Attachment 1 - Statement of Work.pdf

PDF 1 MB Posted

Attached to
Entry Control Point (ECP) Facility for the Integrated Command Center (ICC)
Solicitation number
FA461324Q1056
Issued by

About this file

This document is a Statement of Work (SOW) for a temporary, modular or prefabricated Entry Control Point (ECP) facility to support construction activities for the Integrated Command Center (ICC) at F.E. Warren Air Force Base, Wyoming.

The SOW requires the contractor to provide all labor, materials, and logistics to design, manufacture, deliver, install, and fit-out the 12' x 44' ECP facility. The facility must be modular or prefabricated construction with secure mounting for the local weather conditions, and have a design-life of 18-24 months. The contractor must also perform site preparation, including utility connections and leveling. The government will provide the site location and utilities at no cost to the contractor. This is a Firm Fixed-Price commercial acquisition with a period of performance of 90 calendar days after contract award. Offerors must submit quotes by August 16, 2024, and the award will be made to the lowest-priced, technically-acceptable offer.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK (SOW)

FOR

GROUND BASED STRATEGIC DETERRENT (GBSD)

ENTRY CONTROL POINT (ECP) FACILITY

FOR THE INTEGRATED COMMAND CENTER (ICC)

F.E. Warren AFB, Wyoming

31 July 2024

Prepared By:

GBSD System Program Office (NIC) Air Force Nuclear Warfare Center (AFNWC)

6077 Indigo Lane, Building 1530 Hill Air Force Base (AFB), UT 84056-5816

Attachment 1 - Statement of Work

FA461324Q1056

1. SCOPE:

This Statement of Work (SOW) defines the requirements to provide a temporary, modular or prefabricated Entry Control Point (ECP) office for the construction activities associated with the Integrated Command Center (ICC) facility, on F.E. Warren Air Force Base (AFB), Wyoming.

From this point forward, within this document, this facility will be referred to as ECP (Entry Control Point). The SOW includes Contractor provision of all labor, materials, supplies, and logistics to provide a complete and usable facility to include:

All site preparation, including but not limited to utility (electrical) connection, setting, leveling, blocking and securing the modular unit.

The design, manufacture, delivery, installation of the modular or prefabricated building assembly.

The provision, installation, and fit-out of the facility to include procurement and installation of system furniture workstations and chairs, furniture, counter, cabinets, and cell phone “cubby” shelving.

1.1. BACKGROUND:

The Air Force seeks to purchase an ECP facility (approximately 12’ wide x 44’ long) to provide sufficient space to accommodate approximately 7 personnel within an unclassified area. As the facility is intended to be temporary, the facility must be modular or prefabricated construction with adequate secure mounting for adverse weather conditions as is common in the Cheyenne, Wyoming area requirements, with a design-life period of 18 to 24 months with minimum maintenance, and must be relocatable and salvageable for sale, redistribution, or otherwise disposal upon conclusion of its use.

2. APPLICABLE DOCUMENTS, STANDARDS, CODES, AND SPECIFICATIONS:

Attachment 1a – ECP Trailer Layout Concept Plan

3. REQUIREMENTS:

3.1. GENERAL:

3.1.1. A Facility Concept Plan is provided as Attachment 1a – ECP Trailer Layout Concept

Plan. This Concept Plan is for a “general” floor plan to accommodate the function and flow of an ECP.

3.1.2. Prior to contract award, the contractor shall deliver a 65% design solution, which represents a complete package with all design disciplines, including the furniture design and lay-out, in their initial proposal. Within 14 calendar-days prior to contract award, deliver the 100% final design solution as defined in UFGS Section 01 33 16.00 10.

Government intends to review, comment on, or accept, the 100% design submittal in writing through the government contracting officer within 14 calendar-days after receipt of the submittal.

3.1.3. After contract award and Notice to Proceed (NTP), the contractor shall supply an updated delivery and set up schedule for approval by the Government Project Manager and Contracting Officer.

3.1.4. Identify in the proposal a sole, on-site point of contact for the entire duration of the contract who will be responsible on behalf of the Contactor for meeting the requirements defined in this SOW.

3.1.5. Include in the proposal and schedule the procurement and installation all system furniture, including cubicle, hot desks, chairs, and breakroom and for the facility. Free-standing equipment such as printers/copiers/facsimile devices, shredders, plotters, refrigerators, microwaves, coffee makers, etc., and telephones, computers, monitors, and teleconference equipment will be provided and installed by the Government.

3.1.5.1. Provide one L shaped work-station cube as generally shown in the “Lead Office” area, consisting of free-standing, monolithic, modular panels and L shaped work surfaces which incorporate under desk and panel mounted storage cabinets, and power for computer workstation and telephone. Use a 6’x 6’ L shaped cubical with 4’ high vertical panels. Provide two “Hot Desk” as generally shown in the “Hot Desk Work Area”, consisting of a 60-inch x 24 inch desktop with 4’ high vertical panels for the two “hot seat” units. Provide 12‘long x 36“wide x 36” high counter area for badging and “bag check” station with undercounter cabinet with doors and shelves as generally shown in the “Badging and Check In” area. Provide 6 each black, swivel/tilt Mesh Mid-Back Task Chairs, with Fixed Cantilevered Arms (or similar) for workstations and check in area. Provide 48” round x 29” high break room table with 4 each fixed back cloth chairs.

3.2. TEMPORARY (ECP) MODULAR OR PREFABRICATED FACILITY

REQUIREMENTS:

3.2.1. Manufacture the modular or prefabricated building off-site and deliver and install on-site to the specified location. Expect and accommodate the inspection of building assembly by Government officials at the manufacturing location prior to shipment, and periodically throughout assembly, at the Government’s discretion.

3.2.2. Foundations: As the facility is relocatable and temporary in nature and will be removed upon completion of use, the use of adjustable, heavy duty, screw-type jacks or masonry blocks on the asphalt apron to support and adjust level of the floor structure over the life of the modular units are potential solutions. Tie downs designed and installed by contractor will be required for a secure facility. This facility must be able to withstand the severe weather and wind conditions that are common to the FE Warren AFB area.

3.2.3. Floor Structure: Incorporate a crawl space between the modular floor structure and the existing asphalt apron. Insulate any piping or ducts within the crawl space as appropriate for the climate conditions and provide crawl space access from the interior of the facility through appropriately located, lockable access hatches.

3.2.4. Interior Walls: Use finished interior walls that span from the true floor to the true ceiling.

Provide a minimum interior finished ceiling height of not less than 8’-6”’ through-out the facility (note: the finished ceiling height does not include drop-ceilings required in the occupied interior areas to hide utilities, HVAC, cabling, and wiring, etc.). Finish shall be level 4 minimum.

3.2.5. Entrances and Emergency Exits: Ensure all entrances and emergency exits conform to NFPA and ADA requirements and are connected by concrete sidewalks to adjoining pavements. Provide and install to ECP facility floor height, Aluminum stairs with landings and rails at each entrance (exit).

3.2.5.1. Roof: Incorporate gutters and downspouts placed outside of the fascia and drain to the subsurface collection system where available. Consolidate and minimize penetrations through the roof.

3.2.5.2. Exterior Walls: Finish exterior walls using factory pre-finished siding and colors with not more than one trim color that match the manufacturer’s standard selection.

3.2.5.3. Exterior Entrance/Exit Doors: Use anodized aluminum doors and frames with thermal breaks. Include appropriate hardware, including panic hardware where required, and locksets to match the base Master Key System.

3.2.5.4. Exterior Windows: Provide 2 each 36” x 36” anodized aluminum windows and frames with thermal breaks. Windows are to be energy-efficient, low-e, double-pane glazing, and place at the high-level on the exterior wall to allow use of wall space in the interior. Include blinds on the interior of all windows.

3.2.5.5. Exterior Doors: Use painted, steel frame and steel hollow-core doors not less than 36” wide for exterior applications. Secure with cypher locksets.

3.2.5.6. Interior Doors: Use appropriately sized and rated, painted, hollow steel frame and steel doors in interior spaces Include appropriate hardware, including panic hardware where required, and locksets conforming to the base Master Key System.

3.2.5.7. Interior Walls: Interior walls to be vinyl covered gypsum board wall assemblies. Use neutral colors.

3.2.5.8. Interior Floors: Use laminate flooring in all areas of ECP.

3.2.5.9. Interior Ceilings: Use a suspended ceiling system with fine-texture, revel-edge acoustic tiles set in 2’x 2’ grid with flush mounted overhead lighting to provide a minimum of 30 foot-candles in all areas.

3.2.5.10. Ensure floor construction in areas that accommodate multiple copy/printers, files, or security containers is designed for higher loading capacity (i.e., 5 drawer safes, 18” x 28” base, and weigh up to 1,000 lbs. per safe when loaded).

3.2.6. Crawlspaces: Crawlspace is to have metal skirting that matches exterior of ECP.

3.2.7. Heating, Ventilating, and Air Conditioning System (HVAC): Provide a packaged, module mounted system for HVAC. The systems shall be sized to control using standard 72 Degree F indoor summer control and 68 Degree F winter control.

3.2.7.1. Design systems to be compatible with the severe weather conditions encountered at FE Warren AFB, Wyoming. Use systems appropriately rated for the extremes of the temperature zone and which include an inverter driven compressor to better maintain consistent temperatures.

3.2.8. Electrical and distribution panel: Provide and install the sub-panels, and building distribution system and all lighting, outlets, at workstations, and equipment and appliance locations. Provide an outside connection for a mobile generator to provide emergency power. No generator is to be provided, but a plug in and associated isolation switches so that no back feed to the grid would be possible when the mobile generator is in service.

Once “permanent” power is available to the site construction offices, a feeder is to be connected to the ECP by site General Contractor in lieu of the current generator feed.

3.2.8.1. Use PVC for underground conduits placed no-less-than 24” below grade from the construction site MDP to the electrical connection point of the ECP. Where PVC underground conduits transition to above grade or penetrate slabs, floors, or walls, use rigid galvanized steel. All underground conduits shall have foil locating taped located 12 inches below grade for identification during excavation in future dates.

3.2.8.2. Provide a service-rated main panel in the “Badging and Check In” area rated at 240/120V, single-phase 100 Amps.

3.2.8.3. Use only copper conductors. Use XHHC conductors for service entrance and THHN

& THWN for #8 AWG or smaller conductors and THHN, THWN, and XHHW for larger conductors. For #8 or larger conductors use stranded; for #10 and #12 use solid conductors.

3.2.8.4. Use electrical metal tubing (EMT) conduit for wiring above ceilings and in walls as appropriate. Use flexible metal conduit for whips to light fixtures and mechanical equipment where appropriate. Minimum conduit size is ¾ inch.

3.2.8.5. Lighting: Provide all lighting, including overhead lighting using flush-mounted lay-in, downlight, low-bay and/or industrial type lighting fixtures as appropriate for the function/space having LED light sources with a 4000K Color Correlated Temperature and a color rendering index of no less than 80. Include egress lighting and exit signs in accordance with NFP 101 and exterior lighting to illuminate each entrance/exit and walkway.

3.2.8.5.1. Illumination Levels, Lighting Types, and Controls:

3.2.8.5.1.1. 30 foot-candles at 30” above floor / type LED Linear 2x2 Troffer / Auto-on to 50 percent when occupant activity is sensed, with manual switching to 100 percent. Auto-off within 15 minutes of no occupant activity. Provide conference rooms with multiple zones and manual dimming to independently control lighting zones within the room to facilitate different room uses.

3.2.8.5.1.2. Exterior Entry/Exit: 10 foot-candles at floor / type LED wall-mounted: /Auto-on at dusk and auto-off when sufficient daylight available.

3.2.8.6. Egress Lighting and Exit Signs: Provide exit and egress lighting in accordance with NFPA 101 by selecting and equipping some general illumination fixtures with emergency battery packs.

3.2.9. Communications:

3.2.9.1. A Wireless System will be purchased and installed by Government.

3.3. SITE REQUIREMENTS

3.3.1. Perform all site preparation necessary to install and complete the temporary facility including leveling jacks or blocks and tie-downs and electrical connections.

3.3.2. Pavements:

3.3.2.1. None in this SOW.

3.3.3. Utilities: Electrical are available near the site. The electrical supply to the ECP will be from a temporary generator currently in service abut shall be converted to a permanent feed from Hensel and Phelps construction electrical service once that is in place.

3.3.3.1. Water & Sewer: None required.

3.3.3.2. Gas: None required.

3.3.3.3. Electricity: Coordinate with Hensel Phelps and USACE for connection.

3.3.4. CONTRACTOR’S TEMPORARY BUILDINGS AND INFRASTRUCTURE:

3.3.4.1. Keep existing roads and parking areas operational except for short durations; only one lane closure is acceptable during normal business hours. Any damage to Government property is the responsibility of the Contractor to repair including the grounds, roadways, curbs, and sidewalks. Contractor must comply with base safety and construction policies and with all state and federal safety requirements, laws, and regulations.

3.3.4.2. Use only established roadways and routes approved by the Contracting Officer for access to or traveling on the Base. When materials are transported in prosecuting the work, do not load vehicles beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. Take necessary precautions to protect roads, curbs, sidewalks and driveways from damage; the Contractor is responsible to repair, or pay for repair, of any damaged roads, curbs, sidewalks, driveways.

3.3.4.3. Store and handle materials as recommended by the manufacture and good practice to avoid hindering the work of others, avoid soiling, damage or breakage, and preclude the inclusion of foreign mater or water. Store packaged materials in original containers until ready for use. The Government may reject materials showing evidence of water or other damage, in which case the Contractor is responsible for removing from the Base.

3.3.5. GOVERNMENT FURNISHED EQUIPMENT / PROPERTY / MATERIAL

(GFE/GFP/GFM):

3.3.5.1. The Government provides an appropriately sized plot of land on the Base to support Contractor provided, temporary buildings and infrastructure, laydown yard, and parking and access road(s) while performing work under this contract.

3.3.5.2. The Government allows the use of electrical and water utilities at no cost to the Contractor while performing work under this contract. However, connection to utilities is the responsibility of the Contractor and is subject to review and approval by the Government.

3.3.6. SAFETY REQUIREMENTS:

3.3.6.1. Provide protection to Government property to prevent damage during the period the property is under the control or in possession of the Contractor.

3.3.6.2. Record and report promptly (within one hour) to the Contracting Officer (CO), all available facts relating to each instance of damage to Government property or injury to either Contractor or Government personnel.

3.3.6.3. In the event of an accident/mishap, take reasonable and prudent action to establish control of the accident/mishap scene, prevent further damage to persons or property, and preserve evidence until released by the accident/mishap investigation authority through the CO. (Accident-Safety-Mishap Report CDRL A003). If the Government elects to investigate the accident/mishap, cooperate fully and assist Government personnel in the conduct of investigation until the investigation is completed.

3.3.6.4. Provide and maintain work environments and procedures which:

3.3.6.4.1. Safeguard the public and Government personnel, property, materials, supplies, and equipment exposed to Contractor operations and activities.

3.3.6.4.2. Avoid interruptions of Government operations and delays in project completion dates.

3.3.6.4.3. Comply with all pertinent provisions of the latest version of the U.S. Army Corps of Engineers Safety and Health Requirements Manual, EM 385-1-1, in effect on the date of the solicitation.

3.3.6.4.4. Comply with standards issued by the Secretary of Labor at 29 CFR Part 1926 and 29 CFR Part 1910.

3.3.6.5. Comply with OSHA regulations for storage of combustible materials on the site in

OSHA approved combustible materials lockers at least 50 feet (15 meters) from all buildings unless otherwise specifically indicated by the Government Program Team.

3.3.6.6. If the CO becomes aware of any noncompliance with these requirements, or any condition which poses a serious or imminent danger to the health or safety of Contractor personnel, public, or Government personnel, the CO shall notify the Contractor orally, with written confirmation, and request immediate initiation of corrective action. This notice, when delivered to the Contractor or the Contractor’s representative at the work site, shall be deemed sufficient notice of the noncompliance and that corrective action is required. After receiving the notice, immediately take corrective action. If the Contractor fails or refuses to promptly take corrective action, the CO may issue an order stopping all or part of the work until satisfactory corrective action has been taken. In this event, the Contractor is not entitled to any equitable adjustment of the contract price or extension of the performance schedule on any stop work order so issued.

3.3.7. WEATHER PRECAUTIONS: Ensure weather sensitive materials are only placed within the conditions recommended by the material supplier.

3.3.8. PROTECTION OF EXISTING GOVERNMENT PROPERTY AND EXISTING

WORK:

3.3.8.1. Conduct all operations in such a manner as to prevent injury or damage to Government property and any portions of the existing work which are to remain. This requirement is not limited to the project site but includes landscaping, curbs, pavements, and utilities adjacent to the site as well as along the routes to and from the site. If any ambiguity exists, request clarification from the Contracting Officer before beginning work.

3.3.8.2. Make repairs to, or replace portions of, any environmentally damaged or unduly altered existing facilities during construction operations to match existing or adjoining facilities and environment, as approved by the Government Program Team.

At the completion of operations, ensure existing facilities and environment are in a condition equal to or better than that which existed before new work started.

3.3.8.3. In the event the Contractor fails or refuses to make satisfactory repairs or replacements to property damaged by the Contractor under this contract the Government may elect to have the repairs made at the expense of the Contractor.

3.3.9. UTILITY OUTAGES AND PERMITS:

3.3.9.1. Post permits and closure notices at a conspicuous location in the construction area as early as possible in advance of anticipated utility outages, closures of parking lots and pedestrian walkways.

3.3.9.1.1. The Contractor is not entitled to additional payment for utility outages and connections required to be performed outside regular work hours.

3.3.9.2. Burn Permits. Open burning of any sort is strictly prohibited.

3.3.9.3. Welding, Cutting, and Brazing Permits: An Air Force Form 592 is required daily for all welding, cutting, brazing, soldering and similar hot work. Ensure the form is filled out properly and displayed while all hot work is underway. The Contractor is required to attend a welding, cutting, and brazing certification class prior to construction startup; contact the Base Fire Department for details.

3.3.10. CONTRACTOR ACCESS AND BASE CREDENTIALS:

3.3.10.1. Ensure all Contractor and subcontractor personnel proposed to work on the Base under this contract are U.S. Citizens or Naturalized Citizens and are eligible to work on the premises.

3.3.10.2. Complete and submit to the Government the necessary forms to be issued for base access through the Defense Biometric Identification System (DBIDS) for each employee requiring access to the base through the Period of Performance.

3.3.10.3. Be responsible for prompt return of credentials for any employee who no longer requires access to the Base during performance of the contract and at the termination or completion of the contract. Report any lost badges to the Contracting Officer within one working day of loss.

3.3.10.4. The Government, at its sole discretion, may immediately remove from or deny access of any Contractor employee to any Government property, facility, and installation if that authority determines such action is necessary to protect or preserve Government property, safety and security, or to maintain good order and discipline.

3.3.11. MISSION ESSENTIAL STATEMENT:

3.3.11.1. In accordance with DoDI 3020.37, Continuation of Essential DOD Services during Crisis, the Functional Direction determined that this effort is not considered mission critical and will not continue in the event of a crisis.

4. GENERAL INFORMATION:

4.1. SCHEDULE OF WORK:

4.1.1. Working hours for the Contractor will be between 7:30 a.m. and 4:30 p.m., Monday –

Friday, excluding Saturdays, Sundays, and federal holidays. If the Contractor desires to work during periods other than above, additional Government inspection. forces may be required. The Contractor MUST notify the Government POC (3) days in advance of their intention to work during other periods to allow assignment of additional inspection forces.

4.2.1. Quality Control. Any matter concerning a change to the scope, prices, terms or conditions of this contract shall be referred to the Contracting Officer and NOT to the Government Representative.

4.2.2. The services to be performed by the contractor during the period of this contract shall (at all times and places) be subject to review by the Contracting Officer or authorized representative(s).

4.2.3. Physical Security. The contractor shall be responsible for safeguarding all Government property provided for contractor use. At the close of each work period, Government facilities, property, and materials shall be secured.

4.2.4. Operational Security (OPSEC). The contractor shall adhere to the following minimum requirements in support of this requirement:

4.2.4.1.1. Contractor personnel shall not discuss government operations in public or over unprotected or unencrypted communications. Official Business, controlled unclassified information may only be transmitted as directed in the SOW.

4.2.4.1.2. The Contractor shall not post to company websites, publications, newsletters or other media any images, data or information that reveal sensitive government operations, personnel, equipment, and/or classified or controlled unclassified information. When in doubt, company press releases related to this contract should be coordinated through the Contracting Officer, as applicable.

4.2.5. Because observation of events, operations, physical changes, etc. may reveal National

Security information, specific restrictions are needed to preclude unintentional release of this information to unauthorized parties. (Unauthorized disclosure and transfer of National Security Information is punishable under 18 USC § 793.) Therefore, contractor personnel shall not disclose to unauthorized third parties, post to unofficial sites (including Social Networking sites) any images, data or information, or observed events that reveal sensitive government operations, personnel, equipment, including, but not limited to:

4.2.5.1.1. Tactics, techniques and procedures, production or work schedules, any visible or concealed modifications, upgrades, additions to vessels, aircraft, or weapons or equipment; increases, change, or decreases in work/deployment frequency or government personnel, vehicle, vessel or aircraft movements; specialized equipment orders, deliveries, shipments, etc., Unauthorized disclosures and attempts to solicit this type of information by unauthorized third parties or others not affiliated with this contract shall be reported to the Contracting Officer, as applicable.

4.3.1. Location/Hours of Operation.

4.3.1.1.1. Location. Place of performance is F. E. Warren Air Force Base, WY.

4.3.1.1.2. Normal Hours of Operation. The contractor shall perform the services required under this contract between 7:30am and 4:30pm Monday through Friday. The contractor may work, with prior approval of the Government Representative, extended hours to ensure timely completion of work at no additional cost to the Government.

Contractor shall notify the Government POC three (3) days in advance of the request.

4.3.1.1.3. Recognized Holidays. The contractor is not required to provide service on the following days: New Year’s Day, Martin Luther King Day, Presidents Day, Memorial Day, Juneteenth, Independence Day, Labor Day, Columbus Day, Veterans Days, Thanksgiving Day and Christmas Day. If the holiday falls on Saturday, it is observed on Friday. If the holiday falls on a Sunday, it is observed on Monday. Contractor is not required to perform service during base down days.

4.4.1. Conservation of Utilities.

4.4.1.1.1. The contractor shall instruct employees in utilities conservation practices. The contractor shall be responsible for operating under conditions which prevent the waste of utilities which include the following:

4.4.1.1.2. Lights shall be used only in areas where and when work is actually being performed.

4.4.1.1.3. Mechanical equipment controls for heating, ventilation, and air conditioning systems shall not be adjusted by the contractor or by contractor employees unless authorized.

4.4.1.1.4. Water faucets or valves shall be turned off after the required use has been accomplished.

4.4.1.1.5. Government telephones shall be used only for official Government business.

4.5.1. Environmental Controls.

4.5.1.1.1. Compliance with Laws and Regulations. The contractor shall be knowledgeable of and comply with all applicable Interstate, Federal, State, and Local laws, regulations, and requirements regarding environmental protection. In the event environmental laws/regulations change during the term of this contract, the contractor is required to comply as such laws come into effect. If there is an increase or decrease in cost as a result of the change, the contractor shall inform the Contracting Officer pursuant to notice requirements and negotiate a modification to the contract.

4.5.1.1.2. Notification of Environmental Spills. If the contractor spills or releases any substance contained in 40 CFR 302 into the environment, the contractor or its agent shall immediately report the incident to the F.E. Warren AFB Fire Dept at 911 (landline) or 307-773-2931 (cell phone). The liability for the spill or release of such substances rests solely with the contractor and its agent.

4.5.1.1.3. Hazardous Material (HM). In the event that hazardous materials will be used in the execution of this contract, the contractor shall comply with all federal, state and local regulations concerning the use, storage, and reporting of HM in accordance with AFI 32-7086, Hazardous Materials Management. The contractor shall be required to obtain authorization per the Installation Hazardous Materials Management Program before ordering or purchasing any hazardous product and may not bring a HM onto F.E. Warren AFB property, nor use a HM, until the contractor receives all required authorizations. This authorization process may take up to three weeks.

4.5.1.1.4. Green Procurement Program (GPP). In performance of this contract, contractors shall use Environmental Protection Agency (EPA) designated recycled content products, Information Technology (IT) Energy Star products/appliances, Federal Energy Management Program (FEMP) Designated Energy Efficient Low Stand By Power products/appliances, U.S. Department of Agriculture (USDA) Bio based/Bio preferred products, Environmentally preferable products, Electronic Product Environmental Assessment Tool (EPEAT) registered products, Water Sense or other water efficient products, non- or Low Ozone depleting substances under the Significant New Alternatives Policy (SNAP), non or Low toxic or hazardous constituents (e.g. non-VOC paint) and any other environmentally sustainable product/method, to the greatest extent possible.

4.6.1. SAFETY REQUIREMENTS:

4.6.1.1. In performing work under this contract, the contractor shall:

4.6.1.1.1. Conform to the safety requirements contained in the contract for all activities related to the accomplishment of the work.

4.6.1.1.2. Record and report promptly (within one hour), to the contracting officer or designated

Government Representative, all available facts relating to each instance of damage to Government property or injury to either contractor or Government personnel.

4.6.1.1.3. In the event of an accident/mishap, take reasonable and prudent action to establish control of the accident/mishap scene, prevent further damage to persons or property, and preserve evidence until released by the accident/mishap investigative authority through the contracting officer.

4.6.1.2. Work area(s) shall follow OSHA CFR 29 part 1910-268 standards for safety if not covered by an applicable Air Force Standard. At day’s end, the Contractor shall remove all debris and surplus materials from the workplace. Safety barriers shall be in place to protect unfinished work site at the end of the day. Equipment and materials required to complete the work effort may remain on site as long as they are organized and stored in a manner that does not cause a safety hazard. The contractor shall return all Government furnished lay-down and storage areas to their original condition upon completion of the project.

4.6.1.3.Site Point of Contact (POC). The Contractor shall designate and provide to the Government POC the Contractor's on-site team leader and alternate(s) name and phone numbers as the site POC on the first day of project start. The Site POC or alternate(s) shall be on site during duty hours until project completion and shall oversee all facets of the installation tasks. The Site POC shall be the interface for all work site communications with the Government, including quality, safety, and discrepancy matters.