Construction Specifications Index for NRCS-02/2025 OH-EWP-Blessing Road Project
This document is an index of construction and material specifications for the Natural Resources Conservation Service (NRCS) Blessing Road Erosion and Water Protection (EWP) project in Ohio. The specification document contains 15 construction specifications and 7 material specifications governing all aspects of the project work. Construction specifications address clearing and shaping, pollution control, seeding/sprigging/mulching, mobilization/demobilization, traffic control, water removal, piling, excavation, earthfill, drainfill, rock riprap, plastic pipe, geotextile, and contractor quality control. Material specifications establish requirements for steel piles, aggregates for drainfill and filters, rock for riprap, and plastic pipe.
The project includes six primary bid items: (1) Mobilization and Demobilization (lump sum); (2) Channel Clearing and Shaping from approximately station 0+28 to station 3+04 (lump sum, Method 4 measurement); (3) Steel Sheet Piling using SKZ 20 cold-formed Grade 50 steel with minimum 31.69 in³/ft section modulus and 28.5-foot minimum length, with 8"x8"x1/2" steel angle caps (lump sum, Method 3 measurement); (4) Rock Riprap Transition ODOT Type C; (5) Rock Riprap Toe ODOT Type C; and (6) Drainfill using AASHTO M43 No. 57 crushed limestone aggregate with 4-inch perforated drain pipe and nonwoven geotextile fabric (Method 2 measurement by weight). Subsidiary items include seeding and mulching, removal of water, excavation (unclassified), earthfill (Class C compaction), drainfill bedding for riprap transitions and toes, drain pipe installation, and geotextile fabric. No separate payments are made for pollution control, traffic control, quality control, or subsidiary items; these are included in primary bid item payments. The specifications reference extensive ASTM standards and AWWA specifications for material quality and testing requirements.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
NRCS-02/2025
OH-EWP-BLESSING ROAD
INDEX OF CONSTRUCTION AND MATERIAL SPECIFICATIONS
SPEC
NO.
CONSTRUCTION
SPECIFICATION
SPEC
NO.
MATERIAL
SPECIFICATION
4 Channel Clearing and Shaping
511 Steel Piles
5 Pollution Control
Aggregates for Drainfill and Filters
Seeding,Sprigging and Mulching
523 Rock for Riprap
Mobilization and Demobilization
9 Traffic Control
11 Removal of Water
13 Piling
21 Excavation
23 Earthfill
24 Drainfill
94 Contractor Quality Control
SPEC
NO.
CONSTRUCTION
SPECIFICATION
61 Rock Riprap
Plastic Pipe Plastic Pipe547
95 Geotextile
Geotextile592
Samuel.West Typewritten Text This Page Left Intentionally Blank
(210-VI-NEH, May 2001) 4-1
Construction Specification 4—Channel Clearing and Shaping
1. Scope The work consists of clearing designated areas by the removal and disposal of trees, logs, stumps, shrubs, brush, and rubbish, and the shaping of the channel.
2. Protection of existing vegetation Trees and other vegetation designated to remain undisturbed shall be protected from damage throughout the duration of the construction period. Any damages resulting from the contractor's operations or neglect shall be repaired by the contractor.
Earthfill, stockpiling of materials, vehicle or equipment parking, and excessive foot or vehicle traffic shall not be allowed within the drip line of vegetation designated to remain in place.
Vegetation damaged by any of these or similar actions shall be replaced with viable vegetation of the same species, similar condition, and like size unless otherwise approved by the contracting officer.
Any cuts, skins, scrapes, or bruises to the bark of the vegetation shall be carefully trimmed and local nursery accepted procedures used to seal damaged bark.
Any limbs or branches 0.5 inch or larger in diameter that are broken, severed, or otherwise seriously damaged during construction shall be cut off at the base of the damaged limb or branch flush with the adjacent limb or tree trunk.
All roots 1 inch or larger in diameter that are cut, broken, or otherwise severed during channel shaping shall have the end smoothly cut perpendicular to the root. Roots exposed during channel shaping operations shall be covered with moist soil as soon as possible to prevent roots from drying out.
3. Marking The limits of the area(s) to be cleared and shaped are marked by stakes, flags, paint, tree markings, or other suitable methods or as specified in section 8 of this specification, or they will be shown on the drawings. Trees to remain standing, undisturbed, and uninjured are designated by special markings.
4. Clearing Trees and other vegetation marked for clearing shall be cut off as near the ground surface as conventional tools and equipment normally permit. All trees not marked for preservation and all snags, logs, brush, shrubs, stumps, and rubbish shall be cleared from within the area limits identified.
5. Disposal All woody material, vegetation, and rubbish resulting from clearing from designated areas shall be disposed of at the locations and in a manner shown on the drawings, or as specified in section 8 of this specification.
(210-VI-NEH, May 2001) 4-2
6. Shaping The channel bottom and side slopes shall be shaped as shown on the drawings. The resulting shaped channel surface shall be reasonably smooth. Material excavated during the channel shaping operation shall be removed from the channel and disposed of as specified in section 8 of this specification.
7. Measurement and payment Method 1—For items of work for which specific unit prices are established by the contract, the designated cleared and shaped area is measured and the area determined to the nearest 0.1 acre. Payment for clearing and shaping is made at the contract unit price for the item and shall constitute full compensation for all labor, equipment, tools, applicable permits and associated fees for burning and disposal of refuse, and all other items necessary and incidental to the satisfactory completion of the work.
Method 2—For items of work for which specific unit prices are established by the contract, the length of the cleared and shaped channel designated is measured to the nearest 100 feet. Payment for clearing and shaping is made at the contract unit price for the item and shall constitute full compensation for all labor, equipment, tools, applicable permits and associated fees for burning and disposal of refuse, and all other items necessary and incidental to the satisfactory performance of the work.
Method 3—For items of work for which specific unit prices are established by the contract, the cleared and shaped area(s) is measured and the area determined to the nearest 0.1 acre. The designated cleared and shaped area(s) is determined from the measured width at representative sections and the distance between the sections. Payment for clearing and shaping is made at the contract unit price for the item and shall constitute full compensation for all labor, equipment, tools, applicable permits and associated fees for burning and disposal of refuse, and all other items necessary and incidental to the satisfactory completion of the work.
Method 4—For items of work for which specific lump sum prices are established by the contract, the extent of clearing and shaping is not measured or determined for payment.
Payment for clearing and shaping is made at the contract lump sum price for the item and shall constitute full compensation for all labor, equipment, tools, applicable permits and associated fees for burning and disposal of refuse, and all other items necessary and incidental to the satisfactory completion of the work.
All Methods—The following provisions apply to all methods of measurement and payment.
Compensation for any item of work described in the contract, but not listed in the bid schedule is included in the payment for the item of work to which it is made subsidiary. Such items and items to which they have been made subsidiary are identified in section 8 of this specification.
OH-EWP-BLESSING RD 4-3
8. Items of work and construction details
Items of work to be performed in conformance with this specification and the construction details therefore are:
a. Bid Item 2 - Channel Clearing and Shaping
1. This item shall consist of removal and disposal of trees, logs, stumps, brush, and rubbish along the streambank and the shaping of the channel bank as shown and described in the drawings.
2. All removed woody material and rubbish shall be disposed off-site at an approved dump site. No on-site burning or burying will be authorized.
3. Excess or unsuitable material encountered during channel clearing and shaping such as soils unsuitable for use as fill material, organic material such as roots, or other foreign materials shall not be spoiled or graded within the floodplain. Excess or unsuitable materials shall be disposed off site at an environmentally responsible site approved by the COR.
4. All trees and rootwads shall be removed from within the confines of the proposed steel sheet pile wall and the tie-backs. Any trees designated as not to be disturbed, shall be marked with ribbons.
5. The beginning of the clearing and shaping will be from approximately station 0+28 to approximately station 3+04.
6. Fill material placed in front of the sheet pile wall shall be obtained from the excavation of drainfill and riprap areas or sourced from an off site location.
Fill material shall be capable of supporting vegetation. Fill shall be placed to the lines and elevations indicated by the drawings.
7. Measurement and payment shall be by Method 4.
8. Items subsidiary to this bid item are:
a. Seeding and Mulching - Construction Specification - 6
b. Removal of Water - Construction Specification 11
c. Excavation - Construction Specification - 21
d. Earthfill - Construction Specification - 23
This Page Left Intentionally Blank
(210-VI-NEH, January 2014) 5-1
Construction Specification 5—Pollution Control
1. Scope The work consists of installing measures or performing work to control erosion and minimize the production of sediment and other pollutants to water and air from construction activities.
The following BioPreferred® product categories are applicable to this specification: — mulch and compost materials, erosion control materials, fertilizers, dust suppressants, agricultural spray adjuvants
2. Material Silt fence shall conform to the requirement of Materials Specification 592, Geotextile. All other material furnished shall meet the requirements of the material specifications listed in section 8 of this specification.
3. Erosion and sediment control measures and works The measures and works shall include, but are not limited to, the following:
Staging of earthwork activities—The excavation and moving of soil materials shall be scheduled to minimize the size of areas disturbed and unprotected from erosion for the shortest reasonable time.
Seeding—Seeding to protect disturbed areas shall occur as soon as reasonably possible following completion of that earthwork activity.
Mulching—Mulching to provide temporary protection of the soil surface from erosion.
Diversions—Diversions to divert water from work areas and to collect water from work areas for treatment and safe disposition. They are temporary and shall be removed and the area restored to its near original condition when the diversions are no longer required or when permanent measures are installed.
Stream crossings—Culverts or bridges where equipment must cross streams. They are temporary and shall be removed and the area restored to its near original condition when the crossings are no longer required or when permanent measures are installed.
Sediment basins—Sediment basins collect, settle, and eliminate sediment from eroding areas from impacting properties and streams below the construction site(s). These basins are temporary and shall be removed and the area restored to its original condition when they are no longer required or when permanent measures are installed.
Sediment filters—Straw bale filters or geotextile silt fences trap sediment from areas of limited runoff. Sediment filters shall be properly anchored to prevent erosion under or around them. Silt fences shall be installed and maintained in accordance with ASTM D6462. These filters are temporary and shall be removed and the area restored to its original condition when they are no longer required or when permanent measures are installed.
Waterways—Waterways for the safe disposal of runoff from fields, diversions, and other structures or measures. These works are temporary and shall be removed and the area restored to its original condition when they are no longer required or when permanent measures are installed.
Other—Additional protection measures as specified in section 8 of this specification or required by Federal, State, or local government.
(210-VI-NEH, January 2014) 5-2
4. Chemical pollution The contractor shall provide watertight tanks or barrels or construct a sump sealed with plastic sheets to collect and temporarily contain chemical pollutants, such as drained lubricating or transmission fluids, grease, soaps, concrete mixer washwater, or asphalt, produced as a by-product of the construction activities. Pollutants shall be disposed of in accordance with appropriate state and Federal regulations. At the completion of the construction work, tanks, barrels, and sumps shall be removed and the area restored to its original condition as specified in section 8 of this specification. Sump removal shall be conducted without causing pollution.
Sanitary facilities, such as chemical toilets, or septic tanks shall not be located next to live streams, wells, or springs. They shall be located at a distance sufficient to prevent contamination of any water source. At the completion of construction activities, facilities shall be disposed of without causing pollution as specified in section 8 of this specification.
5. Air pollution The burning of brush or slash and the disposal of other materials shall adhere to state and local regulations.
Fire prevention measures shall be taken to prevent the start or spreading of wildfires that may result from project activities. Firebreaks or guards shall be constructed and maintained at locations shown on the drawings.
All public access or haul roads used by the contractor during construction of the project shall be sprinkled or otherwise treated to fully suppress dust. All dust control methods shall ensure safe construction operations at all times. If chemical dust suppressants are applied, the material shall be a commercially available product specifically designed for dust suppression and the application shall follow manufacturer's requirements and recommendations. A copy of the product data sheet and manufacturer's recommended application procedures shall be provided to the engineer 5 working days before the first application.
6. Maintenance, removal, and restoration All pollution control measures and temporary works shall be adequately maintained in a functional condition for the duration of the construction period. All temporary measures shall be removed and the site restored to near original condition.
7. Measurement and payment Method 1—For items of work for which specific unit prices are established in the contract, each item is measured to the nearest unit applicable. Payment for each item is made at the contract unit price for that item. For water or chemical suppressant items used for dust control for which items of work are established in section 8 of this specification, measurement for payment will not include water or chemical suppressants that are used inappropriately or excessive to need. Such payment will constitute full compensation for the completion of the work.
Method 2—For items of work for which lump sum prices are established in the contract, payment is made as the work proceeds and supported by invoices presented by the contractor that reflect actual costs. If the total of all progress payments is less than the lump sum contract price for this item, the balance remaining for this item will be included in the final contract payment. Payment of the lump sum contract price will constitute full compensation for completion of the work.
(210-VI-NEH, January 2014) 5-3
Method 3—For items of work for which lump sum prices are established in the contract, payment will be prorated and provided in equal amounts on each monthly progress payment estimate. The number of months used for prorating shall be the number estimated to complete the work as outlined in the contractor's approved construction schedule. The final month's prorate amount will be provided with the final contract payment. Payment as described will constitute full compensation for completion of the work.
All Methods—The following provisions apply to all methods of measurement and payment. Compensation for any item of work described in the contract, but not listed in the bid schedule is included in the payment for the item of work to which it is made subsidiary. Such items, and the items to which they are made subsidiary, are identified in section 8 of this specification.
OH-EWP-BLESSING RD 5-4
8. Items of work and construction details
Items of work to be performed in conformance with this specification and the construction details therefore are:
Subsidiary Item - Pollution Control
1. The Contractor is required to provide the Contracting Officer's Representative with a written Pollution Control Plan of Operations for this project. The plan shall be submitted prior to the pre-construction conference, and reviewed by all parties during the pre-construction conference.
2. The Contractor shall perform the work of this project in a manner consistent and in conformance with Federal, State, or Local Government regulations, to protect the site and downstream areas from degradation.
3. Method of Payment.
Section 7 Measurement and Payment does not apply. No separate payment will be made for Pollution Control. Compensation for this item will be included in the payment for Bid Item 1 - Mobilization / Demobilization.
(210-VI-NEH, Amend. 2, Sept 2018) 6-1
Construction Specification 6—Seeding, Sprigging, and Mulching
1. Scope The work consists of preparing the area for treatment; furnishing and placing seed, sprigs, mulch, fertilizer, inoculant, lime, and other soil amendments; and anchoring mulch in designated areas as specified.
The following BioPreferred® product categories are applicable to this specification:
— Mulch and compost materials
— Erosion control materials
— Fertilizers
— Agricultural spray adjuvants
2. Material Seed—All seed must conform to the current rules and regulations of the State where it is being used and must be from the latest crop available. It must meet or exceed the standard for purity and germination listed in section 7.
Seed must be labeled in accordance with State laws and U.S. Department of Agriculture rules and regulations under the Federal Seed Act in effect on the date of invitations for bids. Bag tag figures are evidence of purity and germination. No seed may be accepted with a test date of more than 9 months before the date of delivery to the site.
Seed that has become wet, moldy, or otherwise damaged in transit or storage will not be accepted. The percent of noxious weed seed allowable must be as defined in the current State laws relating to agricultural seeds. Each type of seed must be delivered in separate sealed containers and fully tagged unless an exception is granted in writing by the contracting officer.
Fertilizer—Unless otherwise specified, the fertilizer must be a commercial-grade fertilizer. It must meet the standard for grade and quality specified by State law. Where fertilizer is furnished from bulk storage, the contractor must furnish a supplier’s certification of analysis and weight. When required by the contract, a representative sample of the fertilizer must be furnished to the contracting officer for chemical analysis.
Inoculants—The inoculant for treating legume seeds must be a pure culture of nitrogen-fixing bacteria prepared specifically for the species and must not be used later than the date indicated on the container or as otherwise specified. A mixing medium, as recommended by the manufacturer, must be used to bond the inoculant to the seed.
Two times the amount of the inoculant recommended by the manufacturer must be used, except that four times the amount must be used when seed is applied using a hydraulic seeder. Seed must be sown within 24 hours of treatment and must not remain in the hydraulic seeder longer than 4 hours.
Lime and other soil amendments—Lime must consist of standard ground agriculture limestone, or approved equivalent. Standard ground agriculture limestone is defined as ground limestone meeting current requirements of the State department of agriculture.
Other soil amendments must meet quality criteria and application requirements specified in section 7.
(210-VI-NEH, Amend. 2, Sept 2018) 6-2
Mulch tackifiers—Asphalt emulsion tackifiers must conform to the requirements of ASTM D977, Specification for Emulsified Asphalt. The emulsified asphalt may be rapid setting, medium setting, or slow setting. Non-asphaltic tackifiers required because of environmental considerations must be as specified in section 7.
Straw mulch material—Straw mulch must consist of wheat, barley, oat or rye straw, hay, grass cut from native grasses, or other plants as specified in section 7. The mulch material must be air-dry, reasonably light in color, and must not be musty, moldy, caked, or otherwise of low quality. The use of mulch that contains noxious weeds is not permitted. The contractor must provide a method satisfactory to the contracting officer for determining weight of mulch furnished.
Other mulch materials—Mulching materials, such as wood cellulose fiber mulch, mulch tackifiers, synthetic fiber mulch, netting, and mesh may be required for specialized locations and conditions. These materials, when specified, must be accompanied by the manufacturer’s recommendations for methods of application.
3. Seeding mixtures, sod, sprigs, and dates of planting The application rate per acre for seed mixtures, sprigs, or sod and date of seeding or planting must be as shown on the plans or as specified in section 7.
4. Seedbed preparation and treatment Areas to be treated must be dressed to a smooth, firm surface. On sites where equipment can operate on slopes safely, the seedbed must be adequately loosened (4 to 6 inches deep) and smoothed. Depending on soil and moisture conditions, disking or culti-packing, or both, may be necessary to properly prepare a seedbed. Where equipment cannot operate safely, the seedbed must be prepared by hand methods by scarifying to provide a roughened soil surface so that broadcast seed will remain in place.
If seeding is to be accomplished immediately following construction operations, seedbed preparation may not be required except on a compacted, polished, or freshly cut soil surface.
Rocks larger than 6 inches in diameter, trash, weeds, and other debris that will interfere with seeding or maintenance operations must be removed or disposed of as specified in section 7.
Seedbed preparation must be discontinued when soil moisture conditions are not suitable for the preparation of a satisfactory seedbed as determined by the responsible engineer.
5. Seeding, sprigging, fertilizing, mulching, and stabilizing All seeding or sprigging operations must be performed in such a manner that the seed or sprigs are applied in the specified quantities uniformly in the designated areas. The method and rate of seed application must be as specified in section 7. Unless otherwise specified, seeding or sprigging must be accomplished within 2 days after final grading is completed and approved.
Fertilizer, lime, and other soil amendments must be applied as specified in section 7.
When specified, the fertilizer and soil amendments must be thoroughly incorporated into
(210-VI-NEH, Amend. 2, Sept 2018) 6-3 the soil immediately following surface application.
The rate, amount, and kind of mulching or mesh must be as specified in section 7.
Mulches must be applied uniformly to the designated areas. They must be applied to areas seeded not later than 2 working days after seeding has been performed. Straw mulch material must be stabilized within 24 hours of application using a mulch crimper or equivalent anchoring tool or by a suitable tackifier. When the mulch crimper or equivalent anchoring tool is used, it must have straight blades and be the type manufactured expressly for and capable of firmly punching the mulch into the soil.
Where the equipment can be safely operated, it must be operated on the contour. Hand methods must be used where equipment cannot safely operate to perform the work required.
The tackifier must be applied uniformly over the mulch material at the specified rate, or it must be injected into the mulch material as it is being applied. Mesh or netting stabilizing materials must be applied smoothly but loosely on the designated areas. The edges of these materials must be buried or securely anchored using spikes or staples as specified in section 7.
The contractor must maintain the mesh or netting areas until all work under the contract has been completed and accepted. Maintenance must consist of the repair of areas damaged by water erosion, wind, fire, or other causes. Such areas must be repaired to reestablish the intended condition and to the design lines and grades required by the contract. The areas must be refertilized, reseeded, and remulched before the new application of the mesh or netting.
6. Measurement and payment Method 1—For items of work for which specific unit prices are established in the contract, each area treated is measured as specified in section 7 and the area is calculated to the nearest 0.1 acre. Payment for treatment is made at the contract unit price for the designated treatment, which will constitute full compensation for completion of the work.
When specified as an item of work, mesh or netting is measured to the nearest square yard of surface area covered and accepted. Payment is made at the contract unit price and will constitute full compensation for completion of the work.
Method 2—For items of work for which specific lump-sum prices are established in the contract, the quantity of work will not be measured for payment. Payment for this item is made at the contract lump-sum price for the item and constitutes full compensation for the completion of the work.
Method 3—For items of work for which lump-sum prices are established in the contract, payment is made as the work proceeds. Progress payments are determined as specified in section 7. Payment of the lump sum contract price constitutes full compensation for completion of the work.
All Methods—The following provisions apply to all methods of measurement and payment. Compensation for any item of work described in the contract but not listed in
(210-VI-NEH, Amend. 2, Sept 2018) 6-4 the bid schedule is included in the payment for the item of work to which it is made subsidiary. Such items and the items to which they are made subsidiary are identified in section 7.
OH-EWP- BLESSING RD 6-5
7. Items of work and construction details
Items of work to be performed in conformance with this specification and the construction details therefore are:
Subsidiary Item- Seeding, Sprigging and Mulching
This item shall include seeding and mulching of all disturbed areas within the construction limits as shown and described in the drawings.
1. Fertilizer All areas shall have fertilizer uniformly applied at the following rates:
• Nitrogen (N) - 150 pounds per acre
• Phosphorus P2O5 - 150 pounds per acre
• Potassium K2O - 150 pounds per acre
This specification can be met by applying fertilizer having an analysis of 15-15-15 at the rate of 1000 pounds per acre or 23 pounds per thousand square feet.
2. Seed All seed shall be labeled, tagged or marked in accordance with Section 907.03 of the Revised Code of Ohio. Seed tags showing germination and purity shall be attached to all bags. No pre-mixed seed shall be used unless the following conditions are met:
a. The weight, purity, and germination for each kind of seed is specified on the tag for each lot of seed. Seeding rates shall be adjusted for Pure Live Seed (PLS) at the time of seeding. Pure Seed (PLS) = percent germination. Seed shall have the equivalent of a minimum of 80% pure live seed.
When the percent purity multiplied by the percent germination gives a percentage less than 80, the rate of seeding will be increased to provide a minimum PLS of 80.
b. Seeding mixtures and rates per acre:
Disturbed construction areas -
Kentucky 31 Tall Fescue -60 lbs per acre or 1.5 lbs per 1000 square ft.
Annual Ryegrass -10 lbs per acre or 0.25 lbs per 1000 square ft.
Streambank area (riprap toe to pile wall):
Kentucky 31 Tall Fescue -60 lbs per acre or 1.5 lbs per 1000 square ft.
Annual Ryegrass -10 lbs per acre or 0.25 lbs per 1000 square ft.
Wild Rye (Elymus riparius)-20 lbs per acre or 0.5 lbs per 1000 square ft.
Little Blue Stem -10lbs per acre or 0.25 lbs per 1000 square ft.
OH-EWP- BLESSING RD 6-6
4. Sowing the Seed Seeding shall be completed as soon as practical after final grading. Broadcast the seed and cover approximately 1/4-inch deep with a light harrow, culti-packer, or other suitable equipment, operated across the slope. On areas too steep or otherwise inaccessible to equipment, the seed shall be covered with a hand rake, or other suitable equipment.
5. Mulch and Method of Anchoring Mulch shall consist of (wheat, rye, or barley) straw and shall be applied uniformly at 2 air-dried tons per acre or 100 lbs. per 1000 square feet. Mulch shall be applied within 48 hours after application of seeding. All bailing wire and twine shall be removed from the seeded and mulched areas. No anchoring is required.
6. Erosion Control Blanket Erosion control blanket shall be installed along the stream bank as shown in the drawings. Erosion control blankets shall be double-netted using a mulch medium comprised of straw, coconut fiber, or equivalent material. Erosion control blankets shall have a minimum dry weight per surface area of 0.5 lbs/sq. yd as per ASTM D6475. Erosion control blankets shall have a 12-month function longevity as described in FWHA FP-14. Minimum 6 inch long stables shall be installed per the stapling plan shown in the drawings.
7. Method of Payment Section 6 Measurement and Payment does not apply. No separate payment will be made for Seeding, Sprigging, and Mulching. Compensation for this item will be included in the payment for Bid Item 2 – Channel Clearing and Shaping.
3. Seedbed Preparation Seedbed preparation shall be completed within 48 hours after application of fertilizer. All areas accessible to equipment shall be disked to incorporate fertilizer and to prepare a seedbed a minimum of three inches deep. The final seedbed preparation operation shall be performed across the slope and immediately prior to seeding. Suitable equipment shall be used to smooth the seedbed prior to seeding. On areas inaccessible to a disk, a one-inch minimum seedbed will be prepared using suitable tillage tools or hand tools. All rocks greater than 3 inches in size shall be removed.
(210-VI-NEH, May 2001) 8-1
Construction Specification 8—Mobilization and Demobilization
1. Scope The work consists of the mobilization and demobilization of the contractor's forces and equipment necessary for performing the work required under the contract. It does not include mobilization and demobilization for specific items of work for which payment is provided elsewhere in the contract. Mobilization will not be considered as work in fulfilling the contract requirements for commencement of work.
2. Equipment and material Mobilization shall include all activities and associated costs for transportation of contractor's personnel, equipment, and operating supplies to the site; establishment of offices, buildings, and other necessary general facilities for the contractor's operations at the site; premiums paid for performance and payment bonds including coinsurance and reinsurance agreements as applicable; and other items specified in section 4 of this specification.
Demobilization shall include all activities and costs for transportation of personnel, equipment, and supplies not required or included in the contract from the site; including the disassembly, removal, and site cleanup of offices, buildings, and other facilities assembled on the site specifically for this contract.
This work includes mobilization and demobilization required by the contract at the time of award. If additional mobilization and demobilization activities and costs are required during the performance of the contract as a result of changed, deleted, or added items of work for which the contractor is entitled to an adjustment in contract price, compensation for such costs will be included in the price adjustment for the item or items of work changed or added.
3. Payment Payment will be made as the work proceeds, after presentation of paid invoices or documentation of direct costs by the contractor showing specific mobilization and demobilization costs and supporting evidence of the charges of suppliers, subcontractors, and others. When the total of such payments is less than the lump sum contract price, the balance remaining will be included in the final contract payment.
Payment of the lump sum contract price for mobilization and demobilization will constitute full compensation for completion of the work.
Payment will not be made under this item for the purchase costs of materials having a residual value, the purchase costs of materials to be incorporated in the project, or the purchase costs of operating supplies.
OH-EWP- BLESSING RD 8-2
4. Items of work and construction details
Items of work to be performed in conformance with this specification and the construction details therefore are:
Bid Item 1 - Mobilization and Demobilization
1. This item shall consist of mobilizing and demobilizing all forces, equipment, and materials necessary for performing the work required under this contract.
2. Any ingress/egress or storage/lay-down areas within the Work Limits must be returned to the condition existing prior to construction. Any storage/lay-down areas outside the Work Limits shall be coordinated between the Contractor and Landowner.
3. A written and detailed construction schedule, prepared by the Contractor, will be required prior to beginning work.
4. A portable toilet shall be provided by the Contractor. The portable toilet shall be placed within the Work Limits and shall be operated and maintained by the Contractor for the duration of the project.
5. Approximately 2,000 ft north of the project site, Blessing Rd crosses Raccoon Creek via bridge at 38°46'03.1"N 82°18'41.0"W. No construction traffic shall utilize the Blessing Rd bridge for ingress or egress from the construction site.
All construction traffic shall use alternative routes via Smokey Row Rd.
6. The contractor shall notify Gallia Rural Water via phone at 740-446-9221 at minimum 2 working days prior to the start of construction and at minimum 2 working days prior to the start of sheet pile vibration.
7. The contractor shall contact Buckeye Rural Electric Coop at minimum 30 days prior to the start of construction to coordinate the temporary relocation of the overhead power line. Coordination with Buckeye Rural Electric Coop shall be routed through Matthew Nibert (740-379-9638). Expenses billed from Buckeye Rural Electric Coop pertaining to the temporary relocation of the power line are the responsibility of the contractor and shall be included in this bid item.
8. All concrete barriers and reflectors installed along Blessing Rd shall be removed prior to the start of construction and stockpiled within the work limits for later collection by the Green Township trustees.
Matthew Smith, Assistant Regional Scenic River Manager, shall be invited to the preconstruction meeting between the contractor and NRCS. Matthew Smith shall be notified of the project start date one week prior to prior to the commencement of work. Periodic inspection of the project may take place.
Matthew Smith shall be contacted one week prior to the completion of the project. Matthew Smith can be contacted at matthew.smith@dnr.ohio.gov and/or 440-225-5582.
Items subsidiary to this bid item are:
a. Pollution Control -Construction Specification 5
b. Traffic Control -Construction Specification 9
c. Contractor Quality Control -Construction Specification 94
9.
10.
OH-EWP- BLESSING RD 8-3
(210-VI-NEH, May 2001) 9-1
Construction Specification 9—Traffic Control
1. Scope The work shall consist of establishing traffic control and maintaining safe, convenient use of public roads and rights-of-way.
2. Traffic and access The contractor's operations shall cause no unnecessary inconvenience to the public.
The public rights-of-way shall be maintained at all times unless interruption is authorized by proper local authority. Contractor's authorized closing or detour plans shall be provided to the engineer for approval.
Safe and adequate access shall be provided and maintained to all public protection devices and to all critical utility control locations. Facility access shall be continuous and unobstructed unless otherwise approved.
3. Storage of equipment and material in public streets Construction materials and equipment shall not be stored or parked on public streets, roads, or highways. During any material or equipment loading or unloading activities that may temporarily interfere with traffic, an acceptable detour shall be provided for the duration of the activity. Any associated expense for this activity is the responsibility of the contractor.
Excavated material, including suitable material that is intended for adjacent trench backfill or other earth backfill as specified in section 5 of this specification, shall not be stored on public streets, roads, or highways that remain in service for the public. Any waiver of this requirement must be obtained from the proper local authority and approved by the engineer. All excess and unsuitable material shall be removed from the site as soon as possible. Any spillage shall be removed from roadways before they are used by the public.
4. Street closures, detours, and barricades The contractor shall comply with the requirements of all applicable responsible units of government for closure of any street, road, or highway. The contractor shall provide the required barriers, guards, lights, signs, temporary bridges, and flaggers together with informing the public of any detours and construction hazards by the most suitable means available, such as local newspapers or radio stations. The contractor is also responsible for compliance with additional public safety requirements that may arise during construction. The contractor shall furnish, install, and, upon completion of the work, promptly remove all signs, warning devices, and other materials used in the performance of this work.
Unless otherwise specified, the contractor shall notify, in writing, the fire chief, police chief, county sheriff, state patrol, schools that operate school buses, or any other government official as may be appropriate no less than 7 days before closing, partly closing, or reopening any street, road, or highway.
Unless otherwise specified, the contractor shall furnish to the engineer a written plan
(210-VI-NEH, May 2001) 9-2 showing the proposed method of signing, barricading for traffic control, and safety for street detours and closures.
All temporary detours will be maintained to ensure use of public rights-of-way is provided in a safe manner. This may include dust control, grading, and graveling as required in section 7 of this specification.
5. General and specific references All signs, signals, barricades, use of flaggers, and other traffic control and public safety devices shall conform to the general requirements set forth in the Manual of Uniform Traffic Control Devices (MUTCD) and the latest edition of Standard Highway Signs and Standard Alphabets for Highway Signs and/or OSHA Construction Industry Standards (29 CFR Part 1926), Subpart G, Signs, Signals, and Barricades unless otherwise specified in section 7 of this specification.
6. Measurement and payment For items of work for which specific lump sum prices are established in the contract, payment for the work is made at the contract lump sum price. Progress payments will be made based upon the percentage of estimated total time that traffic control will be required unless otherwise specified in section 7 of this specification. Payment will constitute full compensation for all flaggers, labor, materials, equipment, and all other items necessary and incidental to completion of the work.
Compensation for any item of work described in the contract, but not listed in the bid schedule will be included in the payment for the item of work to which it is made subsidiary. Such items and items to which they are made subsidiary are identified in section 7 of this specification.
OH-EWP- BLESSING RD 9-3
7. Items of work and construction details
Items of work to be performed in conformance with this specification and the construction details therefore are:
Subsidiary Item - Traffic Control
1. Blessing Road may be closed to through traffic during the period of construction. The proposed road closure restrictions and maintenance of traffic requirements are shown in the drawings. The Contractor shall contact the Green Township Trustees to arrange road closure and additional signage required. Notification to the Trustees shall be made at least 3 working days prior to the start of any road closure, to allow the Trustees sufficient time to notify emergency & other services of the closure.
• Contact the Green Township Trustees at (740) 379-2580.
2. Road closures shall be in accordance with ODOT Construction and Material Specifications Item 614.05 and other applicable portions of the specifications, as well as the Ohio Manual of Uniform Traffic Control Devices. A written Traffic Control & Road Closure Plan shall be submitted to the NRCS engineer at the pre-construction conference.
3. Road closures barriers and signage shall be posted at minimum at the locations shown in the drawings. Access to Wray Rd and Smokey Row Rd, with adequate space for traffic turnaround, shall be maintained during the closure of Blessing Rd.
4. Local traffic access shall be maintained for 2050 Blessing Rd and 2100 Blessing Rd from the Blessing Rd bridge and Wray Rd. Local traffic access shall be maintained for 2430 Blessing Rd from Smokey Row Rd.
5. Access to the barn at 2430 Blessing Rd, 484' south of BM2 west of Blessing Rd, shall be maintained for the landowner throughout the construction period.
6. Method of Payment Section 6 Measurement and Payment does not apply. No separate payment will be made for Traffic Control. Compensation for this item will be included in the payment for Bid Item 1 - Mobilization and Demobilization.
This Page Intentionally Left Blank
(210-VI-NEH, May 2001) 11-1
Construction Specification 11—Removal of Water
1. Scope The work consists of the removal of surface water and ground water as necessary to perform the construction required by the contract in accordance with the specifications. It shall include: (1) constructing, installing, building, and maintaining all necessary temporary water containment facilities, channels, and diversions; (2) furnishing, installing, and operating all necessary pumps, piping, and other facilities and equipment;
and (3) removing all such temporary works and equipment after their intended function is no longer required.
2. Diverting surface water The contractor shall install, maintain, and operate all cofferdams, channels, flumes, sumps, and all other temporary diversion and protective works needed to divert streamflow and other surface water through or around the construction site. Control of surface water shall be continuous during the period that damage to construction work could occur. Unless otherwise specified and/or approved, the diversion outlet shall be into the same drainageway that the water would have reached before being diverted.
The contractor shall furnish the contracting officer, in writing, a proposed plan for diverting surface water before beginning any construction activities for which a diversion is required, unless waived in section 8 of this specification. Acceptance of this plan or the waiving of the plan requirement will not relieve the contractor of the responsibilities related to this activity during the process of completing the work as specified.
3. Dewatering the construction site Foundations, cutoff trenches, and all other parts of the construction site shall be dewatered and kept free of standing water and muddy conditions as necessary for the proper execution of the work. The contractor shall furnish, install, operate, and maintain all drains, sumps, pumps, casings, well points, and all other equipment required to properly dewater the site as specified. Dewatering systems that cause a loss of soil fines from the foundation areas will not be permitted.
The contractor shall furnish the contracting officer, in writing, a proposed plan for dewatering before commencing with any construction activity for which dewatering may be required, unless waived in section 8 of this specification. Acceptance of this plan or the waiving of the plan requirement will not relieve the contractor of the responsibilities for completing the specified work.
4. Dewatering borrow areas The contractor shall maintain all borrow areas free of surface water or otherwise provide for timely and effective removal of surface and subsurface water that accumulates within the borrow area, unless waived in section 8 of this specification. Borrow material shall be processed as necessary to achieve proper and uniform moisture content at the time of placement.
If pumping to dewater borrow areas is included as a bid item of work in the bid schedule, each pump discharge pipe shall be equipped with a water meter. The meter shall be such that the measured quantity of water is accurate within 3 percent of the true
(210-VI-NEH, May 2001) 11-2 quantity. The contractor shall provide necessary support to perform accuracy tests of the water meter when requested by the contracting officer.
5. Erosion and pollution control Removal of water from the construction site, including the borrow areas, shall be accomplished so that erosion and the transporting of sediment and other pollutants are minimized. Dewatering activities shall be accomplished in a manner that the water table water quality is not altered. Pollution control activities shall not conflict with the requirements of Construction Specification 5, Pollution Control, if it is a part of this contract.
6. Removal of temporary works When temporary works are no longer needed, the contractor shall remove and return the area to a condition similar to that which existed before construction. Areas where temporary works were located shall be graded for sightly appearance with no obstruction to natural surface waterflows or the proper functioning and access to the works of improvement installed. The contractor shall exercise extreme care during the removal stages to minimize the loss of soil sediment and debris that was trapped during construction.
Pipes, casings, and any other material used to dewater the site shall be removed from temporary wells. The wells shall be filled to ground level with clean gravel or other suitable material approved by the contracting officer. The contractor shall exercise extreme care to prevent pollution of the ground water by these actions.
7. Measurement and payment Method 1—Items of work listed in the bid schedule for removal of water, diverting surface water, and dewatering construction sites and borrow areas are paid for at the contract lump sum prices. Such payment will constitute full compensation for all labor, equipment, tools, and all other items necessary and incidental to the completion of the work.
Method 2—Items of work listed in the bid schedule for removal of water, diverting surface water, dewatering construction sites, and dewatering borrow areas are paid for at the contract lump sum prices. Such payment will constitute full compensation for furnishing, installing, operating, and maintaining the necessary trenches, drains, sumps, pumps, and piping and for all labor, equipment, tools, and all other items necessary and incidental to the completion of the work. The exception is that additional payment for pumping to dewater borrow areas and the removal of water will be made as described in the following paragraph.
If pumping to dewater borrow areas is a contract bid item, payment is made at the contract unit price, which shall be the price per 1,000 gallons shown in the bid schedule.
Such payment will constitute full compensation for pumping only. Compensation for equipment and preparation and for other costs associated with pumping is included in the lump sum payment for removal of water or the lump sum payment for dewatering the borrow areas. Payment is made only for pumping that is necessary to dewater borrow areas that cannot be effectively drained by gravity or that must have the water table lowered to be usable as a suitable borrow source. Pumping for other purposes will not
(210-VI-NEH, May 2001) 11-3 be included for payment under this item.
All Methods—The following provisions apply to all methods of measurement and payment. Compensation for any item of work described in the contract, but not listed in the bid schedule is included in the payment for the contract line item to which it is made section 8 of this specification.
OH-EWP- BLESSING RD 11-4
8. Items of work and construction details
Items of work to be performed in conformance with this specification and the construction details therefore are:
Subsidiary Item - Removal of Water
1. This item shall consist of all dewatering required for the work under this contract.
2. A written dewatering plan from the Contractor is required at the preconstruction meeting and shall be provided to the COR.
3. Method of Payment Section 6 Measurement and Payment does not apply. No separate payment will be made for Removal of Water. Compensation for this item will be included in the payment for Bid Item 2 – Channel Clearing and Shaping.
(210-VI-NEH, May 2001) 13-1
Construction Specification 13—Piling
1. Scope The work consists of furnishing and installing the specified kinds and types of piles at the locations shown on the drawings.
2. Material Piles shall conform to the requirements of following material specifications as appropriate to the kinds of piles specified. For piles of materials other than those listed, the material requirements outlined in section 14 of this specification shall apply.
511—Steel Piles 512—Wood Piles 513—Precast Concrete Piles 514—Cast-in-Place Concrete Piles
3. Site preparation All excavation within the area to be occupied by bearing piles shall be completed before the piles are driven.
4. Protection of pile heads The heads of all piles shall be protected during driving by suitable caps, rings, heads, blocks, mandrels, and other devices.
The heads of timber piles shall be fitted into a steel head block or fitted with heavy steel or wrought iron rings or wire wrapping.
The heads of steel piles shall be cut square and fitted with a steel driving cap.
The heads of precast concrete piles and casings shall be fitted into cushion type drive caps having a rope or other suitable cushion next to the pile head and fitting into a casting that in turn supports a timber shock block.
Driving heads, mandrels, and other devices shall be provided by the contractor as needed for special types of piles and shall conform to the recommendations of the pile manufacturer.
5. Piles, general The contractor shall notify the engineer before pile driving…