Attachment 1 Statement of Work.pdf
PDF 929 KB Posted
- Attached to
- Tunnel Repair-Tobyhanna Army Depot
- Solicitation number
- W25G1V23R0016
About this file
This is a solicitation for tunnel repair services at Tobyhanna Army Depot. The solicitation is a total small business set-aside for NAICS code 238110, with proposals due by July 17, 2023. A site visit will be held on June 26, 2023 for offerors to attend. Camera passes are required for taking photos during the site visit. The scope of work involves repairing the below-grade tunnel located between buildings 10 and 1B, including remedial curtain wall crack injection, crack sealing, and epoxy painting of walls, ceiling and floor. The period of performance is 120 days after notice to proceed.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
IJO# 757511
SPECIFICATIONS
For
BUILDING 10 Tunnel Rehabilitation
Date: February 1, 2023
Prepared By:
TOBYHANNA ARMY DEPOT
ENGINEERING DIVISION
11 HAP ARNOLD BOULEVARD
TOBYHANNA, PA 18466‐5100
Building 10 Tunnel Rehabilitation B10TUNNEL
PROJECT TABLE OF CONTENTS
DI VI SI ON 01 - GENERAL REQUI REMENTS
01 11 00.00 99 08/15 SCOPE OF WORK
01 14 00.00 99 11/11 WORK RESTRICTIONS
01 30 00.00 99 08/15 ADMINISTRATIVE REQUIREMENTS
01 32 33.00 99 03/2014 CONSTRUCTION PHOTOGRAPHY
01 33 00.00 99 01/2018 SUBMITTAL PROCEDURES
01 35 26.00 99 11/15 GOVERNMENTAL SAFETY REQUIREMENTS
01 35 53.00 99 10/21 TYAD SECURITY REQUIREMENTS
01 42 00 11/14 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00.00 99 04/17 QUALITY CONTROL
01 50 00.00 99 08/09 TEMPORARY CONSTRUCTION FACILITIES AND
CONTROLS
01 57 19.00 06 09/17 TEMPORARY ENVIRONMENTAL CONTROLS AND
PERMITS
01 74 19.00 99 01/07 CONSTRUCTION AND DEMOLITION WASTE
MANAGEMENT
01 78 00.00 99 08/11 CLOSEOUT SUBMITTALS
DI VI SI ON 02 - EXI STI NG CONDI TI ONS
02 41 00.00 99 05/10 DEMOLITION
02 82 14.00 99 02/10 ASBESTOS HAZARD CONTROL ACTIVITIES
DI VI SI ON 07 - THERMAL AND MOI STURE PROTECTI ON
07 92 00.00 99 08/16 JOINT SEALANTS
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 1
IJO#757511 02/06/23 -11:23 AM
SECTION 01 11 00.00 99
SCOPE OF WORK
08/15
PART 1 GENERAL
1.1 PROJECT DESCRIPTION
The construction services necessary to complete this contract includes providing all specifications, licenses, permits, labor, materials, equipment, supervision and management to complete the project in accordance with all existing contract documents, Tobyhanna Army Depot (TYAD) Master specifications and Industrial Design Guide (IDG) as well as materials manufacturers specifications. All and any exceptions shall be submitted in writing. The objective of this effort is to rehabilitate the below grade tunnel located between buildings 10 and 1B. Rehabilitation shall include remedial curtain wall waterproof crack injection of walls and ceiling, crack sealing and epoxy painting. The work includes that described in the accompanying Scope of Work listed herein.
1.2 KEY ELEMENTS
1.2.1 Existing Conditions
The existing tunnel between buildings 10 and 1B has sustained water damage due to age and condition. Damages include water seeping into the tunnel, peeling paint and various cracking. The below listed square footage has been determined by record drawing AS-BUILTS and are approximate measurements. Accuracy of the square footage measurements need to be confirmed and Tobyhanna is not responsible for the accuracy of these measurements.
a. The tunnel walls exposed to exterior grade to be repaired is approximately 2,790 square feet. Includes both walls between buildings below Squier Street and an additional ten (10) feet beyond buildings existing foot print to the underside of existing slabs.
b. The tunnel floor to be repaired is approximately 1,840 square feet.
Inlcludes floor between buildings and an additional ten (10) feet beyond buildings existing foot print to the underside of existing slabs.
c. The tunnel ceiling exposed to exterior grade to be repaired is approximately 1,840 square feet. Inlcludes ceiling between buildings and an addtional ten (10) feet beyond buildings existing foot print to the underside of existing slabs.
1.2.2 New Work
Work shall span the lengeth of tunnel between exterior walls of building 10 and 1B, begining ten (10) feet prior to the exterior wall from within building 10 through the exterior wall of building 1B Bay 5 with an additional ten (10) feet beyond and into building 1B Bay 5.
Curtain wall waterproof crack injection of the tunnel shall include both walls exposed to exterior grade between both buildings and below Squier
SECTION 01 11 00.00 99 Page 1
Street as discribed above. Floor, walls and ceiling between both buildings shall receive the crack injection repair and crack/joint sealing, new epoxy primer and two (2) coats of epoxy paint.
a. Curtain wall waterproof crack injection of the tunnel walls from interior with a high-solids grout consisting of a proprietary blend of beonite and polymers formulated for water leaks in existing below-grade structures.
b. Application of grout shall be applied to both sides of the tunnel walls and ceiling by injecting grout to exterior in order to permeate into the soil creating a barrier on three (3) sides of the tunnel where exposed to exterior soil. Application shall be applied according to manufacturer specifications.
c. Contractor shall seal all visible holes, cracks and or gouges in floor, walls and ceiling with an epoxy sealant. All sealant shall be applied using manufacturers recommendations and section 07 92 00.00 99
JOINT SEALANTS.
d. Upon completion of injection grout and crack sealing, contractor shall grind/sand and clean floor, walls and ceiling in preparation of epoxy primer and paint according manufacturers specifications.
e. Contractor shall repaint all floors, walls and ceiling on the interior of tunnel with bonding primer and a minimum of two (2) coats of epoxy coating. Application of primer and epoxy shall be applied according to manufacturers specifications.
1.2.3 Additional Requirements
Contractor and/or sub-contractors shall assume all repsonsibility for preparing floor, walls and ceiling for work to be completed under this task order and the Scope of Work described herein.
1.3 PERIOD OF PERFORMANCE
Period of performance for this task order shall be 120 days after notice to proceed.
1.4 LOCATION
The work is located at the Tobyhanna Army Depot, Tobyhanna, PA, approximately as indicated. The exact location will be shown by the Contracting Officer's Representative (COR).
1.5 OCCUPANCY OF PREMISES
Building(s) will be occupied during performance of work under this Contract. Occupancy notifications will be posted in a prominent location in the work area.
Before work is started, arrange with the COR a sequence of procedure, means of access, space for storage of materials and equipment, and use of approaches, corridors, and stairways.
SECTION 01 11 00.00 99 Page 2
1.6 EXISTING WORK
In addition to FAR 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements:
a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.
b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the COR. At the completion of operations, existing work must be in a condition equal to or better than that which existed before new work started.
1.7 GOVERNMENT-INSTALLED WORK
The Government may install equipment or perform other work at the job site, excluding inspection and testing if it listed in the Scope of Work Appendix.
PART 2 CONTRACT DOCUMENTS
Due to operational security, existing building conditions will be provided via AS-BUILT drawings upon request only.
DRAWING# DATED DRAWI NG TI TLE
620A-1-2 17 APRIL 1952 TUNNELS; Plans, Sections, Details
PART 3 EXECUTION
Not used.
-- End of Section --
SECTION 01 11 00.00 99 Page 3
SECTION 01 14 00.00 99
WORK RESTRICTIONS
11/11
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00.00 99 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Personnel List; G
List of Contact Personnel; G
Vehicle List; G
Statement of Acknowledgement Form SF 1413; G
1.2 CONTRACTOR ACCESS AND USE OF PREMISES
1.2.1 Activity Regulations
Ensure that Contractor personnel employed on the Activity become familiar with and obey Activity regulations including safety, fire, traffic and security regulations. Keep within the limits of the work and avenues of ingress and egress. Wear hard hats in designated areas. Do not enter any restricted areas unless required to do so and until cleared for such entry. Mark Contractor equipment for identification.
1.2.1.1 Subcontractors and Personnel Contacts
Provide a vehicle list, personnel list and list of contact personnel of the Contractor and subcontractors including addresses and telephone numbers for use in the event of an emergency. As changes occur and additional information becomes available, correct and change the information contained in previous lists.
1.2.1.2 No Smoking Policy
Smoking is prohibited within and outside of all buildings on installation, except in designated smoking areas. This applies to existing buildings, buildings under construction and buildings under renovation. Discarding tobacco materials other than into designated tobacco receptacles is considered littering and is subject to fines. The Contracting Officer's Representative (COR) will identify designated smoking areas.
1.2.2 Working Hours
Regular working hours must consist of an 8 1/2 hour period established by the Contracting Officer's Representative, between Monday through Friday, SECTION 01 14 00.00 99 Page 1 excluding Government holidays.
1.2.3 Work Outside Regular Hours
Work outside regular working hours requires Contracting Officer's Representative approval. Make application 15 calendar days prior to such work to allow arrangements to be made by the Government for inspecting the work in progress, giving the specific dates, hours, location, type of work to be performed, contract number and project title. Based on the justification provided, the Contracting Officer's Representative may approve work outside regular hours. During periods of darkness, the different parts of the work must be lighted in a manner approved by the Contracting Officer's Representative. Make utility cutovers after normal working hours or on Saturdays, Sundays, and Government holidays unless directed otherwise.
1.2.4 Occupied Building
The Contractor shall be working in an existing building which is occupied.
Do not enter the building without prior approval of the Contracting Officer's Representative.
The existing buildings and their contents must be kept secure at all times. Provide temporary closures as required to maintain security as directed by the Contracting Officer's Representative.
Provide dust covers or protective enclosures to protect existing work that remains and Government material located in the work area during the construction period.
Relocate movable furniture as required to perform the work, protect the furniture, and replace the furniture in its original locations upon completion of the work. Leave attached equipment in place, and protect it against damage, or temporarily disconnect, relocate, protect, and reinstall it at the completion of the work.
The Government will remove and relocate other Government property in the areas of the building scheduled to receive work.
1.2.5 Utility Cutovers and Interruptions
a. Make utility cutovers and interruptions after normal working hours or on Saturdays, Sundays, and Government holidays. Conform to procedures required paragraph WORK OUTSIDE REGULAR HOURS.
b. Ensure that new utility lines are complete, except for the connection, before interrupting existing service.
c. Interruption to water, sanitary sewer, storm sewer, telephone service, electric service, air conditioning, heating, fire alarm, and compressed air are considered utility cutovers pursuant to the paragraph WORK OUTSIDE REGULAR HOURS. Such interruptions are further limited to 6 hours. This time limit includes time for deactivation and reactivation.
d. Operation of Station Utilities: The Contractor must not operate nor disturb the setting of control devices in the station utilities system, including water, sewer, electrical, and steam services. The Government will operate the control devices as required for normal
SECTION 01 14 00.00 99 Page 2 conduct of the work. The Contractor must notify the Contracting Officer's Representative giving reasonable advance notice when such operation is required.
1.3 SECURITY REQUIREMENTS
Contract Clause FAR 52.204-2 Security Requirements and Alternate II, "FAC 5252.236-9301, Special Working Conditions and Entry to Work Area," and the following apply:
Submit Statement of Acknowledgement Form SF 1413.
1.3.1 Identification Badges
Identification badges, if required, will be furnished without charge.
Application for and use of badges will be as directed. Furnish a completed EMPLOYMENT ELIGIBILITY VERIFICATION (DHS FORM I-9) form for all personnel requesting badges.
This form is available at http://www.uscis.gov/files/form/I-9_IFR_02-02-09.pdf.
Immediately report instances of lost or stolen badges to the Depot Security Office and to the Contracting Officer's Representative.
1.3.2 1.4.1.4 Personnel Entry Approval
Failure to obtain entry approval will not affect the contract price or time of completion. See section 01 35 53.00 99 TYAD SECURITY REQUIREMENTS for additional requirements.
PART 2 PRODUCTS
Not Used.
PART 3 EXECUTION
Not Used.
-- End of Section --
SECTION 01 14 00.00 99 Page 3
SECTION 01 30 00.00 99
ADMINISTRATIVE REQUIREMENTS
08/15
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 (2014) Safety and Health Requirements Manual
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00.00 99 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
View Location Map; G
Progress and Completion Pictures; G
1.3 VIEW LOCATION MAP
Submit, prior to or with the first digital photograph submittals, a sketch or drawing indicating the required photographic locations. Update as required if the locations are moved.
1.4 PROGRESS AND COMPLETION PICTURES
Photographically document site conditions prior to start of construction operations. Provide monthly, and within one month of the completion of work, digital photographs, 1600 x 1200 x 24 bit true color minimum resolution in JPEG file format showing the sequence and progress of work.
Take a minimum of 20 digital photographs each week throughout the entire project from a minimum of ten views from points located by the Contracting Officer's Representative (COR). Submit with the monthly invoice two sets of digital photographs, each set on a separate compact disc (CD) or data versatile disc (DVD), cumulative of all photos to date. Indicate photographs demonstrating environmental procedures. Provide photographs for each month in a separate monthly directory and name each file to indicate its location on the view location sketch. Also provide the view location sketch on the CD or DVD as a digital file. Include a date designator in file names. Cross reference submittals in the appropriate daily report. Photographs provided are for unrestricted use by the Government.
SECTION 01 30 00.00 99 Page 1
1.5 MINIMUM INSURANCE REQUIREMENTS
Provide the minimum insurance coverage required by FAR 28.307-2 Liability, during the entire period of performance under this contract. Provide other insurance coverage as required by State law.
1.6 SUPERVISION
1.6.1 Minimum Communication Requirements
Have at least one qualified superintendent, or competent alternate, capable of reading, writing, and conversing fluently in the English language, on the job-site at all times during the performance of contract work. In addition, if a Quality Control (QC) representative is required on the contract, then that individual must also have fluent English communication skills.
For this task order only, the quality control manager will not be required.
These duties will be the requirements of the site superintendent.
1.6.2 Superintendent Qualifications
The project superintendent must have a minimum of 10 years experience in construction with at least 5 of those years as a superintendent on projects similar in size and complexity. The individual must be familiar with the requirements of EM 385-1-1 and have experience in the areas of hazard identification and safety compliance. The individual must be capable of interpreting a critical path schedule and construction drawings. The qualification requirements for the alternate superintendent are the same as for the project superintendent. The Contracting Officer's Representative may request proof of the superintendent's qualifications at any point in the project if the performance of the superintendent is in question.
For routine projects where the superintendent is permitted to also serve as the Quality Control (QC) Manager as established in Section 01 45 00.00 99 QUALITY CONTROL, the superintendent must have qualifications in accordance with that section.
For this task order only, the site superintendent may serve as the site safety health officer.
1.6.2.1 Duties
The project superintendent is primarily responsible for managing and coordinating day-to-day production and schedule adherence on the project.
The superintendent is required to attend partnering meetings, and quality control meetings. The superintendent or qualified alternative must be on-site at all times during the performance of this contract until the work is completed and accepted.
1.6.3 Non-Compliance Actions
The Project Superintendent is subject to removal by the Contracting Officer's Representative for non-compliance with requirements specified in the contract and for failure to manage the project to insure timely completion. Furthermore, the Contracting Officer's Representative may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to such
SECTION 01 30 00.00 99 Page 2 stop orders is acceptable as the subject of claim for extension of time for excess costs or damages by the Contractor.
1.7 PRECONSTRUCTION CONFERENCE
After award of the contract but prior to commencement of any work at the site, meet with the Contracting Officer's Representative to discuss and develop a mutual understanding relative to the administration of the value engineering and safety program, preparation of the schedule of prices or earned value report, shop drawings, and other submittals, scheduling programming, prosecution of the work, and clear expectations of the "Interim DD Form 1354" Submittal. Major subcontractors who will engage in the work must also attend.
1.8 PARTNERING
To most effectively accomplish this contract, the Government requires the formation of a cohesive partnership within the Project Team whose members are from the Government, the Contractor and their Subcontractors. Key personnel from the Supported Command, the End User (who will occupy the facility), the Government Design and Construction team and Subject Matter Experts, the Installation, the Contractor and Subcontractors, and the Designer of Record will be invited to participate in the Partnering process. The Partnership will draw on the strength of each organization in an effort to achieve a project that is without any safety mishaps, conforms to the Contract, and stays within budget and on schedule.
The Contracting Officer's Representative will provide Information on the Partnering Process and a list of key and optional personnel who should attend the Partnering meeting.
1.8.1 Informal Partnering
The Contracting Officer's Representative will organize the Partnering Sessions with key personnel of the project team, including Contractor personnel and Government personnel.
The Initial Partnering session should be a part of the Pre-Construction Meeting. Partnering sessions will be held at a location agreed to by the COR and the Contractor (typically a conference room provided by the Resident Engineer office or the Contractor). The Initial Informal Partnering Session will be conducted and facilitated using electronic media (a video and accompanying forms) provided by the Contracting Officer's Representative. The Partners will determine the frequency of the follow-on sessions, at no more than 3 to six month intervals.
1.9 ELECTRONIC MAIL (E-MAIL) ADDRESS
Establish and maintain electronic mail (e-mail) capability along with the capability to open various electronic attachments as text files, pdf files, and other similar formats. Within 10 days after contract award, provide the Contracting Officer's Representative a single (only one) e-mail address for electronic communications from the Contracting Officer's Representative related to this contract including, but not limited to contract documents, invoice information, request for proposals, and other correspondence. The Contracting Officer's Representative may also use email to notify the Contractor of base access conditions when emergency conditions warrant, such as hurricanes or terrorist threats.
Multiple email addresses are not allowed.
SECTION 01 30 00.00 99 Page 3
It is the Contractor's responsibility to make timely distribution of all Contracting Officer's Representative initiated e-mail with its own organization including field office(s). Promptly notify the Contracting Officer's Representative, in writing, of any changes to this email address.
1.10 MEETING INVITATIONS/NOTIFICATIONS
Notify the Contracting Officer's Representative of all scheduled meetings a minimum of 48 hours in advance utilizing Microsoft Office Outlook Invite for invitations/notifications unless otherwise noted.
PART 2 PRODUCTS
Not Used.
PART 3 EXECUTION
Not Used.
-- End of Section --
SECTION 01 30 00.00 99 Page 4
SECTION 01 32 33.00 99
CONSTRUCTION PHOTOGRAPHY
03/2014
PART 1 GENERAL
1.1 SCOPE OF SECTION
The work specified in this section includes construction photographs consisting of prints, and digital image files, showing the pre-construction condition, post-construction condition, and progress of each definable feature of work during the contract period, including personnel, work methods, and equipment utilized. Photographs shall be provided for unrestricted use by the Government.
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00.00 99 SUBMITTAL PROCEDURES:
Construction Photographs; G
Email digital images of construction photographs to the Contracting Officer's Representative within 24 hours of when taken. After approval of email, submit construction prints and digital images, within 10 calendar days.
Post-Construction Photographs Email; G
Email digital images of post-construction photographs to the Contracting Officer's Representative within 24 hours of when taken.
Post-Construction Photographs; Prints, and CD; G
After approval of email, submit post-construction prints and digital images, within 10 calendar days.
1.3 GENERAL REQUIREMENTS
1.3.1 Digital Images
Take digital images with a high quality digital camera using a minimum of 6,000,000 pixels (6 Megapixels). Identify images by number, and referenced to a printed listing containing the following information:
name and location of project, item/action being photographed, General Contractor, contract number, orientation of view, date and time.
1.3.2 Quantities
Submit 1 set of all digital images, to the Contracting Officer's Representative.
SECTION 01 32 33.00 99 Page 1
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION
3.1 PHOTOGRAPHY
Photograph personnel, material, work methods, and equipment utilized during the entire contract period, as follows:
a. Prior to commencement of work, take a minimum of 25 Pre-Construction Photographs Email of pre-construction existing conditions. Take photographs as close as possible to the beginning of the work and with sufficient detail to accurately depict existing site conditions.
After approval of email, submit Pre-Construction Photographs Prints of digital images, within 10 calendar days.
b. During the progress of work, take a minimum of 10 Construction Photographs weekly of each defineable feature of work (defineable "feature of work" is defined in Section 01 45 00.00 99 QUALITY CONTROL). Photographs shall be of working personnel and equipment, depicting the work methods being utilized, taken during normal working hours. Photograph special events throughout the contract period as directed by the Contracting Officer's Representative.
c. After completion of work, take a minimum of 25 Post-Construction Photographs, Email from the same pre-construction and progress construction locations. Photography shall be taken immediately after the end of construction work.
d. Submit a reference plan sheet or map with the submitted construction photos, showing the locations of the photographs.
After approval of email, submit Post-Construction Photographs; Prints, and CD of digital images, within 10 calendar days.
3.2 MEASUREMENT AND PAYMENT
No separate measurement or payment will be made for the work specified in this section and all costs in connection therewith shall be included in the contract lump sum price.
-- End of Section --
SECTION 01 32 33.00 99 Page 2
SECTION 01 33 00.00 99
SUBMITTAL PROCEDURES
01/2018
PART 1 GENERAL
1.1 SUMMARY
The Contracting Officer's Representative (COR) may request submittals in addition to those specified when deemed necessary to adequately describe the work covered in the respective sections.
Units of weights and measures used on all submittals are to be the same as those used in the contract drawings.
Each submittal is to be complete and in sufficient detail to allow ready determination of compliance with contract requirements.
Contractor's Quality Control (CQC) System Manager and the Designer of Record, if applicable, to check and approve all items prior to submittal and stamp, sign, and date indicating action taken. Proposed deviations from the contract requirements are to be clearly identified. Include within submittals items such as: Contractor's, manufacturer's, or fabricator's drawings; descriptive literature including (but not limited
to) catalog cuts, diagrams, operating charts or curves; test reports; test cylinders; samples; O&M manuals (including parts list); certifications;
warranties; and other such required submittals.
Submittals requiring Government approval are to be scheduled and made prior to the acquisition of the material or equipment covered thereby.
Pick up and dispose of samples not incorporated into the work in accordance with manufacturer's Safety Data Sheets (SDS) and in compliance with existing laws and regulations.
A submittal register showing items of equipment and materials for when submittals are required by the specifications is provided as "Appendix A - Submittal Register".
1.2 DEFINITIONS
1.2.1 Submittal Descriptions (SD)
Submittals requirements are specified in the technical sections.
Submittals are identified by Submittal Description (SD) numbers and titles as follows:
SD-01 Preconstruction Submittals
Submittals which are required prior to the start of construction.
Certificates of insurance
Surety bonds
List of proposed Subcontractors
List of proposed products
SECTION 01 33 00.00 99 Page 1
Construction progress schedule
Network Analysis Schedule (NAS)
Submittal register
Schedule of prices or Earned Value Report
Accident Prevention Plan (APP)
List of Definable Features of Work (DFOW)
Production Activity Schedule
Quality Control (QC) plan
Environmental protection plan
SD-02 Shop Drawings
Drawings, diagrams and schedules specifically prepared to illustrate some portion of the work.
Diagrams and instructions from a manufacturer or fabricator for use in producing the product and as aids to the Contractor for integrating the product or system into the project.
Drawings prepared by or for the Contractor to show how multiple systems and interdisciplinary work will be coordinated.
SD-03 Product Data
Catalog cuts, illustrations, schedules, diagrams, performance charts, instructions and brochures illustrating size, physical appearance and other characteristics of materials, systems or equipment for some portion of the work.
Samples of warranty language when the contract requires extended product warranties.
SD-04 Samples
Fabricated or unfabricated physical examples of materials, equipment or workmanship that illustrate functional and aesthetic characteristics of a material or product and establish standards by which the work can be judged.
Color samples from the manufacturer's standard line (or custom color samples if specified) to be used in selecting or approving colors for the project.
Field samples and mock-ups constructed on the project site establish standards by which the ensuring work can be judged. Includes assemblies or portions of assemblies which are to be incorporated into the project and those which will be removed at conclusion of the work.
SD-05 Design Data
SECTION 01 33 00.00 99 Page 2
Design calculations, mix designs, analyses or other data pertaining to a part of work.
Design submittals, design substantiation submittals and extensions of design submittals.
SD-06 Test Reports
Report signed by authorized official of testing laboratory that a Canmaterial, product or system identical to the material, product or system to be provided has been tested in accord with specified requirements. Unless specified in another section, testing must have been within three years of date of contract award for the project.
Report which includes findings of a test required to be performed by the Contractor on an actual portion of the work or prototype prepared for the project before shipment to job site.
Report which includes finding of a test made at the job site or on sample taken from the job site, on portion of work during or after installation.
Investigation reports.
Daily logs and checklists.
Final acceptance test and operational test procedure.
SD-07 Certificates
Statements printed on the manufacturer's letterhead and signed by responsible officials of manufacturer of product, system or material attesting that the product, system, or material meets specification requirements. Must be dated after award of project contract and clearly name the project.
Document required of Contractor, or of a manufacturer, supplier, installer or Subcontractor through Contractor. The document purpose is to further promote the orderly progression of a portion of the work by documenting procedures, acceptability of methods, or personnel qualifications.
Confined space entry permits.
Text of posted operating instructions.
SD-08 Manufacturer's Instructions
Preprinted material describing installation of a product, system or material, including special notices and (SDS) concerning impedances, hazards and safety precautions.
SD-09 Manufacturer's Field Reports
Documentation of the testing and verification actions taken by manufacturer's representative at the job site, in the vicinity of the job site, or on a sample taken from the job site, on a portion of the work, during or after installation, to confirm compliance with manufacturer's standards or instructions. The documentation must be
SECTION 01 33 00.00 99 Page 3 signed by an authorized official of a testing laboratory or agency and state the test results; and indicate whether the material, product, or system has passed or failed the test.
Factory test reports.
SD-10 Operation and Maintenance Data
Data that is furnished by the manufacturer, or the system provider, to the equipment operating and maintenance personnel, including manufacturer's help and product line documentation necessary to maintain and install equipment. This data is needed by operating and maintenance personnel for the safe and efficient operation, maintenance and repair of the item.
This data is intended to be incorporated in an operations and maintenance manual or control system.
SD-11 Closeout Submittals
Documentation to record compliance with technical or administrative requirements or to establish an administrative mechanism.
Submittals required for Guiding Principle Validation (GPV) or Third Party Certification (TPC).
Special requirements necessary to properly close out a construction contract. For example, Record Drawings and as-built drawings. Also, submittal requirements necessary to properly close out a major phase of construction on a multi-phase contract.
1.2.2 Approving Authority
Office or designated person authorized to approve submittal.
1.2.3 Work
As used in this section, on- and off-site construction required by contract documents, including labor necessary to produce submittals, except those SD-01 Pre-Construction Submittals noted above, construction, materials, products, equipment, and systems incorporated or to be incorporated in such construction.
1.3 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with this section.
SD-01 Preconstruction Submittals
Submittal Register; G
1.4 SUBMITTAL CLASSIFICATION
Submittals are classified as follows:
SECTION 01 33 00.00 99 Page 4
1.4.1 Designer of Record Approved (DA)
Designer of Record (DOR) approval is required for extensions of design, critical materials, any deviations from the solicitation, the accepted proposal, or the completed design, equipment whose compatibility with the entire system must be checked, and other items as designated by the Contracting Officer's Representative (COR). The DOR review of submittals requiring approval will be completed by the DOR within 10 calendar days after date of receipt and returned to the COR. Within the terms of the Contract Clause SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION, they are considered to be "shop drawings." Contractor to provide the Government with the number of copies designated hereinafter of all DOR approved submittals. The Government may review any or all Designer of Record approved submittals for conformance to the Solicitation, Accepted Proposal and the completed design. The Government will review all submittals designated as deviating from the Solicitation or Accepted Proposal, as described below. Design submittals to be in accordance with Section 01 33 16.00 99 DESIGN DATA (DESIGN AFTER AWARD). Generally, design submittals should be identified as SD-05 Design Data submittals.
1.4.2 Government Approved (G)
Government approval is required for extensions of design, critical materials, deviations, equipment whose compatibility with the entire system must be checked, and other items as designated by the Contracting Officer's Representative. Government approval is required for any deviations from the Solicitation or Accepted Proposal and other items as designated by the Contracting Officer's Representative. Within the terms of the Contract Clause SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION, they are considered to be "shop drawings."
1.4.3 Government Conformance Review of Design (CR)
The Government will review all intermediate and final design submittals for conformance with the technical requirements of the solicitation.
Section 01 33 16.00 99 DESIGN DATA (DESIGN AFTER AWARD) covers the design submittal and review process in detail. Review will be only for conformance with the applicable codes, standards and contract requirements. Design data includes the design documents described in Section 01 33 16.00 99 DESIGN DATA (DESIGN AFTER AWARD). Generally, design submittals should be identified as SD-05 Design Data submittals.
1.4.4 Designer of Record Approved/Government Conformance Review (DA/CR)
1.4.4.1 Deviations to the Accepted Design
Designer of Record approval and the Government's concurrence are required for any proposed deviation from the accepted design which still complies with the contract before the Contractor is authorized to proceed with material acquisition or installation. Within the terms of the Contract Clause SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION, they are considered to be "shop drawings." If necessary to facilitate the project schedule, the Contractor and the DOR may discuss a submittal proposing a deviation with the Contracting Officer's Representative prior to officially submitting it to the Government. However, the Government reserves the right to review the submittal before providing an opinion, if deemed necessary. In any case, the Government will not formally agree to or provide a preliminary opinion on any deviation without the DOR's approval or recommended approval. The Government reserves the right to non-concur
SECTION 01 33 00.00 99 Page 5 with any deviation from the design, which may impact furniture, furnishings, equipment selections or operations decisions that were made, based on the reviewed and concurred design.
1.4.4.2 Substitutions
Unless prohibited or provided for otherwise elsewhere in the Contract, where the accepted contract proposal named products, systems, materials or equipment by manufacturer, brand name and/or by model number or other specific identification, and the Contractor desires to substitute manufacturer or model after award, submit a requested substitution for Government concurrence. Include substantiation, identifying information and the DOR's approval, as meeting the contract requirements and that it is equal in function, performance, quality and salient features to that in the accepted contract proposal. If the Contract otherwise prohibits substitutions of equal named products, systems, materials or equipment by manufacturer, brand name and/or by model number or other specific identification, the request is considered a "variation" to the contract.
Variations are discussed below in paragraphs: "Designer of Record Approved/Government Approved" and "VARIATIONS."
1.4.5 Designer of Record Approved/Government Approved (DA/GA)
In addition to the above stated requirements for proposed deviations to the accepted design, both Designer of Record and Government Approval and, where applicable, a contract modification are required before the Contractor is authorized to proceed with material acquisition or installation for any proposed variation to the contract (the solicitation and/or the accepted proposal), which constitutes a change to the contract terms. Within the terms of the Contract Clause SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION, they are considered to be "shop drawings." The Government reserves the right to accept or reject any such proposed deviation at its discretion.
1.4.6 For Information Only (FIO)
Submittals not requiring Government approval will be for information only. For Design-build construction all submittals not requiring Designer of Record or Government approval will be for information only. They are not considered to be "shop drawings" within the terms of the Contract Clause referred to above.
1.5 PREPARATION
1.5.1 Transmittal Form
Use the transmittal form ENG Form 4025-R for submitting both Government approved and information only submittals in accordance with the instructions on the reverse side of the form. These forms will be furnished to the Contractor. Properly complete this form by filling out all the heading blank spaces and identifying each item submitted.
Exercise special care to ensure proper listing of the specification paragraph and sheet number of the contract drawings pertinent to the data submitted for each item.
1.5.2 Source Drawings for Shop Drawings
The entire set of Source Drawing files (DWG) will not be provided to the Contractor. Only those requested by the Contractor to prepare shop
SECTION 01 33 00.00 99 Page 6 drawings may be provided. Request the specific Drawing Number only for the preparation of Shop Drawings. These drawings may only be provided after award.
1.5.2.1 Terms and Conditions
Data contained on these electronic files must not be used for any purpose other than as a convenience in the preparation of construction data for the referenced project. Any other use or reuse shall be at the sole risk of the Contractor and without liability or legal exposure to the Government. The Contractor must make no claim and waives to the fullest extent permitted by law, any claim or cause of action of any nature against the Government, its agents or sub consultants that may arise out of or in connection with the use of these electronic files. The Contractor must, to the fullest extent permitted by law, indemnify and hold the Government harmless against all damages, liabilities or costs, including reasonable attorney's fees and defense costs, arising out of or resulting from the use of these electronic files.
These electronic Source Drawing files are not construction documents.
Differences may exist between the Source Drawing files and the corresponding construction documents. The Government makes no representation regarding the accuracy or completeness of the electronic Source Drawing files, nor does it make representation to the compatibility of these files with the Contractor hardware or software. In the event that a conflict arises between the signed and sealed construction documents prepared by the Government and the furnished Source Drawing files, the signed and sealed construction documents govern. The Contractor is responsible for determining if any conflict exists. Use of these Source Drawing files does not relieve the Contractor of duty to fully comply with the contract documents, including and without limitation, the need to check, confirm and coordinate the work of all contractors for the project. If the Contractor uses, duplicates or modifies these electronic Source Drawing files for use in producing construction data related to this contract, remove all previous indicia of ownership (seals, logos, signatures, initials and dates).
1.5.3 Electronic File Format
Provide submittals in electronic format, with the exception of material samples required for SD-04 Samples items. In addition to the electronic submittal, provide hard copies of the submittals in the quantities as specified in the paragraphs below. Maintain hard copies of approved submittals at the field locations (field office, site facilities, etc.)
for use by Contractor and Government personnel. Use submittal tracking and transmittal documents (Eng Form 4025). Compile the submittal file as a single, complete document, to include the Transmittal Form described within. Name the electronic submittal file specifically according to its contents, coordinate the file naming convention with the Contracting Officer's Representative. Electronic files must be of sufficient quality that all information is legible. Use PDF as the electronic format, unless otherwise specified or directed by the Contracting Officer's Representative.
Generate PDF files from original documents with bookmarks so that the text included in the PDF file is both searchable and can be copied. If documents are scanned, Optical Character Resolution (OCR) routines are required. Index and bookmark files exceeding 30 pages to allow efficient navigation of the file. When required, the electronic file must include a valid electronic signature, or scan of a signature.
SECTION 01 33 00.00 99 Page 7
Email electronic submittal documents fewer than 10MB to an email address as directed by the Contracting Officer's Representative. Provide electronic documents over 10 MB on a CD-ROM, or through an electronic file sharing system such as the DoD SAFE Web Application when granted an upload invitation by Goverment personel. Located at the following website:
https://safe.apps.mil/.
Provide hard copies of submittals when requested by the Contracting Officer's Representative. Up to four additional hard copies of any submittal may be requested at the discretion of the Contracting Officer's Representative, at no additional cost to the Government.
1.6 QUANTITY OF SUBMITTALS
1.6.1 Number of Copies of SD-02 Shop Drawings
Submit two copies of submittals of shop drawings requiring review and approval only by QC organization and two copies of shop drawings requiring review and approval by Contracting Officer's Representative.
1.6.2 Number of Copies of SD-03 Product Data and SD-08 Manufacturer's Instructions
Submit in compliance with quantity requirements specified for shop drawings.
1.6.3 Number of Samples SD-04 Samples
a. Submit two samples, or two sets of samples showing range of variation, of each required item. One approved sample or set of samples will be retained by approving authority and one will be returned to Contractor.
b. Submit one sample panel or provide one sample installation where directed. Include components listed in technical section or as directed.
c. Submit one sample installation, where directed.
d. Submit one sample of non-solid materials.
1.6.4 Number of Copies SD-05 Design Data and SD-07 Certificates
Submit in compliance with quantity requirements specified for shop drawings.
1.6.5 Number of Copies SD-06 Test Reports and SD-09 Manufacturer's Field Reports
Submit in compliance with quantity and quality requirements specified for shop drawings other than field copies of test results that will be submitted with QC reports.
1.6.6 Number of Copies of SD-10 Operation and Maintenance Data
Submit three copies of O&M Data to the Contracting Officer's Representative for review and approval.
SECTION 01 33 00.00 99 Page 8
1.6.7 Number of Copies of SD-01 Preconstruction Submittals and SD-11 Closeout Submittals
Unless otherwise specified, submit in compliance with quantity requirements specified for shop drawings.
1.7 FOR INFORMATION ONLY SUBMITTALS
Normally submittals for information only will not be returned. Approval of the Contracting Officer's Representative is not required on information only submittals. The Government reserves the right to require the Contractor to resubmit any item found not to comply with the contract.
This does not relieve the Contractor from the obligation to furnish material conforming to the plans and specifications; will not prevent the Contracting Officer's Representative from requiring removal and replacement of nonconforming material incorporated in the work; and does not relieve the Contractor of the requirement to furnish samples for testing by the Government laboratory or for check testing by the Government in those instances where the technical specifications so prescribe.
1.8 SUBMITTAL REGISTER
Prepare and maintain submittal register, as the work progresses. Do not change data which is output in columns (c), (d), (e), and (f) as delivered by Government; retain data which is output in columns (a), (g), (h), and
(i) as approved. A submittal register showing items of equipment and materials for which submittals are required by the specifications is provided as an attachment. This list may not be all inclusive and additional submittals may be required. Maintain a submittal register for the project as specified herein. The Government will provide the initial submittal register in electronic format with the following fields completed, to the extent that will be required by the Government during subsequent usage.
Column (c): Lists specification section in which submittal is required.
Column (d): Lists each submittal description (SD No. and type, e.g. SD-02 Shop Drawings) required in each specification section.
Column (e): Lists one principal paragraph in specification section where a material or product is specified. This listing is only to facilitate locating submitted requirements. Do not consider entries in column (e) as limiting project requirements.
Thereafter, the Contractor is to track all submittals by maintaining a complete list, including completion of all data columns, including dates on which submittals are received and returned by the Government.
The Designer of Record develops a complete list of submittals during design and identify required submittals in the specifications, and use the list to prepare the Submittal Register. The list may not be all inclusive and additional submittals may be required by other parts of the contract.
Complete the submittal register and submit it to the Contracting Officer's Representative for approval within 30 calendar days after Notice to Proceed. The approved submittal register will serve as a scheduling document for submittals and will be used to control submittal actions throughout the contract period. Coordinate the submit dates and need
SECTION 01 33 00.00 99 Page 9 dates with dates in the Contractor prepared progress schedule. Submit monthly or until all submittals have been satisfactorily completed, updates to the submittal register showing the Contractor action codes and actual dates with Government action codes. Revise the submittal register when the progress schedule is revised and submit both for approval.
1.8.1 Use of Submittal Register
Submit submittal register. Submit with QC plan and project schedule.
Verify that all submittals required for project are listed and add missing submittals. Coordinate and complete the following fields on the register submitted with the QC plan and the project schedule:
Column (g) Contractor Submit Date: Scheduled date for approving authority to receive submittals.
Column (h) Contractor Approval Date: Date Contractor needs approval of submittal.
1.8.2 Contractor Use of Submittal Register
Update the following fields with each submittal throughout contract.
Column (b) Transmittal Number: Contractor assigned list of consecutive numbers.
Column (j) Action Code (k): Date of action used to record Contractor's review when forwarding submittals to QC.
Column (l) List date of submittal transmission.
Column (q) List date approval received.
1.8.3 Approving Authority Use of Submittal Register
Update the following fields.
Column (b) Transmittal Number: Contractor assigned list of consecutive numbers.
Column (l) List date of submittal receipt.
Column (m) through (p)…