Attachment 1 Statement of Work.pdf
PDF 109 KB Posted
- Attached to
- Z1DA--Repaint Various Buildings & Corridors Federal contract opportunity
- Solicitation number
- 36C24623B0040
About this file
This statement of work describes a project to repaint basement and connecting corridors at the Salem VA Medical Center. The contractor will be required to scrape and prep existing painted surfaces in the basement corridors and connecting corridors of 15 buildings, applying one primer coat and two finish coats of paint. The work will involve prepping and painting interior corridor walls, door jambs, ceilings, and windows. As lead may be present, the work must be performed in accordance with OSHA lead standards. The contractor must provide all labor, equipment, materials, and supervision for the painting work. The performance period is 365 calendar days from notice to proceed.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| S07 36C24623B0040 Bid Abstract.pdf | ||
| 36C24623B0040 0005.docx | DOCX document | |
| 36C24623B0040 0003.docx | DOCX document | |
| 36C24623B0040 0002.docx | DOCX document | |
| 36C24623B0040 0001.docx | DOCX document | |
| S04 Site Visit 7-6-2023.pdf | ||
| 36C24623B0040.docx | DOCX document | |
| Attachment 4 Wage Determination.pdf | ||
| Attachment 2 Project Specifications.pdf | ||
| Attachment 3 Project Drawings.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SCOPE OF WORK
Repaint Basement and Connecting Corridors
Project Number 658-23-001 Salem VAMC
The Contractor shall furnish all labor, material, tools, equipment, transportation, and qualified supervision to perform the work as described in the contract drawings and specifications for Project
658-23-001 Repaint Various Basement and Connecting Corridors at the Salem VA Medical
Center, Salem, VA. Contractor shall prep/paint all existing interior painted basement building corridor surfaces and interior connecting corridor painted surfaces for Buildings
1,2,4,5,7,8,9,10,11,12,74, 75,76, 77 and 143. The work will be performed on all interior basement corridors and the interior connecting corridors between buildings listed above. Contractor shall scrape existing loose paint and prepare surfaces for painting with 1 primer coat and 2 finish coats.
Work shall require prepping/painting corridor walls and door jambs (both sides of door) in building corridors. For the connecting corridors interior walls, ceilings and windows shall be prepped and painted. Contractor shall assume all painted surfaces contain detectable levels of lead and shall perform work in accordance with OSHA standards for lead in construction. Contractor shall provide all painting labor/equipment/ladders to perform new paint application. All work shall be performed in strict accordance with specifications and drawings.
If selected, the construction time allocated for completion of the work associated with Bid Item I as described above, is 365 calendar days from notice to proceed (NTP) by the Contracting Officer.