About this file

This specifications document outlines equipment requirements for the Pennsylvania Department of Environmental Protection, Bureau of Abandoned Mine Reclamation, for the procurement of two (2) Vaughan Horizontal End Suction Chopper Pumps. The specifications detail the technical requirements and performance standards that the pumps must meet, including operational capabilities, materials of construction, and design features specific to chopper pump functionality for handling abrasive and solids-laden fluids common in mine reclamation applications. The document establishes baseline equipment standards to ensure bidders submit compliant products that meet the agency's operational and durability requirements for this procurement.

The specifications focus on detailed technical parameters including pump configuration, power requirements, performance curves, and materials specifications necessary for evaluation of vendor submissions. Key specifications address the pump's ability to process slurry and solids-laden materials, which is critical for the abandoned mine reclamation work. The document provides clear acceptance criteria for bid evaluation, ensuring that all submitted equipment meets minimum performance and construction standards required by the Pennsylvania Department of Environmental Protection for this two-unit procurement.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

COMMONWEALTH of PENNSYLVANIA

DEPARTMENT of ENVIRONMENTAL PROTECTION

Bureau of Abandon Mine Reclamation Cambria District Office

286 Industrial Park Road Ebensburg, PA 15931

Specifications for Vaughan Chopper Pumps

The Department of Environmental Protection (DEP), Bureau of Abandoned Mine Reclamation (BAMR) requires two (2) Vaughan Chopper Pumps as detailed below that is comparable.

Any questions regarding the technical aspects of the Specifications shall be directed to Jeff Miller, at 814.232.5191 or jejmiller@pa.gov. Questions regarding the contracting or bidding procedures shall be directed to Jeannine Estok at 814.472.1806 or jestok@pa.gov.

Model/Part# Specifications

HE3P6CS-090

Equipment must have the following listed specifications:

Vaughan Horizontal End Suction Chopper Pump/Specifications

• Casing and Backplate, cast ductile iron.

• Impeller, Cutter Bar, Cutter Nut and Upper Cutter, cast steel, heat treated to minimum Rockwell C60.

• Shaft, heat treated steel supported by rolling element bearings.

• Bearings, oil bath lubricated with minimum 100,000-hour L-10 bearing life.

• Bearing Housing, cast ductile iron with sight glass and bonze non-contacting labyrinth bearing isolators at each end.

• Flushless Mechanical Seal, cartridge type with stainless steel housing, integral stainless steel shaft sleeve, and silicon carbide faces.

• Elastomers, Buna N.

• Flanges, three inch (3”) discharge and six inch (6”) inlet, ANSI

Class 125.

• Coupling, elastomeric type by TB Woods.

• Motor Mount, fabricated steel, piloted for self-aligning mounting of a C-face flange mounted motor.

• Base, powder coated steel complete with lifting eyes and anchor bolt holes.

• Premium Pump Finish: Solvent wash, sandblast and coat with minimum 30 MDFT Tnemec Perma-Shield PL Series 431 epoxy.

(Except Motor and powder coated base).

• Electric Motor: Drive 10 HP, 1750 RPM, 230/460/3/60, premium efficient, 1.15 efficient. 1.15 SF, “C” flanged, TEFC enclosure.

• Variable Frequency Drive, 10 HP, 1750 RPM, 3/460/60, Constant

Torque, wall surface mount type with NEMA 4 enclosure. Built in cooling fans to keep the drive cool.

• Drive Setup and Startup include.

Instructions to Bidders: The Department of Environmental Protection (DEP), Bureau of Abandoned Mine Reclamation, is requesting price bids for the following items listed in the Invitation for Bid (IFB) item list section. The bidder must supply a price for two (2) Vaughan Horizontal End Suction Chopper Pumps.

Contract Requirements: Bidder shall complete Attachment 1A, Reciprocal Limitations Act Requirements, and electronically attach to bid. Failure to do so may result in your bid being rejected as non-responsive.

Ship To/Delivery Location: DEP – Bureau of Abandoned Mine Reclamation, Rausch Creek Treatment Plant, 315 Schwenks Road, Valley View, PA 17983. All costs including shipping/handling shall be included in the unit price bid. All deliveries shall be Free on Board (FOB) destination. No additional costs shall be permitted.

Bid Award: The contract shall be awarded to the lowest responsive and responsible bidder based on the lowest total price submitted.

DEP is not responsible for the maintenance of the eMarketplace website.

The Department of General Services Supplier Service Center is available to assist vendors with registration, bidding and account management. For questions regarding registration help, send an email to:

RA-PSC_Supplier_Requests@pa.gov or call (877) 435-7363, then choose Option 1.

For questions regarding bidding help, send an email to srmhelp@pa.gov or call (877) 435-7363, then choose Option 2.

DEP is not responsible for the support or functionality of any DGS Website.

All bids shall be submitted electronically ONLY before closing date and time.

Any questions regarding the technical aspects of the Specifications shall be directed to Jeff Miller, at 814.232.5191 or jejmiller@pa.gov Phone communication is preferred.

Questions regarding the contracting or bidding procedures shall be directed to Jeannine Estok at 814.472.1806 or jestok@pa.gov. Email communication is preferred.

Contract Term: The contract shall commence upon execution of the Notice to Proceed.

Termination shall commence upon delivery of the pumps.

mailto:RA-PSC_Supplier_Requests@pa.gov mailto:srmhelp@pa.gov mailto:jestok@pa.gov

STEEL PRODUCTS PROCUREMENT ACT

In accordance with the Act of March 3, 1978 (P.L. 6 No. 3), as amended, known as the “Steel Products Procurement Act” (73 P.S. 1881 et seq.), Contractor, subcontractor(s), or supplier(s) shall use or permit to be used ONLY steel products produced in the U.S. “Steel products” means products rolled, formed, shaped, drawn, extruded, forged, cast, fabricated or otherwise similarly processed by a combination of two or more of such operations, from steel made in the U.S. by the open hearth, basic oxygen, electric furnace, Bessemer or other steel making process including cast iron products.

With each shipment of steel or cast-iron products delivered to the project site, Contractor shall provide evidence to the Department’s Representative that such steel products comply with this act.

When unidentified steel products are supplied, Contractor shall provide documentation which includes but is not limited to: invoices, bills of lading and mill certification that the steel was melted and manufactured in the U.S., which establishes that Contractor has fully complied with the act. If a steel product is identifiable from its face, Contractor shall provide certification that it has fully complied with the act. The definition of steel products must include machinery and equipment listed in U.S. Department of Commerce Standard Industrial Classification 25 (furniture and fixture), 35 (machinery, except electrical) and 37 (transportation equipment) and made of, fabricated from or containing steel components. If a product contains both foreign and U.S. steel, such product is considered a U.S. steel product only if at least 75% of the cost of the articles, materials and supplies have been mined, produced or manufactured, as the case may be, in the U.S. Transportation equipment will be determined to be a U.S. steel product if it complies with Section 165 of Public Law 97-424 (96 Stat. 2136).

Compliance with the Steel Products Procurement Act will not be required for steel products used as construction tools and which will not serve a permanent functional use in the project. Steel casing must comply with the Steel Products Procurement Act only when it is permanently incorporated into the project such as a water well for a permanent water supply.

The Department shall not provide for, or make any payments to, any person who has not complied with the Steel Products Procurement Act. Any such payments made to any person by the Department which should not have been made as a result of the act will be recoverable directly from Contractor or subcontractor(s) who did not comply with the act. In addition to the above penalties any person who willfully violates the provisions of the act will be subject to other penalties outlined in the act.

Payment Terms: Payment shall be made upon satisfactory receipt of items ordered and submission of corresponding invoice(s).

BUY AMERICA DOMESTIC PROCUREMENT PREFERENCE

Contractor shall comply with the federal “Buy American Build American Act” P.L. 117-58 (also known as the Bipartisan Infrastructure Law or Infrastructure Investment and Jobs Act) regarding any work performed on or after May 14, 2022.

As required by Section 70914 of the Bipartisan Infrastructure Law (also known as the Infrastructure Investment and Jobs Act), P.L. 117-58, on or after May 14, 2022, none of the funds under a federal award that are part of Federal financial assistance program for infrastructure may be obligated for a project unless all of the iron, steel, manufactured products, and construction materials used in the project are produced in the United States, unless subject to an approved waiver. The requirements of this section must be included in all subawards, including all contracts and purchase orders for work or products under this program. In the event of any conflict between this section’s requirements and those described in DEP’s 2016 General Conditions for Construction, including but not limited to Subsections 4.10.K.16 and 5.14.B.3, this section’s requirements are controlling.

Recipients of an award of Federal financial assistance are hereby notified that none of the funds provided under this award may be used for a project for infrastructure unless:

1. all iron and steel used in the project are produced in the United States--this means all manufacturing processes, from the initial melting stage through the application of coatings, occurred in the United States;

2. all manufactured products used in the project are produced in the United States—this means the manufactured product was manufactured in the United States; and the cost of the components of the manufactured product that are mined, produced, or manufactured in the United States is greater than 55 percent of the total cost of all components of the manufactured product, unless another standard for determining the minimum amount of domestic content of the manufactured product has been established under applicable law or regulation; and

3. all construction materials are manufactured in the United States—this means that all manufacturing processes for the construction material occurred in the United States.

The Buy America preference only applies to articles, materials, and supplies that are consumed in, incorporated into, or affixed to an infrastructure project. As such, it does not apply to tools, equipment, and supplies, such as temporary scaffolding, brought to the construction site and removed at or before the completion of the infrastructure project. Nor does a Buy America preference apply to equipment and furnishings, such as movable chairs, desks, and portable computer equipment, that are used at or within the finished infrastructure project but are not an integral part of the structure or permanently affixed to the infrastructure project.

For further information on the Buy America preference, please visit www.doi.gov/grants/BuyAmerica. Additional information can also be found at the White House Made in America Office website: www.whitehouse.gov/omb/management/made-in-america/.

Waivers

When necessary, with the approval of the Department of Environmental Protection, recipients may apply for, and the Department of the Interior (DOI) may grant, a waiver from these requirements, subject to review by the Made in America Office. The DOI may waive the application of the domestic content procurement preference in any case in which it is determined that one of the below circumstances applies:

1. Non-availability Waiver: the types of iron, steel, manufactured products, or construction materials are not produced in the United States in sufficient and reasonably available quantities or of a satisfactory quality;

http://www.doi.gov/grants/BuyAmerica http://www.whitehouse.gov/omb/management/made-in-america/

2. Unreasonable Cost Waiver: the inclusion of iron, steel, manufactured products, or construction materials produced in the United States will increase the cost of the overall project by more than 25 percent; or

3. Public Interest Waiver: applying the domestic content procurement preference would be inconsistent with the public interest.

There may be instances where an award qualifies, in whole or in part, for an existing DOI general applicability waiver as described at:

www.doi.gov/grants/BuyAmerica/GeneralApplicabilityWaivers. If the specific financial assistance agreement, infrastructure project, or non-domestic materials meets the criteria of an existing general applicability waiver within the limitations defined within the waiver, the recipient is not required to request a separate waiver for non-domestic materials.

If a general applicability waiver does not already apply, and a recipient believes that one of the above circumstances applies to an award, a request to waive the application of the domestic content procurement preference may be submitted to the financial assistance awarding officer in writing.

Waiver requests shall include the below information. The waiver will not include any Privacy Act information, sensitive data, or proprietary information within their waiver request. Waiver requests will be posted to www.doi.gov/grants/buyamerica and are subject to public comment periods of no less than 15 days. Waiver requests will also be reviewed by the Made in America Office.

1. Type of waiver requested (non-availability, unreasonable cost, or public interest).

2. Requesting entity and Unique Entity Identifier (UEI) submitting the request.

3. Department of Interior Bureau or Office who issued the award.

4. Federal financial assistance listing name and number (reference block 2 on DOI Notice of Award).

5. Financial assistance title of project (reference block 8 on DOI Notice of Award).

6. Federal Award Identification Number (FAIN).

7. Federal funding amount (reference block 11.m. on DOI Notice of Award).

8. Total cost of Infrastructure expenditures (includes federal and non-federal funds to the extent known).

9. Infrastructure project description(s) and location(s) (to the extent known).

10. List of iron or steel item(s), manufactured goods, and construction material(s) the recipient seeks to waive from Buy America requirements. Include the name, cost, countries of origin (if known), and relevant PSC or NAICS code for each.

11. A certification that the recipient made a good faith effort to solicit bids for domestic products supported by terms included in requests for proposals, contracts, and nonproprietary communications with the prime contractor.

http://www.doi.gov/grants/BuyAmerica/GeneralApplicabilityWaivers http://www.doi.gov/grants/buyamerica

12. A statement of waiver justification, including a description of efforts made (e.g., market research, industry outreach) by the recipient, in an attempt to avoid the need for a waiver. Such a justification may cite, if applicable, the absence of any Buy America-compliant bids received in response to a solicitation.

13. Anticipated impact if no waiver is issued.

Approved waivers will be posted at www.doi.gov/grants/BuyAmerica/ApprovedWaivers; recipients requesting a waiver will be notified of their waiver request determination by an awarding officer.

Questions pertaining to waivers must be directed to the financial assistance awarding officer.

Definitions

“Construction materials” includes an article, material, or supply that is or consists primarily of:

• non-ferrous metals;

• plastic and polymer-based products (including polyvinylchloride, composite building materials, and polymers used in fiber optic cables);

• glass (including optic glass);

• lumber; or

• drywall.

“Construction Materials” does not include cement and cementitious materials, aggregates such as stone, sand, or gravel, or aggregate binding agents or additives.

“Domestic content procurement preference’’ means all iron and steel used in the project are produced in the United States; the manufactured products used in the project are produced in the United States; or the construction materials used in the project are produced in the United States.

“Infrastructure” includes, at a minimum, the structures, facilities, and equipment for, in the United States, roads, highways, and bridges; public transportation; dams, ports, harbors, and other maritime facilities; intercity passenger and freight railroads; freight and intermodal facilities; airports; water systems, including drinking water and wastewater systems; electrical transmission facilities and systems; utilities; broadband infrastructure; and buildings and real property. Infrastructure includes facilities that generate, transport and distribute energy.

‘‘Project’’ means the construction, alteration, maintenance, or repair of infrastructure in the United States.

http://www.doi.gov/grants/BuyAmerica/ApprovedWaivers

STEEL PRODUCTS PROCUREMENT ACT
non-ferrous metals;
plastic and polymer-based products (including polyvinylchloride, composite building materials, and polymers used in fiber optic cables);
glass (including optic glass);
lumber; or
drywall.