This statement of work describes a project to replace the septic system at the Northern Great Basin Experimental Range in Riley, Oregon. The Agricultural Research Service is seeking a contractor to remove the existing corroded metal septic tank and sewer lines connecting two residences, and install a new septic system with a minimum 1000-gallon tank and approximately 250 feet of disposal trenches. The work must be completed by September 1, 2023 and adhere to Oregon regulations for on-site sewage disposal. The contractor will be responsible for obtaining necessary permits and arranging a final inspection from the Oregon Department of Environmental Quality to certify satisfactory completion.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

United States Department of Agriculture Agricultural Research Service

STATEMENT OF WORK

NGBER Septic System Replacement

Range and Meadow Forage

Management Research Laboratory

BURNS, OREGON

STATEMENT OF WORK

TABLE OF CONTENTS

1.0 Project Information

2.0 Project Contact Persons

3.0 Scope of Work

4.0 Project Requirements

5.0 Background and Site Description

6.0 Description of Work

7.0 Specialized Requirements

8.0 Maps

1.0 Project Information:

A. Project Title: NGBER septic system replacement

B. Project Location: Northern Great Basin Experimental Range, Riley, OR;

managed by Range and Meadow Forage Management Unit, Burns, Oregon

2.0 Project Contact Persons:

CONTRACTING OFFICER (CO):

Lam Pham Email: lam.pham@usda.gov

CONTRACTING OFFICER REPRESENTATIVES (COR)

Peter Lane Email: peter.lane@usda.gov

RESEARCH PROGRAM REPRESENTATIVES (RPR):

Dr. Chad Boyd, RL Phone: (541) 573-8939 USDA, ARS, PWA Email: chad.boyd@usda.gov Range and Meadow Forage Management Research Unit 67826-A Hwy 205 Burns, Oregon 97720

LOCATION ADMINISTRATIVE OFFICER (LAO):

Dawnetta Hauth Phone: (541) 573-8909 USDA, ARS, PWA Email: dawnetta.hauth@usda.gov Range and Meadow Forage Management Research Unit 67826-A Hwy 205 mailto:lam.pham@usda.gov mailto:peter.lane@usda.gov mailto:chad.boyd@usda.gov mailto:dawnetta.hauth@usda.gov

Burns, Oregon 97720

A. Area Safety Manager (ASHM):

Phil Smith Phone: (979) 260-9449 USDA, ARS, PWA Email: phil.smith@usda.gov 1001 Holleman Drive East College Station, Texas 77840

3.0 Scope of Work:

The Contractor shall provide all professional services necessary for the accomplishment of each project and such required services shall be in accordance with requirements as described herein.

A. The Contractor shall provide services for the following tasks marked by an

“X”:

[X] Provide a cost estimate to complete the project as per requirements.

[X] Provide materials for and install a new septic system.

4.0 Project Requirements:

Contractor will work with site personnel to ensure each task is accomplished in a timely manner.

A. Project Title: NGBER septic system replacement B. Project Location: USDA-Agricultural Research Service, Northern Great

Basin Experimental Range, Riley, Oregon 97758 C. The contractor’s work shall adhere to the criteria stated within this SOW.

D. Project will be completed on or before September 1, 2023.

E. System will be capable of a 450 gallon/day flow.

F. Septic tank will be a minimum of 1000 gallons.

G. Total linear distance of disposal trench approximately 250 feet.

H. Contour the trenches across the hillside to maintain a 24 inch depth I. All construction must be using Oregon Department of Environmental

Quality approved materials.

J. Any person other than the property owner must be licensed by the Oregon

Department of Environmental Quality to install and/or construct an on-site sewage disposal system.

K. A final inspection is required after the gravel and pipe are installed in the disposal trenches but before the trenches are backfilled. The system must be inspected and a Certificate of Satisfactory Completion issued before it may be used. When you are ready for this inspection, please call the Harney County Planning Department office in Burns at 541-573-6655, or the Department of Environmental Quality Office in Bend at 541-388-6146.

mailto:phil.smith@usda.gov

5.0 Background & Site Description:

The Northern Great Basin Experimental Range (NGBER) is managed by the ARS Range and Meadow Forage Management Unit. NGBER covers approximately 16,000 acres of sagebrush steppe rangeland and is grazed by cattle during the spring and summer months. There are several residences on the property that are used seasonally by researchers when they are conducting research at NGBER. This is convenient, saves travel cost, and increases safety as NGBER it is an 80 mile round trip drive from our Burns office complex.

Two of the residences share a common septic system that has recently malfunctioned, is at the end of its service life, and needs to be replaced. This is a very remote area with very few septic installation companies within a 100 mile radius (See Location Map in section 8.0).

6.0 Description of Work

Work will involve replacement of the septic system shared by two adjacent residences at NGBER (see Residence Map in 8.0 below). The current tank is metal and has corroded to the point where it is not usable and will need to be replaced. Sewer lines from each house to the septic tank will also need to be replaced. The leach field and associated pipe will need to be replaced. Below is the report of completion and drawings for site plans from the previous installation, including a diagram with distances.

7.0 Specialized Requirements

It will be the contractor’s responsibility to obtain all necessary county and state permitting and to arrange for and pass a final inspection from the Oregon Department of Environmental Quality. All work must conform to Oregon Administrative Rules, Chapter 340.

8.0 Location Map

Directions to the Northern Great Basin Experimental Range Facility

After turning south off of Hwy 20, travel 3.8 miles on gravel road to reach NGBER headquarters