Attachment_1_Spray_Foam_SOW.pdf

PDF 142 KB Posted

Attached to
Spray Foam Installation Federal contract opportunity
Solicitation number
140A2323Q0673
Issued by
Department of the Interior Bureau of Indian Affairs Bureau of Indian Education

About this file

This statement of work outlines requirements for spray foam installation at a Bureau of Indian Affairs facility. The project scope involves applying 2 inches of polyurethane spray foam to the ceiling and walls of a 12' x 32' x 108' warehouse building to provide insulation. The contractor must supply all necessary equipment, labor, tools, transportation, supervision and incidentals for the installation. The spray foam must be applied according to manufacturer recommendations and local building codes. The period of performance is 30 days from award, with work to be performed Monday through Friday from 8am to 4pm and coordinated with the contracting officer's representative. Material submittals may be provided to the COR for approval. The facility is a drug and tobacco free campus, and contractors must hold current industry accreditation for high pressure spray polyurethane foam insulation.

View the file

Other files for this federal contract opportunity

Other files attached to Spray Foam Installation, newest first.
File Type Posted
Sol_140A2323Q0673_Amd_0001.pdf PDF
140A2323Q0673_Questions_and_Answers_0001.pdf PDF
Attachment_3_Wage_Determination_OK20230070.pdf PDF
Sol_140A2323Q0673.pdf PDF
Attachment_2_Map.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statement of Work Spray Foam Installa�on

August 2023

I. Purpose:

The warehouse building is not insulated causing unsafe and inefficient protec�on of stored items. This requirement is to provide protec�on against weather elements.

II. Scope of Work:

A. Provide all equipment, labor, tools, equipment, transporta�on supervision and incidentals necessary to install new polyurethane spray foam in accordance with local, state and federal building codes.

B. Spray ceiling and all four walls with a polyurethane spray foam.

C. Building is 12’ (H) x 32’ (W) x 108’ (L). Ceiling is 13’ (H) x 32’ (L) from the center of the building.

D. Spray foam shall be applied in a seamless and fully adhered fashion and according to manufacturer’s recommenda�ons.

E. Apply 2” foam thickness.

F. Provide protec�on to flooring and windows during installa�on.

G. Prepare ceiling and walls to insure a good adhesion of the spray foam.

H. Clean up and trash and debris generated from work.

III. Period of Performance/Schedule:

A. 30 days from award date B. Work to be performed Monday-Friday 8a-4pm. Coordinate schedule with COR.

IV. General Informa�on:

A. Material submitals may be sent o COR for approval.

B. Riverside Indian School is a drug and tobacco free campus.

C. A current industry recognized professional accredita�on or cer�fica�on for high pressure spray polyurethane foam insula�on is required.