Attachment 1 Statement of Work Moxee Farm Well.pdf

PDF 198 KB Posted

Attached to
Urgent Farm Well Repairs, Wapato, Washington
Solicitation number
1232SA26Q0530
Issued by

About this file

This is a Statement of Work (SOW) for a well pump replacement and screen pull project at the USDA Agriculture Research Service Temperate Tree Fruit and Vegetable Research Unit in Wapato, Washington.

The contractor shall furnish a technical and cost proposal to complete the following scope of work: remove the existing riser, motor, pump, and sand separator; pull 148 feet of sand screens located at a depth of approximately 480-600 feet; bail the well for up to 16 hours; video the well; determine the appropriate depth for the new pump assembly; supply and install a new properly sized motor, pump, and sand separator assembly; extend #2 flat jacket wire if necessary; and perform a functionality test to ensure proper operation. All construction must comply with ARS Facilities Design Standards (ARS Manual 242.1, 5-01-12), ARS Energy, Water, and Sustainability Policy (ARS Policy & Procedures 134.2, 11-12-13), applicable building codes, and all local, regional, state, and federal regulations. The contractor is responsible for obtaining all required permits and licenses, with associated costs borne by the contractor. The contractor must maintain quality control, keep the site clean and free of debris, track and document waste diversion to recycling, and provide submittals for all proposed materials to the Contracting Officer and Contracting Officer's Representative (COR) for approval prior to ordering. The contractor shall provide a one-year warranty on all work performed and notify the government in writing 10 days prior to final inspection. No site visit is required. Key government points of contact include the Research Program Representative (Dr. Rodney Cooper), the Engineer Project Manager/COR (John Harvey), and the Location Monitor (Jerald Gefre).

View the file

Other files

File Type Posted
Attachment 2 Wage Determination.pdf PDF
1232SA26Q0530.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Moxee Farm Well

TTFVRU Wapato Moxee Farm well pump replacement and screen pull

USDA Agriculture Research Service

Wapato, WA

Project Title: “TTFVRU Wapato Domestic Water Pump Skid”

1. Government Points of Contact

a) Contracting Officer (CO):

b) Research Program Representative (RPR):

Dr. Rodney Cooper

(509) 454-6565 rodney.cooper@usda.gov

c) Occupational Health and Safety Representative:

Ken Cushman

(510) 559-6002 ken.cushman@usda.gov

d) Engineer Project Manager (EPM)/Contracting Officer’s Representative (COR):

John Harvey (509)454-6553 john.harvey@usda.gov

e) Location Monitor Wapato (LM): Jerald Gefre (509)575-5904 jerald.gefre@usda.gov

2. Location: The site of work is the US Agricultural Research Service location, Temperate Tree

Fruit and Vegetable Research Unit 16290 Hwy 24 Moxee WA 989036

3. Site Visit: A site visit and inspection tour is not required

4. Scope of Service: The contractor shall provide all professional services necessary for the accomplishment of the contract project and such required services shall be in accordance with requirements as described herein.

a) The Contractor shall provide services for the following tasks marked by an “X”.

[X] Provide a technical and cost proposal to complete the project as per project requirements.

5. Project Requirements: Contractor shall furnish a technical and cost proposal to install the following.

I. Contractor will remove existing Riser, Motor, pump and sand separator.

II. Contractor will pull 148’ of sand screens located at a depth of approximately 480-600 feet III. Contractor will bail well for up to 16 hrs.

mailto:rodney.cooper@usda.gov mailto:ken.cushman@usda.gov mailto:john.harvey@usda.gov mailto:jerald.gefre@usda.gov

IV. Contractor will Video well V. Contractor will determine appropriate depth to set new pump assembly.

VI. Contractor will supply and install new properly sized motor, pump, and sand separator assembly.

VII. Contractor will extend #2 flat jacket wire if necessary.

VIII. Contractor will perform a functionality well test to ensure proper function

6. Documents: See attached map

7. Description of Work:

Pump Skid:

a) Remove existing Riser pump assembly

b) Pull existing screens.

c) Bail well.

d) Install riser and new pump assembly.

e) Test

f) References & Standards: All construction shall comply with ARS Facilities Design Standards (ARS Manual 242.1, 5-01-12), ARS Energy, Water, and Sustainability Policy (ARS Policy & Procedures 134.2, 11-12-13), ARS Energy, Water, and Sustainability Policy Bulletin (ARS Policy & Procedures Bulletin 15-134.2), governing Building Codes, and all applicable local, regional, State, and Federal regulations. Where one or more Codes or regulations conflict, the more stringent shall apply.

g) Permits: Where governing regulations and imposed codes and standards require notices, permits, licenses, inspections, tests, and similar items or actions in order to lawfully proceed with the required work, the Contractor shall obtain items and take those actions in accordance with the regulations of the governing authority. The costs of such permits, licenses, inspections, etc., are the obligation of the Contractor.

h) Existing Installations/Demolition:

a) Contractor shall modify existing installations as needed to accommodate the new installation. Where applicable contractor shall coordinate demolition or modification of existing installations with the Owner. All disturbances of existing systems shall be thoroughly coordinated with the Owner to prevent disconnecting equipment that may potentially jeopardize in-progress research.

b) The Owner reserves the right to retain any equipment or materials removed as part of this scope of work. The Contractor shall coordinate any equipment or materials to be retained with the Owner prior to starting demolition operations. The Contractor shall legally dispose all equipment or material removed that will not be retained.

c) The contractor shall divert project waste to recycle where practical. The Contractor shall track and document the amount of waste diverted to recycle. The contractor shall submit diversion documentation as part of closeout. If no waste is diverted to recycle, the contractor shall submit a letter stating so and why diversion was not practical.

i) Quality Control: The work performed under this contract shall be subject to continuous audit by the COR. Quality control is the exclusive responsibility of the Contractor.

j) Temporary Facilities:

a) Temporary utilities (water and electricity) may be furnished to the Contractor by the Government, if so requested. The Contractor shall maintain and protect all such utilities during the course of construction and shall repair or replace any items damaged through its own negligence.

b) Should the Contractor require any power or utility shutdowns during construction, the Contractor shall obtain approval for such shutdown from the Location Monitor three working days prior to the need

k) Site Cleanup: The construction site shall be kept clean and free of debris at all times. Restore areas disturbed as nearly as possible to the original appearance and condition. Upon completion of the project, and prior to final inspection, the Contractor shall remove from the premises all unused material, trash, and debris resulting from the work to the satisfaction of the COR.

8.Submittals:

a) For all proposed material, contractor shall provide concrete mix design, relevant illustrations, standard schedules, performance charts, instructions, brochures, diagrams, manufacturer descriptive literature, or catalog data.

b) The descriptive literature shall be annotated/highlighted to show its conformance with contract requirements.

c) Submittals are required for all building materials and equipment and shall be provided to the CO and COR for review and approval.

d) Contractor is responsible for any costs incurred for equipment ordered without prior approval.

Final Inspection:

The Contractor shall notify the Contracting Officer and Owner in writing 10 days prior to the date that the project will be ready for final inspection. An inspection of the project will be made by the Contracting Officer and Contractor at a mutually agreed upon time. COR and contractor shall compile a “punch list” prior to final acceptance of the installation and submit completed warranty documentation to manufacturer.

Warranty:

In addition to any other warranties set out elsewhere in this contract, the Contractor warrants that work performed under this contract conforms to the contract requirements and is free of any defect of equipment, material or design furnished, or workmanship performed by the Contractor or any of his subcontractors or suppliers at any tier. Such warranty shall continue for a period of one year from the date of final acceptance of the project. Under this warranty, the Contractor shall remedy at his own expense any such failure to conform or any such defect. In addition, the Contractor shall remedy at his own expense any damage to Government owned or controlled real or personal property, when that damage is the result of the Contractor's failure to conform to contract requirements or any such defect of equipment, material, workmanship, or design. The Contractor shall also restore any work damaged in fulfilling the terms of this clause. The Contractor's warranty with respect to work repaired or replaced hereunder will run for one year from the date of such repair or replacement.

Notification and Compliance: The Government shall notify the Contractor in writing within a reasonable time after the discovery of any failure, defect, or damage. Should the Contractor fail to remedy any failure, defect, or damage within a reasonable time after receipt of notice thereof, the Government shall have the right to replace or repair and have the cost billed to the Contractor.

Latent Defects:

The Warranty specified herein shall not limit the Government’s rights with respect to latent defects, gross mistake, or fraud.

Acceptance:

Upon satisfactory submittal of the above documents the Contracting Officer shall issue to the Owner a certificate recommending final acceptance of the project.

Minor unfinished items of work may be listed on the certificate and accepted from final acceptance. A sum sufficient to cover the cost of completing these unfinished items of work will be withheld by the Owner from the final payment. All other funds including retainage shall be due and payable upon receipt by the Owner of the Contracting Officer's certificate. Upon certification by the Contracting Officer that the items of work have been completed, all monies withheld by the Owner shall be due the Contractor

END