This Statement of Work (SOW) details an asbestos testing project for the US Department of Agriculture Forest Service at the Rio Grande National Forest. The project requires a certified contractor to inspect, sample, and report on asbestos-containing materials (ACMs) in eight buildings constructed between 1900 and 1986, with square footages ranging from 443 to 3,063 square feet. Key requirements include identifying and sampling ACMs, creating location diagrams, developing mitigation strategies, and submitting comprehensive reports within 30 days of inspection completion.
The solicitation seeks proposals evaluated on three factors: cost, past performance, and key personnel experience. Contractors must provide detailed documentation including organizational information, project history, key personnel certifications, and laboratory testing credentials. The testing must comply with federal and state safety regulations, using an accredited laboratory to analyze samples. The project scope is specifically for identification and reporting, with actual asbestos removal or mitigation not included in this contract requirement.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 1240LQ25B0002 A0001.pdf | ||
| Attachment 4 Travel map.docx | DOCX document | |
| Attachment 3 WAGE DETERMINATIONS.pdf | ||
| Attachment 2 Pictures of each structure.docx | DOCX document | |
| 1240LQ25B0002.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
US Department of Agriculture (USDA)
Statement of Work
Contents
| Project Title | 3 |
| General Information | 3 |
| 1.0 Background and Purpose | 3 |
| 2.0 Definitions | 3 |
| Contractor Requirements | 3 |
| 3.0 Technical Requirements / Tasks | 3 |
| 4.0 Deliverable / Schedule | 4 |
| 5.0 Contractor’s Proposal Requirements | 4 |
| 6.0 Travel | 4 |
| 7.0 Contractor’s Key Personnel | 4 |
| 8.0 Security Requirements | 4 |
| 9.0 Government Furnished Materials | 4 |
| 10.0 Questions | 4 |
Project Title
Rio Grande National Forest Bunkhouse Asbestos Sampling
General Information
1.0 Background and Purpose
The Rio Grande National Forest utilizes multiple barracks and bunkhouses for housing seasonal employees and in the performance of our mission. These buildings were often built using dangerous Asbestos-Containing Materials, and the Forest Service would like to identify any ACMs present in these buildings and the locations of these materials. Additionally, a mitigation strategy for each ACMs is needed. Mitigation is NOT included in this requirement; the Contractor is only required to find suspected ACMs, testing each sample, providing reports of the testing results, and provide a common recommended mitigation strategy for each instance of ACMs found and tested positive for. For example: removal, abatement, enclosure, regular monitoring, etc..
The goals of this requirement are as follows:
For each of the eight (8) buildings listed in this requirement:
· Identification and sampling of ACMs within each building
· Provide a diagram showing locations of each instance of ACMs for each building
· Provide a recommended mitigation strategy for each instance of ACMs found
· Provide a report(s) on ACMs tested in each building
The buildings to be tested have the following characteristics:
| Year Built |
| Name |
| Square Footage |
| Notes |
| 1986 |
| East Bench Barracks |
| 2298 |
| Tile Flooring Abated and replaced |
| 1930 |
| South Fork Cabin |
| 443 |
| 1957 |
| La Jara Dwelling |
| 1598 |
| 1939 |
| Saguache Bunkhouse |
| 1428 |
| 1939 |
| Saguache Office |
| 2646 |
| Top Floor Tile Abated |
| 1958 |
| Creede Ranger House |
| 1795 |
| 1932 |
| River Springs Ranger House |
| 3063 |
| 1900 |
| River Springs Ranger Office |
| 840 |
2.0 Definitions
ACMs – Asbestos-Containing Materials – Any materials containing more than 1% asbestos.
Contractor Requirements
3.0 Technical Requirements / Tasks
Technical Requirements:
· The Contractor shall be certified to inspect for ACMs according to all Federal and State regulations governing this type of work.
· Contractor shall use a reputable laboratory accredited to test for ACMs using industry standard methodologies.
· The Contractor shall provide the certifications of the individual(s) who will be responsible for identifying and collecting potential sources or ACMs.
· The Contractor shall create and provide a report(s) containing all information that is required by the laws and regulations governing this type of work to the Contracting Officer and to any other agency as required by law.
· The Contractor shall follow all Federal and State safety regulations when disturbing and testing suspected ACMs.
Tasks:
· Inspect and Test eight (8) U.S. Forest Service buildings for ACMs
· Create footprint diagrams showing the location of sampled areas within each building
· Provide a report containing all pertinent information as required by law for each instance of suspected ACMs, and a mitigation strategy for each instance of ACMs.
4.0 Deliverable / Schedule
Key Deliverables
| Item No. |
| Deliverable |
| Objective |
| Due |
| 1 |
| Reports on Asbestos-Containing Materials |
| Report containing all pertinent information on ACMs, including diagrams detailing locations of ACMs and mitigation strategies for each instance of ACMs |
| No later than 30 days after inspections are concluded |
5.0 Contractor’s Proposal Requirements
If your organization has the capacity to perform these services, proposals to complete this requirement shall contain:
· Organization name, address, email address, telephone number
· Proposed cost to the Government to complete this requirement
· List of projects completed in the last three (3) years that with the following information:
· Description of scope and magnitude that demonstrate similarities with this proposal
· Contact information for the customer
· Project price magnitude
· List of key personnel and years of technical experience and relevant certifications
· Name, Address, and Contact Information for Laboratory to be used for testing requirements
The Government will evaluate proposals as described in the attached Evaluation sheet.
There are 3 Evaluation Factors:
· Cost
· Past Performance
· Experience of Key Personnel
6.0 Travel
Project sites are shown on the included map along with a total travel time and local towns and cities.
7.0 Contractor’s Key Personnel
Contractor shall provide a project lead to ensure efficient workflow and completion of all the goals.
Contractor shall provide all necessary personnel to complete the project.
8.0 Security Requirements
Some buildings are protected by a security code or key. Entrances will be coordinated with the Contracting Officer’s Representative.
9.0 Government Furnished Materials
Not applicable
10.0 Questions
Questions related to this request shall be submitted to the Contracting Officer. Questions and answers will be posted in an amended solicitation on SAM.GOV