installed, they face into the mine and away from the portal
d. Bolt the upright footing to the floor using the lowest grate bar. Bolts should be placed on 1’ centers
e. Extend the main upright to the adit roof and locate the position of the rock bolt in the adit roof.
Lower the upright and drill the required hole
f. Extend the main upright to the roof and bolt in place. Then weld the flanges of the main upright to the sides of the upright footing
Crossbars installation:
a. Crossbars are to be welded to the main upright assembly
b. Cross bars must be placed to provide a 5 ¾” free space between the top of each cross bar and the bottom of the next
c. The spacing between the top bar and the adit roof may vary to accommodate the roof line but spacing must not be more than 8”. If spacing along the top for any interval greater than 1 ft is more than 8”, then a final crossbar must be installed to close the gap. Spacing between this crossbar and the last may be less than 5 ¾” to accommodate placement
d. Connections between the adit roof, rib and floor will be made by using 5/8” steel rods (“rock bolts”) anchored in at least 8” of competent rock. The rods may be press-fit or glued in place using a standard construction grade 2-part epoxy
e. The top, bottom, and every 5th crossbar assembly (main crossbar and spacers) must be bolted to the adit rib at both ends
A: Illustration – Closure Using Adjustable Bat-Friendly Grates
B: Illustration – Closure Using Adjustable Bat-Friendly Grates
C: Illustration – Closure Using Adjustable Bat-Friendly Grates
Closure Using Corrugated Steel Pipe: This work shall consist of installing a corrugated steel pipe (CSP) adit closure including clearing and grubbing, excavation of loose material, and trimming of the adit, furnishing all necessary materials including a drainage pipe (when necessary) and a grated access door.
Materials:
Corrugated Steel Pipe (CSP) shall consist of 12-gauge galvanized steel pipe with helical or annular corrugations. The pipe must be free of rust, gaps in seams, holes, and deformation that reduce the inside diameter by more than two inches (2”).
When concrete is used to anchor the CSP, the concrete shall have a minimum rated compressive strength of 3500 psi at 28 days. Structural steel used in the fabrication of the graded closure, shall conform to the requirements of ASTM A-36 all-purpose steel.
Clearing and Grubbing:
The work site shall be cleared and grubbed of debris loose rocks and other items which interfere with construction as approved by the COR. All garbage and debris shall be disposed of at an approved disposal site as directed by the /COR.
Excavation and Installation:
The adit opening shall be cleared of loose rock and debris to create a planar bedding surface for the CSP. Any material placed in the floor of the adit to bed the pipe shall consist of material less than four inches (4”) in diameter. After installation of the CSP, the space between the pipe and the adit walls shall be backfilled with unclassified material the entire length of the CSP except the front three feet 3 of backfill which shall consist of concreted durable rock. The rock to be concreted shall be a minimum of four inches (4”) in diameter. PUF may be substituted for concrete with the consent of the COR.
Grated Access Door Installation:
After placement of the CSP, the grated access door shall be welded in place. Unless otherwise specified, the grated access door shall be a bat-friendly design meeting the specifications listed herein. The grate may be welded or bolted in place. Sufficient space shall be provided for the door to open smoothly to provide full access to the CSP.
Acceptance
720.04 Physical Safety Hazards shall be evaluated by the COR and 106.03 Certification.
Payment 720.05 Payment will be full compensation for the work described for the following:
720.06 Closure with Adjustable Bat-Friendly Grates with Access (48” and 36” Culvert). The accepted quantities at the Sites will be paid at the contract price per unit of measurement for the SPS 720.03 a) pay items listed in the bid schedule. Payment will be full compensation for the work prescribed in this Section. See Subsection 109.02.
Appendix A: Photos
Blue Nose Adit
Lead Queen Fencing
Lead Queen Fencing Fig. 2
Appendix B: Blue Nose and Marstellar Map