Attachment_1_Statement_of_Work.pdf
PDF 421 KB Posted
- Attached to
- QUAIL SPRINGS & COX POND ES&R CHAINING
- Solicitation number
- 140L6425Q0016
About this file
This Statement of Work (SOW) details a wildfire restoration treatment project for the Bureau of Land Management's Arizona Strip District Office. The contract requires chaining approximately 312 acres at Quail Spring and 306 acres at Cox Pond near St. George, Utah, involving a double-pass harrow chaining method to support post-wildfire vegetation management. The work will be conducted between August 15, 2025, and January 31, 2026, with strict timing restrictions to protect sensitive resources, and involves preparing the terrain for seeding by removing pinyon, juniper, and shrub vegetation using dozers and harrow chains.
The contractor will be responsible for providing equipment including dozers, harrow chains, and GPS units, maintaining equipment, protecting archaeological sites and physical structures, and coordinating closely with a separate seeding contract. The project requires careful navigation of treatment boundaries, avoiding slopes over 30%, and minimizing soil disturbance. Payment will be based on completed treatment units, with potential acreage reductions if sensitive resources are identified. The terrain is characterized as gently to moderately rolling hills with some rocky areas, and the contractor must follow specific environmental considerations and communication protocols during implementation.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Bureau of Land Management Arizona Strip District Office
Statement of Work
General Information and Requirements
Project: Quail Spring and Cox Pond Wildfire Restoration Treatment
Description of Work
The work required under this contract is to furnish all labor, equipment, supplies, and materials to chain up to 312 acres on the Quail Spring wildfire and approximately 306 acres on the Cox Pond wildfire (Table 1) of post wildfire area that may include pinyon, juniper, and various shrub species on public lands on the Arizona Strip District near St. George, Utah. The maps and acreage associated with the chaining units are attached to this statement of work.
There is potential for acreage reduction depending on the need to avoid sensitive resources.
Acreage reductions must be approved by the Contracting Officer Representative. Work required will be a double pass chaining with the second pass conducted in the opposite direction as the first pass. Seeding will occur prior to the chaining, under a separate contract, and coordination will be required to ensure this timeline. The chaining units intersect open roads and trails. It will be the contractor’s responsibility to clear vegetation from the roads and trails following the completion of the chaining.
Table 1 – Table of treatment units by line item, treatment and size.
Wildfire/Project area Description Total Acres Quail Spring
2-Way Harrow Chaining 312
Cox Pond 2-Way Harrow Chaining 306
The treatment area boundaries will be outlined on a map provided by the Government. The Contractor will be responsible for following the treatment boundaries with a Global Positioning System (GPS) or similar navigation device. The contractor may flag the boundaries of the unit at their discretion however, the contractor will be responsible for the removal of all flagging prior to the final inspection.
The terrain is typically gently to moderately rolling hills with few large rocks. However, there are some areas of slope that are near or exceed 30% and some areas with some large rocks.
Slopes greater than 30% are outside of the treatment, but may need to cross these areas to access treatment areas. The dozer will be capable of towing a harrow chain to complete the work.
Work Layout
The work units are depicted on the attached maps. The Government will provide a map to the Contractor with the treatment area boundaries (outside perimeter, islands, etc.) necessary for the work executed under the Contract. The Government will provide a shapefile or map (for upload on GPS unit i.e. phone, tablet, etc.) of the project area boundary to the Contractor. An updated map with avoidance areas (archaeological sites; springs; structural range improvements; survey markers such as sections corners, quarter corners, mining claims, etc.) will be provided to the contractor before work begins. Survey markers disturbed or removed during chaining operations shall be reset at the Contractor’s expense. Range improvements or other physical structures damaged or removed during chaining operations shall be repaired or replaced at the Contractor’s expense.
Location and Access to Work Sites
The project is located in Mohave County, Arizona, Quail Spring project is approximately 20 air miles south of St. George, Utah; Cox Pond project is approximately 35 air miles south of St.
George, Utah.
The objective is to restore these two burned areas, that share similar vegetation communities.
Restoration would be accomplished through seeding coupled with chaining to cover the seed.
Some of the access roads are unimproved two-track roads that may require four-wheel drive vehicles with good clearance. Any use of designated closed roads shall be first coordinated and approved by BLM prior to use during project implementation.
The following legal land descriptions apply for the project areas:
Quail Spring Wildfire Restoration Gila and Salt River Meridian, Arizona
T. 40 N., R. 12 W., sec. 19, 20, 28, 29, 30, 31, 32.
T. 40 N., R. 13 W., sec. 24, 26.
Cox Pond Wildfire Restoration Gila and Salt River Meridian, Arizona
T. 37 N., R. 12 W., sec. 5
T. 38 N., R. 12 W., sec. 32
Environmental Considerations
The project site shall be cleaned up, and all refuse removed to an approved landfill at the Contractor’s expense. The Contractor shall not disturb lands adjacent to the project site.
Existing access roads and trails within the project area that are damaged by the Contractor shall be restored at the Contractor’s expense to the same condition they were at the commencement of work. Stream channels, springs and other wet areas will be avoided by vehicles and heavy equipment. No new roads shall be constructed during project implementation. Cross-country travel shall be limited and approved by the BLM. Any heavily travelled areas shall be closed and rehabilitated prior to contract completion. Specifications for closure will be determined on a case-by-case basis in consultation with the BLM.
Any staging areas for fueling or maintenance of equipment shall be approved by the BLM. Any on-site fuel storage tanks shall have a catchment barrier placed underneath the tank to prevent fuel from entering the soil.
Vehicles and other equipment used for implementation of the project shall be washed to remove any vegetation and potential noxious weed and invasive species parts prior to beginning the work and following completion of the work.
Identified cultural sites, cadastral survey markers and other leave areas shall not be disturbed by equipment or the chaining operation. Execution of the work shall be planned in a manner to reduce multiple passes on the same piece of ground with the chain.
Work Schedule
The work schedule shall be submitted at the pre-work conference. The work schedule may be modified if inclement weather conditions occur. The Contractor shall notify the Contracting Officer’s Representative immediately of any changes in the original work schedule.
Work Camp
Camping will be allowed during project implementation only at sites that have been approved in advance by the BLM. All fire regulations and permits shall be followed. All garbage and refuse shall be removed from the camp site by the contractor at the time of project completion. Final payment will be reserved subject to inspection of these sites by the BLM and approval of site cleanup.
Project Meetings
Pre-Work Conference
A pre-work conference will be held prior to the start of work, and within 10 days of Contract award. The Contractor and Contracting Officer’s Representative will schedule a time for the meeting location, date and time. The purpose of the meeting will be to review the required work, the project locations, project specifications, work schedule, payroll and payments, and administrative provisions of the Contract. The Contractor and the persons responsible for coordination of the work shall be present at the meeting. The Contractor shall be prepared to summarize and explain procedures planned for the project.
Progress Meetings
Meetings may be called by either the Contracting Officer’s Representative or the Contractor.
Meetings shall be held at the project site, or as determined by the Contracting Officer’s Representative.
Final Inspection
The final inspection meeting shall be held at the project site, or as determined by the Contracting Officer’s Representative. The Contractor shall notify the Contracting Officer’s Representative at least two (2) working days before the completion date, so the Government can schedule a final inspection. Final payment of the contract will be held pending the completion of a satisfactory final inspection of all associated areas.
Government Furnished and Contractor Furnished Property
Materials/Information Furnished by the Government
The Government will provide paper and electronic copies of maps with the project area boundaries, and a shapefile, Avenza ready (or similar) pdf maps, or KML files of the project area boundaries (for GPS upload). No equipment will be furnished by the Government.
Equipment Furnished by the Contractor
Dozer and Harrow Chain
The Contractor will be responsible for furnishing the dozer capable of pulling a harrow chain assembly. The contractor will provide a harrow chain and repair parts for the above-mentioned equipment.
The dozer must be furnished with skilled and experienced operator and the necessary support.
Equipment shall be clean and in good working order and free of fluid leaks. Spills of any fluids will be the contractor’s responsibility to properly mitigate and clean. All spills shall be reported to the BLM representative.
GPS Units
The Contractor shall, at a minimum, provide one functioning GPS unit for each dozer capable of uploading shapefiles, Avenza ready (or similar) pdf maps, or KML files and displaying them in a manner that can be followed by the contractor’s personnel. It is expected that the individual assigned by the Contractor who is responsible for using the GPS unit to follow and/or mark project area boundaries will be able to operate and trouble shoot the GPS unit.
Communication
Dozer operators shall be able to reasonably communicate to one another while chaining to ensure proper alignment and deployment of the chain and to avoid restricted chaining areas. The Contractor is responsible for establishing a communication protocol with the dozer operators.
Many areas on the Arizona Strip are remote with no cell coverage. It is advised the operators have some type of satellite communication device for safety purposes as well as reliable communication with the Contracting Officer Representative or Project Inspector.
Measurement and Payment
Measurement of Payment
Invoicing may occur after work has been completed for an entire treatment unit.
There are portions of the unit that are steeper than others where some slopes are approaching or exceeding 30%. The contractor is responsible for reviewing the units sufficiently to determine if they have the technical capacity to complete the project in the terrain. The Government recognizes and respects the contractor’s right of refusal to some of these areas for safety and to prevent damage to equipment. If the contractor elects to not complete certain portions of the unit the contractor will notify the government representative with 48 hours with the location of the area and reasons as to why the area will not be completed. It is expected that these areas will not exceed 5% of the total area of any unit. Any acres not completed at the discretion of the contractor will not be paid for and the total price for the unit will be reduced by the per acre dollar amount.
The Contracting Officer or representative will make periodic inspections as a basis for progress payments and recommendations for adjustments in work quality. The Contractor or representative is encouraged to observe inspections at the time they are being made. Work performed according to the specifications will be considered acceptable for payment purposes.
Chaining Specifications
The following is a detailed summary of the work required to complete the chaining treatment for all units.
Type of Work
The project involves the double chaining of pinyon, juniper, and various shrubs. The area to be chained will have been seeded prior to chaining so it is expected that seed to ground contact will be made with double pass (twice over) of the harrow chain.
Treatment Acreage and Areas
The project areas consist of 618 acres. The attached maps delineate the project area boundaries with tentative islands and leave areas. Leave areas and boundaries may be altered prior to implementation of the project to mitigate sensitive resource concerns and may result in further acreage reduction. All reductions must by approved by the BLM.
The area for chaining occurs on a bench considered to be moderate terrain with some rocks. Tree cover in the area is moderately to extremely dense with size ranging from 4-20+ inch diameter at root collar.
Treatment
The chaining shall be conducted based on a double pass. The first pass will be completed, chaining will immediately follow a second time in the opposite direction of the first pass to assist in further removing targeted vegetation and assist in embedding the seed mixture into the soil.
Chaining shall not occur when the soil is saturated or where there is sufficient soil moisture that the equipment is leaving substantial ruts as determined by the Contracting Officer or representative. If and when these conditions are encountered, the Contractor shall stop work and notify the Contracting Officer or designated representative.
Within the project area the units are separated by considerable distance. The contractor will be required to unhook the chain and transport it (not drag) to each of the units. When moving between units it will be the contractor’s discretion whether they “walk” or transport the dozer between units. If the contractor chooses to “walk” the dozer between units the routes must be communicated to the government representative prior to moving the dozer.
Chaining shall not occur under conditions when the seed cannot be properly covered by soil.
These conditions include deep snow, saturated conditions or frozen ground. If and when these conditions are encountered, the Contractor shall stop work and notify the Contracting Officer or designated representative.
The Contractor is required to protect and avoid archaeological sites, survey markers, existing physical structures and springs located within the project area from damage or removal. In case of destruction or removal by the Contractor, they will be replaced or repaired by the Contractor at the Contractor’s expense. These special areas will be delineated within the avoidance areas and identified within the project area as identified on the shapefile, Avenza ready (or similar) pdf maps, or KML files to be uploaded on the contractors GPS unit and government furnished map (if requested) provided.
The Government Project Inspector will conduct periodic inspections to ensure compliance with the contract procedures and specifications.
Loading, Unloading and Transporting Property
The Contractor shall be responsible for providing the necessary handling equipment to load and unload materials and equipment. The Contractor is responsible for any damages incurred to the materials and equipment, incorporated into the work, while loading, unloading and transporting to and from the project sites. Once the work is completed, the Contractor is responsible for loading all of the equipment at the project site.
Loading and unloading of equipment should occur on established roads or within the treatment units as much as possible. The Contractor shall coordinate and gain approval of the Contracting Officer’s Representative for mobilizing the equipment to the project site.
Equipment Maintenance and Repairs
The Contractor is responsible for all maintenance and repairs of Contractor furnished equipment.
The Contractor shall complete sufficient maintenance of the equipment to prevent down-time on the project sites. The Contractor shall furnish all necessary lubricating equipment, proper lubricants and service tools to conduct minor maintenance to the dozer at the work site. The Contractor is responsible for checking bolts, nuts and other parts on dozer and harrow chain periodically to ensure operating efficiency. The Contractor is responsible for all maintenance measures to ensure proper functionality and for safety precautions.
The Contractor shall be equipped with the proper tools to conduct minor repairs to the dozer and the harrow chain assembly at the work site.
The Contractor will be responsible for the installation or repair of all parts, necessitated by normal wear or breakage or due to the fault or negligence of the Contractor.
Areas needed to work and maintain equipment within the treatment unit may be cleared of vegetation while minimizing soil disturbance. These work areas are to be kept to the minimum amount of area required and will not exceed 1/10th of an acre. The BLM will be notified of all of these locations. Upon completion of the work, the contractor will be responsible for hand seeding (the BLM will provide seed) these sites and scattering removed vegetation back on the sites.
Performance Schedule
This contract needs to be tightly coordinated with a seeding contract for the same areas. Period of performance for this work shall begin as soon as possible following the seeding of this site (within the appropriate treatment timeframes). It is anticipated that all work under this contract will occur from August 15, 2025, to January 31, 2026 (cutoff date due to wildlife stipulations).
The Contractor shall be required to start and complete the treatment area within the performance time identified above or as otherwise negotiated during the pre-work conference, provided weather conditions permit. If inclement weather conditions should occur prior to the Contractor completing the project, the Contractor shall be issued a stop work order and the project shall be completed as soon as weather conditions permit.
Due to timing restrictions for sensitive resources, treatments will not occur between February 1 and July 31, unless waiver is granted from the BLM COR. These timing restrictions shall be built into the proposal. No extensions will be granted due to these timing restrictions (except as mentioned with a waiver).