Attachment_1_-_Statement_of_Work.pdf

PDF 272 KB Posted

Attached to
2 TON ASPHALT DISTRIBUTOR COMPACTOR FOR EASTERN NE Federal contract opportunity
Solicitation number
140A1126Q0040
Issued by
Department of the Interior Bureau of Indian Affairs Western Region

About this file

This is a Statement of Work (SOW) for the purchase of a 2-ton trailer-mounted asphalt distributor compactor emulsion transporter by the Bureau of Indian Affairs (BIA) Eastern Nevada Agency. The equipment will be utilized by the Roads/Transportation Department, located within the boundaries of the Shoshone-Paiute Tribes in Owyhee, Nevada, primarily for paving potholes and highway cracks on BIA roads, with particular emphasis on springtime operations and emergency response.

The contractor must deliver the base unit (KM-4000TEDD) along with selected optional items to the BIA-Eastern Nevada Agency at 2719-4 Argent Ave, Elko, Nevada 89801, or electronically to the Contracting Officer's Representative, Dalene Leyva. The contract specifies a maximum performance period of 180 days from notice-to-proceed, with the place of performance at BIA-Eastern Nevada Agency Owyhee, 1324 Justice Road, Owyhee, Nevada (Elko County). The contractor shall provide a one-year minimum warranty on all products, materials, and workmanship, including conveyance of all manufacturer commercial warranties and warranty documentation. The SOW includes 24 line items detailing the base unit and optional equipment, including spare tires, propane cylinders, loading hoists, hand torches, heated tanks, tack spray systems, lighting systems, battery upgrades, and propane bottle racks. The government retains ten working days to review and approve deliverables, with the contractor having ten working days to incorporate any changes and submit final deliverables. Purchase Request Number 0044041200 is classified under NAICS 333120, PSC 3805, and UPC 38951900.

View the file

Other files for this federal contract opportunity

Other files attached to 2 TON ASPHALT DISTRIBUTOR COMPACTOR FOR EASTERN NE, newest first.
File Type Posted
Sol_140A1126Q0040.pdf PDF
Attachment_2_-_Pricing_Schedule.xlsx XLSX spreadsheet
Attachment_3_IEE_Representation_Form.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statement of Work

2 TON TRAILER MOUNT-ELECTRIC BRAKE-DIESEL-DUMP

Asphalt Distributor Compactor Emulsion WITH Optional Items

GENERAL/DESCRIPTION OF REQUIREMENT:

The BIA Eastern Nevada Agency Roads/Transportation Department has identified the need to purchase a 2 Ton Trailer Mount-Electric -Brake-Dump Trailer/transporter. The Roads/Transportation department is located within the boundaries of the Shoshone-Paiute Tribes, in Owyhee, Nevada.

OBJECTIVE AND SCOPE:

The asphalt equipment mounted on its own trailer will be utilized primarily to pave potholes and highway cracks on all BIA roads. The need for an asphalt transporter can be used throughout the season, most importantly during the Springtime. The scope of this request is to provide an adequately sized asphalt transporter operated by qualified employees throughout the year and in case of emergency situations.

DELIVERABLES/DELIVERY SCHEDULE:

A detailed description of the machinery with all options are listed ON PAGE 3. The Contractor shall supply the asphalt machine along with optional items as determined by the Roads Department supervisor to the address listed below.

Codes:

NAICS: 333120 (Construction Machinery Manufacturing) PSC: 3805 (Repair and maintenance of roads and highways) Parent PSC: 38 UPC: 38951900 (Distributor Asphalt Compactor Applicator Emulsion) BOC: 6100.312K0 Asset Code: 27NC380

PURCHASE REQUEST #: 0044041200

Acceptance/Disapproval of Deliverables:

Unless otherwise specified, the Government will have a maximum of ten (10) working days from the day the deliverables are received to review the document, provide comments back to the Contractor, approve or disapprove the deliverable(s). The Contractor will also have a maximum of ten (10) working days from the day comments are received to incorporate all changes and submit the final deliverable to the Government.

Address for Deliverables:

Bureau of Indian Affairs-Eastern Nevada Agency 2719-4 Argent Ave Elko, Nevada 89801

Electronic Submittals of deliverables may be submitted to the email address of the identified COR; Dalene Leyva, (775) 340-0173.

PLACE OF PERFORMANCE:

The place of performance shall be within the boundaries of the Shoshone-Paiute Indian Tribes, Owyhee, Nevada, Elko County.

Physical Location:

BIA-Eastern Nevada Agency Owyhee Transportation/Roads Dept. 1324 Justice Road

Owyhee, Nevada (Elko County) Point of Contact:

Christine Atine, Social Worker

(775) 738-0586 christine.atine@bia.gov 2719-4 Argent, NV 89801

Carlyle Dick, Supervisory Engineer Equipment Operator

(775) 340-5188 carlyle.dick@bia.gov 1324 Justice Road, Owyhee, NV 89832

Bryant Jones, Engineer Equipment Operator

(775) 927-0182 bryant.jones@bia.gov 1324 Justice Road Owyhee, NV 89832

PERIOD OF PERFORMANCE:

The period of performance for this contract is anticipated to be a maximum of 180 days from notice-to-proceed.

WARRANTY:

The contractor shall warrant all products, materials, and workmanship for a minimum of one (1) year from the date of purchase. Conveyance of all manufacturer/source commercial warranties, including a warranty summary documentation shall be part of submittal documentation. Major components requiring extended failure support service or warranty for specific critical components shall be documented, optioned, and submitted to COR for review and Contracting Officer acceptance.

mailto:carlyle.dick@bia.gov

DETAILED LIST OF ASPHALT DISTRIBUTOR COMPACTOR EMULSION TRANSPORTER

Ite m # DESCRIPTION: PART # UNIT QTY

01 2 TON TRAILER MOUNT-ELECTRIC

BRAKE-DIESEL-DUMP KM-4000TEDD EA 1

02 7 Gallon Utility Solvent Tank-Mounted on trailer KM-SOLVENT TANK EA 1

03 4-6 Hole Tool Rack-Mounted on trailer KM-TOOLRACK EA 1

04 ST235/80R6 Tire and Rim-Not mounted on trailer

KM-SPARE TIRE

LOOSE EA 1

05 ST235/80R6 Tire and Rim-Mounted on trailer

KM-SPARE TIRE

MOUNTED EA 1

60 lbs Propane Cyclinders (Replaces standard 30 lbs Cyclinders propane units only

KM-60 LB PROPANE EA 1

100 LBS Propane Cyclinders (replaces standard 30 lbs cyclinder-propane units only

KM-100 LB PROPANE EA 1

08 Loading Hoist/Winch & Davit 12V powered-remote KM-HOIST ELECTRIC EA 1

09 Loading Hoist/Winch & Davit-manual 900 lbs lifting capacity KM-HOIST MANUAL EA 1

10 Hand Torch additional 30 lb Propane Bottle supplied retractable hose reel

KM-ULITITY HAND

TORCH DIESEL EA 1

Ite m # DESCRIPTION: PART #: UNIT QTY

Hand Torch additional 30 lb Propane Bottle supplied-25 FT. Retractable Hose Reel

KM-ULITITY HAND

TORCH LP EA 1

12 Allows Heating of cold patch 60-250 *F (Propane only)

KM-LOW TEMP

THERM EA 1

13 Hand Torch Propane supplied by Hot Box-25 FT. Retractable hose reel

KM-EXTENDED

TRAILER 2 TON EA 1

14 Adds 2FT to overall length (20’ total) KM-EXTENDED

TRAILER 4 TON EA 1

15 Deck Mounted to fit KM 2-18x on front of Hot Box trailer KM-MOUNTED DECK EA 1

16 Heated Shovel deck platform KM-HEATED SHOVEL EA 1

17 30 Gallon Heated Tack Tank 10,000 BTU propane burner

KM-30 GAL TACK

TANK EA 1

18 ¾ Roper Pump, Spray Wand & 5.5 HP Honda engine

KM-SPRAY TACK

TANK EA 1

19 Hot Box LED Amber Strobe Light, mounted & switched

KM-STROBE LIGHT

HOT BOX EA 1

20 LED Directional Arrow Board & Controlled-Mounted KM-LIGHTBAR EA 1

21 2 4” Fender Mounted Strobe Lights (1 strobe light per side)

KM-FENDER

STROBES EA 1

22 Propane Bottle Rack attaches at rearside of unit-holds up to 30 lb cyclinders

KM-PROPANE

BOTTLE RACK EA 1

23 Upgraded from standard AGM Battery KM LITHIUM BATTERY EA 1

24 Requiring Options, requiring 12V connection

KM-SUPPLEMENTAL

BATTERY DIESEL

DUMP HOTBOXES Y-

SRC

EA 1

SOW ASPHALT DISTRIBUTOR MAR 2026 rev
2 TON ASPHALT PHOTO MAR 2026

File details come from the government source that posted it. Updated .