Text version
STATEMENT OF WORK FOR UTILITIES INSTALLATION TO MODULAR BUILDINGS
At The Cabo Rojo National Wildlife Refuge Puerto Rico June 3, 2021
1. Background Due to structural damages to the Visitor Center and office building, the HQ building is scheduled for demolition. A number of temporary facilities are required for storage and operational office spaces. The required task is for the installation of water, electricity and sewage to four modular buildings as per this Scope of Work (SOW).
It is strongly recommended, the Contractor visit the site with the Caribbean Islands NWR Facilities Operations Specialist and Cabo Rojo Wildlife Refuge Manager to verify the location and all required work specified on this SOW. Any revisions will be captured in a revised and final site plan. The contractor shall verify all possible locations for the utilities installations to the building or trailers. Product data submittals shall be required for all construction materials necessary for the installation.
2. Project Location:
Cabo Rojo NWR Carr. 301 Km. 5.1 Bo. Corozo Boqueron, PR 00622 See Attachment 1
3. Points of Contact
Construction Representative / COR Ricardo Antonetti Facilities Operations Specialist PO Box 510 Boquerón, PR 00622 ricardo_antonetti@fws.gov 787-232-8116
Refuge Manager Ana Roman Cabo Rojo NWR Cabo Rojo, PR 00622 ana_roman@fws.gov 787-396-7711
4. General Notes:
| 4.1 | The contractor shall supply all materials, labor, supplies and equipment to perform all tasks required to complete the work in accordance with the scope of work. |
| 4.2 | Contractor needs to coordinate with Refuge Manager concerning the location for temporary office trailer (if required) and storage of material and equipment in the refuge. Contractor will prepare, in coordination with COR and Refuge Manager, a project site plan showing construction and staging areas. Contractors and subcontractors will adhere to this site plan as approved by all parties and if any modification is needed changes will be consulted with the COR and Refuge Manager prior to any action taken. |
| 4.3 | The Information for the utilities and measurements provided are for general guidance only. |
| 4.4 | Product Data Submittals will be required on all materials prior to procurement and installation. All Product Data Submittals shall be transmitted to the Contracting Officer and Contracting Officer Representative / COR. |
| 4.5 | Contractor needs to comply with all federal and local labor, safety and other laws applicable to conduct the contract. |
4.6 All work will be IAW IBC, NEC and all applicable codes and regulations.
4.7 A Pre-Proposal Meeting can be held at a predetermined location in Cabo Rojo NWR.
4.8 Working hours and days will be limited to Monday to Friday, 07:00AM to 04:00PM
4.9 Contractor is responsible to pay all applicable municipal fees and taxes.
Objectives:
Task 1. Electrical power installation to Modular offices or trailer units
1.1 Each trailer will require 120/240 volt 60 to 100 amp service, depending on the calculated load of each trailer.
1.2 Reference to attachment B, D and E for possible aerial runs to trailers in Locations A (Three trailers) and B (One trailer)
1.3 All required line protections and disconnects will be installed as per NEC.
Note:
For Location B, contractor needs to calculate required run from the electrical manhole on attachment E. Underground and aerial.
Task 2. Potable Water installation
2.1 Install ½” water line (PVC Sch 40) for potable water to each trailer.
2.2 A main valve will be required at the connecting point and a water valve outside each trailer.
Reference to attachment E and F for water connecting points.
Task 3. Sewage installation
3.1 Install required (PVC Sch. 40) line for sewage to each trailer. Reference to attachment
3.2 Connect each trailer to sewage line.
3.3 A cleanout will be required mid-point and at connecting point on all locations.
Notes:
1. Reference to attachment E and F for septic system locations.
2. Due to the distance and available slope, the sewage lines can be surface mounted. Install all required support and caution signs or marks.
Project Location
Attachment A Cabo Rojo National Wildlife Refuge
Attachment B
Attachment C
Electrical connection to trailers Location A
Attachment D
Utilities connections to trailer Location B
Attachment E
Available water and sewage in location A
Attachment F image2.png image3.png image4.png image5.png image6.png image7.png image1.png