Attachment 1 Specs_SMVGHeliwell.pdf
PDF 1 MB Posted
- Attached to
- SMVG Heliwell Replacement, Humboldt-Toiyabe NF
- Solicitation number
- 1240LT22Q0101
- Issued by
-
Department of Agriculture Forest Service
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 1240LT22Q0101.pdf | ||
| Attachment 2 Wage Determination.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Section C - Description/Specifications/Statement of Work
GENERAL SPECIFICATIONS
SMVG Heliwell
1.1 SCOPE OF CONTRACT
This project includes removal of necessary equipment and materials, retrofitting new well equipment to existing system at Spring Mountain National Recreation Area, Las Vegas, Nevada. The work includes removing and disposing of old well equipment (pump, motor, pipe, wiring, etc.), retrofitting new well equipment to existing system, connecting to power and control switch, testing proper operation of well house and pipeline to heliwell.
Remove and dispose of existing old well equipment that is not compatible with retrofit.
Install following equipment – 6” 220-250 gpm 13 stage Submersible Pump End;
6” 40 hp 460-480V 3PH Submersible Motor;
3” Galvanized Drop Pipe (462 LF);
3” Check Valves (4 EACH);
#4 Wire, 3 Conductor w/ Ground Sub Cable (500 LF);
Splice Kit #4;
Variable Frequency Drive 460V 40 HP minimum rated, NEMA 3R or IP66(Sine wave filtering shall be provided interior to the VFD or as a separate item fully rated for VFD output.);
Surge Protection Device: SCCR 20kA minimum,-480Y/277V, not to exceed 1200v for line to neutral and line to ground, and 2000V line to line. Ea;
Pressure Transducer 0-145psi 4-20 mA¼ NPT;
Pipe Wrap Tape;
Miscellaneous Small Parts.
Test proper flow through piping to Heliwell.
Provide well report that describes the system in detail. The report shall also document that the system pumps water to the Heliwell location.
Trouble-shoot any minor issues with Heliwell system.
Train Forest Service staff on maintenance, operation and winterization of Heli-Well system.
Attachment #1-1240LT22Q0101
1.2 PROJECT LOCATION
A. The project is located in the Spring Mountain National Recreation Area of the Humboldt- Toiyabe National Forest, Clark County, Nevada, in Section 21, T19S, R57E. It is located approximately 20 miles north-west of Las Vegas, Nevada. The project may be accessed from State Highway 157.
1.3 SITE INFORMATION AND LIMITATIONS
A. The following site conditions are considered incidental to the contract and the contractor will not be paid directly for any of the following items:
1. Construction sites will be closed to the public during construction. The Contractor will be responsible for signing and limiting public access.
2. All construction equipment shall be pressure washed before entering National Forest System lands. The removal of mud and debris from treads, tracks and undercarriage, with emphasis on axles, frame, cross-members, motor mounts, and underneath steps, running boards, and front bumper/brushguard assemblies will be required. The purpose is to reduce or eliminate the transportation of noxious weeds, which is required by Federal and State regulations.
3. Utilities are not available at the site for construction purposes. The Contractor will be responsible for coordinating the installation of temporary power for the site and the cost for the service.
4. The Contractor shall provide temporary toilet facilities (porta-potty) at the site during all construction work.
1.4 TRAFFIC CONTROL AND CONSTRUCTION SIGNING
A. No work that endangers, interferes, or conflicts with traffic or access to work sites shall be performed until a plan for satisfactory warning and handling of traffic has been submitted by the contractor and approved by the COR and Nevada Department of Transportation. Construction signing for traffic control shall conform to the Manual of Uniform Traffic Control Devices (MUTCD). All traffic control signs will be placed in areas adequate for a truck pulling a fifth wheel trailer to be turned around. Contractor shall not be paid directly for this item, rather it will be considered incidental to other items of work listed in the Schedule of Items.
1.5 WORK CAMPS, STAGING AND STORAGE AREAS
A. Areas for staging operations and storage of materials shall be approved by the CO. The Contractor must request in writing for approval from the CO to stage trailers (work) on site.
B. No overnight camping will be allowed on site.
1.6 INSPECTION OF WORKSITE
A. The contractor acknowledges they have taken the necessary steps to ascertain the nature and location of work, and have investigated and satisfied themselves as to the general and local conditions that can affect the work or its cost. Any failure of the contractor to take the actions described and acknowledged in this paragraph will not relieve the Contractor from the responsibility of estimating properly the difficulty and cost of successfully performing the work, or for proceeding to successfully perform the work without additional expenses to the government.
1.7 SPECIFICATIONS
A. The following specifications are attached. Some sections in the schedule of items refer to other sections not listed and are subsidiary to, or are included in payment for other pay items in this contract. These items are considered incidental and no additional compensation will be made.
Attached Specifications Section 011250 – Measurement and Payment
Section 011900 - Mobilization Section 013300 – Submittal Procedures Section 014100 – Quality Control Section 221103 – Plumbing Appurtenances Section 221104 – Equipment Labeling for Water and Wastewater systems Section 221120 – Submersible Well Pumps Section 260500 – Common Work Results for Electrical Section 260519 – Low-Voltage Electrical Power Conductors and Cables Section 260526 – Grounding and Bonding for Electrical Systems Section 260533 – Raceways and Boxes for Electrical Systems Section 260553 – Identification for Electrical Systems
Section 262726 – Wiring Devices Section 264313 – Surge Protection for Low-Voltage Electrical Power Circuits
SECTION 011250 - MEASUREMENT AND PAYMENT
PART 2 - GENERAL
2.1 SUMMARY
A. Measurement and payment for contract work will be made only for and under those pay items included in the Schedule of Items. All other work, labor, materials, equipment, and incidentals necessary to successfully complete the project will be considered as included in the payment for items shown. This section defines the method of measurements and basis of payment for work items listed in the Schedule of Items.
B. When more than one class, size, type, thickness, etc. is specified in the Schedule of Items for any pay item, suffixes will be added to the item number to differentiate between the pay items.
2.2 DETERMINATION OF QUANTITIES
A. The following measurements and calculations shall be used to determine contract quantities for payment.
1. For individual construction items, longitudinal and lateral measurements for area computations shall be made horizontally or corrected to horizontal measurement unless otherwise specified. Measurements for geotextiles, netting and erosion control blankets shall be along slope lines.
2. For excavation or embankment volumes, the average end area method shall be used to compute volumes. However, if in the judgment of the Contracting Officer (CO), the average end area method is impractical, measurement shall be made by volume in hauling vehicles or by other three-dimensional methods.
3. For Structures, they shall be measured according to neat lines shown on the drawings or as altered by the CO, in writing, to fit field conditions.
4. For items that are measured by the linear foot, such as pipe culverts, fencing, guardrail, piping, utilities, and underdrains, measurements shall be made parallel to the base or foundation upon which the structures are placed.
5. For aggregates weighed for payment, the tonnage shall not be adjusted for moisture content, unless otherwise provided for.
6. For standard manufactured items (such as fence, wire, plates, rolled shapes, pipe conduits) identified by gauge, weight, section dimensions, and so forth, such identifications shall be considered the nominal weights or dimensions. Unless controlled by tolerances in cited specifications, manufacturer's tolerances shall be accepted.
B. Earthwork Tolerances - Adjustments of horizontal or vertical alignment, within the tolerances specified in this contract, or shifts of balance points up to 100 feet shall be made by the contractor as necessary to produce the designed sections and to balance earthwork. Such adjustments shall not be considered as "Changes."
2.3 UNITS OF MEASUREMENT
A. Payment shall be by units defined and determined according to U.S. Standard measure and by the following:
1. Acre: Make longitudinal and transverse measurements for area computations horizontally.
2. 50lb Bag: Measurement will be for the actual number of 50lb bags of standard bentonite grout.
3. 94lb Bag: Measurement will be for the actual number of 94lb bags of standard cement or grout.
4. Cubic Yard (CY): A measurement computed by one of the following methods:
a. Excavation, Embankment, or Borrow. The measurement computed by the average end area method from measurements made longitudinally along a centerline or reference line.
b. Material in Place or Stockpile. The measurement computed using the dimensions of the in-place material.
c. Material in the Delivery Vehicle. The measurement computed using measurements of material in the hauling vehicles at the point of delivery.
Vehicles shall be loaded to at least their water level capacity. Leveling of the loads may be required when vehicles arrive at the delivery point.
5. Each (EA): One complete unit, which may consist of one or more parts.
6. Gallons (GAL): The quantity shall be measured by any of the following methods:
a. Measured volume in container.
b. Metered volume by approved metering system.
c. Commercially package volume.
7. Hour (HR): Measurement will be for the actual number of hours (or fraction thereof) ordered by the Contracting Officer and performed by the contractor.
8. Linear Foot (LF): Measurement of work along its length from point-to-point;
parallel to the base or foundation. Do not measure overlaps.
9. Lump Sum (LS): One complete unit.
10. Mile: Measured horizontally along the centerline of each roadway, approach, or ramp.
11. Pound (LB): For sacked or packaged material, measurement will be the net weight as packed by the manufacturer.
12. Square Foot (SF): Measured on a plane parallel to the surface being measured.
13. Square Yard (SY): Measured on a plane parallel to the surface being measured.
14. Ton: Measured as a short ton consisting of 2,000 pounds.
2.4 METHOD OF MEASUREMENT
A. One of the following methods of measurement for determining final payment is designated on the Schedule of Items for each pay item:
1. ACTUAL QUANTITIES (AQ) - These quantities are determined from actual measurements of completed work.
2. DESIGNED QUANTITIES (DQ) - These quantities denote the final number or units to be paid for under the terms of the contract. They are based upon the original design data available prior to advertising the project. Original design data include the preliminary survey information, design assumptions, calculations, drawings, and the presentation in the contract. Changes in the number of units shown in the Schedule of Items may be authorized under any of the following conditions:
a. As a result of changes in the work authorized by the CO.
b. As a result of the CO determining that errors exist in the original design that cause a pay item quantity to change by 15 percent or more.
c. As a result of the Contractor submitting to the CO a written request showing evidence of errors in the original design that cause a pay item quantity to change by 15 percent or more. The evidence must be verifiable and consist of calculations, drawings, or other data that show how the designed quantity is believed to be in error.
3. LUMP SUM QUANTITIES (LSQ) - These quantities denote one complete unit of work as required by or described in the contract, including necessary materials, equipment, and labor to complete the job. They shall not be measured.
4. STAKED QUANTITIES (SQ) - These quantities are determined from staked measurements prior to construction.
5. VEHICLE QUANTITIES (VQ) - These quantities are measured or weighed in hauling vehicles.
PART 3 - PRODUCTS (NOT APPLICABLE)
PART 4 - EXECUTION (NOT APPLICABLE)
END OF SECTION 011250
SECTION 011900 - MOBILIZATION
PART 5 - GENERAL
5.1 SUMMARY
A. This item is intended to compensate the Contractor for operations including, but not limited to, those necessary for the movement of personnel, equipment, supplies, and incidentals to the project site; for payment of premiums for bonds and insurance for the project; and for any other work and operations which must be performed or costs that must be incurred incident to the initiation of meaningful work at the site and for which payment is not otherwise provided for under the contract.
5.2 MEASUREMENT AND PAYMENT
A. The measurement and payment shall be included in base bid item.
1. Bond premiums will be reimbursed after receipt of the evidence of payment.
2. 50% of the lump sum, not to exceed 5% of the original contract amount, will be paid following completion of 5% of the original contract amount not including mobilization and bond premiums.
3. Payment of the remaining portion of the lump sum, up to 10% of the original contract amount, will be paid following completion of 10% of the original contract amount not including mobilization and bond premiums.
4. Any portion of the lump sum in excess of 10% of the original contract amount will be paid after final acceptance.
5. Progress payments for mobilization and preparatory work shall be subject to retainage.
PART 6 - PRODUCTS (NOT USED)
PART 7 - EXECUTION (NOT USED)
END OF SECTION 011900
SECTION 013300 - SUBMITTAL PROCEDURES
PART 8 - GENERAL
8.1 SUMMARY
A. This Section includes administrative and procedural requirements for submitting Shop Drawings, Product Data, Samples, and other miscellaneous submittals. See Table 013300-1 for a summary of required submittals.
B. See other specification section within this package for additional requirements on submittal.
8.2 SUBMITTAL PROCEDURES
A. Coordination: Coordinate preparation and processing of submittals with performance of construction activities.
1. Coordinate transmittal of different types of submittals for related parts of the Work so processing will not be delayed because of need to review submittals concurrently for coordination.
a. The Contracting Officer (CO) reserves the right to withhold action on a submittal requiring coordination with other submittals until related submittals are received.
B. Processing Time: Allow enough time for submittal review, including time for re-submittals, as follows. Time for review shall commence on CO's receipt of submittal.
1. Initial Review: Allow 14 days for initial review of each submittal. Allow additional time if processing must be delayed to permit coordination with subsequent submittals. CO will advise Contractor when a submittal being processed must be delayed for coordination.
2. If intermediate submittal is necessary, process it in same manner as initial submittal.
3. Allow 14 days for processing each re-submittal.
4. No extension of the Contract Time will be authorized because of failure to transmit submittals enough in advance of the Work to permit processing.
C. Identification: Place a permanent label or title block on each submittal for identification.
1. Indicate name of firm or entity that prepared each submittal on label or title block.
2. Provide a space on label or beside title block to record Contractor's review and approval markings and action taken by CO.
3. Include the following information on label for processing and recording action taken:
a. Project name.
b. Date.
c. Name and address of Contractor.
d. Name of manufacturer.
e. Unique identifier, including revision number.
f. Number and title of appropriate Specification Section.
g. Drawing number and detail references, as appropriate.
h. If more than one item is shown on submittal sheet, identify item.
D. Deviations: Highlight, encircle, or otherwise identify deviations from the Contract Documents on submittals.
E. Additional Copies: Unless additional copies are required for final submittal, and unless CO observes noncompliance with provisions of the Contract Documents, initial submittal may serve as final submittal.
F. Use for Construction: Use only final submittals with mark indicating action taken by CO in connection with construction.
8.3 MEASUREMENT AND PAYMENT
A. No separate measurement and/or payment will be made for this section. Payment shall be included with work shown in the schedule of items.
PART 9 - PRODUCTS
9.1 ACTION SUBMITTALS – (Submittals requiring CO approval)
A. General: Prepare and submit Action Submittals required by individual Specification Sections.
1. Number of Copies: Submit one copy of each submittal, unless otherwise indicated.
B. Product Data: Collect information into a single submittal for each element of construction and type of product or equipment.
1. If information must be specially prepared for submittal because standard printed data are not suitable for use, submit as Shop Drawings, not as Product Data.
2. Mark each copy of each submittal to show which products and options are applicable.
3. Include the following information, as applicable:
a. Manufacturer's written recommendations.
b. Manufacturer's product specifications.
c. Manufacturer's installation instructions.
d. Manufacturer's catalog cuts.
e. Wiring diagrams showing factory-installed wiring.
f. Compliance with recognized trade association standards.
g. Compliance with recognized testing agency standards.
C. Shop Drawings: Prepare Project-specific information, drawn accurately to scale. Do not base Shop Drawings on reproductions of the Contract Documents or standard printed data.
1. Preparation: Include the following information, as applicable:
a. Dimensions.
b. Identification of products.
c. Fabrication and installation drawings.
d. Roughing-in and setting diagrams.
e. Wiring diagrams showing field-installed wiring, including power, signal, and control wiring.
f. Notation of dimensions established by field measurement.
2. Wiring Diagrams: Differentiate between manufacturer-installed and field-installed wiring.
D. Contractor's Construction Schedule: The contractor shall submit a Construction Schedule, for approval by CO, in accordance with the contract provisions within 5 day of commencement of work.
9.2 INFORMATIONAL SUBMITTALS – (Submittals NOT requiring CO approval)
A. General: Prepare and submit Informational Submittals required by other Specification Sections.
1. Number of Copies: Submit one copies of each submittal, unless otherwise indicated. CO will not return copies.
2. Certificates and Certifications: Certificates and certifications shall be signed by an officer or other individual authorized to sign documents on behalf of that entity.
3. Test and Inspection Reports: Comply with requirements in Section 014100 "Quality Control."
B. Material Test Reports: Prepare reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting test results of material for compliance with requirements.
C. Field Test Reports: Prepare reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting results of field tests performed either during installation of product or after product is installed in its final location, for compliance with requirements.
D. Maintenance Data: Prepare written and graphic instructions and procedures for operation and normal maintenance of products and equipment.
E. Manufacturer's Instructions: Prepare written or published information that documents manufacturer's recommendations, guidelines, and procedures for installing or operating a product or equipment. Include name of product and name, address, and telephone number of manufacturer.
PART 10 - EXECUTION
10.1 GENERAL
A. Review each submittal and check for compliance with the Contract Documents. Note corrections and field dimensions. Mark with approval stamp before submitting to CO.
B. Approval Stamp: Stamp each submittal with a uniform, approval stamp. Include Project name and location, submittal number, Specification Section title and number, name of reviewer, date of Contractor's approval, and statement certifying that submittal has been reviewed, checked, and approved for compliance with the Contract Documents.
C. CO will not review submittals that do not bear Contractor's approval stamp and will return them without action.
D. Submittals not required by the Contract Documents will not be reviewed and may be discarded.
E. Substitutions – Whenever materials, products, and equipment are listed by name or brand in the specifications and/or on the drawings, it is used as a measure of quality, utility, or standard. If the Contractor prefers to use any other brand or manufacturer of same quality, appearance and utility to that specified, he shall request substitution as provided below, not less than 30 days before the planned installation of the item. The Contracting Officer will approve or disapprove the request for substitution.
F. Requests for substitutions will only be considered if contractor submits the following:
1. Complete technical data including drawings, complete performance specifications, test data, samples and performance tests of the article proposed for substitution.
Submit additional information if required by Contracting Officer. All items in the above information shall be circled, tagged, or marked in some way to indicate all deviations or differences which the proposed item differs from the originally specified item.
2. Similar data as above for item originally specified. All items shall be marked to identify where/how the proposed substitution will differ.
3. A statement by the Contractor that the proposed substitution is in full compliance with the contract documents, applicable codes, and laws.
4. The Contractor shall be responsible for any effect upon related work in the project for any substitution and shall pay any additional costs generated by any substitutions.
10.2 SUBMITTAL SCHEDULE – Submittals shall be made as required by and called for in the drawings and specifications. The following table is a summary of the required submittals for the project - the table is to assist the Contractor and may not be all inclusive
– additional submittals may be required by specific specifications:
TABLE 013000-1
Spec.
Section Section Title Subse ction Required Submittal
013300 Submittal Procedures 8.1 Construction Schedule 014100 Quality Control 11.1 Permits, Licenses, and Certificates 014100 Quality Control 11.1 Test and inspection reports 014100 Quality Control 11.1 As-Built drawings 221103 Plumbing Appurtenances 13.1 Product Data 221103 Plumbing Appurtenances 13.1 Operation and Maintenance Data 221120 Submersible Well Pumps 19.1 Product Data – pump and motor 221120
Submersible Well Pumps
19.1 Provide well report that describes
the system in detail. The report shall also document that the system pump water to the heliwell location.
260500 Common Work Results for Electrical 22.1 Product Data
260500 Common Work Results for Electrical
22,1 Electrical Line Diagram of Proposed System from Power
Meter to Pump 260519 Low-Voltage Electrical Power
Conductors and Cables
24.4 Product Data
260526 Grounding and Bonding for Electrical Systems
24.16 Product Data
260533 Raceway and Boxes for Electrical Systems
24.17 Product Data
260553 Identification for Electrical Systems 24.36 Product Data 262726 Wiring Devices 24.48 Product Data 264313 Surge Protection for Low-
Voltage Electrical Power Circuits
25.1 Product Data
SECTION 014100 – QUALITY CONTROL
PART 11 - GENERAL
11.1 This work shall consist of providing quality control in conformance with the inspection, testing, and product certification requirements of this contract to ensure compliance with the drawings and specifications. The Contractor shall provide all personnel, equipment, tests, and reports necessary to meet the requirements of the contract.
11.2 QUALITY CONTROL
A. The Contractor shall provide and maintain a quality control system that will ensure all services, supplies, and construction work required under this contract conforms to the contract requirements. The Contractor shall perform, or cause to be performed, the sampling, inspection, and testing required to substantiate that all services, supplies, and construction conform to the contract requirements.
B. Special Tests and Inspections: Contractor will engage a testing agency to conduct required special tests and inspections. The Contractor shall authorize the testing agency to perform the required testing and inspections on the work completed. The authority shall include:
1. Testing agency will interpret tests and inspections and state in each report whether tested and inspected work complies with or deviates from the Contract Documents.
2. Testing agency will re-test and re-inspect corrected work.
C. Retesting/Reinspecting: Contractor shall provide quality-control services for retesting and reinspection for replaced construction work or for work that failed to comply with the requirements under the contract.
11.3 SUBMITTALS
A. Permits, Licenses, and Certificates
B. Test and Inspection Reports
C. As-Built Drawings
11.4 MEASUREMENT AND PAYMENT
A. No separate payment will be made for the work included under this section; rather payment shall be considered to be included in the items of work listed in the Schedule of Items.
PART 12 - EXECUTION
12.1 QUALITY CONTROL SYSTEM
A. General: Perform required testing, inspections, sampling, and similar services per direction specified in the contract drawings and specifications and in accordance with established industry standards.
12.2 TEST AND INSPECTION REPORTS
A. Submit one copy of complete test results no later than three calendar days after the test was performed.
B. Submit failing test results and proposed remedial actions within four hours of noted deficiency.
C. Testing and Inspection Reports shall include the following:
1. Date of issue.
2. Project title and number.
3. Name, address, and telephone number of testing agency.
4. Dates and locations of samples, tests, or inspections.
5. Names of individuals performing tests and inspections.
6. Reference Specification Section(s).
7. Complete test or inspection data.
8. Test and inspection results and an interpretation of test results.
9. Ambient conditions at time sample was taken, tested, or inspected.
10. Comments or professional opinion on whether tested or inspected work complies with the Contract Document requirements.
11. Name and signature of laboratory inspector.
12. Recommendations on retesting and reinspecting.
12.3 PERMITS, LICENSES, AND CERTIFICATES
A. For Contracting Officer’s records, submit copies of permits, licenses, certifications, inspection reports, releases, jurisdictional settlements, notices, receipts for fee payments, judgments, correspondence, records, and similar documents, established for compliance with standards and regulations relevant to the on performance of the work.
12.4 AS-BUILT DRAWINGS
A. The Contractor shall maintain a set of the contract drawings depicting as-built conditions.
These drawings shall be maintained in a current condition and shall be available for review. All variations from the original contract drawings shall be indicated in red on the drawings. Upon completion of the contract work, as-built drawings shall be submitted to the Contracting Officer.
12.5 SAMPLING, TESTING, AND CERTIFICATION REQUIREMENTS
A. Sampling, testing, and Certification requirements and frequency for specific items shall be as specified in the drawings and specification. The following table is a summary of the required sampling, testing, and certification for the project - the table is to assist the Contractor, but may not be all inclusive – additional submittals may be required by specific specification section:
B.
TABLE 014100-1
Item
Subsection Certification or Test Required
Frequency
221120 3.6A Mechanical and Electrical Testing (Pump System)
See Spec.
260500 1.5C Electrical Testing See Spec.
END OF SECTION 014100
SECTION 221103 - PLUMBING APPURTENANCES
PART 13 - GENERAL
13.1 SUMMARY
A. This section includes piping, fittings, valves, gauges, backflow preventers, hypochlorinators and other plumbing devices within utility buildings, utility boxes or at other designated locations.
B. Related sections include the following:
1. Section 133400 “Precast Concrete Utility Building.”
2. Section 133402 “Utility Box.”
3. Section 221104 “Equipment Labeling for Water and Wastewater Systems.”
4. Section 260500 “Common Work Results for Electrical.”
13.2 SUBMITTALS
A. Product Data: For the following:
1. Air and vacuum valves.
2. Pressure regulating valves.
3. Backflow preventers and assemblies.
B. Operation and Maintenance Data: To be used in emergency, operation, and maintenance manuals. Include the data for the following:
1. Air and vacuum valves.
2. Pressure regulating valves.
3. Backflow preventers.
13.3 MINIMUM SYSTEM REQUIREMENTS
A. Unless otherwise noted, the minimum working pressure for piping and specialty valves and devices shall be 200 psig.
13.4 QUALITY ASSURANCE
A. NSF Compliance:
1. All products in contact with potable water shall comply with NSF 61 Annex G. All pipes, fittings, fixtures, solder and flux shall meet the 0.25% maximum lead content rules for all wetted components.
13.5 MEASUREMENT AND PAYMENT
A. There will be no separate measurement or payment for work in this Section. Plumbing Appurtenances is considered incidental to other items of work shown in the Schedule of Items.
PART 14 - PRODUCTS
14.1 GENERAL
A. All plumbing appurtenances shall be new and unused, of the type, pressure rating or class, and size specified and as show on the Drawings.
14.2 BALL VALVE
A. Description: Bronze, 400 psi, threaded NPT end connections.
B. Model: LFB6000 Lead Free Ball Valve as manufactured by Watts Regulator, or an approved equal.
14.3 GLOBE VALVE
A. Description: Threaded, 150 psi, union bonnet, renewable composition disc with integral seat, with bronze body.
B. Model: Powell Class 150 as manufactured by Wm. Powell Company, or No. 7, as manufactured by the Crane Company, Chicago, or an approved equal.
14.4 GATE VALVE
A. Description: Bronze, solid wedge disc, 150 psi, non-rising stem, threaded ends, with screwed in bonnet.
B. Model: Powell Gate Valve Class 150, as manufactured by Powell Company or No. 437, as manufactured by the Crane Company, or an approved equal.
14.5 CHECK VALVE
A. Description: Bronze, AWWA C508, swing-check type with 125-psig working-pressure rating, threaded ends, screwed-in cap, renewable brass disc and resilient seat. Include interior coating according to AWWA C550 and ends to match piping.
B. Model: Figure No. 578 as manufactured by Powell Company, or an approved equal.
14.6 UNION
A. Description: Female type, malleable iron, 150 pound, with ground brass to iron seat.
B. Model: Manufactured by Crane Company, or an approved equal.
14.7 PRESSURE GAUGE
A. Description: 2-inch diameter or larger, 0 to 200 psi range, with brass movement, steel case and bottom mounting with NPS 0.25 threads. Include 1/4” ball valve for gauge isolation.
B. Model: Ashcroft Model 1000 or 1005 as manufactured by Dresser Industries, or an approved equal
14.8 PIPE AND FITTINGS
A. Galvanized Steel: ASTM A53, Schedule 40, threaded ends meeting ASME B1.20.1.
1. Fittings: Threaded, ASTM A 338.
PART 15 - EXECUTION
15.1 INSTALLATION
A. Install piping, fittings, valves, gauges, hypochlorinators and other plumbing devices within utility buildings, utility boxes or at other locations according to the manufacturer’s written instructions and as indicated on the Drawings. Install so water can be drained from each appurtenance for winterization of the system.
END OF SECTION 221103
SECTION 221104 – EQUIPMENT LABELING FOR WATER AND
WASTEWATER SYSTEMS
PART 16 - GENERAL
16.1 SUMMARY
A. This Section includes the following:
1. Warning Labels and Signs
2. Equipment identification labels.
16.2 QUALITY ASSURANCE
A. Comply with 29 CFR 1910.145.
16.3 COORDINATION
A. Coordinate identification names, abbreviations, colors, and other features with requirements in the Contract Documents, Shop Drawings, manufacturer's wiring diagrams, and the Operation and Maintenance Manual, and with those required by codes, standards, and 29 CFR 1910.145. Use consistent designations throughout Project.
B. Coordinate installation of identifying devices with completion of covering and painting of surfaces where devices are to be applied.
16.4 MEASUREMENT AND PAYMENT
A. No separate measurement or payment will be made for work specified in this section. All work will be included in other items listed in the Schedule of Items.
PART 17 - PRODUCTS
17.1 WARNING LABELS AND SIGNS
A. Comply with NFPA 70 and 29 CFR 1910.145.
B. Self-Adhesive Warning Labels: Factory printed, multicolor, pressure-sensitive adhesive labels, configured for display on front cover, door, or other access to equipment, unless otherwise indicated.
C. Warning label and sign shall include, but are not limited to, the following legends:
1. Multiple Power Source Warning: "DANGER - ELECTRICAL SHOCK HAZARD
- EQUIPMENT HAS MULTIPLE POWER SOURCES."
2. Workspace Clearance Warning: "WARNING - OSHA REGULATION - AREA
IN FRONT OF ELECTRICAL EQUIPMENT MUST BE KEPT CLEAR FOR 36
INCHES (915 MM)."
3. Flash Protection Warning: Minimum of “WARNING – ARC FLASH HAZARD.”
4. DC Voltage Warning: As shown on drawings.
17.2 EQUIPMENT IDENTIFICATION LABELS
A. Self-Adhesive, Engraved, Laminated Acrylic or Melamine Label: Adhesive backed, with white letters on a dark-gray background. Minimum letter height shall be 3/8 inch.
PART 18 - EXECUTION
18.1 APPLICATION
A. Warning Labels for Indoor Cabinets, Boxes, and Enclosures for Power and Lighting:
Comply with 29 CFR 1910.145 and apply self-adhesive warning labels or baked-enamel warning signs. Identify system voltage with black letters on an orange background.
Apply to exterior of door, cover, or other access.
1. Equipment with Multiple Power or Control Sources: Apply to cover of equipment:
a. Pressure switch.
2. Equipment Requiring Workspace Clearance According to NFPA 70: Unless otherwise indicated, apply to door or cover of equipment:
a. Battery bank enclosure.
b. Safety switches.
3. DC Voltage Warning: Apply next to or on cover of equipment:
a. Safety switch.
b. Solar array.
B. Equipment Identification Labels: On each unit of equipment, install unique designation label that is consistent with schematics, Drawings, schedules, and Operation and Maintenance Manuals. Apply labels to sample taps, pressure gauges, water treatment equipment and other plumbing appurtenances and items as shown on the Drawings.
1. Labeling Instructions:
a. Indoor Equipment: Self-adhesive, engraved. Metal, laminated acrylic or melamine label. Unless otherwise indicated, provide a single line of text with 3/8-inch-high letters on 3/4-inch-high label; where 2 lines of text are required, use labels 1-1/4 inches high.
b. For equipment that lacks a flat surface to install the label, the following method is preferred:
1) Create label with a 1-inch long margin on left side of text.
2) Punch circular hole through center of margin.
3) Attach label to equipment using heavy duty zip-ties or metal wire through hole.
4) Final label should be easy to read, but not easily removed.
c. Label should not obstruct access to or reading of the equipment.
2. Equipment to Be Labeled:
a. Per industry standards
18.2 INSTALLATION
A. Verify identity of each item before installing identification products.
B. Location: Install identification materials and devices at locations for most convenient viewing without interference with operation and maintenance of equipment.
C. Self-Adhesive Identification Products: Clean surfaces before application, using materials and methods recommended by manufacturer of identification device.
D. Underground-Line Warning Tape: During backfilling of trenches install continuous underground-line warning tape directly above line at 6 to 8 inches (150 to 200 mm) below finished grade. Use multiple tapes where width of multiple lines installed in a common trench exceeds 16 inches (400 mm) overall.
END OF SECTION 221104
SECTION 221120 - SUBMERSIBLE WELL PUMPS
PART 19 - GENERAL
19.1 SUMMARY
A. This Section includes furnishing and installing a submersible well pump, motor, the discharge pipe, check valves, and other necessary equipment to make this system operable.
B. Related Sections include the following:
1. Section 260500 “Common Work Results for Electrical.”
19.2 SUBMITTALS
A. Product Data: Submit performance curves and rated capacities of selected well pumps and furnished specialties for each type and size of well pump indicated.
19.3 QUALITY ASSURANCE
A. All work is to be completed according to applicable Federal, State and Local codes. This work includes, but is not limited to, materials, installation, testing and disinfection.
B. Piping materials shall bear label, stamp, or other markings of specified testing agency.
C. NSF Compliance:
1. Comply with NSF 14 for plastic potable-water-service piping. Include marking "NSF-pw" on piping.
D. All products in contact with potable water shall comply with NSF 61 Annex G. All pipes, fittings, fixtures, solder and flux shall meet the 0.25% maximum lead content rules for all wetted components.
19.4 MINIMUM SYSTEM REQUIREMENTS
A. Unless otherwise noted, the minimum working pressure for piping and specialties shall be 160 psig.
19.5 MEASUREMENT AND PAYMENT
A. Well pump, well accessories and power cable shall be paid for in one lump sum item.
B. Submersible Well Pump: Lump Sum for Submersible Well Pump including furnishing and installing the well pump, motor, check valve, discharge pipe, operating and maintenance manuals and all incidentals necessary to complete this item.
C. Well Accessories: Well accessories payment is inclusive to base bid item. This item shall include furnishing and installing the pitless unit and sanitary well cap, including all connections to the well casing, drop pipe and supply line. This item shall also include 10 feet of waterline beyond the well casing.
D. Submersible power cable, underground control cable, conduit and trenching payment is inclusive to base bid item.
PART 20 - PRODUCTS
20.1 SUBMERSIBLE PUMP AND MOTOR
A. Pump
1. Capacity: 220-250 GPM
2. Rated Power: 40 HP
3. Rated Voltage: 460-480 V., 60 Hertz, 3 phase
4. Model: To be supplied by contractor and approved by COR
B. Motor: Capable of continuous operation under water, with protected submersible power cable.
C. Pump Bowls: Made of polycarbonate and free of blow holes, sand holes, and other detrimental defects. Capable of withstanding a hydrostatic pressure equal to twice the head at rated capacity or 1-1/2 times the shutoff head, whichever is greater. Each bowl equipped with replaceable stainless steel wear rings on both sides of the impeller.
D. Impellers: Closed type and statically balanced. Securely fastened to the impeller shaft with splines, keys, taper bushings, locknuts, or setscrews.
E. Pump-to-Motor Coupling: Solid stainless steel, Capable of transmitting the total torque and thrust of the unit in either direction.
20.2 DISCHARGE PIPE
A. Galvanized Steel: ASTM A53, Schedule 40, threaded ends meeting ASME B1.20.1.
1. Fittings: Threaded, ASTM A 338.
20.3 SANITARY WELL CAP
A. Design: Vented, sanitary well seal, with holes for piping, electrical cables and well level measuring tube. Cap shall fit on top of casing, be constructed of steel or aluminum, and shall be removable, waterproof and vermin proof. Sized to fit casing and electrical conduit, meeting the requirements of the "Minimum Standards for Well Construction" for the state in which the well exists and meeting the requirements of Water Systems Council PAS-97. Provide electrical cable seals.
B. Model: WTCC Series, as manufactured by Maass Midwest Manufacturing, Inc., or an approved equal.
20.4 PROTECTIVE WELLHEAD ENCLOSURE
A. Design: Steel with stainless steel lock pins, shielded locks, easy open lid, lift hook, quick release pins for base removal, base ring for concrete anchoring, shielded screened vents, powder coat painted interior and exterior.
B. Model: PWE1216E36 as manufactured by Baker Manufacturing Co, or an approved equal.
20.5 PITLESS UNIT
A. Design:
1. Material: Schedule 40 steel pipe.
2. End: Plain, prepared for welded connection to well casing.
3. Bury Depth: As designed by the contractor.
4. Height Above Finished Grade: 1.5 feet (18 inches)
5. Well Casing Size (Nominal): 8 inches
6. Drop Pipe Size (Nominal): As designed by the contractor.
7. Lateral Discharge: As designed by the contractor.
8. Must meet applicable requirements of the state of Nevada.
9. Accessories:
a. Airline Test Block.
B. Model: As designed by the contractor.
20.6 WELL WATER LEVEL TESTING EQUIPMENT
A. Tubing: NSF approved. Install one continuous section of heavy-duty 1/4-inch poly tubing, suitable for measuring the water level using air pressure, and suitable for installation in a potable water well. Purchase in roll long enough to avoid splices.
B. Well Water Depth Gauge
1. Design: Pressure range of 0 to 200 psi, with adjustable “zero” indicator that can be calibrated to the site. Gauge readings shall directly show current well depth (in feet).
2. Model: CA566 Air Valve, P/N 940238 as manufactured by Maass Midwest Manufacturing or an approved equal.
C. Schrader Valve
1. Design: 1/4-inch NPT Schrader valve.
2. Model: P/N 94009 as manufactured by Maass Midwest Manufacturing or an approved equal.
D. Air Pump
1. Description: Durable, sturdy, manually operated, Schrader-valve compatible floor pump, with steel barrel and base, integrated gauge and maximum working pressure of 160 psi.
2. Model: Joe Blow Sport Floor Pump, as manufactured by Topeak, Inc. or an approved equal.
E. Conduit: 2-inch diameter PVC electrical conduit.
F. Bleed-Off Valve and Other Necessary Appurtenances: According to Section 221103 “Plumbing Appurtenances.”
20.7 DISINFECTION CHEMICALS
A. All chemicals used to disinfect the well or equipment shall meet ANSI/NSF 60.
20.8 OPERATION AND MAINTENANCE MANUAL
A. The Contractor shall furnish three sets of instructions for operating and maintaining all mechanical and electrical equipment for the pump installation. The instructions shall include a complete diagram of the pump and plumbing details, an electrical wiring diagram with color coding indicated, parts lists, and all other drawings and instructions that are required to successfully operate the pump.
20.9 ELECTRICAL SUPPLY AND CONTROLS
A. The power cable and all fittings shall be watertight at the pressure encountered in use.
The cable shall be one continuous length and shall not contain any splices. The cable's jacket material must be oil- and water-resistant synthetic rubber, plastic, or other suitable protective material. The cable shall be of the size recommended by the manufacturer of the submersible pump and shall have a sufficient conductor area to meet the minimum requirement of the Insulated Power Cable Engineer's Association (IPCEA) code for operation in air.
PART 21 - EXECUTION
21.1 DISINFECTING EQUIPMENT
A. Before installing any equipment or other components in the well, the Contractor shall disinfect the equipment by flushing with a 200 PPM chlorine solution.
21.2 SUBMERSIBLE PUMP INSTALLATION
A. Install well pump at the depth indicated on the Drawings, according to HI 2.1-2.5.
Provide access for periodic maintenance.
1. Before lowering permanent pump into well, lower a dummy pump that is slightly longer and wider than permanent pump to determine that permanent pump can be installed. Correct alignment problems.
2. Before lowering permanent pump into well, start pump to verify correct rotation.
3. Securely tighten discharge piping joints.
4. Support pump from pitless unit.
21.3 PITLESS UNIT
A. Excavation and Backfill: According to Section 312000 “Earthwork.”
B. Welded Connection: Weld pitless unit to steel casing in accordance with AWWA C206, penetrate full thickness of pipe.
21.4 WELL WATER LEVEL TESTING EQUIPMENT
A. Install tubing in PVC electrical conduit between wellhead and pump house. Connect to airline test block with necessary fittings. Install tubing in manner that allows unobstructed airflow between well water level and pressure gauge. Pinched or kinked lines are not acceptable.
B. The installed airline and testing equipment shall be airtight, without blockage or obstructions, and capable of measuring the water depth in the well.
21.5 ELECTRICAL SUPPLY AND CONTROLS
A. Sufficient submarine cable shall be provided and installed as recommended, to connect the submersible pump to the control box. In the well, the cable shall be attached to the discharge pipe at intervals recommended by the manufacturer of the pump with non-corrosive metal bands. From the well head to the control box, the cable shall be installed in conduit of the size to handle the cable in conformance with the National Electrical Code.
B. Installation shall conform to Section 260500 “Common Work Results for Electrical.”
21.6 MECHANICAL AND ELECTRICAL TESTING
A. Testing and operation of all mechanical and electrical equipment shall be done by the Contractor, in the presence of the Contracting Officer, to assure satisfactory operation of all components. The pump shall be operated for at least 1 hour to demonstrate that all equipment is functioning as specified.
21.7 DISINFECTING WELLS
A. After the well is cleaned it shall be disinfected with a chlorine solution of such volume and strength so that a concentration of at least 100 ppm of chlorine, after mixing with the water in the well, shall be circulated to all parts of the well. The water in the well must be agitated to mix the solution thoroughly. In addition, surfaces of all components above the water level must be flushed or washed down with the sterilizing solution. The chlorine solution shall remain undisturbed in the well for a period of a least 12 hours, but not more than 24 hours.
B. Introduction of Chlorine Solution to the Well: The method of introducing the chlorine into the well shall be one of the following as recommended by the ANSI/AWWA C654 and approved by the Contracting Officer:
1. Calcium Hypochlorite - Dribble tablets of approximately 5-gram size down the casing vent and wait at least 30 minutes for the tablets to fall through the water and dissolve.
2. Sodium Hypochlorite - Suspend a tube through the well casing vent so that it reaches the bottom of the well. Withdraw the tube as the sodium hypochlorite solution is pumped through the tube.
C. Removing Disinfection Solution from the Well - After disinfection, the well shall be pumped for a minimum of 15 minutes beyond the time that a zero chlorine residual is first detected by the Contractor.
21.8 PUMP, WELL AND ELECTRICAL DATA SHEETS
A. Print and laminate the 11”x17” As-Built Drawing sheets (typically 2 sheets total) that contain the following information:
1. Pump: Pump model, design flow and head. Pump curve if available.
2. Pump Electrical System: Electrical Schematic including float controls meeting requirements of NEC 409.110(6). This may be met by a similar requirement in the electrical specs or drawings, if existing.
B. If a new well was drilled as part of the contract, provide the following information on a separate 8-1/2” x 11” sheet, laminated.
1. Well: Total depth, static water level. Well log and pump test information if available.
C. Permanently attach the laminated sheets to the wall of the pumphouse adjacent to the pump control box (or affix per applicable codes). Sheets must be easily readable at eye-level.
D. Provide well report that describes the system in detail. The report shall also document that the system pump water to the heliwell location.
END OF SECTION
SECTION 260500 - COMMON WORK RESULTS FOR ELECTRICAL
PART 22 - GENERAL
22.1 SUMMARY
A. Section Includes:
1. Electrical equipment coordination and installation.
2. Grout.
3. Common electrical installation requirements.
4. Hangers and supports.
22.2 SUBMITTALS
A. Product Data:
1. For any substitutions for equipment referred to by name in Division 26 specifications or the drawings.
22.3 QUALITY ASSURANCE
A. The installation shall conform to the 2020 Edition of the National Electrical Code (NFPA
70) and to the requirements specified herein.
B. The Contractor shall perform all work necessary and required to accomplish the task as detailed on the drawings and discussed in the installation notes. All work shall be done by a state licensed electrician.
22.4 MEASUREMENT AND PAYMENT
A. The work in this section, including all incidentals in other electrical sections, shall be inclusive to lump sum base bid item:
PART 23 - PRODUCTS
23.1 PRODUCTS REFERRED TO BY NAME
A. The materials referred to by trade name, make, or catalog number on the drawings shall be regarded as establishing a minimum standard of quality; substitutions of equal or greater quality can be made by submitting a data sheet of the proposed substituted item to the Contracting Officer, for approval.
23.2 GROUT
A. Nonmetallic, Shrinkage-Resistant Grout: ASTM C 1107, factory-packaged, nonmetallic aggregate grout, noncorrosive, nonstaining, mixed with water to consistency suitable for application and a 30-minute working time.
PART 24 - EXECUTION
24.1 COMMON REQUIREMENTS FOR ELECTRICAL INSTALLATION
A. Comply with NECA 1.
B. Measure indicated mounting heights to bottom of unit for suspended items and to center of unit for wall-mounting items.
C. Headroom Maintenance: If mounting heights or other location criteria are not indicated, arrange and install components and equipment to provide maximum possible headroom consistent with these requirements.
D. Equipment: Install to facilitate service, maintenance, and repair or replacement of components of both electrical equipment and other nearby installations. Connect in such a way as to facilitate future disconnecting with minimum interference with other items in the vicinity.
E. Right of Way: Give to piping systems installed at a required slope.
24.2 RACEWAY AND SIMILAR PENETRATIONS (NON-FIRE RATED, NOT
SLEEVED)
Electrical penetrations not requiring sleeves occur when raceways, cables, wireways, cable trays, or busways do not penetrate concrete slabs, concrete or masonry walls, or fire-rated floor and wall assemblies.
A. Concrete Slabs and Walls: Core-drilled holes.
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .