Attachment_1_Statement_of_Work.docx

DOCX document 8 MB Posted

Attached to
BFO ROAD MAINTENANCE Federal contract opportunity
Solicitation number
140L6223Q0025
Issued by
Department of the Interior Bureau of Land Management Wyoming Region

About this file

This document contains a statement of work for road maintenance services for the Bureau of Land Management in Wyoming. The contractor will be required to blade approximately 24.7 miles of roads in Johnson and Campbell counties between April and November, including 7.5 miles of Bar C Road maintained in two sections with a 0.7 mile separation, 7.7 miles of Billy Creek Road with 50 cubic yards of gravel placement, 7 miles of Weston Road, and 0.75 miles of Mosier Gulch Road. The contractor must coordinate blading with current moisture conditions, provide one week advance notice to BLM before starting work, and adhere to traffic control standards. Payment will be based on linear miles of blading completed. The related federal contract opportunity is solicitation number 140L6223Q0025 for BFO Road Maintenance services with the Department of the Interior Bureau of Land Management Wyoming Region.

View the file

Other files for this federal contract opportunity

Other files attached to BFO ROAD MAINTENANCE, newest first.
File Type Posted
Questions_Addressed_0001.docx DOCX document
Sol_140L6223Q0025_Amd_0001.pdf PDF
Attachment_4_NEPA_Document.pdf PDF
Attachment_6_Limitations_on_Subcontracting_Breakout.pdf PDF
Attachment_3_Wage_Determination_WY20230036.docx DOCX document
Attachment_2_Bid_Schedule.doc DOC document
Attachment_5_SF_1442_Completion_Instructions.pdf PDF
Sol_140L6223Q0025.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

BUFFALO FIELD OFFICE ROAD MAINTENANCE

STATEMENT OF WORK HIGH PLAINS DISTRICTWyoming - High Plains District Office

SECTION 01009 – GENERAL INFORMATION AND REQUIREMENTS

PART 1: GENERAL

1.1 SUMMARY:

A. Description of Work: Furnishing labor, equipment, supplies, and materials to maintain roads.
Total mileage of road blading is 24.7 miles with an additional 2.5 miles of cleaning andreshaping ditches as directed by the BLM. One culvert cleanout per year, including inlets and outlets, as
directed by the BLM.

1. Bar C Road: Blade 7.5 miles of roadway on Bar C Road, The 7 miles of roadway for the Bar C Road are not contiguous. There is a 0.7-mile separation in the two sections of road that are maintained.

The 0.7-mile section not maintained on the Bar C Road is between the 1st and 2nd Fishing access to the Outlaw Canyon. Contractor shall ensure that there is no disturbance to the road, shoulder, or adjacent landscape on the 0.7-mile section while moving road grader between the two maintained sections.

Bar C Road will be maintained once between 01 May and 31 May and once prior to 03 November.

2. Billy Creek Road: Blade 7.7 miles of roadway, Hauling, placing, and blading of 50 CY of gravel on Billy Creek Road as directed by the BLM. The U.S. Forest Service will make available to the BLM and its contractors, 50 CY of aggregate from the Pole Creek Pit per year.

Billy Creel Road will be maintained once between 01 May and 31 May and once prior to 03 November.

3. Weston Road: Blade 7.0 miles of road.

Weston Hills will be maintained once between 15 April and 15 May.

4. Mosier Gulch: Blade 0.75 miles of road.

Mosier Gulch will be maintained once between 15 April and 15 May.

The Contractor shall coordinate the blading of the roads with the BLM to time the work with current precipitation/moisture. The contractor shall provide at least one week notice to the BLM before starting work on any road. All roads have aggregate surfacing.

A. Location: Work under this Contract is located in Johnson and Campbell Counties, Wyoming. The work locations are shown on the drawings.

1.2 REFERENCES:

A. Referenced Specifications/Standards with Abbreviations and/or Acronyms: Wherever the following acronyms are used in these specifications or on the drawings, they are to be construed the same as the respective expressions represented. Copies of the referenced specifications/standards referred to herein may be procured by the Contractor, from the following:

MUTCD Manual on Uniform Traffic Control Devices for Streets and Highways Superintendent of Documents Government Printing Office Washington, DC 20402

OSHA Occupational Safety and Health Administration's Standards U.S. Department of Labor Occupational Safety and Health Administration Denver Area Office 333 West Colfax Avenue Denver, CO 80204

1.3 QUALITY ASSURANCE:

BUFFALO ROAD MAINTENANCE

GENERAL INFORMATION AND REQUIREMENTS

01009-1

SECTION 01009 – GENERAL INFORMATION AND REQUIREMENTS

A. Codes and Standards: The work shall comply with codes and standards applicable to each type of work and as listed in the individual sections of these specifications. This Contract incorporates materials, applications, and tests by reference, with the same force and effect as when they were given in full text.

B. Conflict: Where a conflict occurs between reference documents and project specifications, the project specifications shall govern.

1.4 PROJECT/SITE CONDITIONS:

A. Access to the Work: Access is via Wyoming State Highways and County roads.

1.5 SEQUENCING AND SCHEDULING:

A. Work Schedule: The schedule for the upcoming season shall be submitted at the pre-work conference. When requested, the Contractor shall submit an updated schedule within 3 calendar days.

B. Weather Delays: In the event of heavy snow on the roads in late spring, coordinate with the Contracting Officer Representative to select an alternative date for completion based on road conditions.

PART 2: PRODUCTS

(There are no applicable requirements.) PART 3: EXECUTION

3.1 PROJECT MEETINGS:

A. Pre-Work Conference:

1. A pre-work conference will be held prior to the start of work. The Contractor will be notified in advance of meeting time, date, and place. The purpose will be to review required work, project drawings and specifications, construction schedules, payroll and payments, and administrative provisions of the Contract.

2. The Contractor, subcontractors, and the persons responsible for coordination of the work shall be present at the meeting.

3. The Contractor shall be prepared to summarize and explain procedures planned for the project [and present the submittals requested in the specifications].

B. Progress Meetings:

1. Meetings shall be held at the project site, or as determined by the Contracting Officer.

2. Meetings may be called by either the Contracting Officer or the Contractor. Request shall

SECTION 01009 – GENERAL INFORMATION AND REQUIREMENTS

state who should attend and include an agenda.

C. Final Inspection:

1. Meeting shall be held at the project site, or as determined by the Contracting Officer.

2. The Contractor shall notify the Contracting Officer in writing at least 3 working days before the completion date so the Government can schedule final inspection.

3. The Contractor shall require the superintendent to be present during this inspection.

3.2 PREPARATION:

A. Work Layout: If requested, the Government will set construction stakes to give the Contractor measurements, lines and grades necessary for the work executed under the Contract. Baseline monuments or benchmarks disturbed or removed during construction shall be reset by the Contractor at the Contractor's expense.

B. Work Limits and Control Points: Will be staked by the BLM as necessary.

PART 4: MEASUREMENT AND PAYMENT

4.1 METHOD OF MEASUREMENT:

A. Units: The work described in this section will not be measured for payment.

4.2 BASIS OF PAYMENT:

A.Payment:No direct payment for the work described under this section will be made.
The Contractor shall include consideration for this item in the bid price for other items of the Contract.

END OF SECTION

SECTION 02213 – SITE GRADING

PART 1: GENERAL

1.1 SUMMARY:

A. Section Includes: Reestablishing roadway template by blading.

1.2 PROJECT/SITE CONDITIONS:

A. Environmental Conditions: Do not attempt to blade frozen or saturated materials. The Contractor shall coordinate the blading of the roads with the BLM in order time the work with precipitation/moisture.

PART 2: PRODUCTS

2.1 EQUIPMENT:

A. Road Blading Equipment: The Contractor shall provide a road grader with a minimum 150 horsepower and twelve-foot blade. The cutting edges of the blade shall be in good condition, free from deformation due to excessive wear. All controls, including brakes, shall be in proper working condition to allow full control of the grading at all times.

PART 3: EXECUTION

3.1 BLADING:

A. Blade shoulders to recover aggregate, destroy vegetation, and ensure drainage from roadway into ditch. Pulling ditches is not required. Roadway shall be reshaped to remix the aggregate, eliminate potholes and wash-boarding, and reestablish the roadway crown.

B. Aggregate material shall not be bladed into cattleguards or into culvert openings.

C. No material shall be left in windrows on the roadway overnight, over weekends, or holidays.

D. Berms shall not be left along the shoulders of the roadway.

E. If contractor notes a problem area where the continuation of work may cause damage to natural resources, structures, roads or any other improvements they shall continue work in another area and contact the BLM in order to re-evaluate the scope of work.

3.2 TRAFFIC CONTROL:

A. The Contractor shall conform to MUTCD requirements for control of traffic in the work zone.

BUFFALO ROAD MAINTENANCE

SITE GRADING

02213-1

SECTION 02213 – SITE GRADING

Pay Item Pay Unit

02213(01) Blading……………………...Linear Mile

UNITED STATES DEPARTMENT OF THE INTERIOR BUREAU OF LAND MANAGEMENT

PROJECT LOCATION MAP BAR-C ROAD

BUFFALO FIELD OFFICE - HIGH PLAINS DISTRICT

PROJECT LOCATION MAP BILLY CREEK ROAD

PROJECTLOCATIONMAP
WESTONROAD

Bid Schedule

Buffalo Road Maintenance High Plains District, Wyoming

Pay Item Pay Unit

02213(01) Blading…………………. Linear Mile image4.png image5.png image6.jpeg image7.png image8.jpeg image8.png image9.jpeg image11.png image12.jpeg image10.jpeg image12.png image13.jpeg image14.png image15.png image16.png image17.png image18.png image19.png image20.png image21.png image22.png image23.png image24.png image25.png image11.emf image1.png image2.png image3.png