Attachment 1 - Statement of Work.pdf
PDF 471 KB Posted
- Attached to
- Purchase and Install Replacement Blinds in Lab
- Solicitation number
- 1232SA25Q0765
About this file
This Statement of Work (SOW) details window treatment upgrades for the USDA Agricultural Research Service's National Center of Agricultural Utilization Research (NCAUR) in Peoria, Illinois. The project requires replacing existing vertical blinds with new roller shade window treatment systems in multiple laboratory and office rooms in the North Wing. Specific requirements include installing Alta/Hunter Douglas roller shades with R80 1% E Screen fabric in white/pearl color, using a clutch-operated control system with spring assist, and a 4" silver fascia. The project covers 14 rooms with 24 windows, including 4 optional bid item windows, and mandates a 5-year parts and labor warranty from the installer and a lifetime limited warranty from the manufacturer.
The SOW specifies that the contractor must perform work in compliance with OSHA safety regulations, coordinate access with the facility point of contact, provide project schedule notification 5 working days in advance, and be responsible for demolition, disposal of existing treatments, surface preparation, and final cleaning. Additional requirements include verifying window dimensions before submission, coordinating any necessary furniture moving, and following the NCAUR Temporary Credentialing Program for site access. The project is scheduled for 2025 and is being managed by Steven Cermak from the USDA-ARS-MWA-NCAUR.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| RFQ_1232SA25Q0765.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
United States Department of Agriculture
Research, Education, and Economics Agricultural Research Service
May 5, 2025
USDA-ARS-NCAUR
1815 North University Street Peoria, IL
Statement of Work: Window Treatment Improvements
To: Innovative Consulting & Management Services (ICMS)
From: Steven Cermak, BOR RL
USDA-ARS-MWA-NCAUR
Please provide a cost proposal for the following scope of work requested by the Government.
The proposal shall include all labor, materials, supervision, equipment and transportation for a complete, properly operating, code legal installation.
Existing Conditions:
The Location currently has vertical blind window treatments in conference rooms, the auditorium, and office areas along the administrative wing. Many of the treatments are in disrepair and require replacement.
Scope of Work Description:
General Requirements:
1. Contractor will perform all job activities in a good and workman like manner and in accordance with OSHA safety regulations.
2. Contractor’s proposal shall indicate whether DBA or SCA rates are priced and what wage determination number was used.
3. Contractor is responsible for repairs of all damage to adjacent building components and equipment that may incur during work activities related to this task. Damaged building components and equipment will be returned to their previous state before damaged at the Contractor’s expense.
4. The furnishing and installation of all improvements indicated shall be complete in every respect, properly operating and ready for use. All work shall be coordinated and scheduled to avoid disrupting and jeopardizing ongoing research.
a. Coordinate access to space with Al Probyn.
National Center of Agricultural Utilization Research (NCAUR)
1815 North University Street, Peoria, Illinois 61604 Phone 309.681.6233 E-mail steven.cermak@usda.gov
USDA is an Equal Opportunity Employer
SOW – 2025 – Window Treatment Upgrades
b. Contractor shall coordinate with Owner any moving of any furnishings needed to complete the project.
5. Contractor shall notify Government’s QA/COR official of project schedule. Provide notification of project schedule a minimum of five (5) working days prior to starting on site work.
6. Contractor shall verify existing conditions prior to submitting proposal.
7. Contractor is responsible for all legal disposal of debris created by this work.
8. Provide final cleaning of project area. Final cleaning shall be of a “broom swept” quality.
Project Specific Requirements:
1. The following rooms are slotted to receive window treatment upgrades. Refer to plans provided for additional information:
a. North Wing Laboratory Room 1201 3 windows
b. North Wing Laboratory Office (East) Room 1201 1 window
c. North Wing Laboratory Office (West) Room 1201 1 window
d. North Wing Laboratory Room 1207 Room 3 windows
e. North Wing Laboratory Room 1204 3 windows
f. North Wing Laboratory Office Room 1204 1 window
g. North Wing Laboratory Room 3200 3 windows
h. North Wing Laboratory Office (East) Room 3200 1 window
i. North Wing Laboratory Office (West) Room 3200 1 window
j. North Wing Laboratory Room 3204 2 windows
k. North Wing Laboratory Office (West) Room 3204 1 window
l. North Wing Laboratory Room 3237 2 windows
m. North Wing Office Room 1000 1 window (optional bid item)
n. North Wing Laboratory Room 1200 3 windows (optional bid item)
o. North Wing Laboratory Office (East) Room 1200 1 window (optional bid item)
p. North Wing Laboratory Office (West) Room 1200 1 window (optional bid item)
2. Contractor to field verify dimensions of all window openings prior to submitting final proposal.
3. Contractor will be responsible for all demolition and disposal of existing window treatments.
4. Contractor will furnish and install new roller shade window treatment systems, including all surface prep, mounting hardware, and miscellaneous components per manufacturer’s installation instructions.
a. Basis of Design – provide the following roller shade package or approved equal.
i. Manufacturer: Alta / Hunter Douglas
ii. Fabric Name: R80 1% E Screen
iii. Color: White / Pearl
iv. Control System: Clutch operated – Skyline with spring assist
v. Top Treatment: 4” Fascia (Silver)
vi. Mount Type: Inside mount (field verify)
vii. Bottom rail: Heat sealed aluminum bar
viii. Chain type: Stainless steel metal bead w/ cord tensioner
ix. Chain position: confirm field conditions per window
b. Warranty:
i. Installer’s coverage requirements
1. 5 years parts and labor
SOW – 2025 – Window Treatment Upgrades
ii. Manufacturer’s coverage requirements
1. Lifetime Limited Warranty
Security Protocols for Site Access:
1. See NCAUR Temporary Credentialing Program.
End of Document